Recommended Fuel Piping Specification For UPP Piping, UL-971
|
|
|
- Dominic Frederick Weaver
- 9 years ago
- Views:
Transcription
1 Recommended Fuel Piping Specification For UPP Piping, UL General The primary delivery piping system shall be for suction or pressure applications and have semi-rigid coaxial type double wall construction, with the primary pipe loosely fitting into the secondary pipe. This loose fit allows for detection and containment of any eventual leak from the primary pipe into the secondary pipe. All pipe and fittings are designed for direct burial and pipe runs can be joined without the use of transition sumps. Direct buried fittings shall be true double wall construction with no bridging from the primary to the secondary pipe. Secondary fittings shall be pressure rated for a minimum of 50 psig. The piping system shall be compatible with chemicals naturally found in the ground and resistant to bacterial attack. Piping shall be supplied in flexible coils for longer pipe runs with no joints where feasible, or in sticks for conventional piping installations. All pipe, fittings and penetration fittings are to be listed by Underwriters Laboratories UL971 and ULC/ORD-C for Nonmetallic Underground Piping for Flammable Liquids and approved for use for Normal Vent, Vapor Recovery and Product Piping. All piping shall meet the UL971 standard for all four test fuels: MV, CT, HB, AM (see section 3.0 for description). Where desired coaxial or single wall pipe may be installed within a 4" dual layer thermoplastic corrugated pipe chase to permit replacement of the pipe without the need of excavation. Pipe shall be available in 1.5" thru 4" diameter and provide bend radius, burst pressures, pressure ratings, vacuum ratings and operational temperatures as listed in Table A below. Piping used for vapor recovery shall be CARB approved. All fittings, penetration fittings and pipe couplers shall be an electrofusion type and made of HDPE material. Fittings, include couplers, elbows, tees, termination fittings with integral nickel plated brass threads, unions or flanges and penetration fittings. Only fittings supplied by the manufacturer may be used and shall carry the UL971 listing. All fittings and pipe which are electrofused may only be fused using the fusion welder supplied by the manufacturer. The electrofusion welder shall be a constant current welder and shall automatically recognize the type and size of fitting along with the ambient temperature when connected to apply the correct amount of energy to provide a successful weld. This automated welder alleviates any operator adjustments to provide a successful weld. Field bonded, swedged, glued or mechanical joined pipe and fittings shall not be allowed. Page 1 of 6
2 Table A. Penetration fittings when used in conjunction with HDPE tank, dispenser or transition sumps shall be the 300 electrofusion series as manufactured by UPP, made of HDPE and fusion welded only. Use of rubber style penetration fittings is not allowed. When tank, dispenser or transition sumps are made of fiberglass construction, penetration fittings shall be the FEB series as manufactured by UPP to provide a rubber-less entry fitting. Secondary containment terminating reducers used for terminating the secondary piping to the primary piping inside of tank, transition or dispenser sumps shall be made of HDPE and fusion welded only. Terminating reducer shall include an integral test port for use in future testing of the secondary containment piping system. Test ports may have internal valves removed to provide draining of primary pipe leaks into low point accumulation sumps. Size Description Weight In Lbs/ft Pressure 75 F (Psig) Ave Burst 75 F Bend 75 F Operation Temp 1 ½" 1 ½" 1 ½ Double Wall Pipe- 33ft 1 ½ Double Wall Pipe- 33ft Primary Secondary ½" 1 ½ Double Wall Pipe-165ft Coil Primary ½" 1 ½" Double Wall Pipe-165 ft Coil Secondary " 2" Double Wall Pipe-33 ft Primary " 2" Double Wall Pipe- 33 ft Secondary " 2" Double Wall Pipe- 38 ft Primary " 2" Double Wall Pipe- 38 ft Secondary " 2" 3" 3" 2" Double Wall Pipe- 100 ft 165 ft Coil 2" Double Wall Pipe- 100 ft 165 ft Coil 3" Double Wall Pipe- 19 ft-38 ft 3" Double Wall Pipe-19 ft-38 ft Primary Secondary Primary Secondary " 4" Double Wall Pipe-19 ft Primary " 4" Double Wall Pipe-19 ft Secondary " 3" 2" Single Wall Vent/Vapor-19 ft 3" Single Wall Vent/Vapor-19 ft Primary Primary Page 2 of 6
3 2.0 References NFPA 30, Flammable and Combustible Liquids Code NFPA 30A, Code for Motor Fuel Dispensing Facilities and Repair Garages NFPA 37, Stationary Combustion and Gas Turbines Underwriters Laboratories UL-971 PEI/RPI-100 Recommended Practices for Installation of Underground Liquid Storage Systems PEI/RPI-200 Recommended Practices for Installation of Aboveground Storage Systems for Motor Vehicle Fueling PEI/RPI-800 Recommended Practices for Installation of Bulk Storage Systems USEPA 40 CFR Parts 280 & 281 Federal UST Standards PPI Plastic Pipe Institute NYCFD New York City Fire Department C of A Approval # Compatibility The piping system and fittings shall be resistant to all of the following: A. Motor Vehicle Fuels (MV) - petroleum based hydrocarbon fuel typically found in consumer dispensing, boiler operations, and emergency generation systems using gasoline or diesel fuels including blended fuels with a maximum 15% MTBE or Methanol or 30% Ethanol. B. Concentrated Fuels (CT) - Alternate un-blended fuels for up to 100% concentrations of Toluene, Methanol and Ethanol. C. High Blend Fuels (HB) - Fuels with higher than normal gasoline blends with maximum 50% Methanol or Ethanol. D. Aviation and Marine Fuels (AM) - Specialty aviation and Marine use fuels for up to 100% kerosene or leaded gasoline 4.0 Underground Piping- Materials and construction Primary & Secondary Pipe and Fittings Material-All primary piping shall be a single-wall UPP brand, as manufactured by Franklin Fueling Systems. All primary piping shall have a pressure rating of 90 psig and a vacuum rating of 26.6 inches of Hg. All secondary containment piping shall be UPP brand, as manufactured by Franklin Fueling System. All secondary containment piping shall have a pressure rating of 58 psig and a vacuum rating of 15 inches of Hg. The primary pipe shall consist of three integrated layers: Black outer structural layer of the pipe is a High Density Polyethylene (HDPE) grade, PE80 or PE100 which allows the use of electrofusion couplers and fittings to construct the pipeline system. The intermediate layer is a tie-layer (adhesive) which permanently bonds the polyethylene layer to the polyamide barrier layer. The yellow inner barrier layer of UPP Extra pipe is specially formulated fuel proof Polyamide which is resistant to absorption and permeation of all motor fuels as described in section 3.0. Page 3 of 6
4 4.1 Fittings All primary couplings, sump entry fittings, and miscellaneous piping appurtenances shall be UPP brand for double-wall, as manufactured by Franklin Fueling Systems. The fittings shall be permanently attached to the primary pipe by electrofusion (or as otherwise specified by the manufacturer). All secondary containment fittings, sump entry fittings and test boots shall be UPP brand as manufactured by Franklin Fueling Systems, and shall allow for 100% inspection of the primary joint pressure test before being be fully air-testable itself. 5.0 Delivery, Storage and Handling: Pipe and fittings shall be protected from damage due to impact and point loading. Pipe shall be properly supported to avoid damage due to flexural strain. The contractor shall not allow dirt, debris or other extraneous materials to get into the pipe and fittings. 6.0 Installation and Training: The piping system shall be installed as specified on contract drawings or at the discretion of the installing contractor to provide a complete pipe conveyance system as required for the project. Pipe sizes shall be as shown on the contract drawings. All pipe and fittings installed or constructed in the field shall be assembled and fusion-welded by employees of the contractor who have been trained and certified by the manufacturer. When required, the pipe manufacturer's authorized trainer shall train the contractor s employees in the proper assembly and fusion-welding procedures necessary for the project. The piping system shall be installed in strict accordance with the manufacturers current installation published installation instructions. The installing contractor shall be responsible for all necessary specialty tools and consumables required for a complete testable piping installation. 7.0 Testing Underground Product Piping 7.1 General Contractor shall notify, where required, any authorities having jurisdiction in advance of any piping tests. Prior to pressure testing, the piping must be isolated from any tanks, pumps, boilers or dispensers. An air pressure test must be performed on the primary and secondary piping to detect any leaks that may exist. Test pressure to be in accordance with UPP Product Installation Manual. All testing shall be in compliance with the pipe manufacturer s installation instructions. 7.2 Prior to Backfill All new piping shall be tested before being covered, enclosed, or placed into service. Test pressure to be in accordance with UPP Product Installation Manual. On double-wall secondary piping systems, after the inner pipe test has been concluded, the contractor must pressure test the secondary containment piping at the air pressure required by the local inspector. 7.3 After Backfilling After backfilling, all underground primary lines shall be tested with a precision testing system by a third party independent testing company. 7.4 Tightness Certificate Upon completion of the test, the Contractor shall provide a Certificate of Tightness to the Owner prepared by the independent testing company. Page 4 of 6
5 8.0 Tank, Transition and Dispenser Sumps All Tank Sumps, Transition Sumps and or Dispenser Sumps shall be made of HDPE and manufactured or otherwise as recommended by Franklin Fueling Systems. 9.0 Acceptable Manufacturer and Products: All pipe, fittings and specialty components for a complete fuel delivery system shall be as manufactured by Franklin Fueling Systems and branded as the UPP pipe system or an approved equal Warranty The piping system manufacturer shall provide a warranty against defects in the pipe and fittings. Refer to Franklin Fueling Systems warranty document #FFS Page 5 of 6
6 2011 FFS Rev 1 Franklin Fueling Systems LTD 8 Olympus Close Whitehouse Industrial Estate Ipswich, Suffolk IP1 5LN United Kingdom Tel: Fax:
STANDARD FOR SECONDARY CONTAINMENT TESTING OF UNDERGROUND STORAGE TANK SYSTEMS I. INTRODUCTION
SANTA FE SPRINGS DEPARTMENT OF FIRE-RESCUE Environmental Protection Division Certified Unified Program Agency 11300 Greenstone Ave, Santa Fe Springs, CA 90670 Phone (562) 944-9713 Fax (562) 941-1817 STANDARD
NFPA31FuelOilPiping 1 Revised 3-1-11
NFPA 31 Fuel Oil Piping, Installation and Testing Chapter 8 Fuel Piping Systems and Components 8.1 Scope. This chapter shall apply to piping systems and their components used to transfer fuel oil from
List of Frequently Utilized Storage Tank Standards and Practices
List of Frequently Utilized Storage Tank Standards and Practices Below is a list of frequently used storage tank standards and practices from organizations that are referenced in 25 PA Code, Chapter 245.
DRAFT REVISED 2015. Musts For USTs DRAFT. Printed on Recycled Paper. Updated June 2015
DRAFT REVISED 2015 Musts For USTs DRAFT Printed on Recycled Paper EPA wrote this booklet for owners and operators of underground storage tanks (USTs). This booklet describes the 2015 revised federal UST
Ethanol Vehicle and Infrastructure Codes and Standards Citations
Ethanol Vehicle and Infrastructure Codes and Standards Citations This document lists codes and standards typically used for U.S. ethanol vehicle and infrastructure projects. To determine which codes and
ALL UST SYSTEMS. MOTOR FUEL, USED OIL, BULK HEATING OIL STORAGE (Federal/State Regulated Systems)
FACTS ABOUT: UST SYSTEMS COMPLIANCE OUTLINE Maryland Department of the Environment In Maryland, certain UST systems must meet various compliance requirements. The following is a summary of the current
Maryland Containment System Testing Protocol. The individual performing the inspection and testing as outlined in this protocol must be either:
MARYLAND DEPARTMENT OF THE ENVIRONMENT Oil Control Program, Suite 620, 1800 Washington Blvd., Baltimore MD 21230-1719 4 410-537-3442 410-537-3092 (fax) 1-800-633-6101 http://www.mde.state.md.us Maryland
PIPES AND TUBES FOR HVAC PIPING AND EQUIPMENT
PIPES AND TUBES FOR HVAC PIPING AND EQUIPMENT GENERAL INFORMATION 1.1 This section applies to piping systems for chilled water, hot water, condenser water, steam, condensate return, fuel oil, refrigerant
SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION
SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density
Secondary Containment Options for Aboveground and Underground Tanks. Wayne Geyer Steel Tank Institute
Secondary Containment Options for Aboveground and Underground Tanks Wayne Geyer Steel Tank Institute Secondary containment tanks first appeared in the United States in the early 1980's, when several local
Fuels Safety Program. Liquid Fuels Handling Code Adoption Document Amendment
Fuels Safety Program Liquid Fuels Handling Code Adoption Document Amendment Ref. No.: FS-207-14 Date: IN THE MATTER OF: Technical Standards and Safety Act 2000, S.O. 2000, c. 16, and Ontario Regulation
CHECKLIST FOR INSTALLING OR CONVERTING EQUIPMENT TO DISPENSE E15, E30 E85 AND OTHER BLENDS OF ETHANOL General Information:
CHECKLIST FOR INSTALLING OR CONVERTING EQUIPMENT TO DISPENSE E15, E30 E85 AND OTHER BLENDS OF ETHANOL General Information: Is your project an equipment conversion, station remodel or new construction?
Application for the Construction or Installation of Aboveground Storage Tank (AST) Systems or Associated Underground or Over-water Piping Systems
Page 1 of 5 Application for the Construction or Installation of Aboveground Storage Tank (AST) Systems or Associated Underground or Over-water Piping Systems New Hampshire Department of Environmental Services
UST RULES CHANGES. Heather Peters, Environmental Specialist
UST RULES CHANGES Heather Peters, Environmental Specialist Today s Topic 2011 Rule package- what s left? Upcoming rule changes Federal Regulation Changes & Testing Protocols How are you doing? 2011 Rule
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe
Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene
Section A SPCC Plan Implementation Checklist This section of the report addresses compliance with certain requirements of Federal Regulations 40 CFR 112. I. STATUS OF SPCC PLAN (40 CFR 112.3) YES NO A.
Technical Requirements for Aboveground Storage Tanks (ASTs) Storing Class IIIB Liquids (other than used oil)
Technical Requirements for Aboveground Storage Tanks (ASTs) Storing Class IIIB Liquids (other than used oil) References: Comm 10 2009 EDITION / NFPA 30 2008 EDITION ITEM DESCRIPTION Comm 10 / NFPA General
Below Grade Spill Containment Manholes 705-5 Gallon 715-15 Gallon 725-25 Gallon. Installation Instructions
Below Grade Spill Containment Manholes 705-5 Gallon 715-15 Gallon 725-25 Gallon Installation Instructions Warning Application and use of this product should be in compliance with local, state, and federal
PETROLEUM DISPENSING. Catalog #06-130 Supersedes Catalog #03-130. Air & Multipurpose General Purpose Heavy Duty Push-on.
PETROLEUM DISPENSING Purpose CUL + Vapor Coupled Page UL Approved Stage II Assist Balance Wire Textile Lengths Aggie Gas 141 Yes Yes Ambassador 142 Yes Yes Yes Arctic Softwall 143 Yes Yes Yes BC Gasoline
September 2008 AFC 4.6.2.1.(2) Page 1 of 5. Maximum Size and Aggregate Capacities of Aboveground Storage Tank Systems at Fuel Dispensing Stations
FIRE CODE VARIANCE September 2008 AFC 4.6.2.1.(2) Page 1 of 5 ISSUE Maximum Size and Aggregate Capacities of Aboveground Storage Tank Systems at Fuel Dispensing Stations The Alberta Fire Code (AFC) limits
Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank
Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank This specification describes requirements for a Diesel Fuel Day Tank System consisting of one or more fuel tanks, an Electronic
Morrison Bros. Co. General Product Specifications
Morrison Bros. Co. General Product Specifications Tank Mounted Spillbox The spill containment device is manufactured to contain spills and drips that may occur at the fill point on aboveground storage
Town House 11265 Center Highway North Huntingdon, PA 15642
APPENDIX C SPECIFICATIONS FOR THE CONSTRUCTION OF BUILDING LATERAL SANITARY SEWERS DECEMBER 2004, INCLUDING AMENDMENTS ADOPTED ON FEBRUARY 6, 2008 AND APRIL 2, 2008; EFFECTIVE ON MAY 1, 2008 Town House
Northern Region. Underground Storage Tank
California CUPA Northern Region Presents Underground Storage Tank Designated Operators Workshop Workshop Agenda Definitions Tank Construction Corrosion Protection Spill Prevention Overfill Prevention Piping
DIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
SUBMERSIBLE PUMPING SYSTEMS SUBMERSIBLE TURBINE PUMPS
1/3 & 3/4 Hp Fixed Speed Submersible Turbine Pumps Marketers concerned about fueling times, efficiency, serviceability, reliability and overall quality find it an easy choice to specify FE Petro brand
A GROUNDWATER PROTECTION PLAN FOR HOME HEATING OIL TANKS
A GROUNDWATER PROTECTION PLAN FOR HOME HEATING OIL TANKS What is a groundwater protection plan? A groundwater protection plan identifies the activities being conducted that can pollute groundwater and
Waste Oil Collection / Storage
ENVIRONMENTAL & REGULATORY SERVICES Storage Tank Regulation Section P. O. Box 7837 Madison, Wisconsin 53707-7837 TDD #: (608) 264-8777 http://www.commerce.state.wi.us http://www.wisconsin.gov Jim Doyle,
NFPA 30-2008: Basic Requirements for Storage Tanks
NFPA 30-2008: Basic Requirements for Storage Tanks New York City Metro Chapter Society of Fire Protection Engineers New York, NY February 22, 2011 NFPA 30, Flammable and Combustible Liquids Code Storage
MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION
Oxford Hills Bus Garage 36 Brown St, Norway, ME Oil Storage Inspection 2/20/14 CONDITIONS OBSERVED Underground Oil Storage: 12,000 gallon underground oil storage tank (split 10,000 gallon diesel/2,000
BP WIND ENERGY POLICIES AND PROCEDURES
BP WIND ENERGY POLICIES AND PROCEDURES Document Control Details 1.0 Purpose/Scope 1.1 This procedure provides the minimum requirements to be followed for the storage of flammable or combustible materials
The following definitions apply with regard to requirements specified in this document:
GUIDELINES FOR INSTALLATION OF TEMPORARY AND PERMANENT ABOVEGROUND DIESEL FUEL TANKS FOR EMERGENCY AND STANDBY POWER SYSTEMS LOCATED OUTSIDE OF BUILDINGS For Use by Unidocs Member Agencies or where approved
Straight Talk On Tanks Leak Detection Methods For Petroleum Underground Storage Tanks And Piping
Straight Talk On Tanks Leak Detection Methods For Petroleum Underground Storage Tanks And Piping Printed on Recycled Paper Contents Do You Have Questions About Leak Detection?...1 An Overview Of Leak Detection
Underground Storage Tank Operational Compliance Field Guide
Underground Storage Tank Operational Compliance Field Guide Created April 2012, Reaffirmed April 2015 Bureau of Underground Storage Tank Regulations http://www.com.state.oh.us/fire/default.aspx Department
UltraTech International, Inc. Canadian Secondary Containment Requirements
UltraTech International, Inc. 11542 Davis Creek Court Jacksonville, Florida 32256 Canadian Secondary Containment Requirements The Canadian Council of Ministers of the Environment (CCME) is the major intergovernmental
Grade Level Spill Containment Manholes
Grade Level Spill Containment Manholes Installation Instructions 705-5 Gallon 715-15 Gallon 725-25 Gallon Manual # Revision Date Changes from Previous Revision F-1307 7 Mar. 2012 Removed reference to pipe
TYPICAL FIRE SAFETY INSPECTION VIOLATIONS
TYPICAL FIRE SAFETY INSPECTION VIOLATIONS The following is a list of typical violations often found by inspectors and a generic solution. You can use this list to improve the safety of your facility, to
MOTOR FUEL DISPENSING SAFETY
STRATEGIC OUTCOMES PRACTICE TECHNICAL ADVISORY BULLETIN January 2010 MOTOR FUEL DISPENSING SAFETY Fire! Not an alarm anyone wants to hear, especially not when the fire is burning at a major fuel source.
How To Safely Handle A Spill
WD DWGB 22 6 2010 Best Management Practices for Fueling and Maintenance of Excavation and Earthmoving Equipment Env Wq 401, Best Management Practices for Groundwater Protection, applies to a variety of
This page left intentionally blank
1 This page left intentionally blank 2 STATE OF TENNESSEE DEPARTMENT OF ENVIRONMENT AND CONSERVATION DIVISION OF UNDERGROUND STORAGE TANKS TECHNICAL CHAPTER 4.2 SPILL AND OVERFILL PREVENTION EFFECTIVE
Sewer Line Rehabilitation
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing sanitary sewers using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
Underground Storage Tanks
Underground Storage Tanks An Informational and Guidance Document for the University Community. Please contact Yale Environmental Health and Safety for latest Regulatory Requirements. A typical UST installation
Tanks: What's in store?
Tanks: What's in store? Technical and regulatory developments in tank construction prompt changes; operations and maintenance receive greater emphasis. Chemical Processing magazine By Wayne Geyer Tanks
SECTION 221413 FACILITY STORM DRAINAGE PIPING
SECTION 221413 FACILITY STORM DRAINAGE PIPING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01
Civil Engineering Sector Labour-Management Health and Safety Committee
PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION SITES Civil Engineering Sector Labour-Management Health and Safety Committee July 2008 PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION
MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water
MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water 105 Decker Court, Suite 825, Irving, TX 75062 P: 469-499-1044 F: 469-499-1063 www.plasticpipe.org HDPE
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
Air Eliminators and Combination Air Eliminators Strainers
Description Air Eliminators and Combination Air Eliminator Strainers are designed to provide separation, elimination and prevention of air in piping systems for a variety of installations and conditions.
Indirect-Fired Storage Water Heater Models WH-30 through WH-80 INSTALLATION AND OPERATING INSTRUCTIONS
Indirect-Fired Storage Water Heater Models WH-30 through WH-80 INSTALLATION AND OPERATING INSTRUCTIONS Contents Page Ratings and Specifications..................... 2 Installation Requirements......................
Spill Containment Device and Containment Sump Testing Protocols. Introduction
Department of Natural Resources and Environmental Control Tank Management Branch 391 Lukens Drive New Castle, DE 19720 (302) 395-2500 (Phone) (302) 395-2555 (Fax) http://www.dnrec.state.de.us/dnrec2000/divisions/awm/ust
FIBERGLASS UNDERGROUND STORAGE TANKS Special Installation Instructions for New York City Gasoline and Diesel Motor Fuels
INTRODUCTION The purpose of this manual is to provide speci c, detailed supplemental instruction regarding the installation of special Fiberglass Double-Wall Underground Storage Tanks (including compartment
TEXAS A&M CENTRAL ACADEMIC BUILDIING & PATRIOT S CASA SUBMITTAL. 23 21 13.19 Pre-Insulated Piping 4-8-13
TEXAS A&M CENTRAL ACADEMIC BUILDIING & PATRIOT S CASA SUBMITTAL 23 21 13.19 Pre-Insulated Piping 4-8-13 MATERIAL SUBMITTAL JOB NAME: TEXAS A&M SAN ANTONIO CENTRAL ACADEMIC BUILDING & PATRIOTS CASA CONTRACTOR:
Used Oil Guidance. Tank and Secondary Containment Requirements For Used Oil Processors
Used Oil Guidance Tank and Secondary Containment Requirements For Used Oil Processors Washington State Department of Ecology Publication Number 05-04-016 November 2005 For more information The Washington
Steel Tank Institute AST Inspections. Dana Schmidt, PE STI/SPFA
Steel Tank Institute AST Inspections Dana Schmidt, PE STI/SPFA Agenda Brief review of SPCC Rule SPCC relevance to small tanks and small facilities. SP001 Standard for Inspection of Aboveground Storage
NEW JERSEY SMALL BUSINESS ENVIRONMENTAL ASSISTANCE PROGRAM. New Jersey Fuel Dispensing Facilities Compliance Calendar
NEW JERSEY SMALL BUSINESS ENVIRONMENTAL ASSISTANCE PROGRAM New Jersey Fuel Dispensing Facilities Compliance Calendar 2016 Welcome The New Jersey Small Business Environmental Assistance Program developed
FIBERGLASS PETROLEUM TANKS FOR UNDERGROUND STORAGE
FIBERGLASS PETROLEUM TANKS FOR UNDERGROUND STORAGE WHY OUR TANKS ARE YOUR BEST INVESTMENT In the early 1960s, the American Petroleum Institute challenged Containment Solutions, Inc. (CSI) to develop a
Notes. Material 1. Appropriate Flammable Liquids
29 CFR 1910.106 Flammable Materials Flammable Liquids Preparation 1. Read Applicable Background information and related Company Policy Chapter. 2. Make Copies of this Lesson Plan for Personnel 3. Make
Secondary Containment: Regulations & BMPs. Beth Powell Vice-President and General Manager New Pig Energy [email protected]
Secondary Containment: Regulations & BMPs Beth Powell Vice-President and General Manager New Pig Energy [email protected] Federal Secondary Containment Safeguarding method in addition to the primary
Ontario Fire Code SECTION 5.13 DIP TANKS. Illustrated Commentary. Office of the Ontario Fire Marshal
Ontario Fire Code SECTION 5.13 DIP TANKS Illustrated Commentary Office of the Ontario Fire Marshal Dip Tanks Illustrated Commentary 1 5.13.1. Location 5.13.1.1. Dip tank operations involving flammable
Above Ground Liquid Storage Solutions
Above Ground Liquid Storage Solutions AVIATION FARMS/FORRESTRY/MINING FLEET/YARD OPERATION Inside Front Cover-See Cover File for Graphic MARINE MILITARY/PUBLIC SAFETY MISSION CRITICAL OPERATIONS WATER
Section 8 Storage Tanks & Equipment
Section Storage Tanks & Equipment Table of Contents Section Storage Tanks & Equipment Above Ground Horizontal Tanks... -1-4 Containment Sumps...-5 Fillrite AC & Transfer Pumps... -9-10 Fillrite Diesel
Dual wall sub-base fuel tanks-ibc Certified 30-230 kw DGHCA/CB/CC/DA/DB (4BT3.3G5) DSFAA/B/C/D/E (QSB5G3) DSGAA/B/C/D/E (QSB7G5) DSHAA/B/C/D (QSL9G2)
Dual wall sub-base fuel tanks-ibc Certified 30-230 kw DGHCA/CB/CC/DA/DB (4BT3.3G5) DSFAA/B/C/D/E (QSB5G3) DSGAA/B/C/D/E (QSB7G5) DSHAA/B/C/D (QSL9G2) Description Features Cummins Power Generation diesel
Secondary Containment & Spill Buckets Inspection, Testing, and Repair Solutions. Allen Porter May 28, 2015
Secondary Containment & Spill Buckets Inspection, Testing, and Repair Solutions Allen Porter May 28, 2015 Welcome and overview Introduction Tanknology Proposed Revisions to Federal Regulations Testing
NOTIFICATION OF PERFORMANCE TESTING FOR GASOLINE DISPENSING FACILITIES (GDFs) NESHAP 40 CFR, Part 63, Subpart CCCCCC (Sections 63.11110 63.
MICHIGAN DEPARTMENT OF ENVIRONMENTAL QUALITY (DEQ), OFFICE OF ENVIRONMENTAL ASSISTANCE NOTIFICATION OF PERFORMANCE TESTING FOR GASOLINE DISPENSING FACILITIES (GDFs) NESHAP 40 CFR, Part 63, Subpart CCCCCC
Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer
Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer The user may choose to adopt part or all of this Model Specification; however, the user should ensure that all parts
Shop Fabricated Aboveground Tank Construction Standards
Shop Fabricated Aboveground Tank Construction Standards Wayne Geyer Steel Tank Institute Fourth Biennial Freshwater Spills Symposium 2002 March 19-12, 2002 Cleveland, OH One key to clean freshwater is
OREGON FIRE CODE Interpretations and Technical Advisories
OREGON FIRE CODE Interpretations and Technical Advisories A collaborative service by local and state fire professionals, along with our stakeholders and customers, to provide consistent and concise application
Gas Risers and Transition Fittings
0 Elster Perfection Elster Perfection service line risers and transition fittings In 97, we developed the natural gas industry s first combination plastic/ steel anodeless service line riser. The first
LAKE COUNTY ANIMAL SERVICES EXPANSION SECTION 15459
SECTION 15459 PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1 Specification sections, apply to work
DRESSER TM PIPELINE SOLUTIONS
Wal-Rich Corporation is a master distributor of Dresser Pipeline Solutions, a trademark of GE. The following pages highlight the items that are in stock at our NY facility. For more information, please
DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY. August 2012
DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY August 2012 SECTION 2 The storage requirements in Directive 055 apply to upstream petroleum facilities, well sites, and pipelines
2010 Residential Water Heater Replacement Check List
2010 Residential Water Heater Replacement Check List The intent of this check list is to provide installers a general reference for the enforcement of code requirements in the Greater San Diego Area. This
Copper and Copper Alloy Tube, Pipe and Fittings
Copper and Copper Alloy Tube, Pipe and Fittings COPPER and COPPER ALLOY TUBE and PIPE Seamless Copper Pipe: Copper pipe is almost pure copper manufactured to the requirements of ASTM B 42 - Standard Specification
Daily Inventory and. Statistical Inventory Analysis. Daily Inventory and Statistical Inventory Analysis (SIA) are inventory control
Introduction: TankSmart Operator Training Class A/B Operators Training Class C Operators Annual UST System Inspections Record Keeping Spills: Cleanup & Reporting Safety Tanks: Double-Walled w/ Continuous
Petroleum Tanks at Municipal Facilities
January/February 2013 Petroleum Tanks at Municipal Facilities This document was reprinted with permission from the New York Association of Towns Talk of the Towns/Topics magazine January/February 2013
District Cooling Best Practices Piping Systems
District Cooling Best Practices Piping Systems International District Cooling Conference January 14-17, 2007 Abu Dhabi, United Arab Emirates Bryan Kleist Agenda Chiller Water Piping Materials Pipe Insulation
Highland Aboveground Steel Storage Tanks
Highland Aboveground Steel Storage Tanks Working for You and a Clean Environment C O N T E N T S The Highland Advantage 1 Horizontal Tank Construction 2 Fireguard Tanks 4 Dike Tanks 6 AREO Style Dike Tanks
SYSTEM INSTALLATION AND INSPECTION MANUAL HEATING OIL STORAGE TANK SYSTEMS
SYSTEM INSTALLATION AND INSPECTION MANUAL HEATING OIL STORAGE TANK SYSTEMS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND CONSERVATION POLLUTION PREVENTION DIVISION PETROLEUM STORAGE
Application Data Important Safety Information
Application Data Important Safety Information Read this page before using any of the information in this catalog. This catalog is designed to be used as a guide in selecting the proper hose for the applications
SMALL GAS OPERATOR OPERATION AND MAINTENANCE PLAN
SMALL GAS OPERATOR OPERATION AND MAINTENANCE PLAN Facility Name: Address: QUALIFIED PERSONNEL All tasks shall be completed by a person that is qualified to that task (see operators qualification of individuals
Multiport Spill Containment with Defender Spill Containers
Multiport Spill Containment with Defender Spill Containers Retrofit Installation Guide Overview Franklin Fueling Systems 3760 Marsh Rd. Madison, WI 53718 USA Tel: +1 608 838 8786 800 225 9787 Fax: +1 608
Model 1210C Battery Powered Pump Shown. Description
12 Volt DC Rotary Vane Pump Series 1200C Model 1210C Battery Powered Pump Shown Description of Included Models Model Number FR1205C FR1210C FR1211C FR2410C FR2411C Description Basic 12 volt DC pump with
Static Electricity. A Health and Safety Guideline for Your Workplace. What Are Some Sources of Static Electricity? What is Static Electricity?
A Health and Safety Guideline for Your Workplace What is static electricity? What causes it? How is it hazardous? And, most importantly, how can it be controlled? All of these questions will be answered
The following definitions apply with regard to requirements specified in this document:
GUIDELINES FOR INSTALLATION OF TEMPORARY AND PERMANENT ABOVEGROUND DIESEL FUEL TANKS FOR EMERGENCY AND STANDBY POWER SYSTEMS LOCATED OUTSIDE OF BUILDINGS For Use by Unidocs Member Agencies or where approved
Farm Fuel Tank Safety Guide
Farm Fuel Tank Safety Guide This brochure is provided by North Dakota Department of Emergency Services, your Local Emergency Planning Committee, and the State Emergency Response Commission along with assistance
Chapter 7 Plumbing Connections
Chapter 7 Plumbing Connections 7-1 General All plumbing equipment and installations must be designed, constructed, and installed in accordance with this code and where not specific, to the applicable provisions
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE
SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent
SECTION 33 11 00.13 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS
SECTION 33 11 00.13 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS PART 1: GENERAL 1.01 SECTION INCLUDES Furnishing and installing up to 16-inch high density polyethylene (HDPE) pipe and fittings for
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS
SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials
Healy Enhanced Vapor Recovery Troubleshooting Guide
Healy Enhanced Vapor Recovery Troubleshooting Guide Franklin Fueling Systems 3760 Marsh Rd. Madison, WI 5378 USA Tel: + 608 838 8786 800 225 9787 Fax: + 608 838 6433 www.franklinfueling.com Contents Important
DC400 Dispensing Cutoff System
DC400 Dispensing Cutoff System DC404 and DC406 Installation Instructions Franklin Fueling Systems 3760 Marsh Rd. Madison, WI 53718 USA Tel: +1 608 838 8786 800 225 9787 Fax: +1 608 838 6433 www.franklinfueling.com
Green Thread Product Data
Green Thread Product Data Applications Dilute Acids Caustics Produced Water Industrial Waste Hot Water Condensate Return Materials and Construction All pipe manufactured by filament winding process using
PREVENTING GROUNDWATER POLLUTION: SECONDARY CONTAINMENT
PREVENTING GROUNDWATER POLLUTION: SECONDARY CONTAINMENT PREVENTING GROUNDWATER POLLUTION IS EVERYONE S JOB! Even if our drinking water comes from rivers, lakes, or reservoirs, we need to be mindful of