Counting Costs. Decommissioning of offshore wind farm assets

Similar documents
London Array. Operations and Maintenance

OWPST & Titan 200 & UK Offshore

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

JEDI Capital Expenditure Update

Developing Ocean Energy in Ireland. Belmullet Wave Energy Test Site

Technical Risks in Wind Project Development

ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION

MAXIMISING YOUR. Offshore wind assets ASSET OPERATION & MAINTENANCE SERVICES

Operational analysis & Optimisation

Pollution Response RESPONDING TO AN OIL SPILL

installation, operations & maintenance

Profile. Offshore Wind Projects. Sustainable EPC and Marine Contractors

Offshore Wind: some of the Engineering Challenges Ahead

Monobuckets and the competitiveness versus monopiles and jacket structures.

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy

Decom North Sea and Bureau Veritas Decommissioning Step by Step: Including Asbestos Guidance 14th March. - Copyright Bureau Veritas

Experience from the first large scale tidal turbine EIA in Europe. How do we work towards effective and proportionate EIA?

Horizon Survey and Geotechnical Companies

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation

Operations in the Arctic areas? New challenges: Exploration Development Production

CCS Roadmap. The regulatory framework

OCEAN LÍDER: Ocean Renewable Energy Leaders

GRAVITY BASE FOUNDATIONS

Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations

Permanent Reservoir Monitoring (PRM) System Installation: The Installers Perspective

Regulating Offshore Renewable Energy Leasing and Development

Firth of Forth Offshore Wind Farm Zone. Offshore and Onshore Project Information

Advantages of our solution

4. PROGRAMME OF WORK: PROJECT ACTIVITIES, TIMESCALE AND COSTS

A consultancy perspective: Building consensus on wildlife monitoring

Impact Assessment (IA)

OPERATIONAL LIMITATIONS DUE TO COMPLIANCE WITH THE JONES ACT

Alternative infrastructure funding and financing

BMP Guidelines. Environmental Impact Assessment (EIA) report for activities related to hydrocarbon exploration and exploitation offshore Greenland

Appendix D: Benefit Cost Analysis: Economic Feasibility of Offshore Wind Energy Development on the California Central Coast

The Total Tax Contribution of the UK Oil & Gas industry

Whole Life-Cycle Costing of Large-Scale Offshore Wind Farms

Offshore Work Packages

Who are we? *Based on an average annual domestic household electricity consumption of 4,700KWh (DECC).

OFFSHORE WIND ENERGY IS GETTING CHEAPER

Developing a framework model of Supply Chain Management : A case study on a Mega construction project in Myanmar.

Offshore Windfarm Egmond aan Zee 4 years of Operation

Offshore Electricity Transmission: Consultation on tender exercises under the enduring regime (178/11)

Supply Chain Plan Final Guidance

Offshore Renewable Energy in Virginia

COWI offshore wind marine engineering services

Insights into Tidal Stream energy

AGM presentation 13 May 2009

Offshore wind farm electrical engineering (when considering the operation of array cabling at voltages of 66kV)

Offshore Transmission: Guidance for Cost Assessment Guidance Document

G9 Offshore wind health and safety association

Making the polluter pay Environmental Damage Regulations March 2009

PROCUREMENT GUIDE: CHP FINANCING

OFFSHORE WIND PROCUREMENT

OFF-TAKE UNDER THE CFD - BUSINESS AS NORMAL? Electricity Market Reform: Edging Towards Delivery 24 September 2014

Depth-independent solution for Offshore Wind the WindFloat

Community and Renewable Energy Scheme Project Development Toolkit

NIA Project Registration and PEA Document

Approaches to cost-reduction in offshore wind

How To Build A Wave Energy Power Station In Germany

ASSOCIATION INC Geothermal Energy: New Zealand s most reliable sustainable energy resource

The implementation of the European Union Environmental Liability Directive

Who are we? Jens Lohmueller, Credit Union Central of Ontario 3/9/2005

Annex B: Strike price methodology July 2013

Cost of and financial support for offshore wind

Essex... A great location for offshore wind

Aviation Demand Forecasting

Consultation on proposals for the levels of banded support for solar PV under the Renewables Obligation for the period 1 April 2013 to 31 March 2017

City of Vernon Request for Expressions of Interest and Information (RFI)

Consultation on changes to Feed-in Tariff accreditation

THE FUTURE OF THE OCEAN ECONOMY: AN OECD/IFP FORESIGHT PROJECT

The world s leading sustainability consultancy. Sustainable Solutions for the Oil and Gas Industry

INSTALLATION and LOGISTICS of OFFSHORE WIND FARMS

Developing a Public-Private Partnership Framework: Policies and PPP Units

Development of a Scottish Government Policy Approach to Repowering. Debbie Harper Arup Glasgow

Critical Limitations of Wind Turbine Power Curve Warranties

Dansk Offshore Netværk, Lindø Industripark, 21. April 2015 The Road to Below 10 ct /kwh

Data Communications Company (DCC) price control guidance: process and procedures

Impact Assessment (IA)

Wind Energy Development in Jamaica

Overturning Stability of Offshore Wind Power Substructure with Bucket Foundation

Scottish Enterprise. Offshore Wind Power: Priorities for Research and Development (R&D) and Innovation. Supporting a globally competitive Scotland

What next for UK auctions of renewable Contracts for Difference?

UNLOCKING MAJOR COST SAVINGS ON OIL & GAS PROJECTS

1. Purpose and scope. 2. SEPA's role in hydropower and planning

Shipping, World Trade and the Reduction of

Cable System Planning and Permitting: Business and Stakeholder Considerations

Oregon Territorial Sea Plan

Proven expertise and total reliability to support globally recognised oil and gas clients

Offshore Renewable Energy Installation Decommissioning Study. Final Report

Offshore Wind. IEEE Boston PES - November 16, 2010

The Siemens Energy Service Training Centre. Delivering skills for the 21st century

Request for Renewable Energy Alternate Use Lease on the Outer Continental Shelf near North Carolina

Environmental damage: extending the Environmental Liability Directive into marine waters

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

Case Study 5 Use of Wind Turbine Technology

Global Infrastructure & Project Finance

THE DECOMMISSIONING OF THE UK NUCLEAR INDUSTRY S FACILITIES

Title: IEC WT 01 vs. IEC Development of a new standard and innovations in certification of Wind Turbines. mike.woebbeking@gl-group.

Future renewable energy costs: offshore wind

Transcription:

Counting Costs Decommissioning of offshore wind farm assets

Introduction To date, no offshore renewable energy project has decommissioned its assets, apart from a meteorological mast. This is simply because no offshore project has reached the end of its life. As a consequence, there is little practical experience within the industry to draw upon when it comes to estimating the costs for decommissioning guarantees / finance (e.g., a bond 1, mid-life accrual fund or letter of credit), other than lessons learnt from oil & gas. Globally, offshore renewables are spreading from its well-defined routes in Europe to more emerging markets, where the need for electricity power is exceeding demands due to industrialization. Whilst the deployment of renewables may counter-balance future power demand short-falls and contribute to meeting CO2 emission targets, they are a long way from the prospect of decommissioning. Yet, planning appropriate decommissioning strategies and estimating their costs need to be considered early in a projects life-cycle to adequate secure bond finance and meet legislative requirements. In the UK, offshore wind farm assets and associated infrastructure for Round 1 projects are now appearing on the horizon, yet detailed decommissioning of offshore renewables remains poorly understood. This paper discusses the major challenges facing anyone estimating the costs for decommissioning of offshore renewable assets for bond security purposes. It is not a review of different types 1. A bond is similar to a loan from the borrower s point of view and often takes the form of a tradable debt instrument, where the issuer (e.g., the Project Company) agrees to repay the bond holder the amount of the bond plus interest on fixed future instalment dates (see Yescombe, E. R. (2014). Principles of project finance. Academic Press 2nd Edition). of financing arrangements as there are already authoritative papers on the topic 2. Avoiding the public burden A common feature of all decommissioning regulations is the requirement of lease holders to follow strict protocols at the end of a projects life. These require assets to be removed, the site reinstated and clearance verified upon lease termination. Obviously, decommissioning regulations will vary in different countries, but they must all achieve their decommissioning objectives in a responsible manner that protects the public interest and commitments to international treaties (e.g., Convention for the Protection of the Marine Environment of the North- East Atlantic ( OSPAR ) 3 ; International Maritime Organization ( IMO ) 4 standards). Governments who fail to take prudent steps before consenting or permitting a project, may result in transferring unnecessary high cost burdens to the public. In this regard, regulators are mandated to ensure decommissioning bonds are secured, so all development entities provide adequate financial resources to protect the government from incurring any financial loss. Estimating costs that adequately inform decommissioning bonds are critical, as too low an estimate then the financial burden of decommissioning may be placed on the public purse. Conversely, estimates that are too high 2. Biricik, S and Haroun, N. (2010) The Importance of Decommissioning Security, Energy Law360 / Environmental Law360 April 12. 3. OSPAR Decision 98/3 on the Disposal of Disused Offshore Installations. 4. Guidelines and Standards for the Removal of Offshore Installations and Structures on the Continental Shelf and in the Exclusive Economic Zone, IMO, 19 October 1989.! " # $ % " %

may become disproportionate costs to the developer, and so potentially compromising commercial viability. Realistic cost estimates also protect Governments from being financially responsible for the short-fall if the lease holder defaults. Decommissioning of offshore renewables Securing bond finance for renewable energy projects is slightly different from oil & gas projects, as they have a greater degree of certainty over their longer-term revenues (i.e. through a Power Purchase Agreement ( PPA )), and so face less uncertainty over revenues towards the end of a projects life. This is important to regulators, as having the assurances that the project owner can ramp-up the necessary revenues to financially commit to decommissioning, when the time comes, provides confidence and so support at the planning stages. It is common practice with many permitting authorities to ensure decommissioning plans are submitted before construction of a wind farm starts and in some cases permit approval. In the United Kingdom ( UK ), a decommissioning plan must be submitted to the licensing authority, the Department of Energy and Climate Change ( DECC ), at least three months prior to the planned decommissioning of the works. Typically, these initial plans contain sufficient information to describe anticipated activities and objectives, and include, for example, removal methods, site restoration, easement activity, schedules and confidential annexes to justify the expenditures for the decommissioning proposed. Plans are updated when project assets are reviewed during the operations phase and at nominate time periods (e.g., at least 12 months, but potentially up to 5 years) before the end of operational life to ensure they reflect best practice (such as the principle of Best Practicable Environmental Option 5 ( BPEO )), at that time, and regulations. It s worth noting that most Original Equipment Manufacturers ( OEM s ) have their own authorised procedures for decommissioning wind turbine. Critically, identifying decommissioning activities must be worked out in advance to promote liability management, regulatory and code compliance, cost and schedule containment, safety and environmental performance. It s not uncommon to fine tune engineering design plans, as the project evolves during development. In some cases, these may have implications for estimating decommissioning costs. The timescales for decommissioning must allow sufficient time to implement a costefficient decommissioning program. Typically, this ranges between one and two years after termination of lease. However, a word of caution, such timescales may not have a bearing on the size or scale of the project. This could pose a challenge for large wind farms like Round 3, for example, that are far offshore and where weather windows are more likely to restrict operations compared to nearshore projects. 5. The principle of BPEO provides the most benefit or least damage to the environment as a whole, at an acceptable cost, in both the long and short term. & ' ( ) ( * ( +, -. ( / 0 1 * / 2. 3 4 * 5 6 7 1 2 8

The ability to standardize decommissioning operations is largely accepted as general practise, but it is the scale of an offshore wind farm (e.g., number of Wind Turbine Generators ( WTGs )) that will have the greatest bearing on costs. That said, offshore wind farms are considered more homogeneous compared to oil & gas facilities, as the template for installing WTGs are typically the same and so simply replicated across the project site. The timescales for decommissioning activities are variable depending on the size and complexity of the asset in question. Operations to remove buoys, bottom mounted moorings and meteorological masts, for example, can last from a just few days to several weeks. By contrast, the decommissioning of a large-scale wind farm involving hundreds of turbines may take months or an entire season or more. Its s worth noting that this has yet to be validated as no offshore wind farms has been decommissioned. To date, decommissioning cost estimates within the European offshore wind industry have been considered by some to be underestimated, and for many viewed very simply as the reverse of installation. Whilst the latter view is largely true, simply removing physical assets underplay environmental considerations, which can lead to more complex environmental concerns than previously anticipated (e.g. presence of toxic gas, bentonite, noise, public safety issues, water quality and impacts on wildlife). For cost estimate purposes, pre-empting such concerns based on project site location, design and installation strategies, may be beneficial to ensuring financial contingencies are proportionate. In some cases, an ( EIA ) may be required to inform the decommissioning process. This is the responsibility of the licensee /owner(s) and may include the commissioning and acquisition of any new site specific information (e.g., side-scan sonar, benthic surveys). In addition, survey evidence to support proof of seabed clearance and restoration, and any ongoing monitoring requirements. Estimating decommissioning costs will always have a degree of uncertainty due to market and information constraints at the time of estimation. Anyone developing an appropriate model for calculating decommissioning costs needs to consider current market conditions and technology, and adjustments for inflation. Other factors include the influence of global economics, navigational safety, technical feasibility, and conservation and biodiversity objectives (e.g., leaving some of the structure(s) in place as artificial reefs). 9 : ; < = > <? 9 : @ = @ A B C D : E E > @ @ > : < > <? : F : F F @ G : H C I > < J F K H E K @ @ C = @

Many operational elements of decommissioning can be well defined. They include, for example, vessel and cargo barge mobilization and demobilization, cutting and lift operations, or onshore transportation where components are being reused or disposed. However, less well define element are costs incurred during the planning or review stages prior to commissioning operational activities. Typically, this review stage comprises of meeting contractual and regulatory obligations, scheduling the availability of services in the market place, procurement of services including work force and engineering management teams, and securing necessary permits to undertake decommissioning and disposal. Another area of uncertainty is whether developers will propose to undertake a comprehensive consultation process with other marine users prior to decommissioning and whether these costs become part of the decommissioning bond estimate. Decommissioning cost estimates Building cost estimate models for decommissioning offshore renewable energy facilities should be project specific, although the underlying methodology is applicable across all facility types. One of the challenges to estimating costs is extrapolating current costs and technologies into the future. for when considering bond or other security financing. Therefore, cost estimate models should factor in different decommissioning options by developing scenarios that test the sensitivity of different strategies on costs. To this end the highest price scenario that is practicable and proportionate to the project may be suitable for estimating the upper limits. Different decommissioning scenarios could include, for example: Is lifting or dredging scour protection practical? Given the potential seabed disturbance and release of particulate matter and other contaminates, which could have an impact on the ecology of the area; or Should electrical cables remain in situ? Given costs and level of potential environmental disturbance if they are already buried at a safe depth below the seabed. All model assumptions should be future proofed to ensure cost estimates remain realistic. Model assumptions are best validated by expert consultants, and, where possible, through engagement with industry and the supply-chain sector (either by written correspondence, telephone or face-to-face meetings). The decision to modify specific aspects of the decommissioning requirements (e.g., leaving facilities in-situ, partial removal, or reefing allowances) is typically permitted only on a case-by-case basis. This is not known until the decommissioning review process (if there is one) is completed. This level of detail and options for decommissioning (close to the end of a project) should already be accounted L M N O N P N Q R S T N U V W P U X T Y Z P [ \ ] W X ^

Developing a specific cost estimate per mega-watt hour may underestimate costs as turbine size, number and foundation type, for example, will vary across projects 6. Moreover, the methods for removal 7 or partial removal, distance of project from shore, environmental conditions and ultimately disposal of components, will also vary across projects. Therefore, developing costs based on per mega-watt hour may not be representative of the actual costs incurred at decommissioning. Cost models should also factor in less predictable variables in light of future market conditions, such as estimated vessel day rates (adjusted for anticipated inflation rates). A starting point for the model is to assume decommissioning is generally installation in reverse, although as previously stated, decommissioning is not always that simple. Estimated costs need to be developed for each stage of installation from foundation, tower, transition section, nacelle, inter-array and export cables, and substations, scour protection, meteorological masts, and bottom fixed anchoring systems etc. Timescales for each stage and their components need to be estimated on a per-unit basis cost to build the model(s), and include contingency down-time associated with weather delays. In addition, costs for monitoring strategy (e.g., use of side-scan sonar surveys, divers etc.) where components are to remain in-situ. Cost estimates typically use a number of theoretical models supported by the engineering literature and / or inhouse engineering teams. They assist in parameterizing inputs from generation capacity, turbine capacity, and distance to port, installation vessel class, installation methods, day rate etc. In addition, data sources from the project or expert consultant teams involved in the cost estimation process, will further refine the reliability of cost estimates. All associated onshore infrastructure that requires decommissioning needs be factored in to the cost estimate modelling, but typically these items are best made available as a separate component. In addition, consideration of multiple project phases may need to be calculated. Any innovative methods to reduce decommissioning costs may be possible despite the offshore renewable energy industry not yet undertaking its own decommissioning. For example, innovation against oil & gas standards could be adopted whereby suction bucket foundation technology could radically reduce the cost of decommissioning. It is worth noting that within the oil & gas sector, partial decommissioning is being considered as a management response to protecting biodiversity through reefing because it may significantly reduce decommissioning costs. 6. Estimated costs for decommissioning a 300MW offshore wind farm is estimated around 40,000/MW or 2% of operating costs when spread over the lifetime of the project (Climate Change Capital, 2010). 7. It is unlikely that removal technologies will change dramatically over the next decade and so variations in cost estimates s are likely to be small. _ ` a b c d b e _ ` f c f g h i j ` k k d f f d ` b d b e ` l ` l l f m ` n i o d b p l q n k q f f i c f

Decommissioning options for the various components of an offshore facility (e.g., foundation, tower, nacelle, mooring etc.) are typically determined and valued using a decision-tree. Figure below shows a high-level example for a fixed WTG. The option(s) that result in the highest cost scenario is identified as an objective of this analysis. Offshore WTG foundation Leave in place Remove Cut to seabed surface Cut to safe navigational depth Complete removal Partial removal Natural recovery Site restoration Relocated to Deep water Relocated to shallow water Transport to shore Reuse Recycle Dispose Reefing allowances Monitoring Adapted from Fowler et al., 2014 8. 8. Fowler, A., Macreadie, P., Jones, D., and Bootha, D (2014). A multi-criteria decision approach to decommissioning of offshore oil and gas infrastructure. Ocean & Coastal Management 87: 20-29. r s t u t v t w x y z t { } v { ~ z v ƒ } ~

The same thought process could be applied across all facility / technology types and can be informed by more detailed data (Table 2). Design criteria characteristics Decommissioning strategy Projection parameters Cost estimate parameters Nacelle Tower section Transition piece Foundation Other subsea structures Inter-array cables Met tower Scour protection Substation top section Substation foundation Complete removal, partial removal or leave in-situ, reuse, recycle, disposal approach, piles cut off just above the level of the bedrock seabed, monitoring strategy for components that remain in-situ, HDD bored capped etc. Number, type, weight of key components, vessel types, distance of project site from port, onshore storage, disposal facilities etc. Day rates, permits, vessels, dredging and barge boat mobilization and demobilization costs, seasonality, duration, lifting gear, labor, dive operation costs, etc. Table 2. Example only: summary of the type of attributes of decommissioning needed to inform cost estimation. ˆ Š ˆ Œ Œ Ž Š Œ Œ Š ˆ Š ˆ Œ Š ˆ Œ Œ Œ

RCG is a specialized expert services firm dedicated to the global renewable energy sector. We are a firm of practical consultants known for our technical expertise, industry foresight, and sleeves-rolled-up approach to projects. From strategy to implementation, we serve businesses, governments, and non-profits around the world with technical, commercial, and advocacy services for both mainstream and emerging energy technologies. At RCG, we are powered by exceptional people united in a relentless pursuit to elevate advisory services, and deliver new levels of value for our clients. We work with the public sector, private equity and financial services firms, utilities and independent power producers (IPPs), and contractors and manufacturers for land-based and offshore wind, solar, hydrokinetic and ocean energy, and energy-storage technologies. 145-157 St Johns Street London, EC1V 4PW 41 Madison Ave, 31st Floor New York, NY 10010 renewablescg.com