Generator Interconnection Low Voltage Network Upgrade Cost Recovery. Issue paper & straw proposal

Similar documents
GIDAP Cluster Process Updated February 2014

Applicability and Eligibility

145 FERC 61,172 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Network Upgrades andSIAs Under California Tariff Clarifications

Generator Interconnection and Deliverability Study Methodology Technical Paper

Renewable Energy Transmission Planning Process (RETPP) Second Draft Final Proposal

Interconnection Process Enhancements (IPE) Draft Final Proposal

CAISO Resource Adequacy Deliverability for Distributed Generation

145 FERC 61,151 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

CALIFORNIA ISO BUSINESS PRACTICE MANUAL (BPM) FOR GENERATOR INTERCONNECTION AND DELIVERABILITY ALLOCATION PROCEDURES (GIDAP)

Issue Paper & Initial Straw Proposal. Settlement Timeline Bridge

Intentionally left blank

Memorandum. This memorandum requires Board action. Executive Summary

Tehachapi Renewable Transmission Project (TRTP)

Addressing Affected System Impacts of Generator Interconnection: Processes and Principles. Stakeholder Call August 23, :30 a.m. - 12:00 p.m.

Tehachapi Wind Energy Storage Project (TSP)

NV Energy ISO Energy Imbalance Market Economic Assessment

Alternative Options for the Availability Standard and Replacement Rule components of the Standard Capacity Product II Initiative March 18, 2010

SCHEDULE 1. Scheduling, System Control and Dispatch Service

135 FERC 61,068 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING PETITION FOR TEMPORARY WAIVER. (Issued April 22, 2011)

SAN DIEGO DISTRIBUTED SOLAR PHOTOVOLTAICS IMPACT STUDY. Final Report

Welcome to the SDG&E Renewable Market Adjusting Tariff (Re-MAT) Program Overview Webinar

Recent Developments in US-Mexico Electricity Trade: A Tale of Two Borders

New ISO-NE Return on Equity Rate Could Impact Future Transmission Decisions

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

APPENDIX VIII FORMULA FOR CALCULATING ANNUAL BASE TRANSMISSION REVENUE REQUIREMENTS UNDER SDG&E S TRANSMISSION OWNER TARIFF

1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) /02/2014 Chris Ong All Reformatting of initial version

Advancing and maximizing the. Technology. December 2014

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Introduction to The Trans Bay Cable Project

AAPG 2011 Annual Convention & Exhibition April 10, 2011

California ISO Straw Proposal. Ancillary Services Procurement in HASP and Dispatch Logic

ELECTRICITY FINAL BUDGET AND FEES:

ALCOA POWER GENERATING INC. Long Sault Division. Open Access Transmission Tariff

Natural Gas Pipeline Penalty Recovery Issue Paper

Opportunities for Biogas Digesters

Aliso Canyon Gas-Electric Coordination. Issue Paper

Business Requirements Specification

FERC Workshop on Price Formation: Scarcity and Shortage Pricing, Offer Mitigation, and Offer Caps in RTO and ISO Markets (Docket. No.

Generation and Transmission Interconnection Process

Corporate Renewable Energy Procurement: Industry Insights

ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Energy Imbalance Market

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

PG&E and Renewable Energy. Chuck Hornbrook Senior Manager Solar and Customer Generation

TRANSMISSION MAINTENANCE COORDINATION COMMITTEE (TMCC) MINUTES January 16, 2014 Meeting from ISO Headquarters Folsom, California

Net Energy Metering and the Future of Distributed Generation

2017 Budget and Grid Management Charge Initial Stakeholder Meeting

Gas transport tariffs calculation

ELECTRICITY FINAL BUDGET AND FEES:

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Updated November 20, Director, System Planning

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

B.9 Terms for Delivering Electricity to Power-intensive Users at Voltages below 132 kv 1

How To Answer The Six Cities' Protest Against The Power Line Project

ESDER Implementation and TeMix Comments

143 FERC 61,246 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market

Section 1: Executive Summary

104 FERC 61,128 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

The Commonwealth of Massachusetts

ENERGY ADVISORY COMMITTEE. Electricity Market Review: Return on Investment

New York s Transmission Challenges and Opportunities: An Overview

PG&E Corporation. UBS Natural Gas, Electric Power and Coal Conference March 5, 2009

132 FERC 61,083 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING AND INSTITUTING SECTION 206 PROCEEDING

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW

MEMORANDUM. March 9, 2007

149 FERC 61,012 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER AUTHORIZING ISSUANCES OF SECURITIES. (Issued October 3, 2014)

Addendum Combined Heat and Power Revisions to the CPUC GHG Calculator Revised Report

State Planning Agency, Tribal Utilities & Renewable Energy Regime in California

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

How To Get A Refund From The Utilities Commission

THE CURRENT BALANCE. The Role of Cost, Reliability, and Environmental Impact in the Massachusetts Electricity Market

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

Affidavit Of Charles A. Smart

Diverse Business Enterprises ( DBE ) Readiness Checklist to Sell Wholesale Power to SCE June 25, 2013

Quail Brush Power Plant is Wrong Approach for San Diego - Local Solar Is the Right Solution. Bill Powers, P.E. Powers Engineering September 21, 2012

SDG&E and Its Illustrative Rate Summary Form

May 26, Governor Charlie Baker Massachusetts State House Office of the Governor Room 280 Boston, MA 02133

Table of Contents. Real-Time Reliability Must Run Unit Commitment and Dispatch (Formerly G-203) Operating Procedure

133 FERC 61,224 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Customer Services and the Changing Needs of the CA Electricity Grid. Stanford University May 5, 2015

Template for Submission of Comments on Convergence Bidding and Bid Cost Recovery

Alberta Reliability Standard Cyber Security Security Management Controls CIP-003-AB-5

EXPLANATORY MEMORANDUM TO THE CONTRACTS FOR DIFFERENCE (ELECTRICITY SUPPLIER OBLIGATIONS) REGULATIONS No. [XXXX]

THE NARRAGANSETT ELECTRIC COMPANY OPTIONAL LARGE DEMAND BACK-UP SERVICE RATE (B-62) RETAIL DELIVERY SERVICE

RULES AND REGULATIONS FOR FINANCING PROJECTS AND COMMERCIAL ACTIVITIES

League of Women Voters of California Education Fund Energy Update Study Guide

SOLAR POWER IN SANTA CLARA COUNTY MARKETS AND DEVELOPMENT TRENDS

Job Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15-

Southern California Edison IEC (Corp ID 6096) Status of Advice Letter 157 As of September 29, Disposition: Effective Date: Accepted

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

Network Code on Harmonised Transmission Tariff Structures for Gas

Comments of the Pennsylvania Department of Environmental Protection

151 FERC 61,108 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING PROPOSED TARIFF REVISIONS. (Issued May 11, 2015)

BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION

2014 EIA Energy Conference. Edward Randolph Director, Energy Division California Public Utilities Commission

Benjamin A. Stafford. February 12, 2010

Transcription:

Generator Interconnection Low Voltage Network Upgrade Cost Recovery Issue paper & straw proposal August 1, 2016

Table of Contents 1 Introduction and Background... 3 2 Stakeholder process... 4 3 Straw Proposal... 4 4 Next steps... 8

Generator Interconnection Low Voltage Network Upgrade Cost Recovery 1 Introduction and Background The ISO tariff requires Participating Transmission Owners (PTOs) to reimburse interconnection customers (ICs) whose generators are interconnecting to their systems for the costs of reliability 1 and local deliverability network upgrades necessary for the interconnection. The PTOs then include those network upgrade reimbursement costs in their regulator-approved rate bases, requiring ratepayers to pay those costs through either low- or high-voltage transmission access charges (TAC). Network upgrades 200 kv and above are considered high-voltage and upgrades below 200 kv are considered lowvoltage. The high-voltage TAC is a postage stamp rate based on the aggregated transmission revenue requirements ( TRR ) of all PTOs for all high-voltage facilities on the ISO system. In contrast, the low-voltage TAC is PTO-specific, charged only to customers within the service area of the PTO who owns the facilities. As such, if a large generator or a large number of generators with significant low-voltage network upgrade costs interconnect to a PTO with a relatively small rate base, that PTO s rate base may increase significantly and can result in rate shock to its ratepayers. The requirement for the individual PTO to reimburse low-voltage network upgrade costs is unrelated to where the interconnecting generators intend to sell their energy or capacity. Thus a PTO with a relatively small rate base could experience a significant cost increase related to the interconnection of generators that intend to supply load-serving entities located throughout the ISO footprint. In such circumstances passing these large costs entirely to the small PTO s ratepayers can result in a substantial increase to the local or low-voltage TAC rate, even when the local ratepayers may not receive commensurate benefit from the added generation. This issue has come to light recently in the Valley Electric Association (VEA) area. There are a number of generation developers seeking to connect hundreds of MWs of renewable generation to the VEA 138 kv system that will require tens of millions of dollars in network upgrades on that system. As an example, adding $25 million of costs to VEA s low-voltage rate base would increase VEA s low-voltage TAC rate by over 90 percent for a system whose annual peak load is only approximately 124 MW. The ISO agrees that this would impose an unreasonable impact on VEA s ratepayers and is therefore opening this initiative to consider alternatives. Although this initiative was triggered by the need to limit extreme impacts on a small PTO s low-voltage TRR and TAC, the options presented in this paper would be applied to all PTOs in the ISO system. 1 Reimbursement for reliability network upgrades (RNU) is limited to $60,000 per installed MW of capacity; there is no limit on reimbursement for costs of other qualifying network upgrades. M&ID Page 3

2 Stakeholder process Timely resolution of this issue is critical as there are many interconnection customers that are currently in the study process or generation interconnection agreement (GIA) negotiation phase and are dependent on the outcome of this stakeholder process. Therefore, the ISO has set out the following accelerated stakeholder process schedule and appreciates stakeholder understanding and participation in this effort. Stakeholder process schedule Step Date Activity Draft Issue Paper/Straw Proposal Revised Straw Proposal Draft Final Proposal August 1, 2016 August 8, 2016 August 19, 2016 September 6, 2016 September 13, 2016 September 20, 2016 October 3, 2016 October 10, 2016 October 17, 2016 Post Issue Paper/Straw Proposal Stakeholder web conference Stakeholder comments due Post Revised Straw Proposal Stakeholder web conference Stakeholder comments due Post Draft Final Proposal Stakeholder web conference Stakeholder comments due Board approval December 14/15, 2016 ISO Board of Governors meeting 3 Straw Proposal The ISO has carefully considered this issue and is proposing the options discussed below for stakeholder consideration. Each option will require tariff changes. Importantly, the ISO believes that it is essential that any solution to this issue be compatible with and retain the fundamental design and features of the Generation Interconnection and Deliverability Allocation Procedures (GIDAP), Appendix DD of the ISO Tariff, specifically: Two-phase cluster-study approach with annual reassessments; Cost certainty to interconnection customers early in the study process through cost caps; and Reliability and local deliverability network upgrades would continue to be reimbursed to interconnection customers upon commercial operation in accordance with the GIDAP. For this reason, the ISO is not proposing options that would, for example, shift network upgrade costs to the interconnection customers who trigger them. Doing so would represent a fundamental paradigm shift for generation development and capacity M&ID Page 4

procurement in the ISO region, and likely would raise some of the myriad issues with which other regions struggle. 2 Options 1 and 2 provide two approaches for mitigating potentially large impacts of lowvoltage interconnection-driven upgrades on the ratepayers of a small PTO. Either option would, of course, apply consistently to all PTOs. Under these proposals the PTOs would maintain their cost allocations for generator-triggered network upgrades already in service, and would apply whichever option is adopted going forward. The transition could, for example, be based on any network upgrades not in service at or near the time the revised tariff provisions go into effect. In any case, the CAISO proposes that revisions resulting from this stakeholder process would have immediate effect on a going-forward basis. Option 1 Include the cost of generator-triggered low-voltage facilities in the PTO s highvoltage TRR for recovery through the high-voltage TAC. This option recognizes that generators provide energy to the ISO markets for the entire region, and generally support public policy goals including resource adequacy, reliability, and renewable generation. The conceptual approach here is that once interconnected to the ISO controlled grid (whether above or below 200 kv), it is connected to the ISO market and benefits all ISO ratepayers, not just those in the local area. This option would apply to all PTOs, is straightforward, and would be fairly simple to implement. For reference, there are currently 90 active generation interconnection projects in the CAISO queue with executed Generation Interconnection Agreements (GIAs). There also are a number of projects that are currently in GIA negotiations with PG&E, SCE, SDGE and VEA. Table 1 below shows the estimated dollar amount for low- and high-voltage reliability and local deliverability network upgrade costs for 90 active projects with executed GIAs in the CAISO interconnection queue and 5 projects interconnecting to VEA that have either Phase-I or Phase-II cost information for network upgrades. VEA has yet to execute a GIA. PTO Table 1 Estimates of Low & High-Voltage RNU and LDNU Costs ($ millions) Number of active projects with executed GIAs Total estimated Lowvoltage (<200kV) network upgrade costs Total estimated highvoltage ( 200kV) network upgrade costs PG&E 38 $76.23 $77.36 SCE 34 $1.85 $696.23 SDGE 18 $7.49 $30.82 VEA 5 3 $9.12 $17.46 2 See American Wind Energy Association, Petition for Rulemaking, FERC Docket No. RM15-21-000 (July 7, 2015). 3 Since VEA has yet to execute a GIA the amounts shown are for the 5 active VEA projects that have either Phase-I or Phase-II cost information for network upgrades. M&ID Page 5

Also for reference, Table 2 shows the current annual low and high-voltage TRRs as of 3/1/2016. Table 2 4 Current Annual Low & High-Voltage TRRs as of 3/1/2016 PTO Filed Annual HV TRR ($) Filed Annual Gross Load (MWh) HV Utility Specific Rate ($/MWh) TAC Rate TAC Amount Filed Annual LV TRR ($) LV Utility Specific Rate ($/MWh) Utility Specific Combined TAC PG&E $607,131,854 90,445,937 $6.7126 $11.1337 $1,006,995,411 $769,307,250 $8.5057 $15.2184 SCE $1,004,417,227 90,511,765 $11.0971 $11.1337 $1,007,728,318 $40,241,005 $0.4446 $11.5417 SDGE $469,609,354 20,824,991 $22.5503 $11.1337 $231,858,623 $298,854,329 $14.3508 $36.9010 Anaheim $29,372,296 2,507,620 $11.7132 $11.1337 $27,919,019 $11.7132 Azusa $3,163,102 257,416 $12.2879 $11.1337 $2,865,985 $12.2879 Banning $1,274,841 144,652 $8.8132 $11.1337 $1,610,508 $8.8132 Pasadena $14,679,975 1,231,980 $11.9158 $11.1337 $13,716,461 $11.9158 Riverside $32,665,860 2,180,985 $14.9776 $11.1337 $24,282,372 $14.9776 Vernon $2,973,458 1,181,728 $2.5162 $11.1337 $13,156,972 $2.5162 DATC Path 15 $25,407,824 $11.1337 Startrans IO $3,587,536 $11.1337 TBC $118,857,411 $11.1337 $9,117,184 $0.1008 5 Citizens Sunrise $11,783,984 $11.1337 Colton $3,485,980 372,179 $9.3664 $11.1337 $4,143,719 VEA $11,934,201 544,970 $21.8988 $11.1337 $6,067,517 $3,413,410 $6.2635 $28.1623 Total $2,340,344,903 210,204,223 $11.1337 $2,340,344,906 $1,120,933,178 $3,461,278,084 4 This table can be found in the following document: http://www.caiso.com/documents/highvoltageaccesschargerateseffectivemar1_2016.pdf 5 The LV utility specific rate for TransBay Cable is derived by dividing the LV TRR by PG&E s gross load, as Trans Bay Cable does not have a load service area, and its low voltage costs are recovered from PG&E customers. M&ID Page 6

If VEA required $25 million in low voltage network upgrade costs, the approximate impact on VEA s low-voltage TAC would be an increase of about $5.87/MWh (from $6.26/MWh to $12.13/MWh), a 94% increase. 6 As mentioned above, this would be a significant impact on VEA ratepayers for facilities that do not provide VEA ratepayers with a commensurate benefit. However if this $25 million were shared across the system and reflected in the high-voltage TAC rate, it would be an increase of $0.0152/MWh (from $11.1337/MWh to $11.1489/MWh), a 0.14% increase shared by all ISO ratepayers. 7 Because this option would be applied to all PTOs, not just VEA, if PG&E required that same $25 million for low voltage network upgrade costs, the approximate impact on PG&E s low-voltage TAC would be an increase of about $0.0355/MWh, from $8.5057/MWh to $8.5412/MWh, a 0.4% increase. 8 Option 2 Split the cost recovery for low-voltage interconnection-driven upgrades between the low-voltage and high-voltage TAC. The split would depend on one of the following approaches to limit increases in a PTO s low-voltage TRR or TAC, with any additional TRR above the limit added to the PTO s high-voltage TRR. a) Place a cap on the share of interconnection-driven upgrades in each PTO s lowvoltage rate base (low-voltage transmission original cost less depreciation). The cap could be based on one-year and/or multi-year calculations (e.g., no more than X% increase annually and/or Y% every five years, where X < Y). b) Limit the incremental revenue requirement increase due to interconnection-related upgrades as a percentage of the PTO s low-voltage annual TRR (using a model like the incremental revenue requirement model the ISO uses in annual TAC calculations). Basing the limit on the impact on TRR, rather than on net rate base, provides a more direct assessment of impact on customers, as not all revenue requirement costs are derived directly from rate base. c) Limit the incremental revenue requirement increase due to interconnection-related network upgrades as a percentage of the high voltage TAC revenue recovered from the PTO s customer base (for load serving PTOs). This last method would make sense because it limits exposure of a local area group of customers to a percentage of their high voltage TAC payments. As such, a utility twice the size of another could reasonably absorb twice the local impact of interconnection-related low 6 The ISO estimated the impact of a $25 million capital expenditure utilizing the existing spreadsheet model used to estimate the impact of transmission capital expenditures on the Regional (High Voltage) Transmission Access charge and employed in the 2015-2016 Transmission Plan. The assumptions are consistent with that model, and using a 10% ROE and 5% social discount rate. The impact over the first 10 years was levelized over the 10 year period, including the mid-year impact on rate base of the first year of operation. This produced an estimate of $3.2 million annual levelized revenue requirement, or 12.8% of the capital expenditure. This provides a reasonable approximation of the impact which varies in each year due to depreciation and other impacts. $3.2 million divided by the VEA load of 544,970 MWh is $5.87/MWh. 7 $3.2 million divided by total ISO load of 210,204,223 MWh equals $0.0152/MWh. 8 $3.2 million divided by PG&E load of 90,445,937 MWh equals $0.0354/MWh M&ID Page 7

voltage network upgrades compared to a utility with a much smaller customer base. Separating this percentage from the low-voltage rate base thus avoids the complexity of two utilities like PG&E and SCE having different approaches that lead to different amounts of sub-transmission costs being recovered through the local (low-voltage) TAC versus being considered distribution tariffs, or utilities that happen to have more or less sub-transmission for relatively comparable loads. Table 3 illustrates a Comparison of a 5% limit for Option 2b (limit based on local TRR) versus Option 2c (limit based on high voltage TAC revenue collection). Note that Option 2a would have very similar results to Option 2b. Table 3 Comparison of a 5% Limit for Option 2b versus Option 2c (Option 2a would have similar results to Option 2b) Utility Local Low- Voltage Revenue Requirement Regional High Voltage TAC revenue collected Impact of 5% Limit Based on Local TRR (Option 2-b) Based on Regional TAC revenue (Option 2-c) Limit on LV Limit on Limit on upgrade incremental Limit on LV incremental capital costs Annual LV upgrade capital Annual LV assigned to the TRR impact costs assigned to TRR impact PTO * the PTO * PG&E $769,307,250 $1,006,995,411 $38,465,363 $300,510,645 $50,349,771 $393,357,582 SCE $40,241,005 $1,007,728,318 $2,012,050 $15,719,143 $50,386,416 $393,643,874 VEA $3,413,410 $6,067,517 $170,671 $1,333,363 $303,376 $2,370,124 Limit 5% * assuming annual TRR is approximately 12.8% of the capital investment 4 Next steps As a next step, the ISO will conduct a conference call to discuss this issue paper and straw proposal on August 8. The ISO then invites stakeholders to submit comments on the ISO s draft issue paper/straw proposal. Comments are due August 19 and should be submitted to InitiativeComments@caiso.com. Following review and evaluation of the comments received, the ISO will consider potential revisions to its proposal and issue a revised straw proposal on September 6. M&ID Page 8