STANDARD SPECIFICATIONS SECTION TEMPORARY BYPASS PUMPING SYSTEMS

Similar documents
Construction Specification for Sewer Bypass Flow Pumping

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Sewer Line Rehabilitation

INSTALLATION OF INSITUFORM LINER

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

CLEANING, INSPECTION, AND TESTING OF SEWERS

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

Section 2100-Trenching and Tunneling

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

SECTION SANITARY SEWER PIPE

DESCRIPTION OF WORK:

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

SANITARY SEWER SPECIFICATIONS

SECTION IX SLIP LINING PIPELINES

Wastewater Capital Projects Management Standard Construction Specification

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SECTION CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

SECTION 603 SANITARY SEWER FORCE MAINS

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

SECTION GRAVITY SANITARY SEWERS

Section 402. STORM SEWERS

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer

SECTION POLYVINYL CHLORIDE (PVC) PIPE

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

STANDARD SPECIFICATIONS SECTION SEWER MAIN AND LATERAL CONNECTION SEALING BY CHEMICAL GROUT

SECTION STORM DRAINAGE TABLE OF CONTENTS

SECTION FACILITY STORM DRAINAGE PIPING

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

FY08 SEWER POINT REPAIRS BID TABULATION

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

EVENT ATTACHMENT C

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

Emerging Technologies in Wastewater Collection Systems

SECTION HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS

DIVISION 4300 STORM DRAINAGE

SECTION PRECAST CONCRETE UTILITY STRUCTURES

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

General Guidelines for Repairing Buried PE Potable Water Pressure Pipes

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

725-R-599 PIPE LINING. (Revised ) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE

C. Section TESTING LABORATORY SERVICE.

DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.

OAR52 A-1 (September, 1981)

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

STANDARD SPECIFICATIONS SECTION CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

Guideline Specification for the Replacement of Mainline Sewer Pipes By Pipe Bursting

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

ORDINANCE NO. 15 BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

LS 2540 SEWER LATERALS AND INSPECTION TEES

STANDARD SPECIFICATIONS SECTION CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL Testing - General

SECTION STORM DRAINAGE SYSTEM

EFFECTIVE FEBRUARY note: drainage permit required to call for a dampproof inspection

SANITARY GRAVITY SEWER LINE TESTING. B. Section CCTV Inspection of Gravity Sewer Lines

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

ITD Pipe Materials Selection & Specification Procedures. July 2011

SANITARY SEWER SYSTEM ASSESSMENT

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET

Let Us Give Utilities the Respect that they Deserve.

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

Date Prepared: By: Wastewater Best Practices Subgroup Final Document:

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

CHAPTER 11 STORM DRAINAGE

Recommended Fuel Piping Specification For UPP Piping, UL-971

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

Jay R. Smith Mfg. Co.

Downspout to storm sewer. Leaky laterals

Type of Sewer Systems. Solomon Seyoum

Town House Center Highway North Huntingdon, PA 15642

FY15 Gravity Sewer and Manhole Rehabilitation

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

SECTION STORM DRAIN SYSTEM

SECTION 3 SANITARY SEWER DESIGN

OVER-HEAD SEWER ASSISTANCE GRANT

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

SECTION ABANDONMENT OF SEWER MAINS

Transcription:

STANDARD SPECIFICATIONS SECTION 02960 TEMPORARY BYPASS PUMPING SYSTEMS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for implementing a temporary pumping system for the purpose of diverting existing sewage flow around work area for duration of the project. 1.2 QUALITY ASSURANCE A. Follow national standards and as specified herein. B. Perform leakage and pressure tests on discharge piping using clean water, before operation. Notify Engineer 24 hours prior to testing. C. Maintain and inspect temporary pumping system every two hours. Responsible operator: on site when pumps are operating. D. Keep and maintain spare parts for pumps and piping on site, as required. E. Maintain adequate hoisting equipment and accessories on site for each pump. 1.3 SUBMITTALS A. Submit following Section 01330. 1. Detailed plan and description of proposed pumping system. Indicate number, size, material, location and method of installation of suction and discharge piping, size of pipeline or conveyance system to be bypassed, staging area for pumps, site access point, and expected flow. a. Size and location of manhole or access points for suction and discharge hose or piping. b. Sections showing suction and discharge pipe depth, embedment, select fill and special backfill, if buried. c. Temporary pipe supports and anchoring required. d. Thrust and restraint block sizes and locations. e. Sewer plugging method and type of plugs. f. Bypass pump sizes, capacity, number of each size to be on site and power requirements. g. Backup pump, power and piping equipment. h. Calculations of static lift, friction losses, and flow velocity. Pump curves showing pump operating range. 02960-1 July 2013

i. Design plans and computation for access to bypass pumping locations indicated on drawings. j. Calculations for selection of bypass pumping pipe size. k. Method of noise control for each pump and/or generator. l. Method of protecting discharge manholes or structures from erosion and damage. m. Schedule for installation and maintenance of bypass pumping lines. n. Procedures to monitor upstream mains for backup impacts. o. Procedures for setup and breakdown of pumping operations. p. Emergency plan detailing procedures to be followed in event of pump failures, sewer overflows, service backups, and sewage spillage. 1) Maintain copy of emergency plan on site for duration of project. B. Submit following Section 01450. 1. Certify bypass system will meet requirements of codes, and regulatory agencies having jurisdiction. 1.4 CONTRACTORS RESPONSIBILITY FOR OVERFLOWS AND SPILLS A. Schedule and perform work in manner that does not cause or contribute to incidence of overflows, releases or spills of sewage from sanitary sewer system or bypass operation. 1.5 DELIVERY AND STORAGE A. Transport, deliver, handle, and store pipe, fittings, pumps, ancillary equipment and materials to prevent damage and following manufacturer s recommendations. 1. Inspect all material and equipment for proper operation before initiating work. B. Material found to be defective or damaged due to manufacturer or shipment. 1. When Engineer deems repairable: Repair as recommended by manufacturer. 2. When Engineer deems not repairable: Replace as directed by Engineer before initiating work. 3. Repair or replacement of defective or damaged material and equipment will be at no cost to Commission. PART 2 PRODUCTS 2.1 MATERIALS A. Discharge and Suction Pipes: Approved by Engineer. 1. Discharge piping: Determined according to flow calculations and system operating calculations. 2. Suction piping: Determined according to pump size, flow calculations, and manhole depth following manufacturer s specifications and recommendations. 02960-2 July 2013

B. Polyethylene Plastic Pipe: 1. High density solid wall and following ASTM F714 Polyethylene (PE) Plastic Pipe (SDR-DR) based on Outside Diameter, ASTM D1248 and ASTM D3550 2. Homogenous throughout, free of visible cracks, discoloration, pitting, varying wall thickness, holes, foreign material, blisters, or other deleterious faults. C. High-Density Polyethylene (HDPE). 1. Homogenous throughout, free of visible cracks, discoloration, pitting, varying wall thickness, holes, foreign material, blisters, or other deleterious faults. a. Defective areas of pipe: Cut out and joint fused as stated herein. 2. Assembled and joined at site using couplings, flanges or butt-fusion method to provide leak proof joint. Follow manufacturer s instructions and ASTM D 2657. a. Threaded or solvent joints and connections are not permitted. 3. Fusing: By personnel certified as fusion technicians by manufacturer of HDPE pipe and/or fusing equipment. 4. Butt-fused joint: True alignment and uniform roll-back beads resulting from use of proper temperature and pressure. a. Allow adequate cooling time before removal of pressure. b. Watertight and have tensile strength equal to that of pipe. c. Acceptance by Engineer before insertion. 5. Use in streams, storm water culverts and environmentally sensitive areas. D. Flexible Hoses and Associated Couplings and Connectors. 1. Abrasion resistant. 2. Suitable for intended service. 3. Rated for external and internal loads anticipated, including test pressure. a. External loading design: Incorporate anticipated traffic loadings, including traffic impact loading. 4. When subject to traffic loading, compose system, such as traffic ramps or covers. a. Install system and maintain H-20 loading requirements while in use or as directed by the Engineer. E. Valves and Fittings: Determined according to flow calculations, pump sizes previously determined, and system operating pressures. F. Plugs: Selected and installed according to size of line to be plugged, pipe and manhole configurations, and based on specific site. 1. Additional plugs: Available in the event a plug fails. Plugs will be inspected before use for defects which may lead to failure. G. Aluminum irrigation type piping or glued PVC piping will not be permitted. H. When approved by Engineer, discharge hose will be allowed in short sections. 2.2 EQUIPMENT 02960-3 July 2013

A. Pumps. 1. Fully automatic self-priming units that do not require the use of foot-valves or vacuum pumps in priming system. 2. Electric or diesel powered. 3. Constructed to allow dry running for long periods of time to accommodate cyclical nature of effluent flows. 4. Provide. a. Necessary stop/start controls for each pump. b. One standby pump of each size maintained on site. 1) On-line, isolated from primary system by a valve. c. Quiet flow pumps at request of Engineer. 2.3 DESIGN REQUIREMENTS A. Bypass pumping systems: 1. Sufficient capacity to pump peak flow of 15 mgd. a. Peak flows greater than 15 mgd as approved by Engineer. b. Commission will provide flow data for bypass system. 2. Operate 24 hours per day. B. Provide pipeline plugs and pumps of adequate size to handle peak flow, and temporary discharge piping to ensure total flow of main can be safely diverted around section to be repaired. PART 3 EXECUTION 3.1 PUBLIC NOTIFICATION A. Follow Section 01110. 3.2 PREPARATION A. Determining location of bypass pipelines. 1. Minimal disturbance to existing utilities. a. Field locate existing utilities in proposed bypass area. 2. Obtain approvals for placement within public or private property. 3. Obtain Engineer s approval of location. 4. Costs associated with relocation of utilities and obtaining approvals at no cost to the Commission. 3.3 INSTALLATION AND REMOVAL A. Provisions and requirements must be reviewed by Engineer before starting construction. 02960-4 July 2013

B. Remove manhole sections or make connections to existing sewer and construct temporary bypass pumping structures at access location indicated on Drawings and as required to provide adequate suction conduit. C. Plugging or blocking of sewage flows shall incorporate a primary and secondary plugging device. When plugging or blocking is no longer needed for performance and acceptance of work, remove in a manner that permits the sewage flow to slowly return to normal without surge, to prevent surcharging or causing other major disturbances downstream. D. When working inside manhole or force main, exercise caution. Follow OSHA, Local, State and Federal requirements. Take required measures to protect workforce against sewer gases and/or combustible or oxygen-deficient atmosphere. E. Installation of Bypass Pipelines: 1. Pipeline may be placed along shoulder of roads. a. Do not place in streets or sidewalks. 2. When bypass pipeline crosses local streets and private driveways, place in roadway ramps. a. When roadway ramps cannot be used, place bypass in trenches and cover with temporary pavement as approved by Engineer. b. Follow Section 02510. F. During bypass pumping operation, protect sewer lines from damage inflicted by equipment. G. Upon completion of bypass pumping operations, and after the receipt of written permission from Engineer, remove piping, restore property to pre-construction condition and restore pavement. PART 4 MEASUREMENT AND PAYMENT 4.1 Except as otherwise specified herein, providing for and complying with requirements in this Section will not be measured for payment, but cost will be considered incidental to Contract. **WSSC** 02960-5 July 2013