ELECTRICAL INSPECTION BULLETIN (Effective 2000-03-01)



Similar documents
Questions and Answers for Heating and A/C Contractors

Top Commercial / Residential Electrical Requirements *

INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, Underground branch circuit feeding a detached garage:

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS

Electrical Grounding. Appendix C

SINGLE FAMILY DWELLING ELECTRICAL SERVICES RATED 225 TO 600 AMPS

RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS:

City of San Diego Residential Photovoltaic Systems Inspection Guidelines

GUIDELINES FOR WIRING SINGLE FAMILY DWELLING UNITS

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

Homeowner Information Guide Electrical Safety. British Columbia Safety Authority

ELECTRICAL - WIRING DESIGN AND PROTECTION SELF INSPECTION CHECKLIST

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings

City of Riverside Building & Safety Division Phone: (951)

SERVICE - GENERAL Residential, Commercial, Industrial

PORTABLE GENERATORS AND OSHA CONSTRUCTION REGULATIONS

MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS

Entrances to and from Electrical Equipment Rooms

Services. Three Phase Service

Grounding & Bonding Why it is done And How to Install Properly

Ontario Electrical Safety Code 25 th Edition/ 2012

Errata NFPA 70. Proposed 2014 Edition

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

County of Riverside Building and Safety Department

PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations.

Article 10 - ADMINISTRATIVE SECTION

Application Bulletin NEC Reference Guide for SolarBridge-Enabled AC Module Installers

Project Name: Nortrax Section Project No: SURGE PROTECTION DEVICES Page 1

MONTGOMERY COUNTY EXECUTIVE REGULATION Offices of the County Executive. 101 Monroe Street. Rockville, Maryland 20850

Mike Holt s Illustrated Guide to. Rule , Articles 445, 700, 701, and 702. Based on the 2011 NEC

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL (352) ; FAX: (352)

Electrical Contractors. and the. New Jersey. Rehabilitation Code

MASTER ELECTRICIAN CODE EXAMINATION EXAMINATION REFERENCE MATERIAL AND CONTENT OUTLINE. Answers to sample questions: CONTENT OUTLINE

Residential Electrical System Aging Research Project. Dave Dini Sr. Research Engineer Underwriters Laboratories

Enphase Microinverters and Ungrounded Renewable Energy Systems: Canadian Electrical Code Compliance

B. Related Sections: 1. Section Raceway and Boxes for Electrical Systems.

INSPECTION GUDELINES

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:

Please check with your local inspection authority for any additional requirements before installation.

AC Module Installation Guide Content

Electrical Extension Cords & Relocatable Power Taps: (RPT s)

Protect your home and family with Advanced Technology from Cutler-Hammer

White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code. June 2015 Revision 1.5

Installation Guide Content for P250xV-240 microinverters

Significant Changes in the 2011 NEC Prepared by Bryan Holland City of North Port

NEC 2014 Code Changes

Common Electrical Hazards in the Workplace Including Arc Flash. Presented by Ken Cohen, PhD, PE & CIH (Ret.)

Electrical Practices for Construction Work

The U.S. Department of Labor projects that electrician careers will grow to 698,200 by 2022.

Solar Panel Installations

CHAPTER 2 EXAMPLES AND TABLES

Residential Electrical Inspection. Checklist

ELECTRICAL SAFETY Information Bulletin

PROTECTION AGAINST ELECTRIC SHOCK by John Ware

San Diego Area Chapter International Code Council

Neutral Wire Facts and Mythology. White Paper #21

Electrical Service Guidelines

BLACK BOX. T1/E1 Link Extenders OCTOBER 2007 MT195A-T1 MT196A-E1

ELECTRICAL SAFETY: QUALIFIED/NON QUALIFIED

DC disconnects for solar photovoltaic installations. Connecting the. power of the sun

PREFACE. Your comments or suggestions are welcome and appreciated. They should be sent to:

CHECKING AND TESTING ELECTRICAL INSTALLING WORK

2011/2008/2005 NATIONAL ELECTRICAL CODE SOLAR PV CODE COMPLIANCE REFERENCE

IRRIGATION PUMPING Table of Contents - Section 900

A. Shop Drawing submittals shall include, but not be limited to, the following:

PV and the Electrical Code Page 1 PV and the Electrical Code

Construction Electrical Terminology. Electricians

TOP 10 CHANGES 2013 CALIFORNIA ELECTRICAL CODE 2013 CALIFORNIA ENERGY CODE (ELECTRICAL)

Electric Service Rules

Electrical Receptacle Outlet Reverse Polarity & Open Ground

Residential Electrical Inspection Checklist

How To Plan Out An Array Of Solar Panels


ELECTRICAL SAFETY. The standard unit for measuring electrical current.

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

ALUMINUM ELECTRICAL WIRING

Circuit Electrical Testing

Arc Fault Circuit Interrupters Frequently Asked Questions

By Mark Coles. This article looks at the temporary use of portable generators in floating, earthed and reference-earthing scenarios.

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems

Title: Grounding and Bonding Rev-01

SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches

PERMIT APPLICATION REQUIREMENTS FOR RESIDENTIAL ROOF MOUNTED PHOTOVOLTAIC SYSTEMS

CITY OF LOS ANGELES CALIFORNIA

Grounding of AC generators and switching the neutral in emergency and standby power systems

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

BERTHOLD ELECTRIC GENERATOR CONNECTION CABINET

Section 2 General Requirements

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1

Atlanta Chapter IEEE Industry Applications Society

Installation Instructions

Connecting the Power of the Sun. DC Disconnects for Solar Photovoltaic Installations. DC disconnects for. solar photovoltaic installations

2012 Canadian Electrical Code, Part I (CEC) Top Fifteen changes

Chapter 9. Bonding and Grounding

Electrical Hazards. Power Tools. Extension Cords

The National Armored Cable Manufacturers Association Presents. Installation Standard for Types AC and MC Cables

Transcription:

ELECTRICAL INSPECTION BULLETIN (Effective 2000-03-01) Rule 28-900 Standby Generator Installations Due to the increasing number of standby generator installations being established to maintain continuity of service to essential loads, should the normal supply fail or need to be removed from operation, the code requirements for transferring between the normal and standby generator supply and for grounding and bonding standby generators require some emphasis and clarification, as provided in this bulletin. The Nova Scotia Electrical Installation and Inspection Act and its Regulations requires that the installation of a standby generator system that is to be interconnected with a permanent electrical system, shall be performed under a wiring permit, by an electrical contractor, and shall be inspected. The requirement for a wiring permit and inspection shall not apply in those cases where an approved cord connected appliance is directly connected to the generator outlet. All equipment installed as part of a standby generator system shall be rated for its intended use and be approved by a recognized certification agency. For a list of certification agencies which are recognized in Nova Scotia, see the Office of the Fire Marshal Electrical Bulletin #98-02 entitled, Approval of Electrical Equipment or NSPI Electrical Inspection Bulletin B-2-024.1 Standby generator supply conductors shall not be installed in the same raceway with other service, feeder or branch circuit conductors as required by Rule 12-904(2). Standby generators shall be equipped with a disconnecting means as required by Rule 28-900. Transfer Switch Requirements: Where a standby generator is interconnected to a service entrance, a feeder or a branch circuit, an approved transfer switch must be installed in such a manner that no operation of the transfer switch will result in an inadvertent interconnection of normal and standby sources of supply which would allow the standby power to feed back into the utility system normal supply, as required by Rules 14-612 and 6-106. Where a transfer switch is to be connected to a main service or feeder or branch circuit, it shall be connected to the load side of the main service, feeder or branch circuit overcurrent device. A supply side connection will only be permitted when the transfer switch is marked as service entrance approved. The transfer switch shall be rated to meet load requirements. This rating shall be equivalent to the rating of the main service, feeder or branch circuit overcurrent device, or the standby generator amperes, whichever is greater Prepared by: Dan Marble Approved by: David Clements Page 1 of 6 March 2007 (Supersedes Mar 2000) B-28-900

Wiring Methods: Portable generator installations shall be equipped with a recessed male receptacle. The wiring between the transfer switch and this receptacle shall conform to the applicable CE Code requirements for fixed wiring methods. Flexible cord is not permitted between the transfer switch and recessed male receptacle. The receptacle may be located adjacent to the transfer switch or located outside on the building wall. When installed outdoors the receptacle shall be installed in a weatherproof outlet box complete with a weatherproof cover. Transfer switches having a factory installed recessed receptacle are acceptable. For connection of the portable generator to the recessed male receptacle, an outdoor flexible cord of the hard usage type will be required, which will be equipped with one female plug for the transfer switch receptacle or the outdoor receptacle connection, and one male plug for the portable generator connection. Acceptable flexible cord specifications may be obtained from Table 11 of the CE Code, Part 1. The recessed male receptacle shall be permanently labelled to identify the type of generator to be connected to the receptacle. Either Neutral Bonded to Frame Only or Neutral Floating Only Note: Anderson Plug devices are not CSA certified for standby generator connection applications. Such plugs are a potentially hazardous device, and will not be acceptable for use as a means of connecting a standby generator to a farm or premise wiring system within the NS Power Electrical Inspection area. Permanently installed standby generator systems shall be wired in accordance to the applicable CE Code Rules for fixed equipment. Grounding and Bonding Requirements: Fixed Standby Generator Neutral Grounding (Fig. 3) A standby generator neutral is to be grounded as required by the CE Code Rules 10-106, 10-206 and 10-210(a) (b). The CE Code requires that the grounded conductor (neutral) shall be grounded at only one point. Therefore, care must be exercised to ensure that this requirement is met for normal and for standby power supply operating conditions. The standby generator neutral shall be grounded at the supply side of the service disconnecting means, as required by Rule 10-204(1b). Furthermore, Rule 10-204(1d) requires that the grounded circuit conductor (neutral) is not to be connected to the service ground electrode on the load side of the service disconnecting means. The grounding of the standby generator neutral is accomplished by one of two possible methods. The method to be used will depend on whether or not the generator neutral is connected to the generator frame or case by the manufacturer. The status of this connection should be provided by the manufacturer, as required by CSA Standard C22.2 No 100-95, and should be indicated on the generator itself or in its documentation. Method 1: Generator Neutral Floating or Isolated from Frame (Fig. 2) The objective in this situation is to prevent the generator neutral from becoming isolated from the system ground electrode resulting in the standby power supply operating as an ungrounded system thereby violating Rule 10-106. For this case, to ensure the generator neutral is grounded to the main service ground electrode, the generator neutral shall be solidly connected to the normal supply neutral at the transfer switch. The neutral conductor shall not be switched at the transfer switch. This type of transfer switch will normally require a two pole design for a single phase system and a three pole design for a three phase system. Method 2: Generator Neutral Bonded to Frame (Fig. 1) Page 2 of 6 March 2007 (Supersedes Mar. 2000) B-28-900

The objective in this situation is to avoid installing a parallel circuit, including the neutral conductor and the bonding path, which would allow a portion of the normal load current to continuously flow through the equipment bonding path including the exposed non-current carrying metal enclosures. For this case, to ensure the neutral is connected to the ground electrode at only one point at any given time, the neutral connections shall be switched at the transfer switch. This type of transfer switch will normally require a three pole design for a single phase system and a four pole design for a three phase system. Equipment Bonding Requirements As required by Rules 10-400 and 10-408, an equipment bonding conductor shall be installed with the circuit conductors to bond all non-current carrying metal parts of the installation, including the standby generator frame, the transfer switch enclosure and the main service panel. For the case of the portable generator with its neutral bonded to frame, it should be noted that the bonding conductor in the flexible cord or cable shall be permitted to perform the function of the grounding conductor. The basic reason for this is that it is not practical to install a separate permanent grounding conductor in compliance with Rules 10-806 and 10-812 to a portable generator. Also it is not realistic to rely on the user to properly connect a separate grounding conductor at the generator. Although not technically in compliance with the Code, the intent of the Code is met by ensuring the portable generator s neutral is connected to a ground electrode. The circuit bonding conductor will be the same size as or one trade size smaller than the circuit conductors and will be adequate. The fixed standby generator shall be permanently bonded and grounded in compliance with the Code at the time of installation. See the figures provided in this bulletin showing the required bonding conductor connections for portable and fixed standby generator cases, where the generator neutral is bonded to the frame. Note: It should be noted that standby generators not equipped with a 120/240 volt, 4-wire bonding receptacle, are not intended for use as a standby generator for connection to a premises wiring system. It is not permitted to use the ground position of a generator 240 volt, 3-wire bonding receptacle as a combined neutral and bonding connection point. Page 3 of 6 March 2007 (Supersedes Mar. 2000) B-28-900

Page 4 of 6 March 2007 (Supersedes Mar. 2000) B-28-900

Page 5 of 6 March 2007 (Supersedes Mar. 2000) B-28-900

Fixed Standby Generator Figure 3: Bonding and Grounding for a Fixed Standby Generator, with the generator neutral bonded to the frame Note: If generator is floating neutral configuration, the neutral shall not be switched at the transfer switch. The generator frame shall be bonded to ground & sized as per Table 16. Page 6 of 6 March 2007 (Supersedes Mar. 2000) B-28-900