CONVERTING TO AND FROM PRIMAVERA SURETRAK AND P3 TO MICROSOFT PROJECT MPX & MPP FORMAT PAUL E HARRIS EASTWOOD HARRIS. REVISED 4 August 2003



Similar documents
USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

LINKING P3 DATABASE WITH ACCESS DATABASE OR EXCEL BY PAUL E HARRIS EASTWOOD HARRIS

TECHNIQUES FOR MANAGING COMPLEX PROJECTS WITH PLANNING AND SCHEDULING SOFTWARE PAUL E HARRIS EASTWOOD HARRIS

NOTES ON XER EXPORT AND IMPORT BETWEEN ASTA POWERPROJECT AND IMPORT TO PRIMAVERA VERSION 5.0 PAUL E HARRIS EASTWOOD HARRIS

CALCULATION DIFFERENCES WHEN IMPORTING FROM INTO ORACLE PRIMAVERA P6 VERSION 7 PAUL E HARRIS EASTWOOD HARRIS

USING P3 VERSION 3.1 IMPORT AND EXPORT FUNCTIONS WITH THE DBF FILE FORMAT AND EXCEL PAUL E HARRIS EASTWOOD HARRIS

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS

PRINCE2 PLANNING AND CONTROL USING MICROSOFT PROJECT UPDATED FOR MICROSOFT OFFICE PROJECT 2007 PAUL EASTWOOD HARRIS

Welcome to the Eastwood Harris Pty Ltd Primavera P6 How Resource Driven Activities Calculate

TRICKS AND TRAPS PRESENTATION

Welcome to the Eastwood Harris Pty Ltd Introduction to PRINCE2 TM Revised 2009 and Microsoft Office Project. Page 1

PLANNING AND SCHEDULING USING MICROSOFT PROJECT 2010 PAUL EASTWOOD HARRIS

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 COST MANAGEMENT WITH EXPENSES

COST MANAGEMENT WITH EXPENSES

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

1. Introduction. P2O is automatically loaded when you open Ms Project (2010 or 2013). The add-in can be found under the M5 Tools menu. 2.

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

PROJECT PLANNING & SCHEDULING USING PRIMAVERA P6 TM. in an PAUL EASTWOOD HARRIS

Applied Project Management ( APM )

COMPARISON OF ORACLE P6 RELEASE 8 EPPM AND PMM

Sample book with only two chapters

Introduction to Microsoft Project 2010

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective

Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

How To Use Ms Powerbook On A Pc Or Mac Or Macbook 2 (Windows)

How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows)

TRAINING OF PLANNING AND SCHEDULING PERSONELL BY PAUL E HARRIS EASTWOOD HARRIS PTY LTD

Open Workbench Warrior. Beginner's Guide to Open Workbench

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A

Check out our website!

Computer Training Centre University College Cork

1. Interpretation of this Schedule

Basic CPM Calculations

Microsoft Project 2010

MS PROJECT FOR CONSTRUCTION SCHEDULERS

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

CPM Scheduling with Primavera Unifier

GUIDEDELINES FOR IMPLEMENTING PLANNING AND SCHEDULING SOFTWARE BY PAUL E HARRIS OF EASTWOOD HARRIS

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project

Project Initiation and Revision Training Manual. Table of Contents

WORK PROGRAM GUIDELINES

ELECTRO-MECHANICAL PROJECT MANAGEMENT

Planning and Scheduling Your Project Using Microsoft Project 2003

Project Management Courses

The Amazing History of Primavera Software

University of Sunderland. Microsoft Project. Basic Guide

Acclipse Document Manager

MS Project 2007 Quick Guide

Creating a New Project

MSP How to guide session 2 (Resources & Cost)

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Developing a Gantt and PERT Chart

Primavera Project Manager for the Enterprise Version 6.1 Custom Training Manual

The first thing to do is choose if you are creating a mail merge for printing or an merge for distribution over .

Project Management Courses

ECDL / ICDL Project Planning Syllabus Version 1.0

8. COMPUTER TOOLS FOR PROJECT MANAGEMENT

OVERVIEW. Microsoft Project terms and definitions

CRITICAL PATH METHOD (CPM) SCHEDULES

Primavera P6 102 Training Manual. Prepared by. Bill Pepoon, Managing Partner Construction Science, LLC

Collaborative Scheduling using the CPM Method

Step by Step guide and best practice methods for working with Consolidations

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

Data Exchange Between FastTrack Schedule and Microsoft Project

MICROSOFT PROJECT TUTORIAL

Microsoft Project 2010 Advanced

SHAREPOINT COLLABORATIVE WORKSPACE

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T T A S K M A N A GEM EN T LEARNING GUIDE

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

Contents Overview... 5 Configuring Project Management Bridge after Installation... 9 The Project Management Bridge Menu... 14

Home Accounts 3. User Guide. A guide to using Home Accounts 3 software

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

Lenovo Online Data Backup User Guide Version

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT

Microsoft Project Activity

Scheduling Document Creation

Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

Outlook 2007: Managing your mailbox

ECDL / ICDL Project Planning Project Management Software Level 2. Syllabus Version 1.0 (UK)

Lab 1 Introduction to Microsoft Project

Microsoft Project Dissected

Student Service Learning Hours

End User Manual. SharePoint. Please send feedback or suggestions for updates to the following address

Transcription:

P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software and Solutions Web: http://www.eh.com.au CONVERTING TO AND FROM PRIMAVERA SURETRAK AND P3 TO MICROSOFT PROJECT MPX & MPP FORMAT BY PAUL E HARRIS OF EASTWOOD HARRIS REVISED 4 August 2003

TABLE OF CONTENTS 1 TERMINOLOGY 3 1.1 MSP 3 1.2 TOPIC ACTIVITIES 3 1.3 MPX 3 1.4 MPP 3 2 PRINCIPALS OF CONVERSION 4 2.1 P3 TO MPX AND MPX TO P3 4 2.2 MSP98 TO MPX 4 2.3 MSP200/20020 TO MPX 4 2.4 MPX TO MSP2000/2002 OR MSP98 4 3 CONVERSION TOOLS 5 3.1 PIPE 5 3.2 SURETRAK 5 3.3 P3 MPX CONVERSION 5 4 NOTES ON IMPORTING A STATUSED MPX PROJECT INTO P3 6 5 NOTES ON CONVERTING FROM SURETRAK/P3 TO MPX 7 2

1 TERMINOLOGY 1.1 MSP Microsoft Project will be reffered to as MSP in this document. 1.2 TOPIC ACTIVITIES Topic Activities are created when using Outlining in SureTrak. Outlining is the default method of summerising activities in MSP and will normally appear a project is imported to SureTrak or P3 from a project in MPX Format derived from MSP. SureTrak supports Topic Activity Types. These may not be created in P3 but when you open a SureTrak project or import a MPX format project, the Topic activities are visible in P3. Topic activities may be deleted but not promoted or demoted or have their Task type changed in P3. 1.3 MPX MPX is a MSP text data format that many planning and scheduling software packages use to interchange data. Due to the differences in the the way the software calculates, a schedule imported from MPX will not always give the same answer when calculated in P3 or SureTrak. 1.4 MPP MPP is the native MSP file format, which may not be read by SureTrak. Project. There are two formats currently in use: 1. MPP used by MSP 2000/2002 (this will be referred as MPP from now on) and 2. MPP used by MSP 98 (this will be referred as MPP(98) from now on). MSP 98 may not read the MPP format, but MSP 2000/2002 may read the MPP(98) format. 3

2 PRINCIPALS OF CONVERSION 2.1 P3 to MPX and MPX to P3 To convert P3 to MPX and MPX to P3 there are three tools: Use the P3 MPX Conversion Utility, found under the Tools option in P3. Use SureTrak to open MPX files and to save SureTrak and P3 files in MPX format. Use PIPE, Primavera Inter Product Exchange, this is still by far the best tool in my opinion & is found on P3 CD's. 2.2 MSP98 to MPX Use the File Save as function and select MPX as the file type. 2.3 MSP200/20020 to MPX MSP2000/2002 will open a MPX file but it will not save one, the options for converting from MSP 2000/2002 tp MPX are: Use MSP2000/2002 and save in MSP98 format, open with MSP98 and save in MPX format. Primavera Systems has a MPP to MPX conversion utility available on their web site at primavera.com. This requires you to have MSP 2000/2002 loaded. There is a MPX2000 conversion utility found at www.scitor.com, I have not used this product seriously as I use MSP 98, if you use it please let me know how you go. I found this program did not convert notes when I tested it but does not require MSP 2000/2002 to be loaded. 2.4 MPX to MSP2000/2002 or MSP98 Use the MPS file open function and select MPX format. 4

3 CONVERSION TOOLS 3.1 PIPE Pipe, which is an older tool used with earlier versions of P3 for converting to and from P3 to MPX. It has a number of options that may provide a better import, as you are able to nominate specific data held in the MSP Text Columns to become specific Activity Codes in the P3 schedule. These facilities are not available in P3 MPX Conversion Utility or SureTrak. Thus you are able to nominate the P3 Activity ID in an MSP Text column and import it as an Activity ID. Pipe is not part of a standard P3 install but is available on some P3 CDs and converted files may be opened with either P3 or SureTrak. 3.2 SureTrak SureTrak will open an MPX file and save the converted file in P3 format and then may the file be opened with P3. A project converted from MPX will have Activity IDs commence with 0001 and these have a direct relationship with the MPX Task Number. Numeric Activity ID s will cause problems when copying and pasting from and too products like Excel, as the leading zeros are lost when pasting into Excel. The are some work arounds to overcome this problem such as putting a letter in front off the Activity ID before copying from SureTrak or formatting the Excel Activity ID column as Text before pasting. 3.3 P3 MPX Conversion This is the P3 menu conversion utility to convert both ways, P3 to MPX and MPX to P3, but does not provide the flexibility of PIPE. 5

4 NOTES ON IMPORTING A STATUSED MPX PROJECT INTO P3 Importing MPX files is always difficult, especially when the project have been statused: When converting from MPP to MPP (98) all tasks which have been assigned a task calendar in MPP format will have the Project Calendar assigned to tasks in MPP (98) format. This is because MSP (98) and MPX do not support task calendars. Therefore before converting from MPP to MPP(98) you should note any task calendar in a text column 1 to 10, and this will be converted to an activity code in P3 and SureTrak and correct calendar may be reassigned after conversion. The calendars are converted and will be available in P3 and SureTrak Ensure that all Actual start dates in MSP which are before the Data Date are marked as Started. (MSP allows activities in the past that have not started). It is recommended that you enter your P3 Activity Codes in MSP Text columns 1 to 10 before you import the file. These are often adopted from the Outline levels. Never import an MPX file into a project that is part of a Project Group, as it will delete/overwrite all your activity codes. It is recommended that you remove all Topic Activities by promoting ALL activities to Outline Level 1 and deleting redundant Parent Activities. You will need to check that all logic is at the lowest Outline Level before promoting activities After an MPX file is imported you may wish to change the Milestones which are imported as Start Milestones to Finish Milestones, (don't forget to change predecessors from FS to FF). There are many other issues involved with importing a MS Project file, especially when importing resources. You may need to rename your resources in MS Project and then reimport the file to achieve your desired result. In MPX and MS Project 98 calendars may only be placed against resources, you may wish to place calendars against activities after importing. 6

5 NOTES ON CONVERTING FROM SURETRAK/P3 TO MPX To convert a project from SureTrak to MS Project in principal all that has to be done is to select File, Save As and under file type select MPX, this will save the file as MPX format which most scheduling packages will open, including MS Project and SureTrak. There are a few issues for the uninitiated: SureTrak calculates differently and so the same data may calculate different dates in MS Project than SureTrak. Due to calendar conversion issues a SureTrak discussed earlier, a schedule with only one calendar converts better than a multiple calendar schedule. Levelled schedules are calculated completely differently in MS Project. In progress tasks in MP Project are calculated differently in MS Project. SureTrak calculation of in progress activities is in my opinion (and most professional schedulers) is far better than MS Project. If a SureTrak has Unlink Remaining Duration & Percent Complete switched on MS Project will not recognise this facility. MS Project does not allow activities with two relationships to another activity, as in SureTrak and this may cause import errors. MS Project does not recognise SureTrak Suspend & Resume. SureTrak Renames the Global Calendar as Standard when saving as a MPX. You should avoid using the name Standard for any calendar in SureTrak if you intend to convert it to MSP. I normally conduct the following tasks before saving a SureTrak file as a MPX: Set the Target Dates in SureTrak using Define, Target Dates, thus when you open the schedule in MS Project the Baseline Dates are what the schedule should calculate to. Rename the calendar that is assigned to the activities as any other name but "Standard". Open the schedule in MS Project, re calculate and compare the Baseline Dates to the schedule dates. You will find the SureTrak Activity Codes will appear in Text 1 to Text 10 in MS Project. In MS Project 2000 the Grouping facility (not available in earlier versions) may be used to Group on these text columns sort of emulate the SureTrak Organise, but it will only have the codes to work on, no ordering or titles are available, not at all satisfactory. 7