PMO-1.7 Cost Estimating. Project Management



Similar documents
Cost Estimating Procedure. Table of Contents

NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services

300 Scheduling and Budgeting

Head, Office of Project Management Oversight

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

CHAPTER 4 TYPES OF COST ESTIMATES

PROJECT COST MANAGEMENT

Quick Reference Guide Interactive PDF Project Management Processes for a Project

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

Project Integration Management

FAR Table Instructions for Submitting Cost/Price Proposals When Cost or Pricing Data Are Required

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011

Program Lifecycle Methodology Version 1.7

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Impact of PMBOK 5 th Edition

Assessment of NCTD Program Management Framework for Positive Train Control Program

Earned Value Management System (EVMS) Manual. System Description and Implementing Procedures

The 10 Knowledge Areas & ITTOs

FOREWORD. Page 2 of 88

Master Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope

Develop Project Charter. Develop Project Management Plan

Project Management Guidelines

Certification Exam Objectives: PK0-003

A Guide To The Project Management Body of Knowledge (PMBOK) Significant Changes from the 3 rd edition to the 4 th edition

The Program Managers Guide to the Integrated Baseline Review Process

Guidelines: Project Schedule Project Management Office (PMO)

PROJECT MANAGEMENT PLAN CHECKLIST

Accounting System. Page 1 of 9

PURCHASE ORDER TERMS AND CONDITIONS FOR MANUFACTURING MANAGEMENT PROGRAMS MIL-STD-1528A APPENDIX 2

Project Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997

Risk Management Plan template <TEMPLATE> RISK MANAGEMENT PLAN FOR THE <PROJECT-NAME> PROJECT

Baseline Change Control Procedure

Training Seminars. Description. Core Courses: The core courses consist of the following:

Project Management System Description (PMSD)

How to successfully manage your mega-project

Project Management Using Earned Value

Project Cost Management

Earned Value Management Systems Application Guide

Minnesota Health Insurance Exchange (MNHIX)

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

THE COMPLETE PROJECT MANAGEMENT METHODOLOGY AND TOOLKIT

Project Management Plan for

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Earned Value Management System Description

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

Earned Value Management Systems Application Guide

INTERNAL CONTROL MATRIX FOR AUDIT OF ESTIMATING SYSTEM CONTROLS Version No. 3.2 June d Page 1 of 7

Auditing Capital Projects and Project Controls. March 2013

PRODUCT DEVELOPMENT TRAINING COURSE

How To Write Ansi/Eia Evm System Acceptanceance Guide

Chapter 7. (PMBOK Guide)

Project Management Fundamentals. Office of the Senior Associate Vice President for Finance

Project Management Standards: A Review of Certifications/Certificates

A COMPARISON OF PRINCE2 AGAINST PMBOK

Project Management Guidebook

FedRAMP Standard Contract Language

Chapter 14 Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases

The Project Manager's Guide to Sarbanes-Oxley

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT Approval Date:

The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman)

Family Computer Centre

FAC-P/PM CROSSWALK FULFILLMENT OF REQUIRED COMPETENCIES THROUGH EXPERIENCE, PROFESSIONAL CERTIFICATION, AND/OR TRAINING. Professional Certification

Project Management Planning

SCOPE MANAGEMENT PLAN <PROJECT NAME>

TOPIC 12 CONTRACT COST AND PRICE ANALYSIS

Project Management Office (PMO)

PROCUREMENT, FABRICATION & CONSTRUCTION

Guidelines. Project Management Methodology. & Step-by-Step Guide to Managing Successful Projects

Project Management Certificate (IT Professionals)

6500m HOV Project Stage 1: A-4500 HOV

Robla School District

Risk/Issue Management Plan

Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

CRITICAL PATH METHOD (CPM) SCHEDULES

Superconducting Magnet Division

ACCOUNTS PAYABLE AUDIT RECOVERING LOST DOLLARS AT NO COST

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)

Project Cost Management

Job Manager for Metal Fabrication

A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition

CPM -100: Principles of Project Management

July 6, (1) CHAPTER 11

PMI PMP & CAPM sertifikacija

Services Contracts and Earned Value Management (EVM)

Project Management Planning

RSMeans Plumbing Estimating Methods. 3rd Edition

AACE International Recommended Practices

Paychex Accounting Online Terms of Use

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Cayo Software Reseller Agreement

Transcription:

Project Management Office Title: Section where used: PMO-1.7 Cost Estimating Project Management Prepared by Date Approved by Date Kurt Deshayes, LBNL EVMS Surveillance Officer Jim Krupnick, Laboratory Project Management Officer Revision Log: Rev. No. Effective Date Pgs. Affected Brief Description of Revision 0.0 June 1, 2005 All Original Document 1.0 February 2009 All Miscellaneous Updates, Review and Revisions to EIA-748B 1.0 PURPOSE This document describes the methodology for establishing cost estimates for projects managed by LBNL in a manner that is compliant with the standards for implementation of appropriate Project Management controls and Earned Value Management. 2.0 SCOPE Cost estimates, including Estimate to Complete (ETC), are prepared in a clear, consistent, comprehensive format that facilitates review of details and assumptions throughout the cost estimation process. Activities to be estimated are identified in sufficient detail to support the cost estimate methodology used. The objectives of the cost estimating process are to: (1) support the establishment of the Performance Measurement Baseline (PMB); (2) serve as the basis for change control; and (3) support the establishment of the ETC. Project cost estimates shall be traceable to documented sources and based on accepted methodologies. 3.0 REFERENCES DOE Order 413.3A. LBNL Earned Value Management System Description. Revision 1.0 - February 2009 1 of 6

PMO-1.7 Cost Estimating LBNL CFO Rate Book. PMO Procedure 1.2, Work Breakdown Structure (WBS). PMO Procedure 1.5, Control Account Plan/Work Authorization. PMO Procedure 1.6, Project Schedule. Indirect/Overhead Rates for collaborating institutions 4.0 PROCEDURE 4.1 Estimate Preparation and Review The estimate preparation phase begins with the issuance of guidance and instructions from the Project Manager and encompasses those activities that translate technical design and fabrication into detailed labor and procurement elements (organized by Work Breakdown Structure (WBS)) and identified costs. Labor rate tables, indirect costs, and escalation rates will be provided by Project Controls to assist Control Account Managers (CAMs) in budget development. The Project Manager will review this information and approve all budget plans prior to implementation. Escalation should generally be based on rates provided by the Department of Energy (DOE) as published in the LBNL Forward Pricing Sheet (aka CFO Rate Book). If work is being executed by collaborator or subcontractor in another geographic area where the escalation rates are different, rates for those areas should be used in lieu of the LBNL rates. Judgment should be used to verify the appropriateness of the published rate in light of current market conditions. Documentation of the rates used and the basis should be maintained. The resulting cost estimate should be analyzed for appropriate time-phasing with budget authority and budget outlay, consistent with the project appropriation profile, as directed by the Funding Agency. 4.1.1 Preparation of Detailed Estimate CAMs shall be responsible for preparing or obtaining cost estimates for Work Packages and Planning Packages. The CAMs will forward copies of the estimates to Project Controls for validation. 4.1.2 Cost Estimate Methodology The result of the project cost estimate process shall be the CAMs most current, detailed cost estimate, commensurate with design maturity. The CAM will use one of the approved methodologies: Revision 1.0 - February 2009 2 of 6

PMO-1.7 Cost Estimating A description of these methodologies is provided in the Appendix. CAMs should use Categories 1, 2, 3, and 7 when possible, especially for high-cost items, as this will provide maximum estimate support. The CAMs basis for all estimates will be documented for each project and retained by the Project Manager, with a copy provided to Project Controls. The documentation includes files to support project cost estimates (such as books, vendor quotes, engineering notes, memos, records of conversations with vendors, drawings, code output) with appropriate safeguards for proprietary information provided. Cost estimates are developed for each WBS element at the Work Package level or lower as deemed necessary by the CAMs. They shall be broken down by project phase, institution, and labor discipline as appropriate. Items and activities in the estimate shall be of sufficient detail to support interpretation by independent reviewers. When the project includes collaborating institutions, estimates prepared by non-lbnl CAMs shall use equivalent methodologies. 4.2 Documentation The Project Manager shall control supporting documentation and ensure that it is retained by WBS element. The Project Manager shall forward copies of the documentation to Project Controls. Proper care shall be given to protect business-confidential and proprietary information from unauthorized disclosure. Documents and records generated as a result of implementing this procedure shall be generated in a manner suitable for reproduction and signed and dated at the time of completion or approval. Official signed documents shall be retained by the Project Manager, with copies to Project Controls. Documents, records, and work papers shall include but not be limited to the following: Estimate spreadsheets. Work papers, including vendor quotes, telephone records, material take-offs, basis notes, calculations, etc. Analysis, such as contingencies, escalation application, and quantity discounts. Estimating codes, such as labor disciplines and phase codes. Application rates and associated application methodology. 4.3 Management Reserve/Contingency The Project Manager, CAMs, and other Stakeholders shall work together to determine a risk-based level of Management Reserve/Contingency. Revision 1.0 - February 2009 3 of 6

PMO-1.7 Cost Estimating 5.0 APPENDIX Appendix A: Cost Estimating Process Flow Diagram. Appendix B: Estimate Methodologies. Revision 1.0 - February 2009 4 of 6

Title APPENDIX A: Cost Estimating Process Revision 1.0 - February 2009 5 of 6

Title APPENDIX B: Estimate Methodologies Estimate Methodologies Code Type of Estimate Description 1 Catalog Listing or Industrial/ Construction Databases 2 Documented vendor Estimate Based on Drawings/Sketches and Specifications 3 Engineering Estimate Based on Drawings/Sketches and Specifications. 4 Engineering Estimated Based on Similar Items or Procedures 5 Engineering Estimate Based on Analysis 6 Expert Opinion (Engineering Allowance) This category will be used when most of the costs in an estimate can be documented from current vendor catalogs or from published or proprietary industrial or construction databases. The estimate is primarily based on vendor estimates obtained for the specific item or activity. To the extent possible, these estimates will be written rather than oral. If the latter, they will be documented. Such quotes by a vendor indicate that a design is sufficiently mature that its cost can be independently estimated (i.e., significant detail in drawings and specifications have been prepared), although the quotes will not be taken as an offer to sell at that price. Estimates in this category have the same level of detail available as in (2) above, but the estimates are done by an expert estimator at LBNL, or a subcontractor who is not likely to be a vendor. Estimates are chiefly based on items or activities that have previously been procured or undertaken. The basis for scaling up or down, or factoring (e.g., known cost sensitivities) should be documented in the Estimate Files. Given the variable degree of similarity between components of various LBNL projects, judgment must be used in selecting between (4) and (5). Estimates of items or procedures that are different from previous experience, and while sketches and specifications may exist, the level of detail is not sufficient to quality for (3) above. Some labor costs, such as assembly of an item not previously built, may fall into this category. Supporting background for procured items would include, for example, standard costs for fabricating a given material and the mass of material needed. This category should be used for items or procedures having little documented basis for the estimate. It indicates little confidence in the estimate. Its use should obviously be minimized in the final estimate. It will be used as the estimate preparation develops, however, to measure the maturity of the estimate at any given point. 7 Existing Lien A contract has already been awarded. Revision 1.0 - February 2009 6 of 6