Remediation Weekly Activity Summary Report Ameren LaSalle Former MGP - Soil Removal Action



Similar documents
Remediation Weekly Activity Summary Report Ameren LaSalle Former MGP - Soil Removal Action

SECTION 202. REMOVAL Of ROADWAYS AND BUILDINGS

City of Shelbyville Site Inspection Checklist

ONSITE SEWAGE TREATMENT AND DISPOSAL SYSTEM REQUIREMENTS

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Collection Systems Technology Fact Sheet Sewers, Conventional Gravity

Routine Maintenance and Inspection

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

5. Environmental Analysis

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT

FY08 SEWER POINT REPAIRS BID TABULATION

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

SANITARY SEWER BACKUP. Causes & Prevention

Specifications for Residential Property Owners Connection to New Public Sewer

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name

SILICON VALLEY CLEAN WATER. May 2015

VILLAGE OF GRANVILLE SEWER BACK-UP and WATER LEAK POLICIES

First in Service First in Safety

consulting engineers and scientists

Extreme Wet Weather in Brookfield. How to Keep Your Basement Dry During Heavy Rains and Floods

Lansdowne Stormwater UPDATE

CITY OF WASHINGTON SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN

International University of Monaco 27/04/ :55 - Page 1. Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday 04/05 Saturday 05/05

International University of Monaco 21/05/ :01 - Page 1. Monday 30/04 Tuesday 01/05 Wednesday 02/05 Thursday 03/05 Friday 04/05 Saturday 05/05

Construction Site Inspection Checklist for OHC By making use of some simple Best Management Practices (BMPs) a construction site operator can

MATCHDAY September 2014

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System

SECTION ABANDONMENT OF SEWER MAINS

Kansas City s Overflow Control Program

MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials

SEWER BACKUPS WHAT TO DO AND HOW TO PREVENT

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

San Luis Obispo County Los Osos Wastewater Project Development TECHNICAL MEMORANDUM SEPTAGE RECEIVING STATION OPTION TABLE OF CONTENTS

Wastewater Collection Practice Test #3 Page 1 of 15

Academic Calendar for Faculty

Concrete Waste Management

How To Get A Stormwater Discharge Permit In A City Of Scottsdale

HOW A SEPTIC SYSTEM FUNCTIONS

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

FINAL PLAN OF REMEDIAL ACTION

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

Ameren Callaway Energy Center-Water Treatment Plant Sedimentation Basins #5 &#6, MO , Construction Permit No. CP , Callaway County

Part 9 SUBDRAIN DESIGN AND LAYOUT

Designing a Zero-Waste Concrete Mix Testing Lab

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

WET/DAMP BASEMENTS ANSWER: BASEMENT WALLS AND FLOORS CAN BECOME WET BY A LEAK, CAPILLARY SUCTION OR CONDENSATION.

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

Most agencies think about cleaning because of debris in the line.

2006 Standard Application Processing Time. 10 months. 14 months

CONSTRUCTION AND DEMOLITION (C & D) Waste Management Plan Form:

Constructing Cistern Installations

Secondary Containment: Regulations & BMPs. Beth Powell Vice-President and General Manager New Pig Energy bethp@newpigenergy.com

Beseck Switching Station Inspection

A. Describe the existing drainage patterns on-site as shown on Map I, including any potential flooding and erosion problems.

IC24. DISPOSAL OF WASTEWATER GENERATED BY MOBILE BUSINESSES AND OUTDOOR ACTIVITIES

3.1.8 Utilities and Service Systems

L2571-AZE: Water Supply and Sanitation Investment Program Nakhchivan City Water Supply and Sewerage Subproject (Tranche 1)

WILDCAT CANYON ROAD SPECIFICATION NO SLIDE REPAIR BIDDER'S PROPOSAL (continued)

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

Construction Site Draina e

How To Install An Overhead Sewer

Permeable Pavers. calstone.com. Permeable Interlocking Concrete Pavements (PICP s)

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

PRIVATE WELL SEPARATION

Protect Your Home From Flooding. A guide for Lethbridge Residents

Protect your. home from. basement. have you done everything you can?

Practice Tests Answer Keys

SURFACE REMEDIATION AND MANAGEMENT OVERVIEW

SUMP PUMP DISCHARGES INFORMATIONAL PACKET

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1

Household customer. Wastewater flooding guidelines.

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

RESIDENTIAL SERVICES. compost recycle landfill

EFFECTIVE FEBRUARY note: drainage permit required to call for a dampproof inspection

STORM WATER PROJECT COST ESTIMATES & LOCATION MAPS. Appendix F

Transformer Deluge Systems

Section 402. STORM SEWERS

SAMPLE COPY. Stormwater Pollution Prevention Plan. A site map must be developed and must contain, at a minimum, the following information:

Improper storage of fuel on construction sites will increase the risk of water pollution that may occur as a result of leaks or spills.

SECTION SELECTIVE DEMOLITION

Mandatory Weeping Tile Disconnection to Reduce the Impact of Basement Flooding

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

SECTION 810 SEWER LINE CLEANING

Sanitary Sewer Master Plan

ENVIRONMENTAL HEALTH FACT SHEET NO. 500

Sewerage Management System for Reduction of River Pollution

Frequently Asked Questions about Septic Systems

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL Testing - General

ASBESTOS CEMENT PIPE: WHAT IF IT NEEDS TO BE REPLACED?

Transcription:

Remediation Weekly Activity Summary Report Ameren LaSalle Former MGP - Soil Removal Action Page 1 Period: August 11 through 17, 2014 (Week 48) PSC Project Number Completed By: Jeff Adams 624-1202-0012 General Remediation Activities Completed: PSC continued active onsite remediation activities, including completion of the Phase 9 and 10 backfill, and beginnning phase 11 excavation. The sketch on Page 2 shows the extent of the excavation and completed backfilling activities. A total of 3,561.82 tons of Construction Debris (0 tons this week) and 30,601.43 tons of Non-Source Material (1,688.26 tons this week) were removed and hauled to Republic Services-Ottowa, Illinois Landfill. A total of 3,768.71 tons of clay (0 tons this week) and 30,371.14 tons of rock (lime screenings, one-inch minus, and two to threeinch clean rock; 0 tons this week) have been hauled onsite to use as backfill material. In addition, 471.90 tons of clean one-inch stone (0 tons this week) have been brought in to address the haul roads and parking areas. Approximately 4,000 gallons of water removed from the excavation are currently containerized, while approximately 484,300 gallons (20,300 this week) have been hauled offsite for disposal. Monday - August 11th: Completed backfilling and compaction of the Phase 9/10 excavation with lime screenings from LaFarge's Utica Quarry. Phase #11 was prepared for excavation. Approximately 1,000 gallons of water was pumped into the onsite storage from the excavation. QLF continued aeration of the stormwater basin using an air compressor and hauled 2 loads of ammonia impacted water from the basement for offsite disposal. Water is being hauled from the frac tanks offsite to PDC. Tuesday - August 12th: Began excavation of phase #11, Soil must be excavated to a stockpile and then loaded, due to proximity to overhead lines. Approximately 3,000 gallons of water was pumped into the onsite storage from the excavation. QLF continued aeration of the stormwater basin and hauled 2 loads of ammonia impacted water from the basement for offsite disposal. Bodine hauled water from the frac tanks offsite to PDC. Kaskaskia Engineering Group (KEG) was onsite to evaluate the site layout to develop sewer bypass design. Wednesday - August 13th: Continued excavation of phase #11. Approximately 3,000 gallons of water was pumped into the onsite storage from the excavation. Water is being hauled from the frac tanks offsite to PDC. QLF continued to haul ammonia impacted basement water offsite for disposal (2 loads), and continued aeration of the stormwater basin. Thursday - August 14th: Continued excavation of phase #11. Approximately 3,000 gallons of water was pumped into the onsite storage from the excavation. Water is being hauled from the frac tanks offsite to PDC; all frac tanks have been emptied at the end of the day. QLF continued to haul ammonia impacted basement water offsite for disposal (3 loads), and continued aeration of the stormwater basin by spraying water again. Friday - August 15th Continued excavation of phase #11. QLF continued to haul ammonia impacted basement water offsite for disposal (3 loads), and continued aeration of the stormwater basin by spraying water again. A local haul truck has been added so that the requested number of haul trucks are being supplied by the landfill. Saturday - August 16th: No site work performed. Health & Safety Activities: Weather Conditions: H&S Issues/Other: Out of Scope Items: None Mostly sunny with some clouds and high temperatures from the 70s to the 90s. Discussed being in the wrong place, line of fire, following to closely and general safety. occurred. No recordable accidents or incidents

Remediation Footprint and Excavation Progress Map Ameren LaSalle Former MGP - Soil Removal Action Page 2 Period: August 11 through 17, 2014 (Week 48) PSC Project Number 624-1202-0012 Completed By: Jeff Adams

Air Monitoring Activity Summary Report Ameren LaSalle Former MGP - Soil Removal Action Period: August 11 through 17, 2014 (Week 48) PSC Project Number Completed By: Chris Dawdy Page 3 624-1202-0012 4 4 3 4 3

Air Monitoring Station Locations Ameren LaSalle Former MGP - Soil Removal Action Page 4 Period: August 11 through 17, 2014 (Week 48) PSC Project Number 624-1202-0012 Completed By: Jeff Adams

Project Milestones Summary Report Ameren LaSalle Former MGP - Soil Removal Action Period: August 11 through 17, 2014 (Week 48) PSC Project Number Completed By: Jeff Adams Page 5 624-1202-0012 Project Milestones Actual Quantities Weather: Prior Total: This Period: Total To Date: Rainfall (inches) 29.72 0.00 29.72 Snowfall (inches) 60.15 0.00 60.15 Material Type: Project Estimates Original: Revised: Solid Waste Material: Construction & Demolition Debris-Republic (tons) 3,561.82 0.00 3,561.82 0 0 MGP Impacted Soil (Non Source)-Republic (tons) 28,913.17 1,688.26 30,601.43 120,000* 0 MGP Impacted Soil (Source)-PDC (tons) 0.00 0.00 0.00 0 0 TOTAL 32,474.99 1,688.26 34,163.25 0 0 Addt. Solid Waste Material: Clean Brick-Canon Pit (loads) 111.00 0.00 111.00 0 0 Asbestos Containing Material (ACM)-Republic (tons) 1,240.00 0.00 1,240.00 0 0 Scrap Material (loads) 8.00 0.00 8.00 0 0 Clean Material: CM-06, 1-Inch Minus (tons) 15,056.95 0.00 15,056.95 0 0 Lime Screenings (tons) 13,277.26 0.00 13,277.26 CS-02, 2 to 3-Inch Clean Stone (tons) 2,036.93 0.00 2,036.93 0 0 2-Inch Clean Stone (tons) 0.00 0.00 0.00 0 0 1 1/2-Inch Rock (tons) 0.00 0.00 0.00 0 0 4 to 8-Inch Rip Rap (tons) 0.00 0.00 0.00 0 0 4-Inch Crushed Concrete (tons) 0.00 0.00 0.00 0 0 Stone Backfill Subtotal 30,371.14 0.00 30,371.14 0 0 CA-7, 1-Inch Clean Stone (tons) 471.90 0.00 471.90 0 0 Clean soil backfill (tons) 3,768.71 0.00 3,768.71 0 0 Top Soil (cubic yard) 0.00 0.00 0.00 0 0 TOTAL 34,611.75 0.00 34,611.75 0 0 Treated Wastewater: Discharged to PDC (gallons) 464,000 20,300 484,300 0 0 * MGP Impacted Soil volume is data presented in the site investigation report. Trucks Transporting: Monday Tuesday Wednesday Thursday Friday Issues Actually Received 0 2 3 3 3 Requested 0 3 2 2 3

Page 6 Cement plug in abandoned concrete storm sewer in SW corner of Phase 9/10 Looking southeast, Phase #11 ready to begin excavation.

Page 7 Looking northwest, southeast corner of Phase #11. 4" diameter pipe running North-South through Phase #11, with MGP impact inside.

Page 8 Dozer pushing material under power line to excavator for loading Looking South, Excavation of Phase #11.

Page 9

Page 10

Page 11