Planning and Scheduling Your Project Using Microsoft Project 2003
|
|
|
- Thomas Britton Copeland
- 10 years ago
- Views:
Transcription
1 Planning and Scheduling Your Project Using Microsoft Project 2003 Sridhar Pandurangiah Director - Engineering [email protected]
2 Meeting Protocol
3 Agenda Project File Project Calendar Creating Tasks and WBS Milestones Recurring Tasks Dependencies Lead and Lag times Constraints Deadlines Split Tasks Resources Contouring Over allocations Cost Optimise Plan Earned Value Management
4 Create a Project File Create a new file Choose one of the templates Complete the summary tab Complete Project Information
5 Change Project Calendar Working time Week starting (middle east projects will have their weekends on Thursday and Friday) Holidays Staff leave
6 View Options Change the date format to that used by the client Change the currency symbol, decimal digits to the currency you would use to track the project cost.
7 General Options Specify the user name, standard and overtime billing rates For Whizible users Uncheck Advice From Planning Wizard
8 Schedule Options Change the duration from days to hours For Whizible users Uncheck Show Scheduling messages Uncheck Tasks will always honour their constraint dates Click Set as Default
9 Enter tasks and Duration % Complete, WBS, Task name, work, duration, start, finish, predecessors, resource names Enter tasks and duration Don t enter the start and finish dates. Also enter the notes. Elapsed Duration (ed) is calendar duration Indent tasks to create a logical outline Break large tasks to smaller tasks
10 Enter tasks and Duration For Whizible users Use the Text 30 field to define Task Type Use the following priority Low (0 to 400) Medium (401 to 600) High (601 to 900) NULL ( ) Ignored by Whizible You can assign a Task Calendar to a task. Then the option Scheduling ignores resource calendar
11 Identify Milestones Identify significant events as milestones [Creating a task of 0 days marks it as a milestone] Indicated by Change Icon
12 Create Recurring Tasks Weekly team meetings, SQA reviews, Weekly Progress Reporting all recur at predetermined intervals Roll Gantt Bar to Summary Specific task information defined in the Gantt Bar Styles rolls up and shows in the summary task Hide Task Bar Hides the Bar
13 Specify task dependencies Automatically a finish to-start dependency is created
14 Task Dependencies You can specify start-to-start, finish-to-finish or start-to-finish
15 Lead and Lag Times Overlap tasks or enter lead / lag times Lag times are +ve values while lead times are ve values Lag and lead can be entered as a % or absolute values
16 Constraints Set specific start or finish dates Specify a start date start no earlier than (SNET) constraint is set Specify a finish date -finish no earlier than (FNET) constraint is set Use this feature sparingly
17 Add Deadlines Deadlines don t affect scheduling mechanisms Microsoft Project will inform you that a task will finish past its deadline. You then have the option of adjusting the schedule to meet that deadline. Drag the green arrow to reset deadlines
18 Split tasks If work on the task is interrupted and then resumes later in the schedule
19 Assign Resources Specify type of resource work / material Specify the number of resource units available for this resource in the max. Units field, as a percentage. E.G., Type 300% to indicate three full-time units of a particular resource.
20 Specify Resource Groups For each material resource (supplies consumed throughout the project), in the material label field, type a measurement unit for the material resource, such as ton. Resource groups can be used for sorting, filtering, or grouping tasks by resources belonging to a particular group. You can use groups to indicate the department a human resource belongs to or to specify accounting codes for billing purposes.
21 Change work schedule for Resource Modify the individual resource calendar
22 Specify Costs for Resource Specify the Standard and Overtime rates
23 Specify Workgroup Information and availability for Resource Use this to specify long absences e.g. sabbatical leaves Independent of resource calendar
24 New Base Calendar If a group of resources has the same special working hours and days off, you can create a new base calendar for them
25 Assign Resources Support for Active Directory / Address Book / Microsoft Project Server Assign multiple resources at once (CTRL and drag) Replace a resource by choosing the resource and clicking replace then reassign a fresh resource A Valid work value can be entered then units = entered work/duration Automatic assignment of resources can be disabled in Tools / Options / General tab
26 Fix the task duration If a task is 8 hrs duration and 8 hrs work with a single resource adding a second resource reduces the duration to 4 hours (effort driven) Turn this feature off to increase the work to 16 hours Turn off globally in Options / Schedule
27 Plan Optimisation Duration Compression Crashing Fast Tracking Resource Levelling Heuristics
28 Edit resource assignments (Assignment Contours) Effective way to remove over allocation (shown in red) Just drag and drop tasks under the resource
29 Predefined Assignment Contours
30 Predefined Assignment Contours CONTOURS SEGMENTS Flat Back Loaded 10% 15% 25% 50% 50% 75% 75% Front Loaded 75% 75% 50% 50% 25% 15% 10% Double Peak 25% 50% 50% 25% 25% 50% 50% 25% Early Peak 25% 50% 75% 50% 50% 25% 15% 10% Late Peak 10% 15% 25% 50% 50% 75% 50% 25% Bell 10% 20% 40% 80% 80% 40% 20% 10% Turtle 25% 50% 75% 75% 50% 25%
31 Automatic Resource Levelling Levelling Order Standard : Considers links, slack, dates and priorities ID Only : Delays task with the highest ID Priority : Priority of tasks takes precedence Level only within the available slack Adjust Individual assignments on a task : To level only over-allocated resources AVOID AUTOMATIC LEVELLING
32 Manual Resource Levelling Create Delays Remove or Replace resources Reduce Units
33 Creating Delays
34 Assign Costs to resources Default rates for all resources can be assigned (Tools / Options / General) If costs change use the Resource Information / Costs Tab and specify the costs with effective dates (useful if a resource gets a salary revision during the course of the project)
35 Set Fixed Costs Useful when the exact cost associated with a cost is known View / Table / Costs
36 Define When Costs Accrue Accrual can be prorated, at the start or at the end of a project
37 Review the cost of tasks and resources From the Resource sheet click View / Table / Cost
38 Cost distribution over a task Choose View / Task Usage Choose Format / Details / Cost
39 Resource Costs (Detail) Choose view / resource usage Choose format / details / cost
40 Resource Costs (Graphical) Choose view / resource graph Choose format / details / cost or Cumulative cost
41 Cost of Entire Project Choose Project / Project Information / Statistics
42 View the entire project From the GANT Chart Choose View / Zoom / Entire Project
43 Check the Project dates Check the project s START and FINISH dates
44 Identify Critical Path Critical Path Has Zero Slack Tasks can t be delayed without affecting overall schedule Use the GANTT chart wizard to identify the critical path
45 Viewing Critical Tasks Filter using the menu
46 Switching Views Choose View / More Views
47 Different Fields in a View View / More Views View / Table / More tables
48 Using Filters Interactive Filters can be applied Resource filters cannot be applied to tasks and vice versa
49 Sorting Tasks Variety of sorts are possible Renumbering tasks permanently Its possible to maintain the hierarchy of the subtasks to its parent task
50 Grouping Information Variety of Group by options are available
51 Save the Plan Save the plan with a baseline it helps in tracking your project To save the budget, enter the costs before saving the baseline Interim plans act as checkpoints, upto 10 interim plans can be saved
52 Earned Value Management Planned Value (PV) or Budgeted Cost of Work Schedule (BCWS) Earned Value (EV) or Budgeted Cost of Work Performed (BCWP) Actual Cost (AV) or Actual Cost of Work Performed (ACWP)
53 EVM Cost Variance (CV) = EV AC Schedule Variance (SV) = EV PV Cost Performance Index = EV / AC Schedule Performance Index = EV/PV Positive Values are good. Negative Values Bad Ratio s closer to 1 are good
54 Thank You
INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS
INTRODUCTION TO MICROSOFT PROJECT 2007 CONTENTS What is a Project... 2 The Steps involved in Setting up a Project... 3 Views... 4 How To Start a new project... 6 The Gantt Chart... 8 Outlining/Summary
OVERVIEW. Microsoft Project terms and definitions
PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training
How To Use Ms Powerbook 2.5.2.2 On A Pc Or Mac Or Macbook 2 (Windows)
Overview 1 Content Overview Open a project file Create a new project plan Track progress View and print reports Share a project plan Conclusion 2 Overview With you can: create new/update project plan open
Microsoft Project 2013 Guide to Task and Resource Planning
Starting a Project The Microsoft Project 2013 Start screen Double click Blank Project, select a Recent project, or click Open Other Projects to work on a saved project stored on disk or on SkyDrive. To
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects
ELECTRO-MECHANICAL PROJECT MANAGEMENT
CHAPTER-9 ELECTRO-MECHANICAL PROJECT MANAGEMENT Y K Sharma,SDE(BS-E), 9412739241(M) E-Mail ID: [email protected] Page: 1 Electro-mechanical Project Management using MS Project Introduction: When
MS Project 2007 Quick Guide
MS Project 2007 Quick Guide 1. Setup your project Add project information Determine project start date Check / Edit the standard/base calendar Check / Edit calendar calculation options Fine-tune your configuration
Using MS Project in Translation Projects Management
Using MS Project in Translation Projects Management When building a translation project plan, there must be taken into account: the tasks involved by the project, duration of each task, task dependencies,
USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS
P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: [email protected] Australia Software
IT Training. Microsoft Project. Vicky Samways, IT Training Information System Services Version 2.1
IT Training Microsoft Project Vicky Samways, IT Training Information System Services Version 2.1 Scope Learning outcomes Find out when and how to use Microsoft Project. Learn how to create a project, break
Resource Allocation in MS Project
Resource Allocation in MS Project Calendars The project calendar determines the working days and hours available to your project, In addition each resource can have their unique calendars to mark time
Computer Training Centre University College Cork
Computer Training Centre University College Cork Project 2013 Table of Contents What's new in Project 2013... 1 Manual scheduling... 1 Graphical Reports... 1 Trace task paths... 1 Easier view customization...
Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa
Project Creation and Gantt Chart Design Using Microsoft Project R. Baker The University of Tampa What is Microsoft Project? Microsoft Project is a software package designed help managers manage a variety
MS Project 2000 Tutorial: Introduction
MS Project 2000 Tutorial: Introduction - Anjana Srikanth Stylus Systems is a Internet Technology company located in Bangalore India. One of our mottos is "a quality process creates a quality product."
MSP How to guide session 2 (Resources & Cost)
MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or
Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by
Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones
Session 6. Microsoft Project. Emanuele Della Valle. http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza
Session 6 Microsoft Project Emanuele Della Valle http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza Credits 2 This slides are largely based on CEFRIEL s slides for PMI Certification and Prof.
Project Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.
Planning and Managing Software Projects 2011-12 Class 10 Hands on Microsoft Project (Part I) From a WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start
Project Management is the discipline of planning, organizing, and managing resources to complete a specific goal. Microsoft Project is software that helps you. Start your project Open Project 2010 and
Topics. Project plan development. The theme. Planning documents. Sections in a typical project plan. Maciaszek, Liong - PSE Chapter 4
MACIASZEK, L.A. and LIONG, B.L. (2005): Practical Software Engineering. A Case Study Approach Addison Wesley, Harlow England, 864p. ISBN: 0 321 20465 4 Chapter 4 Software Project Planning and Tracking
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft
NE-50413B Mastering Microsoft Project 2010
NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
MICROSOFT OFFICE PROJECT - SYLLABUS
MICROSOFT OFFICE PROJECT - SYLLABUS Sessions Session 1 Description 1. INTRODUCTION a. Introduction to CADFORUM and PPM b. Project c. Examples of project d. Project Triangle e. Project Management f. Life
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010 This document provides an introduction in using Microsoft Project 2010. Microsoft Project is a project management application that contains a set of tools to help
Planning and Managing Projects with Microsoft Project Professional 2013
Slides Slides Slides Steps to Enter Resource Types: 1. Click View and Resource Sheet 2. In the Type column of a resource, select Work, Material, or Cost, and press Enter on your keyboard Important
PERCEPTION PERT-PAC Using Microsoft Project 2000
PERCEPTION PERT-PAC Using Microsoft Project 2000 to Plan & Schedule A Training Tutorial (Sample Hull Block Construction) 1 This training tutorial outlines the basic features of the Microsoft Project 2000
Mastering Microsoft Project 2010
Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
Creating a New Project
Creating a New Project Microsoft Project is a project management software program designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets,
Microsoft Project 2007 Tutorial Boston University. Boston University, Dept of Administrative Sciences, Project Management Programs (2010)
Microsoft Project 2007 Tutorial Boston University Boston University, Dept of Administrative Sciences, Project Management Programs (2010) 1 2 Microsoft Project 2007 Tutorial Boston University Contents Table
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
Microsoft Project 70-178 Exam Study Guide
Microsoft Project 70-178 Exam Study Guide Prepared by The Versatile Company for MPUG. www.versatilecompany.com The Versatile Company, 2012. About this Study Guide This guide was developed based upon the
Project Management: Intermediate Microsoft Project 2010
Project Management: Intermediate Microsoft Project 2010 This document includes instructions for managing resources, updating project plans, and designing visual reports. Managing Resources in a Project
Microsoft Project Activity
Microsoft Project Activity Purpose: The goal of this activity is to lead you through the most important data entry and formatting activities in MS Project and to provide you with the fundamental knowledge
How To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows)
Project management M project tutorial Part 1: Project beginning and the Gantt chart Purpose Project management by using Microsoft Project software Introduction Project management is a process of organizing,
ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0
ECDL European Computer Driving Licence Project Planning Project Management Software BCS ITQ Level 2 Using Microsoft Project 2013 Syllabus Version 1.0 This training, which has been approved by BCS, The
Microsoft Project 2010 Advanced
Microsoft Project 2010 Advanced Table Of Contents SECTION 1 - REFRESH OF THE BASICS... 3 GUIDE INFORMATION... 4 Introduction... 4 How To Use This Guide... 4 Objectives... 4 Instructions... 4 PROJECT INFORMATION
Appendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2010-11 Session 6 Microsoft Project From the WBS to a Complete Schedule Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 These
technical tips and tricks
technical tips and tricks Looking for schedule variances Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart
Lesson 6 - Managing Resources in a Project Plan
Lesson 6 - Managing Resources in a Project Plan Lesson Objectives In this lesson, you will manage resources in a project plan. You will: Create a resource calendar. Assign resources to tasks. Assign additional
MICROSOFT PROJECT 2010 - II
MICROSOFT PROJECT 2010 - II Course Material This 2-day course is for intermediate and advanced users of the MS Project scheduling application who want to increase their capabilities managing projects in
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Applied Project Management ( APM )
Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and
Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project
Construction Planning, Equipment and Methods ENGI 8749 Fall Semester, 2008 Tutorial #2 Resource Leveling using MS Project Project Example Overview Microsoft Project, in addition to scheduling calculations,
Developing a Gantt and PERT Chart
Developing a Gantt and PERT Chart October 2004 Edition UNITAR-executed GEF Medium-Sized Project, on behalf of UNDP Table of Contents Module 1. Creating a Gantt Chart Using MS Project... 1 Introduction...
MS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado
CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado
Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)
Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the
1 Start a new project
Project Management Quick Reference Guide for Microsoft Project 2010 Before beginning a new project, an organization must determine whether the project fits its strategic goals. Executives should classify
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
Project Management Courses
"A well planned project will give results exactly as planned." Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the
Project 2010 Introduction
Microsoft Application Series Project 2010 Introduction Best STL Courses never cancelled: guaranteed Last minute rescheduling 24 months access to Microsoft trainers 12+ months schedule UK wide delivery
I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE
I N FO RM A T I O N T EC H N O L O G Y S ERV I C ES M I C ROSOFT PROJ EC T 2 0 1 0 T A S K M A N A GEM EN T LEARNING GUIDE Workshop Information Information Technology Services is happy to provide you with
Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015
Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2
Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems
Bradley University College of Liberal Arts and Sciences Department of Computer Sciences and Information Systems Computer Lab # 1 Time Management (with Microsoft Project 2007) Lab Manual (with master s
University of Sunderland. Microsoft Project. Basic Guide
University of Sunderland Microsoft Project Basic Guide 21/11/2008 A Course in using Microsoft Project Garry Storer Learning Objectives 1. What project management software is, basic concepts, the tasks
Project 2010. Quick Reference. The Assignment Equation. EPM Architects www.epmarchitects.com
The Assignment Equation The following equation controls the relationship between the Work, Duration, and Assignment Units for a task assignment: Or Or Work: The number of hours of real work effort spent
CLARITY PPM TIPS, TRICKS, and TERMINOLOGY
CLARITY PPM TIPS, TRICKS, and TERMINOLOGY Clarity PPM Knowledge Sharing Series Helping the Clarity PPM Community Members Benefit from Best Practice TABLE OF CONTENTS 1 OVERVIEW... 3 2 OVERVIEW PAGE...
Project planning with MindGenius
Project planning with MindGenius This workshop looks at using MindGenius for planning and monitoring smaller projects. MindGenius is available free of charge on all University of Brighton staff and student
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL INTRODUCTION Microsoft Project is a Windows-based project management software package. It provides the flexibility to help manage your project, provides assistance in every phase
CDC UNIFIED PROCESS JOB AID
Purpose The purpose of this document is to provide guidance on the practice of using Microsoft Project and to describe the practice overview, requirements, best practices, activities, and key terms related
Earned Value Analysis Exercise
Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)
Microsoft Project 2007 Level 1: Creating Project Tasks
Microsoft Project 2007 Level 1: Creating Project Tasks By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS Regardless of job title, most of us have needed to act as a project manager, at one time or another.
Mastering Microsoft Project 2013
Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals
www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP
PMBOK Guide 5 th Edition and MS Project 2010: A Practical Step-by-Step Approach 1. Abstract By Satya Narayan Dash, PMP, CSM, MCP Project Management Body of Knowledge (PMBOK) Guide, from PMI, comes with
MICROSOFT PROJECT SOFTWARE FOR THE PROJECT SCHEDULING
MICROSOFT PROJECT SOFTWRE FOR THE PROJECT SCHEDULING ŠÁRK ČEMERKOVÁ Silesian University in Opava School of usiness dministration in Karviná Department of Mathematical Methods in Economics Czech Republic
Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days
3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: [email protected] Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:
Project Management Courses
A well planned project will give results exactly as planned. Project Management Courses Professional Development Training has a specialised division of Project Management experts that will tailor the delivery
8. COMPUTER TOOLS FOR PROJECT MANAGEMENT
8. COMPUTER TOOLS FOR PROJECT MANAGEMENT The project management is a complex activity that requires among others: Information intercourse referred to the project, information that is in big amounts more
ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5
Table of Contents ABOUT THIS COURSE...3 ABOUT THIS MANUAL...4 EXCHANGING PROJECT PLAN DATA WITH OTHER APPLICATIONS...5 IMPORT A TASK LIST FROM AN EXCEL FILE INTO A NEW PROJECT PLAN... 6 Import a Task List
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Revealing the Secrets of Microsoft Project
2 Revealing the Secrets of Microsoft Project To know that one has a secret is to know half the secret itself. Henry Ward Beecher Topics Covered in This Chapter Recognizing the Underlying Rules of Project
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
Applied Software Project Management
Applied Software Project Management Project Schedules http://www.stellman-greene.com 1 What is a project schedule? The project schedule is a calendar that links the tasks to be done with the resources
QUICK START GUIDE RESOURCE MANAGERS. Last Updated: 04/27/2012
QUICK START GUIDE RESOURCE MANAGERS Last Updated: 04/27/2012 Table of Contents Introduction... 3 Getting started... 4 Logging into Eclipse... 4 Setting your user preferences... 5 Online help and the Eclipse
Microsoft Project 2013. Microsoft Project 2013. The smart way to learn. Microsoft Project 2013. one step at a time!
spine = 1.32 one step at a time! Experience learning made easy and quickly teach yourself how to manage the complete project life cycle with Project 2013. With Step by Step, you set the pace building and
LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)
LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) GOAL In this lecture, we ll learn: Background of Primavera Project Planner (P6) Getting Started P6 Interface Basic Navigation and Operation Setting
Project Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
4.0 - Using the Microsoft Project Plan
4.0 - Using the Microsoft Project Plan 153 4.0 - Using the Microsoft Project Plan 1.0 Introduction to PM 2.0 Plan Project 21 2.1 22 2.2 23 2.3 Prepare Estimates Develop WBS Develop Schedules 3.0 Manage
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3. User and Installation Guide
Virto SharePoint Gantt Chart App for Office 365 Release 1.0.3 User and Installation Guide 2 Table of Contents OVERVIEW... 3 FEATURES LIST... 3 SYSTEM/DEVELOPER REQUIREMENTS... 3 OPERATING SYSTEM... 3 SERVER...
How to use Microsoft Project? Basic Training to Help You during the BYI challenge
How to use Microsoft Project? Basic Training to Help You during the BYI challenge Table of Contents I. Main Concepts 1. Overview of Microsoft Project 2. Explanation of the main concepts II. How to : Create
Release Notes Assistance PSA 2015 Summer Release
Release Notes Assistance PSA 2015 Summer Release (August 2015) Advanced Opportunity Management The Microsoft Dynamics CRM Opportunity functionality has been extended with Assistance PSA functionality.
Planning and Managing Projects with Microsoft Project Professional 2013
Project management deliverables (e.g. reports); WBS deliverables can be used for report timing Steps to Create a Project from an Existing Template: 1. Click File then New. 2. Select any of the featured
Microsoft Project Server 2010 Project Manager s Guide for Project Web App
Microsoft Project Server 2010 Project Manager s Guide for Project Web App Copyright This document is provided as-is. Information and views expressed in this document, including URL and other Internet Web
Glossary. Release 13.3.00
Glossary Release 13.3.00 This Documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational purposes
Microsoft Project 2007 Level 2: Working with Resources and Managing a Project
Microsoft Project 2007 Level 2: Working with Resources and Managing a Project By Robin Peers Robin Peers, 2008 ABOUT THIS CLASS In Microsoft Project 2007 Level 1: Creating Project Tasks, the focus was
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
CA Clarity PPM. Glossary. Release 13.1.00
CA Clarity PPM Glossary Release 13.1.00 This Documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation ) is for your informational
ECDL / ICDL Project Planning Syllabus Version 1.0
ECDL / ICDL Project Planning Syllabus Version 1.0 Purpose This document details the syllabus for ECDL / ICDL Project Planning. The syllabus describes, through learning outcomes, the knowledge and skills
Project Management Quick Reference Guide for MS Project 2010
Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides
Tracking Project Progress
L E S S O N 2 Tracking Project Progress Suggested lesson time 45-55 minutes Lesson objectives To begin tracking an active project, you will: a b c Modify the environment for tracking. You will use the
Unit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may