1 Planning and Managing Software Projects Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza

2 Credits 2 These slides are partially based on CEFRIEL slides for PMI Course and Certification

3 Today Agenda 3 Microsoft Project Fundamentals 1. Define Activities (WBS) 2. Sequence Activities 3. Estimate Work 4. Define Resources 5. Allocate Resources 6. Inspect Schedule 7. Refine Schedule (this will be discussed in class 15) 8. Level Resources (this will be discussed in class 15) 9. Control Project (this will be discussed in class 16)

4 How to attend MSFT Project Labs lessons 4 I discuss some slides introducing tool features Please, follow the slides DO NOT try to use the tool now I demonstrate the previously discussed features using my PC If you feel confident, you can try yourself to reproduce my operations on your/lab PC I give you enough time to perform a practical exercise You have to use the tool on your/lab PC Feel free to call me at your desk for on-demand support

5 Introduction to Microsoft Project 5 Current version: Microsoft Project 2010 Used version: Microsoft Project 2007 Very similar to 2003 version Similar GUI to other Microsoft Office Programs Word, Excel, Powerpoint, It s a project management tool It is not useful if Project Manager doesn t have a sufficient Project Management knowledge! Some tutorials and quick references

6 Creating a new project 6 1. Open Microsoft Project from Start menu Or 2. File (from menu) 3. New

7 Saving a project 7 1. File (from menu) 2. Save The current project will be saved as a.mpp file

8 New Project left-side Menu 8

9 Project Templates 9 1. File (from menu) 2. New 3. On My Computer 4. Project Templates 5. Select the Software Development template

10 Gantt Chart View View -> Gantt Chart (if Gantt chart is not shown) 2. Drag right the vertical slide to show all the columns Note: by default, the tables show only some columns. To add more columns: Right-click on a column and select insert column

11 Network Diagram View View 2. Network Diagram

12 Task Information forms From the Gantt view (or the Network Diagram view) 2. Double click on a task

13 Resource Sheet View View 2. Resource Sheet It shows the list of resources and their type

14 Resource Usage View View 2. Resource Usage It shows the daily work of each resource per each task

15 Task Usage View View 2. Task Usage It shows the daily work of each task per each resource Dual than previous

16 Resources Graph View View 2. More Views (if Project 2003) 3. Resources Graph 4. Apply

17 Timeline zooming 17 For the views which have a timed graph on the right Gantt, Resource Usage, Resource Graph, 1. Right click on the timeline (in the upper ribbon) 2. Choose Timescale + and zoom in or out The hand icon scrolls the diagram to the selected task

18 Project Information form Project (from menu) 2. Project Information Il you open an old project (e.g. a template), pay attention to the current time: you may not see anything in some views

19 Microsoft Project Options Tools (from menu) 2. Options I personally prefer to use days for both duration and work

20 Today Agenda 20 Microsoft Project Fundamentals 1. Define Activities (WBS) 2. Sequence Activities 3. Estimate Work 4. Define Resources 5. Allocate Resources 6. Inspect Schedule 7. Refine Schedule (this will be discussed in class 15) 8. Level Resources (this will be discussed in class 15) 9. Control Project (this will be discussed in class 16)

21 Create an Empty Project File (from menu) 2. New 3. Empty Project

22 Set project start date Project (from menu) 2. Project Information

23 Insert Activities/Tasks (from WBS) Insert the names of activities/tasks of the WBS in the Task Name column Activity vs. Task : Microsoft Project adopts Task

24 Group Tasks in Phases (as in WBS) 1. Select tasks to be grouped under the same phase 2. Click on the right green arrow 24 Multiple grouping level support Left green arrow means ungroup to previous level

25 Add Milestones Add tasks for meaningful releases or deliverables 2. Set Duration = 0 tep 1

26 Set Additional Task Constraints Double click on a task 2. Go to the Advanced tab Contractual milestones should have a Finish No Later Than constraint Meetings with externals people should have a Must Start On constraint Microsoft Project will raise a warning when a constraint is violated Limit yourself in setting useless constraints

27 Today Agenda 27 Microsoft Project Fundamentals 1. Define Activities (WBS) 2. Sequence Activities 3. Estimate Work 4. Define Resources 5. Allocate Resources 6. Inspect Schedule 7. Refine Schedule (this will be discussed in class 15) 8. Level Resources (this will be discussed in class 15) 9. Control Project (this will be discussed in class 16)

28 Dependency types 28 Finish-to-start: A f-to-s B : B cannot start until A finishes. B can start after A finishes. A FS B Start-to-start: A s-to-s B : B cannot start until A starts. B can start after A starts. SS A B Finish-to-finish: A f-to-f B : B cannot finish until A finishes. B can finish after A finishes A B FF Start-to-finish: A s-to-f B : B cannot finish until A starts. B can finish after A starts. B SF A

29 Define Dependencies Go to the Predecessors column 2. Insert the ID of the predecessor task 3. Follow the ID with the type of dependency (FS is the default) If a phase has a dependency, all its internal tasks get the same dependency Dependencies are reflected in the GANTT diagram on the right Use the ; to insert multiple dependencies (, with English regional settings) Acronyms may be translated if you are using a non-english versions of MSFT Project

30 Define Dependencies (alternative way) Double click on a task 2. Go to the Predecessor tab 3. Click on the first empty cell in Task Name column 4. Select the dependent task from the list 5. Click on the respective cell in the Type column 6. Select the type from the list Lag time can be set here. Lead time is equal to lag time with a negative value tep 2

31 Today Agenda 31 Microsoft Project Fundamentals 1. Define Activities (WBS) 2. Sequence Activities 3. Estimate Work 4. Define Resources 5. Allocate Resources 6. Inspect Schedule 7. Refine Schedule (this will be discussed in class 15) 8. Level Resources (this will be discussed in class 15) 9. Control Project (this will be discussed in class 16)

32 Insert estimated Work (= effort) 32 Visualize the Work Column 1. Right click on the Start column 2. Insert Column and choose work Inserted estimated work on each task To change default work from hours to days: Tools (from menu) Options Select the Schedule tab Look for the option Work is entered in: Set it to Days tep 3 Duration is still not defined! Allocating resources will define the duration of tasks

33 Practical Exercise n.1 33 Open a template and try the different views Start from scratch a new project Define tasks (about 20-50) Organize tasks in groups and subgroups Define milestones Define dependencies among tasks Estimate Work on each task Look at a realistic example (similar to the maximum we can expect from your homework 4) P&MSP2012_10_SoftwareDevelopmentTemplate.mpp

34 Today Agenda 34 Microsoft Project Fundamentals 1. Define Activities (WBS) 2. Sequence Activities 3. Estimate Work 4. Define Resources 5. Allocate Resources 6. Inspect Schedule 7. Refine Schedule (this will be discussed in class 15) 8. Level Resources (this will be discussed in class 15) 9. Control Project (this will be discussed in class 16)

35 Resources Definition and Allocation 35 Resources allocation involves determining which type of resources (persons, equipment, or materiel), how many resources will be used and when each resources will be available to perform project activities This process is closely coordinated with the Costs Estimating process The objective is optimizing resources in order to have a continuous and consistent use of the minimum number of resources Three Resource Types: Limited availability: Work Unlimited availability: Material Fixed outcome: Cost

36 Resource Type Limited availability resources: Work 36 Resources whose availability is limited E.g. Humans (team, partners, customers, ), pay-peruse SW licenses or HW rental They are described by two main factors: Standard Cost (e.g. 20 /hour) Max daily allocation level (e.g. 50%) 100%: full availability between 0 and 100%: partial availability > 100%: when there are more than one resource but they cannot be distinguished (optionally) Overrate cost (e.g. 30 /hour) Work Resources must be leveled to avoid overallocation

37 Resource Type Unlimited availability resources: Material 37 Resources that can be allocated on a task without limit More consume of the resource implies more cost E.g. CDs or DVDs necessary to distributed a SW releases are assumed to be unlimited, as more are consumed as more is the total cost They are described by one main factor: Standard cost per unit (e.g. 1 /CD) Material resources do not have to be leveled

38 Resource Type Fixed outcome: Costs 38 Quantified costs associated to a specific task E.g.: Travel Costs, HW/SW purchase costs They are described by the cost defined when the resource is allocated to a task

39 Define Resources View (from Menu) ->Resource sheet 2. Per each row: 1. Insert Resource Name 2. Select the type of resource 1. Work 2. Material 3. Cost 3. Insert details 1. Max units 2. Std. Rate 3. Ovt. Rate

40 Set Resources Availability Double click the corresponding row to open the resource information form 2. Define Resource Availability (when he/she is available) tep 4

41 Today Agenda 41 Microsoft Project Fundamentals 1. Define Activities (WBS) 2. Sequence Activities 3. Estimate Work 4. Define Resources 5. Allocate Resources 6. Inspect Schedule 7. Refine Schedule (this will be discussed in class 15) 8. Level Resources (this will be discussed in class 15) 9. Control Project (this will be discussed in class 16)

42 Before allocating resources to tasks Visualize Task Form 1. Return to Gantt Chart 1. View (from Menu) -> Gantt Chart 2. Visualize Task Form 1. Windows (from menu) -> Split 2. Select bottom window 3. View (from menu) -> More Views -> Select Task Form 3. To create a quick shortcut on the right-click on the left vertical gray bar 1. Edit (in More Views) -> Show in Menu -> OK 42 Resources, Units and Work can be specified per each task

43 Resources Allocation Techniques 43 Unit Allocation is expressed by the time of the resource dedicated to the specific task i.e.: Resource1 is allocated the 50% of his time on Task1 Work Allocation is expressed by total time that the resources will dedicate to a task i.e.: Resource1 will work 1 day on Task1

44 Allocate Resources to Tasks Select a Task 2. Select Resource Name (in the bottom window) 3. Insert Units or Work per each resource 1 resource at 50% for 1 day of Work Microsoft Project estimates the Duration in 2 days Let s consider just 1 resource for now

45 Duration, Units and Work proportion Work [t] Duration[ t] Work[ t] *100 Units[%] 45 Work[ t] Units[%] Duration[ t]* 100 Units [%] Duration [t] Units[%] Work[ t] *100 Duration[ t] If Units = 50% & Work = 1 day Duration = 2 days If Units = 100% & Work = 5 days Duration = 5 days If Duration = 3 days & Units = 50% Work = 1.5 days If Duration = 4 days & Work = 1 day Units = 25% This proportion is always kept consistent by MS Project!

46 Allocate one Resource to Tasks 46 Return to the Gantt view 1. Select a task (in the top window) 2. Add one resource (in the bottom window) 3. Define it s units 4. Click OK 5. Check how MS Project estimates the Duration

47 Allocate more Resources to Tasks (by units) Select the task (in the top window) 2. Add two resources (in the bottom window) 3. Define their units 4. Click OK Task work = the sum of work of each resource Task duration = the max of duration for each resource

48 Allocate more Resources to Tasks (by work) Select the task (in the top window) 2. Add two resources (in the bottom window) 3. Define their work (without changing the total work on the task) 4. Click OK Task work = the sum of work of each resource Task duration = the max of duration for each resource

49 Complete Resource Allocation Per each task, allocate one or more resources tep 5

50 Today Agenda 50 Microsoft Project Fundamentals 1. Define Activities (WBS) 2. Sequence Activities 3. Estimate Work 4. Define Resources 5. Allocate Resources 6. Inspect Schedule 7. Refine Schedule (this will be discussed in class 15) 8. Level Resources (this will be discussed in class 15) 9. Control Project (this will be discussed in class 16)

51 Inspect the current schedule 51 In the Gantt view 1. Tasks and Milestones have estimated dates 2. Tasks and Summary tasks show estimated duration 3. Zoom-out the Gantt chart to view it completely

52 Critical Path and Slack Times 52 The specific set of sequential tasks upon which the project completion date depends The sequence of tasks that determines the duration of the project A delay of a task in the critical path implies a delay in the final date If the Total Slack time of task is 0 then it is on the critical path A delay in the ending date negatively affect the downstream activity and the end of the total project

53 Inspect Critical Path Right Click on the white background of the Gantt chart 2. Gantt Chart Wizard 3. Next, Select Critical Path, Click Finish and Click Format It Critical Path is highlighted in red

54 Inspect Slack Times Right Click on a column (e.g. Resource Names) 2. Select Insert Column 3. Choose Free Slack 4. (Repeat 1-2 and then choose Total Slack)

55 Inspect Costs of each Task From Gantt Chart view 2. Right click on a column E.g. Resource Names 3. Insert Column 4. Cost 1. View 2. Table entry 3. Choose Cost

56 Inspect Costs of each Resource View (from menu) 2. Resource Usage view 3. View (from menu) 4. Table: usage 5. Choose cost tep 6

57 Practical Exercise n.2 57 Define resources (about 5) Humans, materials and costs Allocate resources to tasks (don t forget material resources) Inspect critical path, slack times, costs

58 Questions? 58

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These

More information

Session 6. Microsoft Project. Emanuele Della Valle. http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza

Session 6. Microsoft Project. Emanuele Della Valle. http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza Session 6 Microsoft Project Emanuele Della Valle http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza Credits 2 This slides are largely based on CEFRIEL s slides for PMI Certification and Prof.

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

Introduction to Microsoft Project 2010

Introduction to Microsoft Project 2010 Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help

More information

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety

More information

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)

How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows) Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open

More information

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start Project Management is the discipline of planning, organizing, and managing resources to complete a specific goal. Microsoft Project is software that helps you. Start your project Open Project 2010 and

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

OVERVIEW. Microsoft Project terms and definitions

OVERVIEW. Microsoft Project terms and definitions PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training

More information

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects

More information

How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows)

How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows) Project management M project tutorial Part 1: Project beginning and the Gantt chart Purpose Project management by using Microsoft Project software Introduction Project management is a process of organizing,

More information

Project Management Dashboard Pro v5 Documentation

Project Management Dashboard Pro v5 Documentation Project Management Dashboard Pro v5 Documentation Installation There is NO installation required. It s just a macro enabled excel file that opens if you have Excel 2007, 2010, 2013 and 2016 on your Windows

More information

Microsoft Project 2013 Guide to Task and Resource Planning

Microsoft Project 2013 Guide to Task and Resource Planning Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To

More information

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0 ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The

More information

Microsoft Project 2013

Microsoft Project 2013 CALIFORNIA STATE UNIVERSITY, LOS ANGELES INFORMATION TECHNOLOGY SERVICES Microsoft Project 2013 Summer 2014, Version 1.0 Table of Contents Introduction...2 Overview of the User Interface...2 Creating a

More information

Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems

Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems Computer Lab # 1 Time Management (with Microsoft Project 2007) Lab Manual (with master s

More information

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute

More information

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project

Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Creating and Viewing Task Dependencies between Multiple Projects using Microsoft Project Preliminary 1. You must have Microsoft Project 2003 or higher installed to complete these procedures. 2. If necessary,

More information

How to use Microsoft Project? Basic Training to Help You during the BYI challenge

How to use Microsoft Project? Basic Training to Help You during the BYI challenge How to use Microsoft Project? Basic Training to Help You during the BYI challenge Table of Contents I. Main Concepts 1. Overview of Microsoft Project 2. Explanation of the main concepts II. How to : Create

More information

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project

Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Project Example Overview Microsoft Project, in addition to scheduling calculations,

More information

Project 2010 Introduction

Project 2010 Introduction Microsoft Application Series Project 2010 Introduction Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery

More information

Lab 1 Introduction to Microsoft Project

Lab 1 Introduction to Microsoft Project Lab 1 Introduction to Microsoft Project Statement Purpose This lab provides students with the knowledge and skills to use Microsoft Project. This course takes students step-by-step through the features

More information

Microsoft Project 2010

Microsoft Project 2010 Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window

More information

Project Management: Intermediate Microsoft Project 2010

Project Management: Intermediate Microsoft Project 2010 Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project

More information

Planning and Scheduling Your Project Using Microsoft Project 2003

Planning and Scheduling Your Project Using Microsoft Project 2003 Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering sridhar@sastratechnologies.in Meeting Protocol Agenda Project File Project Calendar Creating

More information

MS Project 2007 Quick Guide

MS Project 2007 Quick Guide MS Project 2007 Quick Guide 1. Setup your project Add project information Determine project start date Check / Edit the standard/base calendar Check / Edit calendar calculation options Fine-tune your configuration

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1

IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1 IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break

More information

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project

Microsoft Project 2007 Level 2: Working with Resources and Managing a Project Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was

More information

MICROSOFT PROJECT TUTORIAL

MICROSOFT PROJECT TUTORIAL MICROSOFT PROJECT TUTORIAL INTRODUCTION Microsoft Project is a Windows-based project management software package. It provides the flexibility to help manage your project, provides assistance in every phase

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

Microsoft Project 2010 Advanced

Microsoft Project 2010 Advanced Microsoft Project 2010 Advanced Table Of Contents SECTION 1 - REFRESH OF THE BASICS... 3 GUIDE INFORMATION... 4 Introduction... 4 How To Use This Guide... 4 Objectives... 4 Instructions... 4 PROJECT INFORMATION

More information

Microsoft Project Activity

Microsoft Project Activity Microsoft Project Activity Purpose: The goal of this activity is to lead you through the most important data entry and formatting activities in MS Project and to provide you with the fundamental knowledge

More information

Beginning Microsoft Project

Beginning Microsoft Project Beginning Microsoft Project BEGINNING MICROSOFT PROJECT...1 WHAT IS PROJECT? WHAT IS IT USED FOR?...1 PROJECT WINDOWS... 1 Views and Tables...1 PHASE 1: PLANNING AND SETTING UP PROJECT...2 PLANNING AND

More information

Computer Training Centre University College Cork

Computer Training Centre University College Cork Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010)

Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010) Microsoft Project 2007 Tutorial Boston University Boston University, Dept of Administrative Sciences, Project Management Programs (2010) 1 2 Microsoft Project 2007 Tutorial Boston University Contents Table

More information

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado

MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Steps to Enter Duration: 1. In the Duration column of a task, enter a value, and press Enter on your keyboard Important Points: The default time unit is days, so when you enter 5, this becomes 5

More information

Microsoft Project 2007 Level 1: Creating Project Tasks

Microsoft Project 2007 Level 1: Creating Project Tasks Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.

More information

Lesson 6 - Managing Resources in a Project Plan

Lesson 6 - Managing Resources in a Project Plan Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional

More information

Creating a New Project

Creating a New Project Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,

More information

Project planning with MindGenius

Project planning with MindGenius Project planning with MindGenius This workshop looks at using MindGenius for planning and monitoring smaller projects. MindGenius is available free of charge on all University of Brighton staff and student

More information

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

Developing a Gantt and PERT Chart

Developing a Gantt and PERT Chart Developing a Gantt and PERT Chart October 2004 Edition UNITAR-executed GEF Medium-Sized Project, on behalf of UNDP Table of Contents Module 1. Creating a Gantt Chart Using MS Project... 1 Introduction...

More information

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective

Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective 1. Abstract PM WORLD TODAY FEATURED PAPER MARCH 2009 Synergy between PMBOK and MS Project 2007 A Schedule Management Perspective By Satya Narayan Dash, PMP, MCP and Uttam Kumar Singh, PMP, PAHM MS Project

More information

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING

MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING MICROSOFT PROJECT SOFTWRE FOR THE PROJECT SCHEDULING ŠÁRK ČEMERKOVÁ Silesian University in Opava School of usiness dministration in Karviná Department of Mathematical Methods in Economics Czech Republic

More information

PERCEPTION PERT-PAC Using Microsoft Project 2000

PERCEPTION PERT-PAC Using Microsoft Project 2000 PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000

More information

ELECTRO-MECHANICAL PROJECT MANAGEMENT

ELECTRO-MECHANICAL PROJECT MANAGEMENT CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: yogeshsharma@bsnl.co.in Page: 1 Electro-mechanical Project Management using MS Project Introduction: When

More information

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan.

Create task relationships by linking tasks. Switch task scheduling from manual to automatic. Set nonworking days for the project plan. 2 In this chapter, you will learn how to: Start Microsoft Project Standard or Professional and save a new project plan. Enter task names. Estimate and record how long each task should last. Create a milestone

More information

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP PMBOK Guide 5 th Edition and MS Project 2010: A Practical Step-by-Step Approach 1. Abstract By Satya Narayan Dash, PMP, CSM, MCP Project Management Body of Knowledge (PMBOK) Guide, from PMI, comes with

More information

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010) Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the

More information

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS

INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary

More information

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 Agenda Revision of 108.03 Schedule How CDOT Uses Construction Schedules Critical Path Method Scheduling Microsoft Project Overview 1 Revision

More information

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands.

Explore commands on the ribbon Each ribbon has groups, and each group has a set of related commands. Quick Start Guide Microsoft Project 2013 looks different from previous versions, so we created this guide to help you minimize the learning curve. Quick Access Toolbar Customize this area so your favorite

More information

Project Management Quick Reference Guide for MS Project 2010

Project Management Quick Reference Guide for MS Project 2010 Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides

More information

MSP How to guide session 2 (Resources & Cost)

MSP How to guide session 2 (Resources & Cost) MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or

More information

Module A2 Item Activities, Gantt Chart and Utilization Sheet

Module A2 Item Activities, Gantt Chart and Utilization Sheet Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Module 1. Project item activities, Gantt Chart & Utilization Sheet Contents...

More information

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet

Module A2 Item Activities, Gantt Chart and Utilization Sheet. A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet Module A2 Item Activities, Gantt Chart and Utilization Sheet A2.1 Project item activities A2.2 Gantt chart A2.3 Utilization sheet 1 Assistance PSA: Advanced Functionalities Welcome to the Advanced Functionalities

More information

Before starting this section

Before starting this section Before starting this section SAVE AS YOUR EXISTING MS PROJECT FILE AS -part3-1 1.Click on View Entering Resources-1 Resource Sheet Entering Resources-2 Entering Resources-3 1.Click on the Resource

More information

T12. Excel and Microsoft Project. Introduction LEARNING OUTCOMES

T12. Excel and Microsoft Project. Introduction LEARNING OUTCOMES P L U G - I N T12 Creating LEARNING OUTCOMES Gantt Charts with Excel and Microsoft Project 1. Explain a Gantt Chart. 2. Describe the main steps involved in creating a Gantt Chart using Excel. 3. Describe

More information

4.0 - Using the Microsoft Project Plan

4.0 - Using the Microsoft Project Plan 4.0 - Using the Microsoft Project Plan 153 4.0 - Using the Microsoft Project Plan 1.0 Introduction to PM 2.0 Plan Project 21 2.1 22 2.2 23 2.3 Prepare Estimates Develop WBS Develop Schedules 3.0 Manage

More information

Tracking Project Progress

Tracking Project Progress L E S S O N 2 Tracking Project Progress Suggested lesson time 45-55 minutes Lesson objectives To begin tracking an active project, you will: a b c Modify the environment for tracking. You will use the

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important

More information

Project 2013: An introduction

Project 2013: An introduction Project 2013: An introduction TPAF Revision Information Version Date Author Changes made 1.0 February 2013 Jean Glendinning Created 2.0 November 2013 Jean Glendinning Amended elements 3.0 Feb 2014 Jean

More information

Project Management within ManagePro

Project Management within ManagePro Project Management within ManagePro This document describes how to do the following common project management functions with ManagePro: set-up projects, define scope/requirements, assign resources, estimate

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals

More information

1 Start a new project

1 Start a new project Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify

More information

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days 3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: rwhitney@discoveritt.com Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:

More information

A. Look at the Resource Sheet and Gantt Entry View Sheet to see what and where resources are over allocated.

A. Look at the Resource Sheet and Gantt Entry View Sheet to see what and where resources are over allocated. Microsoft Project Pro Steps to completing Project Pro Assignments PART B. (These instructions include all you need to know about adjusting your project in Microsoft Project Pro 2013 and may include instructions

More information

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule

More information

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL

More information

Open Workbench Warrior. Beginner's Guide to Open Workbench

Open Workbench Warrior. Beginner's Guide to Open Workbench Open Workbench Warrior Beginner's Guide to Open Workbench Table of Contents Introduction...3 Open Workbench Functionality...3 Project Planning...3 Project Tracking and Management...3 Sample Project...3

More information

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John

More information

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com

Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com The Assignment Equation The following equation controls the relationship between the Work, Duration, and Assignment Units for a task assignment: Or Or Work: The number of hours of real work effort spent

More information

MS Project 2000 Tutorial: Introduction

MS Project 2000 Tutorial: Introduction MS Project 2000 Tutorial: Introduction - Anjana Srikanth Stylus Systems is a Internet Technology company located in Bangalore India. One of our mottos is "a quality process creates a quality product."

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org

Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Planning and Managing Software Projects 2010-11 Session 5 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides

More information

Microsoft Office PowerPoint 2003. Creating a new presentation from a design template. Creating a new presentation from a design template

Microsoft Office PowerPoint 2003. Creating a new presentation from a design template. Creating a new presentation from a design template Microsoft Office PowerPoint 2003 Tutorial 2 Applying and Modifying Text and Graphic Objects 1 Creating a new presentation from a design template Click File on the menu bar, and then click New Click the

More information

Project Initiation and Revision Training Manual. Table of Contents

Project Initiation and Revision Training Manual. Table of Contents for Engineering and Construction v.4.1 Project Initiation and Revision Training Class Conducted by Evans Technology June 2005 Table of Contents Introduction to Primavera... 3 Project Management (P3eC)...

More information

EXCEL Tutorial: How to use EXCEL for Graphs and Calculations.

EXCEL Tutorial: How to use EXCEL for Graphs and Calculations. EXCEL Tutorial: How to use EXCEL for Graphs and Calculations. Excel is powerful tool and can make your life easier if you are proficient in using it. You will need to use Excel to complete most of your

More information

Scheduling Document Creation

Scheduling Document Creation Scheduling Document Creation What is a Schedule in epm? Schedules The epm Schedule application is an integral part of the Portfolio Management suite of applications. Start and end dates for each summary

More information

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE

I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE Workshop Information Information Technology Services is happy to provide you with

More information

USER S GUIDE for DSM@MIT

USER S GUIDE for DSM@MIT USER S GUIDE for DSM@MIT TABLE OF CONTENTS 1. OVERVIEW...3 2. INSTALLATION...5 3. FUNCTIONS...7 3.1 Inputs for the Structuring Module...7 3.2 Analyses in the Structuring Module...8 3.3 Editing the DSM...13

More information

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Precedence Diagram Method. CSTM 462 Planning & Scheduling Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.

More information

Using Microsoft Project 2000

Using Microsoft Project 2000 Using MS Project Personal Computer Fundamentals 1 of 45 Using Microsoft Project 2000 General Conventions All text highlighted in bold refers to menu selections. Examples would be File and Analysis. ALL

More information

Microsoft Access 2010 handout

Microsoft Access 2010 handout Microsoft Access 2010 handout Access 2010 is a relational database program you can use to create and manage large quantities of data. You can use Access to manage anything from a home inventory to a giant

More information

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.

More information

Microsoft Project 70-178 Exam Study Guide

Microsoft Project 70-178 Exam Study Guide Microsoft Project 70-178 Exam Study Guide Prepared by The Versatile Company for MPUG. www.versatilecompany.com The Versatile Company, 2012. About this Study Guide This guide was developed based upon the

More information

Microsoft Project 2013. Microsoft Project 2013. The smart way to learn. Microsoft Project 2013. one step at a time!

Microsoft Project 2013. Microsoft Project 2013. The smart way to learn. Microsoft Project 2013. one step at a time! spine = 1.32 one step at a time! Experience learning made easy and quickly teach yourself how to manage the complete project life cycle with Project 2013. With Step by Step, you set the pace building and

More information

Using Microsoft Office to Manage Projects

Using Microsoft Office to Manage Projects (or, Why You Don t Need MS Project) Using Microsoft Office to Manage Projects will explain how to use two applications in the Microsoft Office suite to document your project plan and assign and track tasks.

More information

Resource Allocation in MS Project

Resource Allocation in MS Project Resource Allocation in MS Project Calendars The project calendar determines the working days and hours available to your project, In addition each resource can have their unique calendars to mark time

More information

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT LECTURE -01 TO PROJECT MANAGEMENT AND MS PROJECT 2 Objective LEARNING OBJECTIVES To learn Project Management Software and their Application to Civil Engineering Books Microsoft Office Project Step by Step

More information

Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3. User and Installation Guide

Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3. User and Installation Guide Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3 User and Installation Guide 2 Table of Contents OVERVIEW... 3 FEATURES LIST... 3 SYSTEM/DEVELOPER REQUIREMENTS... 3 OPERATING SYSTEM... 3 SERVER...

More information

CDC UNIFIED PROCESS JOB AID

CDC UNIFIED PROCESS JOB AID Purpose The purpose of this document is to provide guidance on the practice of using Microsoft Project and to describe the practice overview, requirements, best practices, activities, and key terms related

More information

Revealing the Secrets of Microsoft Project

Revealing the Secrets of Microsoft Project 2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project

More information

Project Management Courses

Project Management Courses A well planned project will give results exactly as planned. Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the delivery

More information

5. Creating a Gantt Chart

5. Creating a Gantt Chart 5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

Planning and Managing Projects with Microsoft Project Professional 2013

Planning and Managing Projects with Microsoft Project Professional 2013 Project management deliverables (e.g. reports); WBS deliverables can be used for report timing Steps to Create a Project from an Existing Template: 1. Click File then New. 2. Select any of the featured

More information