FREEBORN HALL SYSTEMS ASSESSMENT



Similar documents
17,280 square feet Overview:

Building Condition Assessment Report

Architectural Condition Survey

COST OF WORK FORM. Abbreviations: ea = each, LF = linear feet, SF = square feet, HSF = square feet of living area (including garage conversion space)

PUBLIC RESTROOMS, DESIGN INTENT

Facility Assessment Report, Montgomery Independent School District

Building Condition Assessment Report

SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST

Historic Preservation Certification Application Part Main Street West South Haven, Vermont NPS Project No

3. Tile used in the toilets is generally in good shape, though somewhat dated looking. The floor tile is slippery when wet.

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

CLIENT. Inspection Report. 271 Front St. Alert Bay, B.C. Island Building Inspections V ANCOUVER I SLAND B. C.

48. AQUARIUM. Aquarium. Classification: Cluster: Location: Close to junction of Inselrhue and Loiter Way, Belle Isle. Total Area: No.

October 5, 2015 Dear Client,

Point Auditorium Design Narrative PROJECT NAME: Point Auditorium DATE: 06/25/15 TO: Lance Francis FROM: Leslie Ellsworth

Estimating Database Checklist

IMPROVEMENT COST ESTIMATE powered by HomeFixers

Whitley Manufacturing Co., Inc. 201 W. First Street S. Whitley, IN Phone (260) Sales Fax (260)

Facility Assessment for East Main Street, Huntley, IL

VJ ASSOCIATES 1825 K STREET NW, #1100 WASHINGTON, DC TEL: (202) INITIAL PROJECT COST ANALYSIS

March 19, Ms. Jean McDonald CAP Management th Street, Suite 1010 Denver, Colorado 80202

Total Home Inspection Checklist

WASHROOM UPGRADE SIR CHARLES TUPPER BUILDING 2250 RIVERSIDE DRIVE, OTTAWA, ON SIR CHARLES TUPPER BUILDING A0.0 COVER SHEET / DRAWING LIST

SECTION EXISTING HAZARDOUS MATERIALS CONDITIONS

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule

Mobile Home Pre-Inspection Checklist

GENERAL PROVISIONS

U.S. Department of Housing and Urban Development Office of Public and Indian Housing. A Good Place to Live!

Inspection Item COMMENTS

Self-Home Inspection Checklist

47 Levencourt Way London SW8 1HR. Tenant: Eric Stevenson Prepared for: Elizabeth Collins

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

Executive Summary. June 2005 Auke Bay Elementary School Condition Survey Report Page 4 of 228

Inspecting to a higher standard.

Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year

CONDITION OF QUALITY ITEMS

Georgia Home Inspection Services

Vision Home Inspection

May 5, Client Client Address. Re: Inspection Address, Chicago, Illinois. Dear Mr. Client,

Crawford Inspection Services C.C.B. #

DEPARTMENT OF AIRPORT OPERATIONS CLEANING SCHEDULE FOR CONTRACT 2014

BUNKER HILL ELEMENTARY SCHOOL

CONSERVATION MAINTENANCE WORKSHEET Universal Checklist

8629 S. Kimbark, Chicago, IL PROJECT SPECIFIC SCOPE:

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

PUBLIC MINUTES PROPERTY MAINTENANCE APPEALS BOARD. Wednesday, November 25, 2015, 3:46 p.m. Committee Room B, City Hall

SPACE TYPE: LABORATORY (WET) FOR CHEMISTRY AND BIOLOGY

PRE-PURCHASE INSPECTION REPORT

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

Slavic Village Building Condition Review

EAST LYME HIGH SCHOOL

Irvinton Village Apartments 2901 Fulton Houston, Texas Houston Housing Authority J. Allen Management Managing Agent

The replacement or modification of existing windows shall comply with the following requirements:

How To Check For A Deficiency

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000

Katharine Teats House HABS No. CA Seventh Avenue San Diego San Diego County /J/Vf# <? California /WtO

Pre-Drywall Inspection Report

Items in red were complete Items in green were complete on Lined out items are Life Safety Codes.

SECTION 3 ONM & J STRUCTURAL ANALYSIS

Memorandum. July 16, To: Plan Commission City of Madison

BUILDING PERMIT SPECIFICATIONS

LITITZ MUTUAL INSURANCE COMPANY 2 North Broad Street Lititz, Pennsylvania - MAIN OFFICE -

ADDENDUM # 1 To: RFP for: Various Construction Maintenance & Repair Services

Town of Sandwich Facilities Department Summary of Building Repairs from Prior 5 7 Years List Updated August 7, 2015

How To Plan A Building

Nominal Life Expectancy for Building Components

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY

PARKVILLE HIGH SCHOOL LIMITED RENOVATION

Damage Charge Lists. FLOORING Replace Repair Carpet per square foot (Mohwak heat carpet tile)

Home Warranty Inspection Report

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

Seattle Tacoma International Airport Restroom Standards

PROFESSIONAL ENGINEERING INSPECTIONS, INC.

Comment Form on Proposed Gut Rehabilitation Alternatives

SECTION TABLE OF CONTENTS. H Proposed Material, Product or Equipment Substitution Request

Schedule of Maintenance Fees

Property Condition Assessment

first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel

Park View Place. Compass. House. Royal Wharf Gardens Endeavour. House. Thameside. Sienna. House. House. Apartments Townhouses.

Estimator: Miami Estimates Business: (305) Date Entered: 04/30/2008

CITY OF SHAKER HEIGHTS HOUSING INSPECTION DEPARTMENT 3450 LEE ROAD SHAKER HEIGHTS, OHIO (216) POINT OF SALE CERTIFICATE OF INSPECTION

Orlando Home Inspection Services

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.

HISTORIC PRESERVATION COMMISSION ADMINISTRATIVE APPROVAL ISSUED JULY - SEPTEMBER 2014 DATE PROJECT ADDRESS PROJECT DESCRIPTION

EAST STROUDSBURG BOROUGH RESIDENTIAL RENTAL INSPECTION CHECK LIST

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

SPACE TYPE: AUDITORIUM

Residential Deck Safety, Construction, and Repair

Second Floor Plan, Pre-restoration

LEASE BETWEEN RALEIGH PORTFOLIO JH RETAIL, LLC AND CITY OF DURHAM FOR SPACE IN THE BUILDING AT 2945 S. MIAMI BOULEVARD; DURHAM, NC EXHIBIT A

Rehab Inspection Report Page 1

MRI RF SHIELDING DESIGN

Doughty Environmental Hygiene Associates

Code Enforcement Inspection Manual. City of Virginia Beach Department of Housing and Neighborhood Preservation Code Enforcement Division

The schedule is based upon a five (5) day work week (Monday through Friday). Weekend service is only when requested.

Transcription:

FREEBORN HALL SYSTEMS ASSESSMENT Project No. 2829570 Prepared by the Engineering and Commissioning Group and PRIMEbusiness April 23, 2013

Table of Contents Page Executive Summary 1 1. Architectural System Exterior 2 2. Architectural System Interior 7 3. Site Utilities 25 4. Fire Sprinkler System 27 5. Plumbing Systems 28 6. HVAC Systems 30 7. HVAC Controls System 35 8. Electrical Systems 36 9. Telecommunication System 38 10. Fire Alarm System 39 11. ADA Compliance 40 12. Hazardous Materials 40 13. Acoustical and Performance System 40 Appendix A Photographs Appendix B Renovation Log Appendix C BMS Personnel Appendix D ADA Compliance Drawings Appendix E Hazmat Report Appendix F Acoustical Systems Study Appendix G Current Room Configuration of Lower Freeborn

Executive Summary Originally known as Assembly Hall, Freeborn hall was constructed in 1961. The structure and the exterior envelop have changed very little since originally constructed. The interior finishes have experienced some minor upgrades, but much of the hall is original. Over the last fifty#two years, there have been many renovations and upgrades. These projects have been cataloged, with a brief description of the work, in Appendix B. The hall is functioning on a daily basis. This report gives the current status of all systems and finishes throughout Freeborn Hall. Our recommendations are based on the program remaining the same in each area. Because it is unknown what seismic solution will ultimately be administered, we have not addressed that part of the recommendations. This assessment of the building Mechanical, Electrical and Plumbing (MEP) systems evaluates the ability of the existing systems to support the proposed building modifications. It is based on a review of the available record drawings, field verification, and discussions with the Building Maintenance Services (BMS) personnel. A list with contact information for BMS personnel is included in Appendix C. It was prepared by in# house, state licensed, professional mechanical and electrical engineers, and is organized as outlined in the Table of Contents. The MEP systems assessment describes the general type, layout and condition of each system and it provides recommendations for work needed under this project. The equipment condition was assessed on a three#tier scale: good, serviceable and poor. The general thought is that equipment in good condition can continue to serve the building and no work would be required under this project. Similarly, equipment in serviceable condition would require some repair and upgrade while equipment in poor condition would require major overhaul or complete replacement. In some cases, where the condition of a system or its components could not be verified, the recommendation is to perform additional verification and evaluation. This applies mainly to underground drainage piping and equipment located in ceiling areas with difficult access. 1

1. Architectural System Exterior 1.1 Roof 1.1.1 Roof Description Building Systems The existing copper roof was installed in 1961. It is an approximately 35,000 sq. standing seam roof, constructed of 16 oz. copper roofing on top of asphalt saturated felt, 1 ½ rigid fiberglass insulation BD., and 1 ½ steel roof deck. The roof protrudes from the building at a distance ranging from 10 2 and to 38, with eves that have plaster soffits on the underside. The roof is complete with a smoke hatch over the stage. 1.1.2 Roof Condition The roof has held up well over the years and has 30 / 40 years of useful life left. However, there are a few minor issues. The solder around the drains has broken/down or cracked at all twelve down spout locations on the building s north and south face (Roof Photo #1 For all photographs Appendix A) There appears to be minor repair work done at the high point between each down spout. There are two known leaks inside the building in the stage area. These leaks are possibly originating at the smoke hatch, located above the stage at the west end of the building (Roof Photo #2). The roof jacks are in various states of repair, but none appear to be letting water into the building. The plaster soffit under the eve is in very good condition with few areas that need repair. 1.1.3 Roof Recommendation 1.2 Exterior Brick Replace and re/solder the down spouts at all twelve locations including seams surrounding these areas. Remove and re/attach smoke hatch with new copper flashing. Check all roof jacks for repair if needed. Clean to remove bird droppings without removing patina. Clean plaster soffit and repair any cracks. 1.2.1 Exterior Brick Description The four corners, and back exterior wall, of Freeborn Hall are fabricated of brick veneer over concrete. The bricks are 12 x 4 x 2. The brick veneers are laid in a stack pattern with a 2 x 1 1/2 reveal every 4, with standard mortar joints. There is an exterior brick screen wall on the north side of the building. The wall is laid in a stack pattern with cross laid area to create other patterns. 2

1.2.2 Exterior Brick Condition Brick veneer exterior appears to be in good structural condition. Bricks are solid with very few cracks. Mortar is intact and does not appear to need pointing up. However, there is effervescence coming out in various parts of the building and screen walls. (Brick Photo #1) There are other areas that have paint overspray and other colored materials on the brink. This is especially evident at the ticket office windows (Brick Photo #2). There are few locations where items have been removed from the surface of the brick and holes remain (Brick Photo #3). 1.2.3 Exterior Brick Recommendation 1.3 Exterior Doors Clean all brick surfaces with an industrial level cleaner. Repair and replace any damaged bricks, especially in the areas where items have been removed from the bricks. Clean off overspray from needed areas. Replace any bricks that are damaged because of other upgrades. 1.3.1 Exterior Doors Description All the exterior doors are hollow metal doors. The exterior doors on the north and south sides of the building are incorporated into the curtain wall. Each side has 3 sets of double doors. The south side has one extra set of doors that goes into the stairway area. The north side has an extra single door also into the stairway area. The east entrance of the building has 4 sets of double doors. The west, back of the building only has one single door and a roll/up door (discussed in a separate section). 1.3.2 Exterior Doors Condition The hollow metal doors around the exterior of the building are in different stages of decay (Ex. Door Photo #1 & 2). The doors at the north screen wall are past their useful life (Ex. Door Photo #3). The main entrance doors are damaged and many are rusting at the base (Ex. Door Photo #4). Some of handles on these doors are mismatched, some wood and some plastic (Ex. Door Photo #5). The aluminum doors appear to be in fair to good condition. 1.3.3 Exterior Doors Recommendation Replace all hollow metal doors on the building. Assess the frames on a case/ by/case basis. If decay is extensive, replace hollow metal frame and door. Replace hollow metal doors and frames at north screen wall with galvanized steel gates with plate stock for privacy. Refurbish and update hardware on aluminum doors as required. 3

1.4 Curtain Wall with Insulated Metal Panels 1.4.1 Curtain Wall with Insulated Metal Panels Description On the north and south elevations of the building, the outer envelope mainly consists of aluminum curtain walls with insulated metal panels with porcelain enameled exterior and galvanized sheet metal interior. The east elevation has curtain wall from the ground to the roof for the center section. This curtain wall area incorporates the main entrance. This area is primarily glazed with ¼ inch plate glass. In 1977, the lower level glass was replaced with tempered glass per an OSHA upgrade. 1.4.2 Curtain Wall with Insulated Panels Condition The condition the curtain wall varies. At many locations on the north side, the base is coming apart. There are many locations where the gaskets are coming out (Curtain Wall Photo #1). It appears over the years some of the panels have been replaced with a different white metal (Curtain Wall Photo #2). The south side is in better condition than the north; however it still needs to be updated. The metal panels are intact on the east entrance elevation. 1.4.3 Curtail Wall with Insulated Panels Recommendation Clean all aluminum mullions and muttons. Replace all aluminum panels with insulated aluminum panels. Replace all glazing with insulated glass. Only the east elevation above the exterior canopy would need low/e glass. 1.5 Exterior Concrete North Yard 1.5.1 Exterior Concrete Description The north yard is exposed aggregate, poured in place concrete panels, with redwood dividers. 1.5.2 Exterior Concrete Condition The exposed aggregate concrete in the north yard area is deteriorating (Exterior Concrete Photos #1 & 2). There are uneven areas: broken, chipped and cracked concrete through enclosure (Exterior Concrete Photos #3 & 4). There is a walkway approaching a man door to the west, where the concrete has sank and created an uneven step into the building. 1.5.3 Exterior Concrete Recommendation The north patio area should be demolished. The base under the panels should be removed and reused if possible. Replace area with new concrete, similar to existing. 4

1.6 Roll/Up Door 1.6.1 Roll/Up Door Description There is a steel roll/up door on the west elevation. The dimensions for the door are 12' x 16'. 1.6.2 Roll/Up Door Condition The door operates functionally but has numerous dents throughout and the paint is failing (Roll/Up Door Photo #1). 1.6.3 Roll/Up Door Recommendation 1.7 Trellis Replace the roll up door. 1.7.1 Trellis Description The large steel trellis spans the east entrance of the building. It has a structural steel frame, metal deck and single ply roof. 1.7.2 Trellis Condition All the functional components appear to be in good shape. The paint is flaking off in many areas and birds are currently nesting inside the trellis (Trellis Photos #1 & 2). 1.7.3 Trellis Recommendation Clean and prep all painted steel. Resurface with a high quality exterior grade industrial paint. To stop birds from nesting, fill underside of trellis with a soffit. 1.8 Grating at Areaway 1.8.1 Grating at Areaway Description There are multiple galvanized grates over the areaway that the west side of the building. The entire grate is 46 x 8. 1.8.2 Grating at Areaway Condition The grating at the areaway was used as a backdrop for painting. The grating is in good condition (Grating Photo #1). 1.8.3 Grating at the Areaway Recommendation Clean the grating and re/install. 5

1.9 Exterior Informational Signage 1.9.1 Exterior Informational Signage Description Signs on the exterior of the building that guide to the box office and the upper and lower regions of freeborn. 1.9.2 Exterior Informational Signage Condition Signs are very faded. 1.9.3 Exterior Informational Signage Recommendation Replace with new signs. 6

2. Architectural Systems Interior 2.1 First Floor Lobby 2.1.1 First Floor Lobby Description The main lobby has high vaulted ceilings with painted concrete beams and plaster. The main floor is carpet tiles laid over the original terrazzo flooring with carpet tile 4 base. There are 6 8 x 4 walk/off mats in front of each entry door. There are terrazzo stairs on the north and south side of the lobby leading up to the mezzanine area. The wall mounted aluminum rails on the sidewall and 32 picket aluminum rail on the lobby side. The lower north wall has oak veneer flush mounted panels with a reddish brown stain on them. There are also two doors, one 3 0 x 7 0 oak veneer door entering one office area, and a 3 0 x 7 0 entering the co/ed accessible bathroom. The east wall is an aluminum mullion curtain wall with ¼ plate glass and insulated metal panels covered by fabric covered acoustical panels. It has four 6 0 x 7 0 double oak veneer doors exiting the lobby. All have rim device panic hardware with a center mullion. The lower west wall has oak veneer flush mounted, stained panels. There are four ¾ oak veneer doors entering the main auditorium, with an 8 plaster soffit above the doors. The wall up to the ceiling above the soffit is painted texture plaster. 2.1.2 First Floor Lobby Conditions The plaster ceiling has some cracking (Lobby Photo #1) and there is a crack out of the apex of the underside of the concrete beam. The painted beams have some minor flaking in a couple of areas (Lobby Photo #2). The terrazzo stairs leading to the mezzanine have various chips in the nosing (Lobby Photo #3). The aluminum wall rails on the north and south are loose. The guard rails at the stair landings have missing pickets (Lobby Photo #4). The carpet tile has edges coming up and some minor pulls. The lower north wall flush veneer panels have some scratches and other areas the finish has been removed (Lobby Photo #5). The restroom door and office door have scratches and finish issues on the frame and damage to the casing. The lower south wall has minor scratches and some holes from earlier mountings. The doorframe and casing to the ticket office has damage. The curtain wall to the east had plate/tempered glass installed in 1977. There is vandalism scratched into one glass pane on the south lower corner panel (Lobby Photo #6). The acoustical panels have minor blemishes on one panel at the north door, the rest appear clean (Lobby Photo #7). The exit doors all have finish damage to the inside oak veneer in the upper half of the doors (Lobby Photo #8). The automatic door bottoms on all east doors are not sealing tightly to the thresholds. The lower west wall has some finish missing where surface mounted wire molds and electrical boxes have been removed (Lobby Photo #9). The rest of panels and the door casing have finish damage. The four sets of entry doors to the 7

auditorium have minor finish damage. The plaster soffit above the auditorium entry has some insets, but the plaster has no visible cracks or damage. The upper west plaster wall has some dirty areas, but otherwise is solid. 2.1.3 First Floor Lobby Recommendations Repair and repaint concrete beams and ceiling. Repair chipped terrazzo on the stairs. Replace all handrails and guard rails with code compliant rails. Refinish all panels and doors. Clean all acoustical panels. Replace all entry doors and hardware. Replace damaged glass. 2.2 Lobby Co/Ed Bathroom 2.2.1 Lobby Co/Ed Bathroom Description The downstairs co/ed bathroom for the lobby has 2 x 2 acoustical tile ceilings. The floor is 2 x 2 ceramic tile with a floor drain in the center of the room. The north wall has a 5 2 x 2 white ceramic tile wainscot with painted gypsum board wall. There are two paper dispensers, a grab bar and an out of order feminine product dispenser on the wall. The west wall has 5 ceramic tile wainscot with painted gypsum board to ceiling level. This wall has a wall mounted lavatory with a 2 x 3 stainless steel trim mirror and sanitary napkin dispenser. The east wall has 5 ceramic tile wainscoting and painted gypsum board above. This wall has a soap dispenser, 2 paper towel dispensers and a baby changing station. The south wall has 5 ceramic tile wainscot with painted concrete above. There is a 3 0 / 2 0 oak veneer door with 2 sets of coat hooks mounted on it. 2.2.2 Lobby Co/Ed Bathroom Condition The ceramic tile on the wainscot has grout deteriorating and is falling out (Lobby Co/Ed Bathroom Photo #1). The door is missing a closer cover (Lobby Co/Ed Bathroom Photo #2). The hollow metal steel door frame has the paint coming off of it. The rest of the finishes are okay. 2.2.3 Lobby Co/Ed Bathroom Recommendations Re/grout ceramic tile on all wainscot, where deterioration has occurred. Replace the closer cover. Prep and paint the doorframe. Refinish the door. 2.3 Assembly Area 2.3.1 Assembly Area Description The main auditorium has high vaulted ceilings with every other bay alternating between plastered and plaster with 1 x 1 glue/up acoustical tile. The bays are separated by large concrete precast beams that create the frame of building. The painted beams are ~ 25 on center with large light troughs 8

suspended in the center of the open bays. The bottom of the center ridge is ~ 90 above finish floor. The north and south walls are aluminum curtain walls with insulated metal panels and ¼ plate glass. These curtain walls are covered by white peg board, installed for acoustics. There are 2 sets of metal clad exit doors on each side. The east wall is clad with acoustical oak wall from the ceiling to 8 above finish floor. The lower wall has two types of vinyl wall covering separated by an oak chair rail with 1 ½ oak baseboard. At the north end of the wall, there is a double door entering the office area. The door is a 1 ¾ 6 0 x 7 0 solid core wood door. There are four double doors entering the main lobby. The south end has standard utility double 1 ¾ 6 0 x 7 0 solid core wood doors entering the storage area. The west wall is the stage with a wood proscenium made of oak veneer and acoustical panels with oak trim. The stage front is oak veneer panels. There are oak cabinet doors that open to under the stage. There is an upper seating area approximately 21 above the main floor with ramps coming out in the north east and south east corners. There are 2 sets of 3 riser stairs coming out of the lower level. The upper area is lined with aluminum rail 36 high with aluminum pickets on the rails. The south upper seating area has wooden ramps into the stage area. The north area has wood stairs onto the stage area. The flooring on the upper and lower levels is all composed of tongue and groove 2 ¼ solid maple. The upper seating, both north and south, has two sets of fives tier retractable seating with 12 seats per row with an additional 2 seats on the top row. The east retractable tier seating has tiers with 32 seats per tier. The thirteenth tier has 38 seats. 2.3.2 Assembly Area Condition The plaster ceiling has very few small cracks. Tiles are separating, causing ridges in some of the areas with 1 x 1 glue/up acoustical tile. The painted beams are in good conditions. The metal light troughs appear to have very few dents (Assembly Photo #1). The condition of the curtain walls behind the peg board and the exit door are being addressed in the exterior sections. The peg board covering the curtain wall on the inside has few areas that need minor repair (Assembly Photo #2). The upper acoustical wall on the east is in good condition. The vinyl wall covering on the lower two section has some buckling and seam separation. The chair rail is in good shape. The wood base is in need of refurbishing. The 6 0 x 7 0 door at the north end of the east wall is damaged. The four 3 double doors entering the lobby are in need of paint on the auditorium side. The utility doors into the stage area are damaged with small dents. On the proscenium walls, the acoustical panels are dirty. 9

The wood veneer panels are faded, scratched and damaged. The wood trim is faded and the finish is damaged. The doors to the storage area under the stage are worn and scratched and some are missing wood pulls on the front. The doors mostly function well. The maple stairs on the southwest side of the auditorium have a cracked lower tread (Assembly Photo #3). The face of the upper riser on the two stairs on the north is coming apart (Assembly Photo #4). All four stairs have finish issues and damage to the nosing strips (Assembly Photo #5). The face of the upper seating area has 10 wood base that is separating from the wall. In some places it is separated up to 3/8. The bottom of the northeast ramp into the lower area has damage at the end of the inner ramp curb (Assembly Photo #6). The 36 aluminum rail that lines the upper seating area is damaged in places and missing some pickets throughout (Assembly Photo #7 & 8). The inner handrails on both ramps out of the lower seating area are loose and one is detached. The 2 ¼ tongue and groove maple flooring throughout the upper and lower levels has some cracking and separation (Assembly Photo #9). 2.3.3 Assembly Area Recommendations Clean the ceiling beams and light troughs. Repair holes in the peg board. Replace all vinyl wall coverings. Refinish the chair rail and oak base on the east wall. Refinish the doors entering the lobby. Repair and refinish the utility doors into the storage room on south end of the west wall. On the proscenium walls, replace the acoustical panels; refinish the panels and wood trim. Repair and refinish the doors to the under stage area. Repair and refinish all maple stairs and trim in this area. Replace all aluminum handrails along the edge of the lower seating area. Refinish all the tongue and groove maple flooring. 2.4 First Floor NW Corner Dressing Room 2.4.1 First Floor NW Corner Dressing Room Description Area includes rooms 111, 112, 114, 119 and the adjacent stairs. Room 111 has carpet flooring, painted walls and 1 x 1 acoustical glue/up tile ceiling. There is a long make/up mirror and countertop applied to concrete along the north wall. Room 112 is a bathroom, with epoxy flooring and painted gypsum board tile. The walls are a solid surface polymer. Rooms 114 & 119 have painted gypsum board walls with carpet floors and painted concrete ceilings. 2.4.2 First Floor NW Corner Dressing Room Condition The carpet has pulls and stains in it. The painted walls have scratches and gouges with the paint peeling off. The glue up 1 x 1 tile ceiling looks tight and sound with a couple of dented tiles. The make/up mirror is in good condition. The counter top has some scratches and is pulling away from the wall mounted splash. Caulk has been tried as a repair. The wood door and 10

frame exiting the room on the west are chipped and damaged. The epoxy floor in the bathroom looks in good shape, but has some water stains. The solid surface walls look good. All finishes in Room 114 are in good condition. Access was not available to Room 119, we are assuming it is in similar condition to Room 114. 2.4.3 First Floor NW Corner Dressing Room Recommendations Leave the restroom and shower area as is. Install new make/up counter and patch and repaint walls. Replace damaged ceiling tile and paint to blend. Replace all carpet. Refinish the exit door. 2.5 Second Floor NW Corner Dressing Room Area 2.5.1 Second Floor NW Corner Dressing Room Area Description This area includes rooms 214, 215, 216 & 218. The stairs leading to the dressing room are concrete with painted walls. The stairs have mounted oak handrails. Room 214, the main dressing room, has carpet flooring, painted walls and glue/up 1 x 1 acoustical tile ceilings. There is a counter and long make/up mirrors surrounded by lights on the north wall. Room 216 is a bathroom and shower. The room has epoxy flooring, painted gypsum ceilings and solid surface walls. Rooms 215 and 218 are both storage rooms. They have painted gypsum board walls and carpet floors and concrete ceilings. 2.5.2 Second Floor NW Corner Dressing Room Area Condition The concrete stairs leading up to the upper dressing room are in good condition with some nosing strips worn down. The plaster wall to the north in the stairwell has a large crack going horizontally and vertically down the wall with some spawling (Second Floor NW Dressing Room Photo #1). The oak rail is secured to wall, but has paint on the backside of the rail (Second Floor NW Dressing Room Photo #2). The painted walls have some chips (Second Floor NW Dressing Room Photo #3). The 1 x 1 acoustical tiles look sound except for a few dents. The make/up mirrors and lights look good. The plastic counter top has many scratches. The bathroom painted ceiling is in good shape. The epoxy floor is in good shape. The solid panels on the walls are in good condition. The storage closet 218 finishes are good. Room 215 was not able to be accessed and assume it is similar to 218. 2.5.3 Second Floor NW Corner Dressing Room Area Recommendations Repair the large crack in the stair wall. Ground and polish the concrete stairs and put new nosing strips on them. Strip and refinish oak handrail. Patch and paint all walls. Replace carpet with a commercial grade multi/color tight carpet. Replace the make/up counter. Replace the damaged 1 x 1 acoustical ceiling tile and paint. 11

2.6 Stage 2.6.1 Stage Description The stage floor is a black welded vinyl with a 2 ¼ tongue and groove maple flooring apron. The room to the north that contains the electrical and audio panel is framed with K studs with lath and plaster and painted black. The south side enclosure is a concrete shaft painted black. All the utilities in the above stage area are painted black. The west wall of the stage is concrete painted black with a roll away door, in front of the roll/up door entering the back of the stage. The east wall is gypsum board, painted white. On the south side of the stage, there is a small hallway wood stair with three raisers and an oak handrail. The walls are gypsum board, painted white. There is an exit door at the bottom of the stair with rim mounted panic hardware and a cardboard exit sign. The floor at the bottom of the landing is concrete. The south most side of the stage has the entrance to the freight elevator set in a concrete wall, painted white. There is a painted wood door through the southern proscenium wall as well as at the north. The northern most wall is a mixture of gypsum board, plaster and concrete, all painted white. There is a painted wood door entering 214. There is a rigging frame mounted to the wall. In this area the ceiling is exposed and unpainted. There is an exit hallway with wood treads and raisers and an oak handrail. There is a hollow metal exit door at the bottom of the stairs exiting to the rear of the building. This area has concrete walls to the west with gypsum and plaster walls to the east. To the east is a wood entrance door to the dressing room. This area has a plaster ceiling. 2.6.2 Stage Condition The black vinyl floor is in good condition with some scratches and scuffs, but no more than normal wear and tear of a stage. The maple tongue and groove apron is holding together tightly with a few minor gaps. The maple floor has scratches and scuffs throughout (Stage Photo #1). The plaster enclosure to the north needs minor patchwork and painting. The concrete shaft to the south needs very minor touch/up paint in areas. The paint on the structure and utilities about the stage appears fresh. The painted concrete west (back) wall is in good condition. The large sliding door has a few minor dents. The back of the south proscenium wall has some gouges that need patch and repair (Stage Photo #2). The south exit door riser treads and skirt of the wood exit stair needs refinishing. The east wall has some dents and bubbles in the paint. The exit sign is made of cardboard and is in unacceptable condition. The oak handrail is solid. The southern wall containing the freight elevator has some gouges out of the wall and torn base. The wood frame and door exiting the stage area through the proscenium wall are both damaged (Stage Photo #3). The north door has minor scuffs. The north stage wall is in sound condition. 12

The door going into room 214 has paint peeling off. The wood exit stairs appears structurally sound but are dirty and the handrail is loose. The corner of the wall is chipped. The ceiling is functional. 2.6.3 Stage Recommendations Repair and refinish the maple flooring on the stage apron. Patch and repair all the minor plaster and gypsum walls and repaint. Refinish both the stairs to exits north and south and install new abrasive nosing strips. Replace exit signs into the southwest stair wall from the south exit from the stage area. Repair loose handrail on the north stair to the rear exit. Prep and repaint door entering the upstairs dressing room. 2.7 South Lobby Mezzanine 2.7.1 South Lobby Mezzanine Description The south and west walls are oak veneer architectural wood panels flush mounted with trim at the base of wall and door casings. There is an oak veneer door to Room 209, the Men s Restroom and Room 207, the Control Room. The east wall is textured plaster painted white. The floor is sectioned terrazzo with two different aggregate patterns and separated by black inlay. There is an aluminum rail bordering the north side of the platform. 2.7.2 South Lobby Mezzanine Condition The oak veneer panels are in good condition with a few minor chips in the finish. The oak door to the men s room is scratched and the finish is chipped (South Lobby Mezzanine Photo #1). The door to Room is 207 is scratched. The plaster on the east wall has minor cracks from where a previous repair was done. The terrazzo floor is in excellent condition. The aluminum rail has some missing brackets (South Lobby Mezzanine Photo #2). 2.7.3 South Lobby Mezzanine Recommendations Repair minor blemishes in the wood panels and refinish as needed. Refinish the doors to the men s room and control room. Replace all aluminum guardrails with new code compliant railing. 2.8 North Lobby Mezzanine 2.8.1 North Lobby Mezzanine Description The north and west walls have oak veneer architectural wood panels flush mounted with trim at the base of wall and door casings only. There is an oak veneer door to Room 204, the Woman s Restroom and Room 207, the control room. The east wall is textured plaster painted white. The floor is sectioned 13

terrazzo with two different aggregate patterns and separated by black inlay. There is an aluminum rail bordering the north side of the platform. 2.8.2 North Lobby Mezzanine Condition The oak veneer panels are in good condition with a few minor chips in the finish. The oak door to the women s room is scratched and the finish is chipped. The door to Room is 207 is scratched. The terrazzo floor is in excellent condition. The aluminum rail has some missing brackets. 2.8.3 North Lobby Mezzanine Recommendations Repair minor blemishes in the wood panels and refinish as needed. Refinish the doors to the women s room and control room. Replace all aluminum guardrails with new code compliant railing. 2.9 Mezzanine Men s Restroom 2.9.1 Mezzanine Men s Restroom Description The entrance vestibule has four vinyl covered painted walls. There is a hollow metal door with a louver entering the mechanical room 210. There is an oak veneer door entering the upper lobby to the mezzanine. A painted wood door enters the men s room. The floor is terrazzo with a four inch cove base around the room. The ceiling is glue/up 1 x 1 acoustical tile with 2 x 2 surface mounded lights. The washroom has painted gypsum board walls on the north, south and east. The west wall is a patterned 1 x 1 ceramic tile. The wall has four stainless steel framed mirrors with a 4 stainless steel shelf below. There are wall mounted soap dispensers and two wall mounted mirror lights. The north and south walls have two towel dispensers. The ceiling is glue/up 1 x 1 acoustical tile with 2 x 4 surface mounded lights. The floor is terrazzo with 4 core base. In Room 209B, the west wall is 4 x 4 ceramic tiles to the top of the door jamb with painted gypsum board to the ceiling level. There are four urinal stalls with solid polymer grey privacy screens separating them. The north and south wall are painted gypsum board outside the stall area. The stalls area is 4 x 4 ceramic tiles on the east, north and south walls. There are five standard stalls with water closets, seat guard dispensers and toilet paper dispensers. The stalls are painted metal. The ceiling throughout the room is painted gypsum board. 2.9.2 Mezzanine Men s Restroom Condition In Room 209, the paint looks good but the wall covering is peeling at the base of the wall (Mezzanine Men s Restroom Photo #1). The terrazzo floor and base 14

have little damage. The ceiling is in fair condition. There is a non/functioning light in the center of the ceiling. In Room 209A, the painted wall panels are peeling off from the bottom up. The west wall tile is intact. The wall mounted sinks are an old style with different fixtures and one is missing the ply where the soap dispenser used to be (Mezzanine Men s Restroom Photo #2). The right hand mirror is delaminated from the face of the glass. Soap dispensers are working. The towel dispenser on the north and south wall appear to be retrofitted into an old trash receptacle. In Room 209B, the west wall ceramic tile is in fair condition with some cracking. Painted gypsum board is in good condition. The urinal fixtures are in mixed condition and are the old style. The urinal screens are a solid polymer and appear to be fairly new (Mezzanine Men s Restroom Photo #3). 2.9.3 Mezzanine Men s Restroom Recommendations The bathroom needs to be fully renovated. 2.10 Mezzanine Woman s Restroom 2.10.1 Mezzanine Woman s Restroom Description In the entrance vestibule has four vinyl covered painted walls. There is a hollow metal door with a louver entering the mechanical room 208. There is an oak veneer door entering the upper lobby to the mezzanine. A painted wood door enters the women s room. The floor is terrazzo with a four inch cove base around the room. The ceiling is glue/up 1 x 1 acoustical tile with a 2 x 2 surface mounded light and a smaller round light. Room 201 has 4 large, square mirrors along the west wall with a counter and benches. There are 3 wall mounted lights above the mirrors (Mezzanine Women s Restroom Photo #1). The ceiling is glue/up 1 x 1 acoustical tile with 2 x 4 surface mounded lights. The floor is terrazzo with 4 core base. In Room 202, there are 5 lavatory stalls along the east wall. The stalls are made of metal. Each stall has a toilet seat cover dispenser, toilet paper dispenser and a trash receptacle. The walls in the stalls are 4 x 4 ceramic tiles. The floors are the same terrazzo with 4 cove base as in the rest of the area. The west wall 4 sinks, 2 on either side of the opening into Room 201 (Mezzanine Women s Restroom Photo #4) 2.10.2 Mezzanine Women s Restroom Condition The 1 x 1 acoustical tile is old and dirty throughout (Mezzanine Women s Restroom Photo #2). The vinyl wall covering is peeling up at the bottom in room 201 (Mezzanine Women s Restroom Photo #3). The terrazzo floor 15

throughout is in good condition, with some water damage under the sinks and toilets. The paper towel dispenser in room 202 is broken, but functional. 2.10.3 Mezzanine Women s Restroom Recommendations 2.11 Control Room The bathroom needs to be fully renovated. 2.11.1 Control Room Description The Control Room is Room 207. The room has gypsum board walls and painted flat black ceiling. The floor is concrete. There are two large plexi/ glass windows in the center that face out to the auditorium, and two smaller plexi/glass windows on each side. The inside window sill and jambs are oak veneer. There is a small partial window in the hallway. 2.11.2 Control Room Condition The ceiling is in good condition. The walls have some chipping in the paint and areas where the gypsum board has broken. The wood door exiting the room on the south is chipped and scratched (Control Room Photo #1). The concrete floor has cracks throughout (Control Room Photo #2). The large windows to the auditorium are in good shape. The slider on the north is intact, but the tracks on the slider broken (Control Room Photo #3). The glass is missing on the south slider. The oak veneer trim on the windows is in good condition. The portal window has no glass just frame. The north door is scratched. 2.11.3 Control Room Recommendations 2.12 Crew Room Fix all minor wall damage and repaint the wall. Reinstall missing plexi/glass sliders and viewpoints. Refinish the doors. 2.12.1 Crew Room Description This is the beginning first floor of the suite. All walls are painted purple with yellow trim. The utilities in the ceiling area are exposed and painted yellow. The floor is stained concrete with vinyl base. There is a stage cage to the east, a double oak veneer door into the auditorium area and tow oak veneer doors on the south wall entering the offices. 2.12.2 Crew Room Condition The painting appears to have not been done by a tradesman, there is over paint on the jambs. The oak door in to the auditorium has scratches and 16

dings in it. Sections of vinyl base are coming loose. There is a new conduit hole on the south wall that needs to be sealed. 2.12.3 Crew Room Recommendations Repair and refinish doors to the auditorium. Prep and repaint room. 2.13 The Offices, Room 104A, 104B and 104C 2.13.1 The Offices, Room 104A, 104B and 104C Description In Room 104 A, the east wall is painted gypsum board. It has oak veneer doors with hollow metal frames and four fixed windows at the ceiling level. The north and south wall are painted gypsum board with oak veneer doors in hollow metal frames. The west wall is concrete painted grey. The ceiling is 1 x 1 glue/on acoustical tile. The flooring is carpet with vinyl base. In Rooms 104B & 104C, the north and east walls are painted gypsum board. The south wall is painted concrete. The west wall is painted gypsum with hollow metal frame with wood veneer door and there are two fixed windows of ceiling level. The ceiling is 1 x 1 glue/on acoustical tile. The flooring is carpet with black vinyl base. 2.13.2 The Offices, Room 104A, 104B and 104C Condition In Room 104A, the north and south painted walls are in fair condition. The oak veneer door entering the crew room appears in good condition. The one on the south entering the lobby has a chip in it. The glue/on acoustical tile ceiling looks in fair condition with some tile damage. The carpet is in poor condition. In Rooms 104B & 104C, the painted walls appear in good condition. The hollow metal doorframe has paint chips on it and is missing silencers. The ceiling had some damaged tiles. 2.13.3 The Offices, Room 104A, 104B and 104C Recommendations Refinish doors in this area. Install new carpet and base throughout. Prep and repaint walls. Repair damaged ceiling tiles and repaint. 2.14 Auditorium Storage Room, Room 109 2.14.1 Auditorium Storage Room, Room 109 Description This area is a general storage room. The west wall is painted concrete and plaster. There is a serving window in the center of the wall with a stainless steel jamb and two oak doors that open into the auditorium. There are two sets of wood double doors in hollow metal frames. The set to the north opens into the auditorium and the one to the south opens into the room. There are 17

stainless steel corner guards on the inside jambs. The north wall is painted plywood. The east wall is a combo of painted gypsum board and plaster. The south wall is painted plaster with a single 3 0 x 7 0 door exiting to the south with a hollow metal frame. The flooring is 12 x 12 ceramic tile with 4 base. The ceiling has 2 x 4 acoustical ceiling tile. The south wall has a double sink with a cabinet below and a laundry counter. There is wood shelving on the wall. 2.14.2 Auditorium Storage Room, Room 109 Condition The painted concrete finish on the west wall is in fair condition with marks and scratches. The north door is coming loose and will not close properly. The closures are mismatched. The jambs are chipped and the paint is flakey. The north wall is in good condition for a storage room wall. If the program for the room changes, this wall would need to be improved. The east wall has damaged corners and holes (Storage Room Photo #1). The south wall is in fair condition, but the door jamb is chipped. The sink counter and cabinets are damaged (Storage Room 109 Photo #2). The ceiling is in poor condition with many broken tiles (Storage Room 109 Photo #3). The tile floor is in good condition, but some of the base is missing. 2.14.3 Auditorium Storage Room, Room 109 Recommendations Repair, repaint or refinish all doors in the room. Patch and repair all walls and repaint. Replace cabinets and counter tops. Replace acoustical ceiling. 2.15 Box Office, Room 107 2.15.1 Box Office, Room 107 Description The box office room has a 2 x 4 acoustical tile ceiling. The floor is 12 x 12 VCT standard beige tile with 4 brown resilient base. The west wall is painted concrete with an oak veneer. The room has a 1 ¾ door in a hollow metal frame. The door has a 2 x 3 plexi/glass ticket window with 2 x 7 stainless steel shelf on both sides of the door, ~42 off the floor. The south wall is painted gypsum board wall. The west wall is painted plaster with exposed wire mold and conduits. The east wall is painted gypsum wall board with plexi/glass ticket windows set between wood 4 x 4 stainless steel sections with a plastic laminate counter top. There are plastic laminate draws and cabinets under 15 deep counters along the wall. There are four 2 x 4 x 3 6 plastic laminate vinyl banding sections of the counter that come out between the ticket windows. They have plastic laminate shelving draws and cabinets under these sections. There are three 1 x 1 9 privacy partitions on top of the counter on the left side of the last three ticket windows. 18

2.15.2 Box Office, Room 107 Condition The 2 x 4 acoustical ceiling is in poor condition with separated grid and broken tiles (Box Office Photo #1). The VCT flooring is worn through the finish is some areas. The painted wall has chips and gouges. The west wall has cracks and a hole with wires hanging out (Box Office Photo #2) and multi/ colored surface mounted. Some of the cabinets under the ticket counter have missing doors (Box Office Photo #3). 2.15.3 Box Office, Room 107 Recommendations This room would need a complete renovation, replacing all finishes. 2.16 Storage Room, Room 106 2.16.1 Storage Room, Room 106 Description The ceiling is 2 x 4 acoustical tile. The flooring is 12 x 12 VCT with 4 vinyl base. The north wall is painted concrete with 2 strips of 1 x 1 acoustical tile running horizontal in a 5 x 7 band. The west wall is painted gypsum board with the 5 x 7, 1 x 1 acoustical tile band on it. There is a standard oak veneer door with a louver and a painted hollow metal door frame. The south wall is covered in 1 x 1 acoustical tile and painted white. The east wall is painted plaster with a stained oak veneer door and a painted hollow metal frame. 2.16.2 Storage Room, Room 106 Condition The 2 x 4 acoustical tile is in poor condition. The gird is separating and some tiles are broken. The VCT floor has the finish worn off in some areas. The north and west wall acoustical tile bands are intact. The south solid 1 x 1 acoustical tile wall has some damage. The east wall has minor paint damage. The oak door has minor blemishes and the door frame paint is chipped. 2.16.3 Storage Room, Room 106 Recommendations Replace the VCT floor tiles and the acoustical ceiling. Repaint the walls. Refinish the doors. 2.17 Lower Freeborn Corridors 2.17.1 Lower Freeborn Corridors Description The corridors throughout the majority of lower freeborn have plaster walls & ceilings and 9 x 9 VAT tile floors. The exception to this is in the western most corridor outside of Room 5. This area has 2 x 4 acoustical panel ceiling and the west wall is painted CMU. 19

2.17.2 Lower Freeborn Corridors Condition The 9 x 9 VAT tiles are in poor condition. The flooring in the southwest of the building has cracks and large crevasses, where it appears the material underneath the tile has sunk down (Lower Corridor Photo #1). The vinyl baseboard throughout the corridors is in poor condition (Lower Corridor Photo #2). It is cracked and missing pieces in many places. 2.17.3 Lower Freeborn Corridors Recommendations It is recommended that the flooring and baseboards be replaced in all the corridors. Repair substrate damage and install new VCT and vinyl base. 2.18 Student Affairs Office 2.18.1 Student Affairs Office Description This area consists of Rooms 10A/J, 7A/C, 6 and 6A in Lower Freeborn. This area has carpet floors, painted walls and a 2 x 4 second look acoustical tile ceiling. 2.18.2 Student Affairs Office Condition The condition of this entire area is very good. The paint looks fresh and the carpet has little to no wear. The entire area was remodeled in two different phases, Room 10 in 1996 and rooms 6 & 7 in 2002. 2.18.3 Student Affairs Office Recommendations No architectural recommendations. 2.19 KDVS Radio Station 2.19.1 KDVA Radio Station Description The KDVS Radio Station is made up of Rooms 14A/N and Room 15. Rooms 14, 14A, 14E, 14F, 14L and 15 have plaster ceilings. Rooms 14B, 14C, 14D, 14G, 14H, 14M & 14N all have 1 x 1 glue/up acoustical tile. The entire area is 9 x 9 VAT tile. Portions of the tile have been covered with pieces of carpet. Rooms 14, 14B, 14C, 14D, 14E and 14L have carpet laid over the tile. All the walls are painted. Rooms 14B, 14C and 14E have acoustic foam glued to the walls because they are sound studios. 2.19.2 KDVS Radio Station Condition The conditions of these rooms range from fair to poor. The plaster ceilings are intact and do not appear to have any cracks. However the walls and ceilings are covered in posters and flyers, so the view of the condition is often obstructed. The 1 x 1 acoustical tile ceilings could use some improvements. 20

This is especially true in rooms 14B & 14C. The users informed us they no longer use 14B for radio shows because the tiles continually fall down (KDVS Photo #1). The acoustical foam on the walls in this room is also damaged and falling off in places (KDVS Photo #2). The floors are in okay condition. 2.19.3 KDVS Radio Station Recommendations Replace all VAT flooring and repair ceiling and walls. 2.20 The Newspaper Rooms 2.20.1 The Newspaper Rooms Description Rooms 24 and 26 are used for the Aggie newspaper. This area also includes a darkroom that is off of room 24. The rooms have 1 x 1 glue/up acoustical tile and 9 x 9 VAT tile. The walls are a mix of painted gypsum and plaster walls. There is a fire curtain in the north wall of the room into the corridor. It has a stainless steel shelf on both sides. 2.20.2 The Newspaper Rooms Condition The conditions of these rooms are poor. The ceiling tile is very old, dusty and damaged (Newspaper Room Photo #1). The air vents are old, and the one in the darkroom is missing. There is a large crack in the wall at the door to the darkroom (Newspaper Room Photo #2). 2.20.3 The Newspaper Rooms Recommendations Replace all 9 x 9 VAT tile with new VCT tile. Repair ceilings, replace damaged tiles. Clean and paint ceiling. Repair and paint all walls and doors. 2.21 The Dance Room, Room 5 2.21.1 The Dance Room, Room 5 Description This room has 2 x 4 acoustical ceiling tiles and Masonite flooring on wood. The other areas are 9 x 9 VAT and carpet tile. The north wall has a full length dance mirror along the wall. The east wall has a dance bar running the length of the wall. The walls are painted plaster. 2.21.2 The Dance Room, Room 5 Condition The room overall is in fair condition. The Masonite flooring is in poor condition. It has water marks (Dance Room Photo #1) and is peeling up at the seams in some places (Dance Room Photo #2). The 2 x 4 acoustical tiles on the ceiling are functional. They have some watermarks and some pieces are askew. 21

2.21.3 The Dance Room, Room 5 Recommendations Replace the Masonite with dance floor material. Replace ceiling tiles as needed. Replace VAT tile with VCT tile. Paint all walls. 2.22 Rooms 5B, 5C, and 5D 2.22.1 Rooms 5B, 5C and 5D Description These storage rooms have 2 x 2 acoustical tile ceilings and 9 x 9 VAT floors. Painted black chain link fence sections separate the rooms. The south and west walls are painted CMU. The north wall is painted concrete and the east wall is painted gypsum board. 2.22.2 Rooms 5B, 5C, and 5D Condition The flooring has water damage near the south wall (Room 5B, 5C & 5D Photo #1). The ceiling is old with broken and peeling tiles (Room 5B, 5C & 5D Photo #2). The CMU wall to the west has a large crack in it. The other walls have chips and other blemishes in the paint. 2.22.3 Rooms 5B, 5C and 5D Recommendations Replace VAT tile with VCT. Remove ceiling and paint. Repaint walls. 2.23 Room 13, 13A & 13B 2.23.1 Room 13, 13A & 13B Description These rooms have 9 x 9 VAT tile floors and 1 x 1 glue/up acoustical tile ceilings with surface mounted lights. The southwest and north walls are painted gypsum board. The east wall has a door to room 13A and two doors to 13B. The flooring in 13A has carpet over the 9 x 9 VAT tile floor. 2.23.2 Room 13, 13A & 13B Condition The ceilings and walls are in poor condition (Room 13 Photo #1). The east wall of room 13 is painted acoustical fabric panels. The door to 13A is missing (Room 13 Photos #2). There are light lenses missing. The carpet in 13A is torn and beyond repair. 2.23.3 Room 13, 13A & 13B Recommendations Replace VAT tile with VCT. Remove ceiling and paint. Repaint walls. 22

2.24 Room 3A 2.24.1 Room 3A Description The electrical room has exposed insulation on the walls and ceiling. The floors are concrete. 2.24.2 Room 3A Condition Insulation has been removed in some areas. Floors have some spawling in the concrete. 2.24.3 Room 3A Recommendations Repair floors and replace all the insulation with spray on acoustical/thermal insulation. 2.25 The Mechanical Room 2.25.1 The Mechanical Room Description The room has exposed insulation on the ceiling. South, east, west and part of the north wall has exposed insulation as well. The remainder of the north wall is painted gypsum board and concrete. The floor is concrete. 2.25.2 The Mechanical Room Condition The insulation is coming off in places throughout the walls (Mechanical Room Photo #1). The floor has a lot of spawling (Mechanical Room Photo #2). There is some abandoned equipment (Mechanical Room Photo #3). 2.25.3 The Mechanical Room Recommendations 2.26 The Elevator If a complete mechanical renovation is proposed, remove all abandoned equipment. Remove all unneeded curbs and pads. Fix all spawled concrete areas. Remove all the old insulation and use a spray/on product that will harden and work as an acoustical and thermal barrier. 2.26.1 The Elevator Description The freight elevator is in the southwest corner of the building. It goes from lower freeborn to the south side of the stage. It is very seldom used. My understanding is that it has been used 3 times in 7 years. It is currently used for storage. 2.26.2 The Elevator Condition 23

The elevator is in good, working condition. It cannot be used for passengers because of proximity and code restrictions. 2.26.3 The Elevator Recommendations Leave in place, as is. 2.27 Lower Freeborn Restrooms 2.27.1 Lower Freeborn Restrooms Description The lower freeborn restroom area includes rooms 16 & 18. Both bathrooms have a vestibule entrance with 1 x 1 glue/on acoustical tile ceiling and terrazzo flooring with 4 integral cove base. The walls are painted plaster. The door to the main bathroom and the exit door are painted. The main bathroom also has 1 x 1 acoustical tile ceiling and terrazzo flooring with 4 integral cove base. The walls have plastic panels with aluminum trim. All the partitions are solid polymer. Room 18, the men s restroom, has two standard stalls and one ADA stall. There are three urinals with solid polymer privacy screens on the north wall. The south wall has three lavatories and three mirrors with soap and towel dispensers. The west wall is painted gypsum board. Room 16, the women s restroom, has four standard stalls and one ADA stall on the south wall (Lower Freeborn Photo #1). Each stall has a trash receptacle, toilet paper dispenser and a toilet seat cover dispenser. The north wall has three sinks with mirrors, two soap dispensers and two paper towel dispensers, mounted on the wall (Lower Freeborn Photo #2). 2.27.2 Lower Freeborn Restrooms Condition In Room 18, the vestibule has cracked plaster around the light switch (Lower Freeborn Photo #3). The paint in the door entering the main bathroom is chipped (Lower Freeborn Photo #4). The lever door hardware is not functionally properly (Lower Freeborn Photo #6). The main restroom has a few mounting holes in the north wall (Lower Freeborn Photo #5). The rest of the bathroom is in good condition. Room 16 is in very good condition. There are some water stains on the terrazzo flooring under the sinks. 2.27.3 Lower Freeborn Restrooms Recommendations In room 18, repair hardware on exit door. Repair plaster, patch and repaint. Repair holes in north wall in the main room and paint. 24

3. Site Utilities 3.1 Site Utilities / Description and Condition Refer to table below for a summary of plumbing related site utilities which serve this building. HVAC and Electrical utilities are described in the HVAC Systems and Electrical Systems sections of this report. Utility Domestic Water Size 4" Fire Water 8" Sanitary Sewer Storm Drain Natural Gas 4 4 4 10 3/4" Building Service Area Entrance Served Location West wall of Entire Bsmt. Mech. Bldg. Rm. 3 Entire Bldg. West Side & Bsmt. North- East Side South- East Side Entire Bldg. Emerg. Generat or West wall of Bsmt. Mech. Rm. 3 West wall of Bsmt. Mech. Rm. 3 North-East corner South-East corner South-East corner North-West corner Campus Source 10" DW Main along West Quad Ave. 10" DW Main along West Quad Ave. SSMH9-3NW on 8" SS Main along West Quad Ave. SSMH10-0NE on 8" SS Main along North Quad Ave. SSMH8-2NW on west south side of Bldg. to 8" SS Branch Main to 10' SS Main along West Quad Ave. SDMH8-0NW on 10 SD Branch Main to SDMH10-0NW 2" NG Main along North Quad Ave. (10 psig service) No BFP No Meter Comments PIV at street DCV in in Mech Rm 3 OS&Y in Mech Rm 3 FDC on west wall SS Lift station in Mech Rm 3 PRV & Seismic shut-off valve Serves only the emergency generator The Domestic and Fire Water building services are in serviceable condition and can be reused for the proposed renovation work scope. The condition of the Sanitary Sewer and Storm Drain is currently unknown. The Building Maintenance Services (BMS) personnel have reported that some pipe 25

sections do not drain adequately. A detailed camera inspection should be performed to determine the exact condition of piping and required work scope. 3.2 Site Utilities Recommendations Upgrade the Domestic Water service to current campus/standard configuration. This includes the addition of a backflow preventer and a water meter. These devices should be installed in the landscaped area at the west side of the building. Upgrade the Fire Water service to current campus/standard configuration. This includes the removal of the Post Indicator Valve (PIV) and the addition of a backflow preventer to replace the existing one located in the Basement Mechanical Room # 3. The new device should be installed in the landscaped area at the west side of the building. Perform a detailed camera inspection of the sanitary sewer and storm drain piping to determine the exact condition of piping and required work scope. The pipe sections to be inspected should be selected in consultation with UCD Engineering and BMS. 26

4. Fire Sprinkler System 4.1 Fire Sprinkler System Description Currently there are no fire sprinklers in Upper Freeborn Hall. Lower Freeborn has a standard fire sprinkler system throughout. 4.2 Fire Sprinkler System Condition The existing fire sprinkler system does not comply with NFPA 13/25 and UCD campus standards. The non/conforming items include the type of sprinkler heads and their placement, pipe risers with alarmed checks, seismic restraint at piping system, inspector test and drain risers, and the fire smoke alarm system. 4.3 Recommendations We recommend upgrading the fire sprinkler system to current campus standards. 27

5. Plumbing Systems 5.1 Domestic Water Systems 5.1.1 Domestic Water Systems Description and Condition Refer to the table included in the Site Utilities section for a description of the building domestic water service. Domestic hot water is generated via a storage type, steam to hot water heat exchanger located in Mechanical Room 3. The heat exchanger is original equipment of 1960 vintage, is in poor condition and has far exceeded its economic useful life. The DCW water supply to the heat exchanger is untreated water. Also, there are no tempering/scalding safety controls. The building water distribution piping is copper and appears to be in serviceable condition. The age of the plumbing fixtures located in various restroom clusters varies greatly. Most of them are outdated and worn out, while some are still in serviceable condition. 5.1.2 Domestic Water Systems Recommendations Due to age and condition, the domestic hot water heat exchanger should be replaced. The DCW supply to the heat exchanger should be provided with a non/chemical type water conditioning system (i.e. Scale Blaster). The Heat exchanger controls should have the capability to prevent against scalding conditions. If the restroom remodeling work scope is not extensive, the plumbing fixtures should be surveyed in detail to determine if they can be reused. However, if the restrooms will be extensively remodeled, then new plumbing fixtures should be provided. 5.2 Building Sewer System 5.2.1 Building Sewer System Description and Condition Refer to the table included in the Site Utilities section for a description of the building sanitary sewer service. The building sanitary sewer piping is cast iron and its condition is currently unknown. The BMS personnel have reported that some pipe sections do not drain adequately. A detailed camera inspection should be performed to determine the exact condition of piping and work scope required. A duplex Sanitary Sewer Lift Station (SSLS) is located in the Basement Mechanical Room 3 and collects all drainage from the basement restrooms 28

before pumping it up to the building main sewer system. The SSLS appears to be in serviceable condition and no issues have been reported by the BMS personnel. 5.2.2 Building Sewer System Recommendations Perform a detailed camera inspection of the sanitary sewer main piping to determine its exact condition and work scope required. This should be done by a contractor or consultant with a camera at specific locations to determine the overall system condition. Based on the experience of the campus maintenance personnel it is likely large portions of the system are in too poor of condition to support this facility for the long term. If this is confirmed, we recommended replacing the waste and vent systems in the building with new. Perform a detailed evaluation of the SSLS to determine its condition and work scope required. 5.3 Building Storm Drain System 5.3.1 Building Storm Drain System Description and Condition Refer to the table included in the Site Utilities section for a description of the building storm drain service. The building storm drain piping is cast iron and, while no major problems have been reported, its condition is currently unknown. 5.3.2 Building Storm Drain System Recommendations Perform a detailed camera inspection of the storm drain main piping to determine the exact condition of piping and work scope required. 5.4 Natural Gas Systems 5.4.1 Natural Gas System Description and Recommendations Refer to the table included in the Site Utilities section for a description of the building natural gas service. The natural gas building piping is routed from its point of entry to an Emergency Generator located in an outdoor enclosure at the North/West corner of the building. The gas piping and components are in good condition and no work is required. The generator exhaust system is not low NOx compliant and the exhaust system location does not meet building code requirements. We recommend reviewing the areas of non/compliance with the appropriate Campus department to identify options. 29

6. HVAC Systems 6.1 HVAC Air Systems 6.1.1 Air Handling Systems Description and Condition 6.1.1.1 Freeborn Hall is served by six air handling systems installed during the original building construction in 1960. AHU/1 (S1) has been upgraded in 2010, while the rest are as originally installed. These systems are summarized in the table below. Syst. Name AHU/1 (S/1) AHU/2 (S/6) AHU/3 (S/3) AHU/4 (S/4) AHU/? (S/5) MZU (S/2) AHU Location Bsmt. Mech. Rm. 3 Bsmt. Mech. Rm. 3 Janitor Rm. 204 Janitor Rm. 210 Projection Rm. Bsmt. Mech. Rm. 3 Syst. Type Single/zone VAV Single/zone CAV Single/zone CAV Single/zone CAV Single/zone CAV Multi/zone CAV Capacity* (cfm/hp) SF/30,000± RF/30,000± SF/??? SF/3,280/1.5 SF/4,480/3 SF/1,750/0.5 SF/13,960/15 * Data taken from original mechanical schedules Area Served Auditorium Basement Radio Station Lobby 1 st Flr. NE Rms. Mezz. NE Restroom Lobby 1 st Flr. SE Rms. Mezz. SE Restroom Projection Room Basement Office Spaces AHU/1 (S/1) was originally a single/zone CAV machine but it was significantly upgraded in 2010 to a fan array (Hunt Air) and converted to a single/zone VAV machine. It has a supply fan array (10 fans), a return fan array (8 fans), variable speed drives (PIC M01) for each fan motor, economizer section, primary and secondary filters, heating coil and new cooling coil. The distribution system consists of GSM supply air ductwork located above the Auditorium ceiling with ceiling supply diffusers, and GSM return air ductwork located above the Basement ceiling with side/wall return air registers located around the Auditorium perimeter. It is controlled by a Siemens Apogee DDC system. This system is in good condition. AHU/2 (S/6) is a single/zone CAV machine and was installed in 1967 when the Offices located on the East side of the basement were converted to a Radio Station. It has a supply fan, an economizer section with power exhaust into mechanical room, primary and secondary filters, heating and cooling coils. The distribution system consists of GSM ductwork located above the Basement ceiling, ceiling 30

supply diffusers and return air registers. It is controlled by a Siemens Apogee DDC system. (PIC M02) This system is original equipment of 1967 vintage and has far exceeded its economic useful life. However, it still appears to be in serviceable condition. AHU/3 (S/3) is a single/zone CAV machine. It has a supply fan, a mixing plenum with fixed outside air, primary filters, heating and cooling coils. The distribution system consists of GSM ductwork located above the First floor and Mezzanine ceiling, ceiling supply diffusers and return air registers. It is controlled by a Siemens Apogee DDC system. This system is original equipment of 1960s vintage and has far exceeded its economic useful life. However, it still appears to be in serviceable condition. AHU/4 (S/4) is a single/zone CAV machine. It has a supply fan, a mixing plenum with fixed outside air, primary filters, heating and cooling coils. The distribution system consists of GSM ductwork located above the First floor and Mezzanine ceiling, ceiling supply diffusers and return air registers. It is controlled by a Siemens Apogee DDC system. This system is original equipment of 1960s vintage and has far exceeded its economic useful life. However, it still appears to be in serviceable condition. AHU/5 (S/5) is a single/zone CAV machine. It has a supply fan, a mixing plenum with fixed outside air, primary filters, heating and cooling coils. The distribution system consists of GSM ductwork located above the Projection Room ceiling, ceiling supply diffusers and return air registers. It operates under stand/alone thermostat control and is not controlled by a Siemens Apogee DDC system. This system is original equipment of 1960s vintage and has far exceeded its economic useful life. However, it still appears to be in serviceable condition. The Multi/zone unit (MZU) has supply and return fans, economizer section with power exhaust into mechanical room, primary filters, heating and cooling coils and four pairs of zone mixing dampers. The distribution system consists of GSM ductwork located above the basement ceiling, ceiling supply diffusers and return air registers. The MZU is controlled by a Siemens Apogee DDC system. This system is original equipment of 1964 vintage and has far exceeded its economic useful life. However, it still appears to be in serviceable condition. The louvers (with backdraft dampers) at the west wall of the mechanical room which are connected to the concrete air/way are intended to relief exhaust air from the Multi/zone unit and AHU/2. 31

These dampers are of 1960 vintage and are not in operable condition. It does not appear they are in serviceable condition. All ductwork insulation is un/faced, 1 thick and either in poor condition or missing. Supply and return main ducts (with the exception of AHU/1 (S1) are of 1960 vintage, government clip and flange or slip and drive type. Joints are in poor condition and leak excessive amounts of air. Duct gauge and stiffening are not per SMACNA recommendations for operating pressures at AHU systems. Sound attenuation intended to muffle dynamic noises from mechanical equipment at mechanical room walls is un/faced 2 thick fiberglass insulation. The insulation is of 1960 vintage, is torn and delaminating in numerous areas and generally in poor condition. There are (1) 5/ton and (1) 3/ton condensing units in Basement Mechanical Room 3. The 5/ton unit is paired with a 6/ton Fan Coil Unit (FCU) which serves the Aggie Newspaper space. The FCU has exposed ductwork, a dedicated condensate pump, and is controlled by a stand/alone wall thermostat. The equipment was installed in 2003 and is in good condition. The 3/ton condensing unit is paired with a wall/mounted FCU which serves the Electrical Room. The FCU is controlled by a stand/alone wall thermostat. The Electrical Room is located inside the Basement Mechanical Room 3 at its north end. The 3/ton equipment is about ten years old, is in poor condition and it does not appear to provide adequate cooling. The refrigeration lines are not installed per manufacturer s recommendations. 6.1.2 Air Handling System Recommendations With the exception of AHU/1 which has been recently upgraded, the air handling units serving Freeborn Hall are original equipment of 1960s vintage and have far exceeded their economic useful life. They are not energy efficient and are not able to provide adequate temperature comfort for the various types of spaces they serve. However, mechanically speaking, they still appear to be in serviceable condition. This means that, with proper maintenance, their life could be extended for a few more years, but this should only be considered if the spaces they serve will not be remodeled during the seismic upgrade. The exhaust air backdraft dampers and louvers located at west wall of the air/ way should be replaced with new dampers, louvers and controls. All supply and return air ductwork insulation should be replaced with code/ complying insulation. All supply, return, and outside air ductwork located inside Mechanical Room 3 should be replaced with new ductwork constructed with leak/proof joints, 32

seams, and of SMACNA/ approved construction for the service pressure class. All other ductwork that would become exposed during the remodeling work should be evaluated at that time if it can be reused or replace with new. Since AHU/1 has been recently upgraded it will not require a significant amount of work. We recommend replacing or refurbishing all the dampers and actuators associated with the economizer section because they have not been included in the upgrade work. This includes the outside air, return air and exhaust air dampers. Both condensing units installed in Mechanical Room 3 do not comply with the building code. The 5/ton system is in serviceable condition, but may not be worth saving due to the costs associated with relocating the condensing unit and modifications to comply with the manufacturer s requirements. The 3/ton system is old and not worth keeping. We recommend replacing these with chilled water Fan coil Units. The general recommendation is to replace all air handling systems of 1960s vintage with modern, energy efficient systems. The exact system type and configuration should be determined by the design engineer in consultation with UCD Engineering based on space type and usage requirements. 6.1.3 HVAC Hydronic Systems 6.1.3.1 HVAC Hydronic Systems Description and Condition The building is connected to the campus chilled water system via a set of 6 pipes entering the building through the west wall of the Basement Mechanical Room 3. Water is circulated to the air handlers by a set of constant/volume, base/mounted, end/suction pumps located in the same mechanical room. The pumps are old, in poor condition and have far exceeded their economic useful life. Before the building was connected to the campus chilled water loop, chilled water was provided by steam/powered absorption chiller located in the Basement Mechanical Room 3 and a matching cooling tower located outside at the south/west corner of the building. This equipment, including the steam PRV and chemical treatment have been decommissioned. The chiller has been abandoned in place and the cooling tower removed. The building is also connected to the campus high pressure (150 lbs.) steam system via a set of 4 steam and 2 condensate pipes. The steam pressure is reduced by a single/stage pressure reducing station providing low pressure steam for the building. The low 33

pressure steam serves the hydronic and domestic water heating equipment. The condensate is returned to the campus system by a duplex, electric driven condensate return pump. All of this piping and equipment is located in the Basement Mechanical Room 3. While some of the pressures reducing valves are in serviceable condition, the majorities of steam components are in poor condition and have far exceeded their economic useful life. The hydronic heating system consists of one steam to water, shell and tube heat exchanger, two constant/volume heating hot water pumps and supply and return piping to air handlers and zone reheat cols. The system circulates 140 F to 180 F water throughout the building. The heat exchanger is in poor condition. The pumps are old, in poor condition and have far exceeded their economic useful life. 6.1.4 HVAC Hydronic Systems Recommendations Due to the age, condition and configuration of the equipment and systems, we recommend replacing all chilled water, steam and heating hot water equipment and piping within Mechanical Room 3 with new, efficient equipment configured to match the current campus standards. The controls and CHW building valve, CHW bypass valve and BTU meter could remain and be reused. The abandoned absorption chiller (PIC M03) should be removed and sold for its salvage value. This will free up valuable space in the basement, allow an efficient configuration of the mechanical room equipment and possibly return some space for other usage. 34

7. HVAC Controls System 7.1 Direct Digital Controls System / Description The building HVAC systems are controlled by a campus/standard Siemens Apogee, DDC EMS system which has been installed incrementally over the past several years. This includes controls for the HHW system, CHW system, and all AHUs with the exception of AHU/5. An air compressor located in Mechanical Room 3 provides compressed air for all pneumatic control devices. 7.2 Direct Digital Controls System Condition The DDC EMS system is in serviceable condition. The control/air compressor is in good condition and with proper service could continue to provide reliable service. 7.3 Direct Digital Controls System Recommendations The recommendations for the HVAC Control system depend on the type of work proposed for the HVAC systems. If the existing air handlers are refurbished and continue to be used in their present configuration, then no controls work is required. If new air handling systems will be provided, these would have to be fitted with new controllers which are capable of implementing the latest Campus Standard control strategies including trending and monitoring. The UCD Energy Management Office should be given the opportunity to salvage any controls components installed on equipment planned for demolition. 35

8. Electrical Systems 8.1 Electrical System Description The Freeborn Hall electrical service is fed to the site from the west via the Campus 12.47KV medium voltage distribution system. The existing facility is served via a 500KVA Dry/type transformer located in the electrical vault on the west side of the building. This service transformer was replaced 10 years ago by the Electrical Improvements Project Phase 2B including a 1600A main distribution board (PIC E01) adjacent to the service transformer in the electrical vault to feed existing bus duct serving the existing main switchboard of the building and electrical services to the utility well pump. The system voltage is 120/208Volts. The main switchboard feeds panel PL1A, distribution panel (DA) and motor control center (MCCA). Distribution panel DA feeds Panels SA, 1A, 1B, BA, BB, BC and BD. Panels SA, 1A and 1B are two section panels. The emergency system consists of a natural gas powered generator on the northwest side of the building. Lighting: The lobby area contains several multi pendent lights with combined controls at the front doors. The lighting in the main assembly hall is 2x8 fixtures above panels that have T12 lamps and smaller bug eye type lights underneath. (PIC E02) These primary lights appear to be controlled from an LCP in the back stage area which is fed by panel SA/1 & 2. The basement corridors have 1x4 surface mounted fluorescent lights, the ancillary areas mostly contain 2x4 fixtures some are surface mounted and newer renovations are recessed. The bathrooms and stair wells were upgraded with multilevel LED lights and motion control in the Smart Lighting Initiative project (PIC E03) that was preformed campus wide. Suite 10 has recessed 2x4 fixtures in ACT grid. Suite 5 has 2x4 fluorescent lights that are surface mounted on ACT ceiling. The radio station lighting consists of 1x4 fluorescents, surface mounted on hard lid ceilings. Areas 7 and 6 pendent mounted focal point lights in main areas, sub/offices have 2x2 light fixtures. The Aggie TV area appears to contain primarily 2x4 fluorescent lights that are surface mounted. 8.2 Electrical System Condition The entire electrical system is more than 50 years old which is past its lifetime and no preventive maintenance has been performed on record, physically they appear in good condition considering their age. In 2009 panel PL1A was added feed from the main switchboard. It fed new panel AV and dimming rack #2. Panel BD appears to have a newer section but no date could be confirmed. Panels NPLAB, P and NA1B appear to be added later than 1960 but no hard dates could be found. The generator was installed in 1975 (project #750102), then replaced in 1993 (project #20805) (PIC E04). 36

Lighting: Lobby lights appear to be installed after the original project; however a definitive date was not found. They appear in good condition. Lighting in radio station (suite 14) was reconfigured in 1967. Current Lighting in auditorium was installed in 1987. 1x4 lights in accessible restroom and storage room on first floor replaced in 1996. Suite 10 was renovated in 1996. The lights in room 22 and 22A appear to have been changed in 2002 with 1x4. The production lighting was upgraded in 2009. 8.3 Electrical Recommendations 8.3.1 Provide a new main switchboard, distribution panel boards including feeders, and branch panels. 8.3.2 Provide emergency egress lighting throughout to meet latest code requirements. 8.3.3 Consider providing a lighting control system to minimize energy consumption. 8.3.4 Consider upgrading all lighting to LED standards. 37

9. Telecommunication System 9.1 Telecommunication System Description The main telecom room is shared with electrical. It is located in the basement on the west side of the building. The primary telecom equipment is in this room. The fiber optic boards are also located in the main electrical/telecom room. The primary feeds come from a vault just north of the building. The building distribution consists of several Telecom cabinets, three of which are located in the basement and the other three are on the first floor. There are several WAP placed on the first floor and basement. 9.2 Telecommunication System Condition The incoming outside plant cabling (copper and fiber) are up to date. The main telecom room has inadequate HVAC. Many of the telecom outlets throughout the building are surface mounted and were installed after the original contract. Almost all of the Fiber Outlets are surface mounted. The Network 21 box appears to be in very good condition and relatively new. 9.3 Telecommunication System Recommendations 9.3.1 Provide a separate room with sufficient cooling to be designated as the main telecom room. 9.3.2 Relocate all primary telecom equipment and cabling to the new main telecom room. 38

10. Fire Alarm System 10.1 Fire Alarm System Description The current fire alarm system contains a Silent Knight 5820 panel, power module 5895XL and a voice evacuation system; these are located on the first floor. The remote annunciator panel is located in the lobby near the manager s office. A music relay was installed that overrides the sound system when an alarm is triggered. There are many dedicated speakers for the voice evacuation system throughout the building. The basement overhead doors have dedicated addressable area smoke detectors located adjacent to them. Each of the exits has pull stations, and there is duct detection in the assembly hall. The basement halls and rooms have horn/strobes and area smoke detectors. 10.2 Fire Alarm System Condition The existing fire alarm panel appears to be in good condition. The Fire Alarm renovation project (#842) in 2000 upgraded many of the fire alarm implements. 10.3 Fire Alarm System Recommendations 10.3.1 Upgrade the fire alarm panel to the latest version to accommodate additional device required during renovation. Expander boards and power supplies will be required to add more devices. 10.3.2 If required for freight elevators, provide elevator recall during alarm and re/wire system for all existing devices to send signal to the fire alarm panel. 10.3.3 Provide additional detection and notification devices in areas to be renovated. 10.3.4 Upgrade all smoke detectors located inside AHUs and FCUs. 39

11. ADA Compliance The accessible path of travel and ADA compliance report is done on a set of drawings included here in Appendix D. 12. Hazardous Materials Hazardous material could be part of the renovation project based on what areas are impacted. The current UCD hazardous reports for Freeborn Hall are attached in Appendix E for both asbestos and lead. Before any project begins, all affected areas would need to be tested. All of lower Freeborn has 9 x 9 VAT tile that usually tests positive for asbestos. 13. Acoustical and Production Systems There was an acoustical study done in 2004. The preliminary report dated 07/26/2004 and recommendation dated 09/09/2004 are included in Appendix F. There was also a report dated 10/12/2004 titled Preliminary Recommendations for Audio/Visual System Design at U.C. Davis Freeborn Hall. From these reports a Production System Improvements Master Plan was developed. Attached is the work scope key from that master plan with a check next to the completed items. 40

APPENDIX A

Roof Photo #1 The soldering has broken down around the down spout. Roof Photo #2 Damage at the smoke hatch

Brick Photo #1 Effervescence coming out of the brick Brick Photo #2 Paint on the bricks that does not match Brick Photo #3 Items have been removed from the brick and holes remain.

Ex. Door Photo #2 Close up of the base of Ex. Door Photo #1. Ex. Door Photo #1 Exterior door in poor condition Ex. Door Photo #3 Deterioration of the doors at the brick screen wall. Ex. Door Photo #5 Entrance doors with mismatched handles Ex. Door Photo #4 The bottom of the entrance doors with noticeable rust.

Curtain Wall Photo #1 Gasket coming out of the curtain wall Curtain Wall Photo #2 Panels that have been replaced by a different white metal

Exterior Concrete Photos #1 & 2 Gasket coming out of the curtain wall Exterior Concrete Photos #3 & 4 Uneven and broken areas in the exterior concrete north yard

Roll-Up Door Photo #1 Dents & scratches can be seen in many places on the door.

Trellis Photo #1 Paint flaking off Trellis Photo #2 Paint flaking off and some rusting present.

Grating Photo #1 Paint overspray on the grating.

Lobby Photo #1 Cracking in the plaster on the ceiling Lobby Photo #2 Paint flaking off the concrete beams Lobby Photo #3 Chips in the terrazzo stairs

Lobby Photo #4 Missing pickets on guard rails Lobby Photo #5 Scratches on the oak veneer Lobby Photo #6 Vandalism in front curtain wall

Lobby Photo #7 Minor blemishes on one acoustical panel at the north door Lobby Photo #8 Example of damage at exit doors Lobby Photo #9 Some finish missing where surface mounted wire molds and electrical boxes have been removed.

Lobby Co-Ed Bathroom Photo #1 Grout deteriorating on the ceramic tile Lobby Co-Ed Bathroom Photo #2 Door is missing closer

Assembly Photo #1 Metal light trough Assembly Photo #2 Damage to peg board

Assembly Photo #3 Cracked Stair Assembly Photo #4 Upper risers coming apart Assembly Photo #5 Damage to nosing strips

Assembly Photo #6 Damage to ramp Assembly Photos #7 & 8 Missing pickets Assembly Photo #9 Separation of flooring

Second Floor NW Dressing Room Photo #1 Crack in the plaster wall Second Floor NW Dressing Room Photo #1 Paint on the hand rail Second Floor NW Dressing Room Photo #1 Chipping in the paint on the walls

Stage Photo #1 Maple apron has scratches and scuffs Stage Photo #2 Back of south proscenium wall has gouges. Stage Photo #3 Wood door and frame are damaged

South Lobby Mezzanine Photo #1 Door to the men s restroom has chips in the finish South Lobby Mezzanine Photo #1 Railings have some brackets missing

Mezzanine Men s Restroom Photo #1 The vinyl wall covering is peeling off Mezzanine Men s Restroom Photo #1 Room 209A Mezzanine Men s Restroom Photo #3 Room 209B

Mezzanine Women s Restroom Photo #1 Room 201 Mezzanine Women s Restroom Photo #2 Dusty acoustical tile ceiling Mezzanine Women s Restroom Photo #3 Vinyl wall separating Mezzanine Women s Restroom Photo #4 Room 202

Control Room Photo #2 Cracking in the concrete floor. Control Room Photo #1 Chipping and scratches in the door Control Room Photo #3 The broken track for the sliding window

Storage Room Photo #2 Sink and cabinet are Storage damaged Room Photo #2 Sink and cabinet are damaged Storage Room Photo #1 East wall with damaged corners and holes. Storage Room Photo #3 The acoustical tiles are in poor condition

Box Office Photo #1 Acoustical tile ceiling separating from the wall Box Office Photo #2 A hole on the west wall with wires coming out Box Office Photo #3 Cabinets missing doors

Lower Corridor Photo #1 Sunken tile Lower Corridor Photo #2 Vinyl base coming apart

KDVS Photo #1 Ceiling tiles that are falling down KDVS Photo #2 Acoustical foam missing from the wall

Newspaper Room Photo #1 Dusty acoustical ceilings Newspaper Room Photo #1 Crack in the wall at the door to the darkroom

Dance Room Photo #1 Water marks on the Masonite floor Dance Room Photo #2 Seems coming apart on the Masonite Floor

Room 5B, 5C & 5D Photo #1 Water Damage on the floor Room 5B, 5C & 5D Photo #1 Holes and scratches in the ceilings

Room 13 Photo #1 The ceiling is in poor condition Room 13 Photo #2 Door to 13A is missing

Mechanical Room Photo #1 Exposed Insulation Mechanical Room Photo #2 Spawling in the concrete floor Mechanical Room Photo #3 Abandoned Equipment

Lower Freeborn Photo #3 Cracked plaster at the light switch in Room 18 Lower Freeborn Photo #4 The paint on the door was scratched and chipped. Lower Freeborn Photo #5 There are mounting holes in the north wall Lower Freeborn Photo #6 The door hardware was not functioning properly

Lower Freeborn Photo #1 Room 16 stalls Lower Freeborn Photo #2 Room 16, north wall

M01 VFD for Fan Wall in the basement mechanical room M02 Siemen s Control Panel in basement mechanical room

M03 Chiller to be removed, no longer in service, basement mechanical room E01 Main Distribution Panel, Electrical room, Basement

E01 Primary lighting in Auditorium E03 Stairwell Lighting, Upgraded

E04 Generator Panel, Electrical Room E05 Telecoms Boards, Electrical room, Basement

E06 Fire Alarm Panels, First Floor

APPENDIX B

Freeborn Renovations Summary 1960: Assembly Hall Built 1.Assembly Hall (04.25.1960) All Disciplines: 1961: Original Drawings 1965: 1966: 2. Assembly Building (AS-BUILT)(01.24.1961) All Disciplines: Original clarifications for parts of the building including: stairs, Floor plan of observations room (room 207), grating, elevator louvers, Pantry room and Equipment room layout 3. Assembly Hall - Basement Modifications (10.23.1961) Mechanical: Basement Mechanical Layout Civil: Manhole Alterations 4. Campus Utilities, 1964-65 - Utility Project 2 (BID)-Electric-new conduit, existing duct-east Quad north to North Quad along Freeborn and MU. (06.07.1965) 5. Remodel Room 7 - Lighting - Freeborn Hall (12.08.1966) Architectural: Relocate partitions. Paint walls and acoustic tile. Mechanical: Relocate existing air duct and thermostat. Plumbing: Relocate Fire Sprinklers to avoid florescent lights Electrical: Relocate florescent lights. Separate so they are on two switches

1967: 1969: 6. Remodel Freeborn Hall for Radio Station (04.06.1967) Architectural: Convert Student Office at North East Section on the basement into the radio station (Room 14 became Rooms 14 A-K). All walls added for various rooms, including sound attenuating insulation. Include new doors and architectural finishes for new rooms. Mechanical: Adjust fire sprinkler layout for new rooms Electrical: Adjust Electrical for new rooms. Add outlets and AV where noted. 7. Freeborn Hall Sound System (04.11.1969) Electrical: Adjust Sound System for main hall. Mount speakers above the stage. Equipment is both new 1974: and existing. Speaker and Microphone outlets on stage. 8. Freeborn Hall - Basement Alterations (12.12.1974) ROOMS 6 & 7 Architectural: Partition installed in Room 7. Mechanical, Electrical: 1975: Adjustments to ductwork, electrical and telecom. 1977: 9. ¾ inch Gas Freeborn Hall - New Generator (AS-BUILT)(01.25.1975) Mechanical: New Generator for Freeborn hall. 1 gas line changed to ¾ gas line to generator. 10. Cal Osha Corrections Step One Freeborn Hall (09.07.1977) Architectural: OSHA Tinted Safety Glass Upgrade. 24 Panels of Glass on the North and South sides of the Building

11. Cashier s Office Mrak & Freeborn Hall (11.11.1977) Architectural: 1982: Plans were unclear if the work was being done in both Mrak & Freeborn 1984: 1985: 13. Basement Floor Plan Air Conditioning Freeborn Hall (05.22.1982) Mechanical: Modify Basement Air Conditioning Unit & Controls Electrical: Adjust Wiring for AC modifications 14. Air Conditioning Modifications Freeborn Hall Mechanical Room 3 Drawings don t seem to match title Architectural: Renovate lower Freeborn rooms 9, 11, 12 & 13. Rooms 9 & 12 remove doors and add windows, doors to be added once you enter though room 11. Add a window to room 11. Layout changes so you enter through room 11 and there are 6 offices. Labeled 1 6. Install carpet in Office 2, 5, 4 & 6. Install Tile in Office 1 & 3. Install cabinets and counters in Office 1, 3, 4 & 6. Paint throughout Mechanical: There are two mechanical sheets in this set of drawings that don t appear to correspond with the remodel (?) Electrical: Relocate electrical to fit new floor plan. 15. Cooling Tower Replacement Freeborn Hall (11.01.1985) Mechanical & Plumbing: Replace cooling tower. Add or replace any ductwork/piping needed to attach new tower. Electrical: Provide any new electrical need for new tower.

1987: 1988: 1992: 16. Freeborn Hall Upgrade (03.01.1987) Architectural: Remove Existing Proscenium of Stage, and replace. Add 8 slots across stage ceiling for lighting and curtains. Replace stage floor with vinyl. Remove paste at the back of stage. New ramps, when entering the assembly area. Modify floor in area between lobby and assembly and add wall covering, Demo old ceiling and add new ceiling in lobby. Ceiling Hung by supportive cables. Mechanical: Add new ductworks throughout assembly. Electrical: New Stage Lighting. New loudspeaker at the top of stage. New florescent lights throughout auditorium 17. FTE Office Trailer Freeborn Hall (06.04.1987)(N/A) 18. Freeborn Hall - Stage Fire Sprinklers AS-BUILT (07.14.1987) Architectural: New suspended metal roof 19. Freeborn Hall Storage Addition (11.01.1988) Architectural: Storage Addition to the North Side of the Building (55 sq ft) New Architectural Finishes New Exterior Storefront to match existing including aluminum curtain wall Electrical: All new electrical for area (switches and lights) 20. Security Plan CCTV Freeborn Hall (07.22.1992) Electrical: Added Security System

1993: 1994: 1996: 1997: 21. North West Corner of First Floor Emergency Generator Area (05.10.1993) Civil: Enclosure for New Generator. (38 Sq Ft). New Concrete slab for area Mechanical: Remove and cap existing sprinkler line Electrical: New Generator 22. Replace & Refinish Main Floor - Freeborn Hall (06.28.1994) SUMMARY Architectural: Existing Maple Wood Flooring to be sanded and refinished (Approximately 14,200 Sq Ft) Add additional wood framing to flooring system entry (Approximately 330 sq ft) Install new maple T & G wood flooring at entry (Approximately 747 sq ft) 23 & 27. Freeborn Hall Accessible Employee Restroom (02.01.1996)(12.15.1998) Architectural: North East corner of the building Modify existing area to be a storage room and bathroom. Mechanical: Tie new ductwork into existing. Exhaust and supply fan Plumbing: New plumbing for toilet and sink 24. Lower Freeborn Room 10 (07.18.1996) Electrical: New receptacles throughout lower freeborn Room 10

2000: 2001: 2002: 25 & 26. Chilled Water Loop Connection Freeborn Hall (bid)(12.01.1997) Plumbing: New Chilled Water Lines, connect to existing lines and pumps 28. Freeborn Hall- Fire Alarm System Renovation (BID)(05.16.2000) Plumbing: Upgrade to fire alarm system all floors Electrical: Upgrade to fire alarm system all floors 29. Freeborn Hall Renovations Integral System Two Building Automation System (07.13.2001) Mechanical: Updates for Air Handler and Multi Zone Air Handler. Electrical: Electrical for Air Handler 30. Freeborn Hall Remodel Room 22 (01.03.2002) Architectural: Remodel to Room 22: New Office and Barber Shop 31. Staefa D MUX Replacement MU, MU II and Lower Freeborn Hall (AS-BUILT)(03.05.2002) Mechanical: Update and replace controls for Lower Freeborn Hall D-MUX 32 & 33: Lower Freeborn Rooms 6 & 7, MUBO-SPAC Renovation (BID)(05.10.2002) Architectural: Remove: Existing 68 & 49 walls and doors, and architectural finishes. Add: New 80 and 38 walls, doors, ceiling tiles and paint. Plumbing: Add fire sprinklers where needed. Tie into existing Electrical: New lights with different zones on separate switches. Six panel base infeeds to be added.

2003: 2006: 2007: 34. MU Lower Freeborn Hall - Economizer Valve Replacement (AS-BUILT)(04.07.2003) Mechanical: Replace the Economizer Valve for Lower Freeborn for the Chilled Water System 35. Freeborn Hall Restroom Renovation Basement (BID)(09.10.2003) Architectural: Basement Bathroom Renovations Rooms 16 and 19: Made bathroom wheelchair accessible. Renovate stalls. The majority of architectural finishes stayed and were relocated if needed. 36. Freeborn Hall Production Systems - Improvements, Demolition, Abatement & Stage Renovation (BID)(08.01.2006) Architectural: New Flooring for the stage. Remove acoustic ceiling panels. Paint exposed ducts, raceways and pipe. Mechanical, Plumbing & Electrical: Mechanical and electrical to remain 37. Freeborn Hall - Install Electric Outlines (AS-BUILT)(02.06.2007) Electrical: Electrical work under stage and surrounding area. 2 20ga GFI receptacles and 2 retractable 2009: cord reels 38. Freeborn Hall Production System Improvements (BID) (08.01.2009) Electrical: New Electrical, AV and telecom for stage and theater.

APPENDIX C

Freeborn Building Assessment - Building Maintenance Personnel Shop Contact Name Email Phone Electrical John Dees JohnDees99@comcast.net 1 (530) 681-2277 Fire Alarm Matt Monroe mgmonroe@ucdavis.edu 1 (530) 752-0446 Telecom David Hamaoka dhamaoka@ucdavis.edu 1 (530) 752-2908 Elevator Shawn Beaman srbeamanjr@ucdavis.edu 1 (530) 681-9252 Plumbing/Steam Dave Henderson dghenderson@ucdavis.edu 1 (530) 752-8293 HVAC Patrick Taylor pwtaylor@ucdavis.edu 1 (530) 979-1887 Controls Fred Haynes fwhaynes@ucdavis.edu 1 (530) 754-7820

APPENDIX D

APPENDIX E

Asbestos Results for: Stanley B. Freeborn Hall Construction Completion Date: 5/1/1961 Street Address: CORE CAMPUS SampleID 11 022 Date Zone Area Location Description Lab Results Job 1/25/2011 B015 Elevator Room Plaster on Wall ND 2135445 Removed 03 319 102C 10/7/2003 B015 Entry rm 19, Mens rm W. wall by dr frame White wall plaster ND 1412694 03 319 102B 10/7/2003 B015 Entry rm 19, Mens rm E. wall by dr frame Gray wall plaster ND 1412694 03 319 102B 10/7/2003 B015 Entry rm 19, Mens rm E. wall by dr frame White wall plaster ND 1412694 03 319 102A 10/7/2003 B015 Entry rm 19, Mens rm W. wall by dr frame White wall plaster ND 1412694 03 319 101C 03 319 101C 03 319 101B 10/7/2003 B015 Corridor off rm 16, Ladies rm S. side of dr frame 10/7/2003 B015 Corridor off rm 16, Ladies rm S. side of dr frame 10/7/2003 B015 Corridor off rm 19, Mens rm S. side of dr frame Gray wall plaster ND 1412694 White wall plaster ND 1412694 Gray wall plaster ND 1412694 03 319 101B 10/7/2003 B015 Corridor off rm 19, Mens rm S. side of dr frame White wall plaster ND 1412694 03 319 101A 10/7/2003 B015 Corridor off rm 19, Mens rm N. side of dr frame White wall plaster ND 1412694 03 319 103C 10/7/2003 B015 Rm 16A, Ladies rm., S wall by Dr frame White wall plaster ND 1412694 03 319 103B 10/7/2003 B015 Rm 16, entry to Ladies rm., N wall by Dr frame White wall plaster ND 1412694 03 319 103A 10/7/2003 B015 Rm 16, entry to Ladies rm., W wall by Dr frame White wall plaster ND 1412694 01 458 101C 10/1/2001 B015 Room 14 White sheetrock, white mud, composite Y Sheetrock: ND, Mud: 1 2% Chrysotile, 1219627SGU Thursday, March 28, 2013 Page 1 of 6

SampleID 01 458 101B 01 458 101A 02 142 103C Date Zone Area Location Description Lab Results Job 10/1/2001 B015 Room 14 White sheetrock, white mud, composite 10/1/2001 B015 Room 14 White sheetrock, white mud, composite Y Sheetrock: ND, Mud: 1 2% Chrysotile, Y Sheetrock: ND, Mud: 1 2% Chrysotile, 1219627SGU 1219627SGU 2/14/2001 B015 Room 7 Yellow carpet mastic ND 1243216SGU Removed 02 142 102C 02 142 102B 02 142 102A 02 142 101C 02 142 101B 02 142 101A 02 142 103B 2/14/2001 B015 Room 6, side, 4" wall White sheetrock, new type, 4" wall, white joint compound, composite, 2/14/2001 B015 Room 6, side, 4" wall White sheetrock, new type, 4" wall, white joint compound, composite, 2/14/2001 B015 Room 6, side, 4" wall White sheetrock, new type, 4" wall, white joint compound, composite, 2/14/2001 B015 Room 6C, entrance White sheetrock mica type, white joint compound, composite 2/14/2001 B015 Room 7A, small vacant room 2/14/2001 B015 Room 7A, small vacant room White sheetrock mica type, white joint compound, composite White sheetrock mica type, white joint compound, composite Not analyzed, prior positive Not analyzed, prior positive Y Sheetrock: ND, compound: 1 2% Chrysotile, Not analyzed, prior positive Not analyzed, prior positive Y Sheetrock: ND, compound: 1 2% Chrysotile, 1243216SGU 1243216SGU 1243216SGU 1243216SGU 1243216SGU 1243216SGU 2/14/2001 B015 Room 7 Yellow carpet mastic ND 1243216SGU 02 142 103A 2/14/2001 B015 Room 7 Yellow carpet mastic ND 1243216SGU 00 166 02C1 4/18/2000 B015 Rm 10, 5' south of center of east wall Homogeneous white drywall ND 1052609SUU 00 166 02B3 4/18/2000 B015 Rm 10, east wall at outside corner Nonhomogeneous white composite ND 1052609SUU 00 166 02B2 4/18/2000 B015 Rm 10, east wall at outside corner Homogeneous white joint compound ND 1052609SUU 00 166 02B1 4/18/2000 B015 Rm 10, east wall at outside corner Homogeneous white drywall ND 1052609SUU 00 166 02A 4/18/2000 B015 Rm 10, center of east wall Homogeneous white drywall ND 1052609SUU 00 166 02C2 4/18/2000 B015 Rm 10, 5' south of center of east wall Homogeneous white joint compound ND 1052609SUU Thursday, March 28, 2013 Page 2 of 6

SampleID 00 166 01B Date Zone Area Location Description Lab Results Job 4/18/2000 B015 Rm 10, center of ceiling Homogeneous grey 12x12 ACT ND 1052609SUU Removed 00 166 04B 4/18/2000 B015 Rm 10, South center of ceiling Homogeneous brown ACT mastic ND 1052609SUU 00 166 01A 4/18/2000 B015 Rm 10, south center of ceiling Homogeneous grey 12x12 ACT ND 1052609SUU 00 166 01C 4/18/2000 B015 Rm 10, north center of ceiling Homogeneous grey 12x12 ACT ND 1052609SUU 00 166 02C3 4/18/2000 B015 Rm 10, 5' south of center of east wall Nonhomogeneous white composite ND 1052609SUU 00 166 03A 4/18/2000 B015 Rm 10, south center of ceiling Homogeneous white ceiling plaster ND 1052609SUU 00 166 03B 4/18/2000 B015 Rm 10, center of ceiling Homogeneous white ceiling plaster ND 1052609SUU 00 166 04A 4/18/2000 B015 Rm 10, center of ceiling Homogeneous brown ACT mastic ND 1052609SUU 00 166 05A 4/18/2000 B015 Rm 10, east wakk outside corner Homogeneous brown rubber base cove mastic ND 1052609SUU 00 166 05B 4/18/2000 B015 Rm 10, center of east wall Homogeneous brown rubber base cove mastic ND 1052609SUU 00 166 06A 4/18/2000 B015 Rm 10, center of space Homogeneous grey 2x4 SCP ND 1052609SUU 00 166 06B 4/18/2000 B015 Rm 10, center of space at 12x12 ACT Homogeneous pink 2x4 SCP ND 1052609SUU 00 166 06C 4/18/2000 B015 Rm 11, center of ceiling Homogeneous grey 2x4 SCP ND 1052609SUU 00 166 03C 4/18/2000 B015 Rm 10, north center of ceiling Homogeneous white ceiling plaster ND 1052609SUU 3773 1 3/13/1997 B015 Exterior wall, air well 10' N of SW corner Concrete (gray) ND 963594751 3773 3 2/3/1995 B015 Rm 11, Sue's Station 1/2 wall Sheetrock joint compound (white) ND B1215 9434480 3773 1 2/3/1995 B015 Rm 11,Yuni Station 1/2 wall Sheetrock joint compound (white) ND B1215 9434480 Thursday, March 28, 2013 Page 3 of 6

SampleID 3773 2 Date Zone Area Location Description Lab Results Job 2/3/1995 B015 Rm 11,Yuni Station 1/2 wall Cove Base mastic (brown) ND B1215 9434480 Removed 3773 002 3773 001 3773 0045 10/15/1994 B015 Basement, North stairwell, North wall by Rm 11 10/15/1994 B015 Basement Hole in Wall Near Rm 11, North Stairwell Plaster, Brown coat (white) ND BC125 9421498 Finish coat plaster (white) ND BC125 9421498 8/22/1994 B015 Rm 25, NE corner ceiling Ceiling plaster ND 9406518SC2 3773 0044 8/22/1994 B015 Rm 25, N. center ceiling White 12' ceiling tile ND 9406518SC2 3773 0043 8/22/1994 B015 Rm 25, N. wall plaster White plaster ND 9406518SC2 3773 0042 7/5/1994 B015 Storage exterior wall, NE corner of building Panel (gray) ND RD063 9311265 3773 0034 6/15/1994 B015 Ticket canopy,center Brown coating ND BC129 11307 3773 0033 6/15/1994 B015 Ticket canopy,center Black material ND BC129 11307 3773 0035 6/15/1994 B015 Ticket canopy,center Finish coating,white ND BC129 11307 3773 0036 6/15/1994 B015 Ticket canopy,roof,top layer Gray mastic (brown) ND BC129 11307 3773 0041 6/15/1994 B015 Ticket canopy roof,above wall flashing Flashing/motar (black) ND BC129 11307 3773 0038 6/15/1994 B015 Ticket canopy roof, 2nd layer Felt (brown) Y 20 30% Chrysotile BC129 11307 3773 0039 6/15/1994 B015 Ticket canopy roof,3rd layer Roofing tar (brown) ND BC129 11307 3773 0032 6/15/1994 B015 Ticket canopy,center Patching material, white ND BC129 11307 3773 0040 6/15/1994 B015 Ticket canopy roof,4th layer Caulking (black) ND BC129 11307 3773 0037 6/15/1994 B015 Ticket canopy,roof,top layer Brown mastic (gray) Y 20 30% Chrysotile BC129 11307 Thursday, March 28, 2013 Page 4 of 6

SampleID 3773 0031 Date Zone Area Location Description Lab Results Job 5/3/1994 B015 Rm 112, ceiling west of wing wall White smooth plaster and tan paint ND B1215 38616 Removed 3773 0030 5/3/1994 B015 Rm 112, behind toilet on floor Grey plaster and brown material ND B1215 38616 3773 0029 5/3/1994 B015 Rm 112, Floor at shower dam Grey plaster/cement ND B1215 38616 3773 0028 3773 0016 4/25/1994 B015 Rm U501, underside of cover in front of ticket booth Grey cement trowelled on surfacing 10/1/1992 B015 Rm 5, floor Off white stipple, gyp brd Y 1 5% Chrysotile ND BC129 B1215 0373 3773 0027 10/1/1992 B015 Rm 5, floor Dark brown mastic under 9x9" brown floor tiles NOT ANALYZED B1215 0373 3773 0007 10/1/1992 B015 Rm 5A, E wall, 4ft up from floor wht cem/plas ceil tile smooth, painted ND B1215 0373 3773 0009 10/1/1992 B015 Rm 5A, E wall, corner Off white stipple, gyp brd ND B1215 0373 3773 0010 10/1/1992 B015 Rm 5A, W wall 4 ft up from floor Off white stipple, gyp brd Y <1% Chrysotile B1215 0373 3773 0011 10/1/1992 B015 Rm 5A, W wall, 4ft down from ceiling Off white stipple, gyp brd ND B1215 0373 3773 0012 10/1/1992 B015 Rm 5A, W wall, corner White stipple, gyp brd Y 1 5% Chrysotile B1215 0373 3773 0013 10/1/1992 B015 Rm 5, W wall, 4ft up from floor White stipple, gyp brd Y 1 5% Chrysotile B1215 0373 3773 0014 10/1/1992 B015 Rm 5, E wall, corner White stipple, gyp brd Y 1 5% Chrysotile B1215 0373 3773 0015 10/1/1992 B015 Rm 5, W wall in seam Off white stipple, gyp brd Y 1 5% Chrysotile B1215 0373 3773 0008 10/1/1992 B015 Rm 5A, E wall 4ft down from ceiling tan wall material (masonite panel) ND B1215 0373 3773 0017 10/1/1992 B015 Rm 5, floor Off white stipple, gyp brd Y 1 5% Chrysotile B1215 0373 3773 0018 10/1/1992 B015 Rm 5, floor 9x9" tan floor tiles Y 1 5% Chrysotile B1215 0373 Thursday, March 28, 2013 Page 5 of 6

SampleID 3773 0019 Date Zone Area Location Description Lab Results Job 10/1/1992 B015 Rm 5, W. wall 9x9" tan floor tiles Y 1 5% Chrysotile B1215 0373 Removed 3773 0020 10/1/1992 B015 Rm 5, E. wall 9x9" tan floor tiles Y 1 5% Chrysotile B1215 0373 3773 0021 10/1/1992 B015 Rm 5, S. wall Brown 4" cove base ND B1215 0373 3773 0022 10/1/1992 B015 Rm 5, W. wall Brown 4" cove base ND B1215 0373 3773 0023 10/1/1992 B015 Rm 5, E. wall Brown 4" cove base ND B1215 0373 3773 0024 10/1/1992 B015 Rm 5, S. wall Brittle brown mastic under brown 4" covebase ND B1215 0373 3773 0026 10/1/1992 B015 Rm 5, floor Brittle brown mastic under brown 4" covebase ND B1215 0373 3773 0025 10/1/1992 B015 Rm 5, floor Brittle brown mastic under brown 4" covebase Y 1 5% Chrysotile B1215 0373 3773 0006 9/20/1991 B015 North wall, outside, west end, wall material Tan wall material (masonite panel) ND RB030 0619 3773 0005 8/29/1991 B015 Rm 29, ceiling tile White cem./plas ceil. Tilesmooth painted ND SB603 9192 3773 0004 8/29/1991 B015 Rm 27, ceiling tile Adh. Ceiling tile 12x12 white striated ND SB603 9192 3773 0003 8/27/1991 B015 Room 15, Loc C White ceiling plaster ND PX092 2315 Thursday, March 28, 2013 Page 6 of 6

Lead Search Results for : ConstructionCompletionDate: 5/1/1961 Street Address: CORE CAMPUS Stanley B. Freeborn Hall Date Zone CAAN Location Sample Description LabResults PPM LabResults weight LabResults TTLC LabResults STLC LabResults TCLP B015 3773 Elevator Mech Rm Paint 200 0.02% 11 022 Job Sample 5/31/1999 B015 3773 Center of ceiling, Rm 10 12x12 ceiling tile paint chip <100 <0.010% 1052609SUU 00 166 01L 6/1/1999 B015 3773 Rm 10, east wall center of space 6/2/1999 B015 3773 Rm 11 wall, center of west wall Wall paint chip <100 <0.010% 1052609SUU 00 166 02L Wall paint chip <100 <0.010% 1052609SUU 00 166 03L 6/3/1999 B015 3773 Room 14, radio station White paint on sheetrock wall 6/4/1999 B015 3773 Room 6C, office Gray paint on metal door frame 6/5/1999 B015 3773 Room 6B, office White paint on sheetrock divider 120 0.00012 1219627SGU 01 458 201Pb 4200 0.0042 1243216SGU 02 142 201Pb <100 <0.010% 1243216SGU 02 142 202Pb 6/6/1999 B015 3773, N. side of door frame, rm 19 6/7/1999 B015 3773 E. wall by door frame, rm 19 6/8/1999 B015 3773 W. wall by door frame, rm 16 Paint on Plaster <100 <0.010% 1412694 03 319 201Pb Paint on Plaster 500 0.0005 1412694 03 319 202Pb Paint on Plaster 2200 0.0022 1412694 03 319 203Pb 1/8/2011 B015 3773 Stage area Varnish on Wood 240 0.024% 2139473HZ 11 015 Thursday, March 28, 2013 Page 1 of 1

APPENDIX F

The Group The Acoustics & Vibration Group 5700 Broadway Sacramento, CA 958201852 916#5?4.444' FAX: 916-457-1475 Consultants tn Acoustics, Vibration & fioise Control Acoustics (The Acoustics & Vibration Group) July 26, 2004 Adam Shalleck The Shalleck Collaborative, Inc. SUBJECT: Preliminary Results of Acoustical Analysis and Evaluation of U. C. Davis Freeborn Hall Dear Adam, This letter documents the initial results of acoustical testing and analysis of Freeborn Hall at U.C. Davis. Freeborn Hall was originally designed to be used as a concert hall for the University=s orchestral group plus for use for conferences and pop concerts. Today it serves as a multipurpose room for lectures, banquets, pop music concerts, and more. The orchestra no longer uses Freeborn Hall for performances, since they have the new Mondavi Center. Changing the main role of Freeborn Hall requires changes to the acoustics and audiovisual system. This process starts by identifying existing acoustical conditions at the site and then doing acoustical modeling of the space. Sound tests were performed on May 28, 2004 at the project site. Tests include measurement of the reverberation times in the hall using impulsive balloon pops and pink noise, background sound level measurements with the HVAC system operating, and sound distribution tests of the installed loudspeaker system. Each of these test types are discussed. Architectural Acoustics The results of balloon pop and pink noise reverberation time tests indicates that while the decay times are closer to ideal for natural music enhancement, they are too high for amplified music, lectures, banquets or dramatic performances. Displayed in Figure 1 is a sample of sound decay test results using balloon pops as the source of sound. The reverberation times varied at each position, although at higher frequencies the variation, was less. Also shown in Figure 1 are the ideal design goals for the new uses of the assembly hall. Both upper and lower goals are used to provide a range of acceptable sound decay times. Again, as apparent in Figure 1, there is not enough absorption in the middle frequencies and too much sound absorption in the upper frequencies above 4000 Hz. During the tests a slap echo was heard between the parallel walls on either side of the front of the stage. A person speaking on stage would likely hear themselves a second time after their initial word is spoken. The side walls at the front of the stage should be redesigned to eliminate the apparent echo. In addition, it is unclear whether the diffusions panels along the sides and rear of the assembly hall are doing much to diffuse the sound. For amplified music and lectures, these panels will not be needed and should be removed as part of the redesign. 17

Ro4i4 2: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, July 26, 2004 frsshb The computer model is showing that insufficient sound is being absorbed on the ceiling. Most of the additional acoustical treatment will be added to the ceiling. The fine print of the PDF drawing file indicates that the perforated board along the side should be pegboard rather than asbestos boards I assume that this is what James Monday found. We will send you additional treatment options later this week. This may include removing the perforated board. Let us know what your thoughts are for treatment that fits with the aesthetics. Mechanical Acoustics Background sound levels of Freeborn Hall were measured with the HVAC system operating. Figure 2 shows the results of background sound measurements at various positions throughout the assembly hall compared to Room Criterion, RC, curves published by the American Society of Heating, Refrigerating, and Air-Conditionirig Engineers (ASHRAE)[i]. Ideally, the sound from the HVAC system in the hall should fall in the range between an RC 25 to 30. Under ideal conditions, this equal an A-weighted sound level of 32 to 37 db(a). Background sound levels currently fall between an RC of 32 to 37 depending on the location with A-weighted levels of 32 to 44 db(a). The highest levels were measured on the main floor on the right side of the room. Higher levels would have been measured if the tests had been done closer to the returns mounted in the side wall between the main floor and mezzanine. While the sound levels are higher than ideal, the background sound at least follows the slope of the RC curves very well. That is, there are no pure tones or substantial peaks or valleys across the frequency range. Further evaluation of the mechanical system is required to provide any recommendations for improvement. Subjective evaluation of the room showed high vibration levels on the stage. As a minimum this would be a distraction for those performing on the stage. The vibration appears to be related to the mechanical equipment. Further analysis is required to find the source and develop a fix. Finding a fix is recommended. Sound Distribution The house sound system was evaluated for frequency response and sound distribution as part of the acoustical tests. Figure 3 gives a set of frequency response curves for the sound reinforcement system. First of all, it is evident in the graph that the system was not properly equalized. There is a substantial dip in the sound levels around 315 Hz at every position. Secondly, the variation in sound levels at the measurement positions is higher than our typical performance specification for sound systems. Sound levels varied by 7 db(a) throughout the seats in the hall. This translates into a distribution of V 3.5 db(a). Ideally, the distribution should be V 2 db(a) or better. As part of our analysis, we are looking at corrections to the sound system. This will be a general overview of what type of system should be installed, where speakers should be placed and what kind of video system will be required. 18

Ro414 2 - Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, July 26, 2004 OTOUD Please call if you have any questions regarding these results and comments. Let us know what additional information you need. We have received verbal authorization for doing the sound system, but no mitten confirmation for either proposal. Because of insurance requirements, we need some letter of authorization. I would appreciate it we could receive such a letter. Thanks. Sincerely, Brian R. Smith, Senior Engineer Approved by, Steve Pettyjohn, Principal Certified: Institute of Noise Control Engineers-1981 19

>3 o B ri EL S 4 5' p c a & cn *3 cr 1 o ffi s P C. a. w TJ O i.a 4 1.4 Shalleck Collaborative, UCD Freeborn Hall Impulse Reverb Tests; Curtains Opn, Seats Out T30 tv_-* r ' & V 4 h' f v ; * : -nm. 2 Balloon Pops i CO *. r 1.2 } 1.0 - if c o 3 E - 8 0) -8 0.8 > 0> 0.4 0.2 Tested On 28-May-04 125 20Q 315 500.800 1250. 2000 315.0 5000 3000 Linear 100 160 250 40Q 630 1000 ' 1600 2500 4000 S30Q 10000 A-Vtfci 1/3-Octave Band Center Frequency, Hz Site 1b, RS Msz * Site 4, Mez RS Rear.Site.13, Fir RS Front Lower Goai 7* II - - - Site 11b, Fir Cntr Rear...s. Upper Goal (? i-i a M en I I 8 9 n 8- o & SL!» cr. n O n 2. S M OS H 0

R04142: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, July 26, 2004. W «x o ^ > J N o <D -5 LL Q O to t K 3 - O B o is < I 2 J5 "o O O 0 (3 T3 c CO T3 C =3 O OT 8 CD d-\- '* ffw-t- «- -.«"t " ' s ' " r ' * «*... *.*/... I,»', it'-imvf-'i*'* 1. *.* ««! «:-i. t.. *ff f~..m «->-m «f- J ' >- ' if... ;.: *....; c ^ O 9 0 OJ ta 1- oi a ui D in a in a io a in am o m a m co r-- fn-to to u> m vr *r m nfn cm *- t- d^02" ^ -9P c ea8n ejnssajd punog IB OS c 5 < o_ hi \1 a cn is o c ce ' QJ ^' "as»- a 2 CD a r. >_ CB Q_ cd a. cr z> o "=t o or I g un IN o Cd Q (3 03 CD *S CO g E W u_ -DO 05 N CD W 1 i m \ I * o a LL. X3 CD.fc 55 O CD s t- 0 CD t; _O C/3 LL. A Figure 2. Background Sound Measurements of Freeborn Hall with HVAC System Operating Compared to Design Goals. 21

R04142: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, July 26, 2004 vv- 4»- JS-» <0 o ja o 0 Q O <D > M o _Q "5 o o o 15 CO 0 y-- CO 0 Q_ 1 CO i, CD \ to CD Z3 >* O I =3 r~ h- 0 C0 f^-%1 t a-te V ^ V-ts o o * M*>~ s xs c CL _ O -3 n _Q Q CZ _3 o CO a a > % V O 2 c 05 1= O "O u_ m g A 9~. o o a a U_ Ll_! I ' M CC W O Ol CC EE cn co I C er g C CK 5 «I i S w o E cr 03 o u_ 00 _i ^ cc fcj cu w 0J bo 2 Bd^O^0-* -QP 'IQA "] jrissajd punog Figure 3. Results of Pink Noise Sound Distribution Tests of House Loudspeaker System at Freeborn Hall in Davis. 22

R04142: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, July 26,2004 Group REFERENCES 1. Anon, "Chapter 47: Sound and Vibration Control", from 2003 ASHRAE Handbook: Heating, Ventilating and Air-Conditioning Applications, Inch-Pound Edition, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc., Atlanta, Georgia, 2003. 23

The Acoustics 6t Vibration- Group Group 3?00 Broadway Sacramento, CA 9S32CM8S2 ' 91&45 :?-:1;444' fm. 916-457-1475' ' September 9, 2004 Consultants.!!"! Acoustics, Vibration & ttolse Control Adam Shalleck The Shalleck Collaborative, Inc. 203 Randall St. San Francisco, CA 94131 SUBJECT: Recommendations for Architectural Acoustic Treatment of U.C. Davis Freeborn Hall Dear Adam, Documented in this letter report are the results of acoustical modeling and analysis of Freeborn Hall at U.C. Davis. Sound tests were conducted at the end of May in Freeborn Hall to learn the existing acoustical conditions within the space. Results of those tests were presented and discussed in a previous report dated July 26, 2004 [i]\ A computer model was developed for Freeborn Hall and compared with measured results. Once an accurate model was constructed, acoustical treatment was added to the various room surfaces to reduce the reverberation times in octave bands to acceptable levels. As stated in the previous report, insufficient sound is being absorbed by the ceiling. The existing glued-on thin acoustical ceiling tile is inadequate in quantity to absorb enough of the sound energy. Because the ceiling tile is thin without insulation or an airspace behind, the ceiling tile absorption is skewed toward the high frequencies. The side walls appear to have plenty of absorption from the curtain treatment, with the exception of the slap echo between the parallel walls at the front of the stage. Currently, these wall surfaces are covered in wood. paneling. The rear wall has a slat absorber/diffuser tuned to approximately 350 Hz, as calculated from the slat design. Absorption of the rear wall is therefore most prominent in, the 250 and 500 Hz octave bands. Further sound absorption in the current space comes from the upholstered seating, even with the riser-style seating folded down and stacked in the retracted position. Additional acoustical treatment is needed to lower the reverberation times to acceptable levels as shown in Figure 1. Both an upper and lower design goal is given to designate an acceptable range of sound decay times. Two conditions were modeled. One condition leaves the current ceiling system as is except the ceiling tile and angle sound diffusersq would be removed while for the second condition, the ceiling or a false ceiling would be dropped. Ideal for acoustics under the second condition is providing better diffusion using a random a semirandom pattern or a barrel/convex shape from side to side to distribute the sound better. We have not heard back regarding structural limitations or seen any proposals for changes, so have limited ceiling changes to these two conditions. Acoustical treatment of surfaces remains the same for both options. * - Number in brackets refers to references listed at the end of this letter report. 24

R04142.2: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design^ September 9,2004 The The side and rear wall reflective panels should be removed to allow more sound to reach the draperies on the side and the wood-slat rear wall.[the rear wall works well at absorbing mid frequencies and does not need to be replaced. If atlifferent look is desired for the rear wall, the slat absorbers can be redesigned or replaced with l-inch. thick fiberglass panels over a hard surface or several other options are available..the ;pegboard can be replaced as it is having no acoustic influence. If sound absorptive material, i.e., regular building insulation were installed behind the peg board, the acoustical value would increase. However, the model is suggesting that additional sound absorption is not needed on this surface. An assumption was made that the number and size of the windows would not change and, therefore, the square footage of drapery would remain the same. The draperies are important to the total sound absorption provided by the sound walls. Thus, if these are to be replaced, the acoustical sound absorption quality of the material is an important issue. This must be part of the criteria for any changes that are made. The stage area has not been completely evaluated, pending proposed changes to this space. The existing ceiling system can be replaced with one that is better for the proposed uses since symphonic groups are not expected to play at Freeborn Hall. Several treatment options were modeled, with most of the treatment on the ceiling surface. Both Two of the treatment possibilities are provided for review, one is a fiberglass panel system and the other is a spray-applied acoustical plaster. Figure 2 displays the effects of the two acoustical treatment options compared with the design goals and current conditions in the hall. The fiberglass panel treatment works a little bit better in that it requires less material and does not have excess absorption at 4000 Hz. Unfaced fiberglass insulation can be substituted for the panels depending on cost or aesthetics. Either acoustical treatment will be a vast improvement to the current design. The square footage of material required for each treatment option is listed below along with acceptable product manufacturers; 1. Option 1: 2" Thick Fiberglass Panels or Exposed Insulation 1. 2 inch cloth or vinyl wrapped or painted fiberglass panels or 2-inch thick insulation with a minimum Noise Reduction Coefficient (NRC) of 0.85 when tested per ASTM C423 using a mounting Type A per ASTM E795. 2. Approximately of 5700 square feet of 2" thick fiberglass panels or insulation should be applied to the underside of the ceiling. 3. Acceptable suppliers - panels, the following or equal: 1. Wall Technologies 2. Conwed 3. Decoustics 4. Lamvin 5. LBI/Boyd 4. Acceptable suppliers - unfaced insulation: 1. Owens Corning 2. Knauf 3. CertainTeed 25

Ro4i4 2 2: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, September 9,2004 5. Aesthetics 1. Panels are either wrapped in breathable cloth, perforated vinyl or painted surface with almost limitless variety of colors and patterns 2. Unfaced insulation that is 2-inches thick would probably be a black duct liner. Cotton is also available as a substitute for fiberglass in a variety of colors 2. Option 2: Spray Applied Acoustical Plaster 1. 1V4 inch thick spray-on acoustical treatment with a minimum NRC of 0.70 when tested per ASTM C423 using a mounting Type A per ASTM E795. 2. Approximately 7200 square feet of 1V4 inch thick spray-on acoustical plaster should be applied to the underside of the ceiling. 3. Acceptable suppliers - spray applied plaster 1. Pyrok 4. Aesthetics 1. A variety of finishes are available including a rough plaster look similar to stucco and a semi-smooth finish 2. Color can be mixed into the product or the product can be painted with up to 4 coats of latex paint without affecting the acoustical properties of the plaster. In addition to the options listed above, absorptive or diffusive products or both should be incorporated on the side walls of the stage to eliminate the slap echo. This can be done with simpler-inch thick cloth wrapped fiberglass panels for absorption, or with specially designed Barrel or random diffusion panels. If you can provide us with proposed changes in the shape and finishes for the room, we can provide additional analysis of the acoustic influences of these changes. The shape and the finishes are both important. We have not done any further analysis of the mechanical system as it was not part of the scope-of-work. Vibration problems on the stage should be addressed along with some of the high sound levels near the return air openings on the main floor. Both the background sound levels and the vibration levels exceed recommendations exceed guidelines published by the American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) [2]. Let us know if additional information is required to address these issues. Please call if there are any questions or comments regarding the results of this report. We look forward to working with you as this renovation project moves forward. Sincerely, Brian R. Smith, Senior Engineer Approved by, Steve Pettyjohn, Principal Certified: Institute of Noise Control Engineers-1981 26

to \l w a 5 % p d S 8 co 1 cu O o 3 r+ 3 rc era o 5L CO O o T3 3 B >1 n> Cb 9 a o 3 a? >->» o p a o a. w fc ft u* o 2.0 1.8 V ' 1 c "O 1.6 C o 1-4 (/) (D1.2 E H 1.0 - nso.b - <D XZ JjjD.6 > 0) Q D.4 Q.2 0.0 Shalleck Collaborative; UC Davis Freeborn Hall Assembly Hall, Existing Space vs. Design Goals 4! ; - ' - t ' m i ; - : - 1 i : - 4 - _< y -«_ s - ' 4 u - - i : : ; 125 25D 1000 2000 4DDD Octave Band Center Frequency, Hz -a As Designed, Existing Space w/500 People --o--lower Goal * - Upper Goal ; \ S i-t M tf. CO >3 5" I «

to CO o 3.?" fo I ft! 3 $ rt> <T> a o 0 >d 3 OS 1 01 P- r+ o O CfQ D Q o o* t-j 3 rt rt c 1 ' o 1-1 d ffi a h 1.7-1.6 v> T3 C 1.5 O 0) to 1-4 V 0) V c o.2.1 1_ 0) ol.q 0 >0.9 0 (V 0.8 0.7 Shalleck Collaborative; UC Davis Freeborn Hall Treatment Options vs. Design Goals, 500 People * ^ V \ V ^ V\ 250 -Hfc.. 500 000 2000 Octave Band Center Frequency, Hz Current Space - -m- - Lower Goal - - 2"Fiberglass Panels on Ceiling & - Upper Goal 1.25" Spray-on Ceiling 4000 ps o fc. M» S* Bv 9 «! a f9 l S3.? 3 rt & L > CO «JP 1 N 4^ o

R04142.2: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, September 9, 2004 jl'l. REFERENCES 1. B. Smith and S. Pettyjohn, Preliminary Results of Acoustical Analysis and Evaluation of U.C. Davis Freeborn Hall0, for The Shalleck Collaborative, San Francisco by "Hie Acoustics & Vibration Group, Sacramento; Project No. R04142.1, July 26,2004. 2. Anon, "Chapter 47: Sound and Vibration Control", from 2003 ASHRAE Handbook: Heating, Ventilating and Air-Conditioning Applications, Inch-Pound Edition, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc., Atlanta, Georgia, 2003, CD Edition. 29

The Acoustics & Vibration Group.. S700 Broadway ' Sacramento, CA 93820-.1852 916-4574444 PAX: 916-4574.-4?5 Consultants.in. Acoustics, Vibration & Motse Control Audio-Video Systems (The Acoustics & Vibration Group) October 12, 2004 Adam Shalleck The Shalleck Collaborative, Inc. 582 Market St., Suite 2002 San Francisco, CA 94104 SUBJECT: Preliminary Recommendations for Audio-Video System Design at U.C. Davis=s Freeborn Hall Dear Adam, This report documents the preliminary remedial audiovisual system design a:t Freeborn Hall on the U.C. Davis campus. As the needs and uses of Freeborn Hall have changed over the years from an orchestral performance space to an events center, an upgrade to various systems within the hall is needed. After the lighting system has been upgraded, next on the list of items that need modernization is the video presentation system. Once the lighting and video presentation systems have been upgraded, the audio system can receive a makeover. This report is intended to provide an unbiased design and cost estimate for the video and audio system upgrades. Equipment is listed by type without brand names, along with an estimated cost for each item. Existing Systems Currently, the video presentation system is composed of a portable projector and screen that are set up and torn down by support staff after every event. A presenter plugs directly into the stand-mounted projector. The screen is typically positioned at the center of the stage. The video system is currently not integrated into the house audio system. The audio system consists of permanent and portable speakers, amplifiers, processors, microphones, source devices, and a mixing board. Two equipment racks in the control booth house the amplifiers, electronics, and various tape/cd source devices. An assisted listening system exists as well, fed by a microphone at the back of the hall. Main speakers are arranged in left, center, and right clusters above the front of the stage. The speaker system performance, documented in a previous report by TAVG, does not provide even sound coverage throughout the hall. The main speakers are from a company that specializes in guitar amplifiers and other systems meant for individual instruments, and are not ideal for the space to serve as a main reinforcement system. Ancillary speakers for the lobby and control booth are fed by the microphone mounted to the rear wall of the hall, the same microphone used by the assisted listening system. The assisted listening system and the lobby speakers should not be fed by 30

Ro414 2-2: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, September 9, 2004 f this microphone as it results in poor intelligibility through these systems. The position of the microphone results in a large portion of the sound being affected by the reverberant field. Proposed Systems and Components Video Freeborn Hall will accommodate a variety of events ranging from award banquets to touring concerts.. As such, a permanently installed video system needs to be easy to use and setup while providing a high quality picture in varied lighting environments. A mirrored pair of video projectors and screens is proposed for visual presentations. Each screen will be positioned in the stage wing areas so the center of the stage remains clear, hung from above by a new support structure. The screens will be motorized to tuck away when not in use and tensioned to provide a flat surface for showing data and video. Both screens will be a minimum of 10 feet tall by 13 feet 4 inches wide, a 200-inch diagonal viewing area. The projectors will be either based on Liquid Crystal Display (LCD) or Digital Light Processing (DLP) fixed pixel display technologies with a light output of 6000 ANSI lumens or more each. The high brightness will allow images to be clearly visibly on the large screens with normal lighting conditions in the hall. Other features of the projectors include a native SXGA resolution, horizontal and vertical lens shift, network connectivity, and various lens options. The projector will be mounted to a motorized lift to help align the projector with the top of the screen and to allow the projector to retract when not in use. Both the projector lift and electric screens can be raised or lowered with wall-mounted buttons or a key. A matrix switcher/scaler will be at the heart of the video system, allowing up to 8 different sources to be directed to 2 independent outputs scaled to the native resolution of the projectors. Each of the two projectors can show separate sources simultaneously with this device. The matrix switcher also routes the audio corresponding to each of the video sources to the outputs. Source devices include a DVD player, a VHS player, motorized video cameras, a document camera, and two computer connections. The outputs of the matrix will be sent to a distribution amplifier to transmit the video signal over Category 5 or 6 cable. A receiver at each projector separates the data back into computer video signals. Distribution of the video through Cat'5 or 6 cable simplifies the conduit and decreases the cost of cable. In addition, multiple video output locations can be wired with the low cost cable for immediate or future needs. Audio The audio system redesign focuses on improving the signal routing and overall audio quality in Freeborn Hall. Problems such as the poor intelligibility in the assisted listening system need to be addressed. Changes in the audio system need to reflect the new architectural acoustic design of Freeborn Hall. One of the main portions of the audio system that should be changed are the loudspeakers. The loudspeakers should come from a company that manufacturers numerous products for permanently installed sound reinforcement systems such as JBL, Electro-Voice, Renkus-Heinz, EAW, or one of many others. The speaker drivers should be horn-loaded to provide a tighter pattern control, keeping sound where it is needed and away from reflecting surfaces and open microphones. The speakers should be capable of full frequency range sound to handle the various music and speaking formats. 31

R04142.2: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, September 9,2004 A Digital Signal Processing (DSP) based audio signal routing system is proposed for the hall. The DSP unit-not only handles most of the signal routing, but also replaces equalizers, crossovers, limiters, and any other processors in the equipment rack. One set of mixing board sends can be input into the DSP and routed to not only the amplifiers and on to the loudspeakers, but also to ancillary speakers and the assisted listening system. A direct output from the mixing board will solve the intelligibility issues with these systems. The basic DSP unit is an 8-input and 8-output module, expandable by adding additional modules. Another feature of the DSP is that it clan store scene@ settings recalled at the touch of a button depending on the type of event at the hall. A simple three-button programmable control panel with an LCD screen can be remote mounted in a one-gang wall box in multiple locations within the hall. The control panel is programmed to control any of the DSP parameters including volume level and scene recalls. One other item that the staff of Freeborn Hall wants to see added is a new 24 channel analog mixing board. The microphones probably do not need replacement, although a new wireless system and accessories could be added to the existing system. To power the new loudspeakers, the existing amplifiers may need to be supplemented with additional amplifier units. Other Equipment A floor-standing equipment rack will be needed to house the new audio and video components. The equipment rack will be positioned in the control room adjacent to the existing racks. A new power sequencing system is recommended to turn on and off all equipment. Currently, staff must follow a set procedure for turning on each piece of equipment manually. With an automatic sequencing system, the operator initiates the on@ command with a button or key and the equipment powers on in a predetermined sequence with adjustable delay between sequences. A rack-mount sequencer and remote sequencers at the projectors will be required. On the electrical side, it is recommended that all of the existing and future audio/video equipment be powered by circuits on an independent 10-circuit technical power isolated ground panel. The panel should be on an isolation transformer sized per the equipment load to prevent drawing from other building systems and to reduce noise. The equipment racks will need 3 or 4 20-amp circuits, with an additional 20-amp circuit at the mixing board location in the control room. A 20-amp circuit should also be used for the video projectors. Another 20- amp circuit should be used for the mixing location on the assembly hall floor, and at least a pair of a/v 20-amp circuits should be used for the stage area. Cost A cost analysis is provided at the end of this report. The estimate shows the main components broken out and a price associated with each item. Specific brands and models are not listed. Only list prices are given, actual street prices vary from product to product and will be less than the prices shown. The highest cost item for the video system is the projector. Projectors that meet the design criteria vary greatly in list price, ranging from $20,000 to more than $50,000 per projector. Typically, the higher cost projectors will produce better quality images, but this is not always the case. For this application, we feel that anything much more than $35,000 list price per projector and lens is not worth the additional cost Many other 32

R04142.2: Shalleck Collaborative, UCD Freeborn Hall, Remedial Acoustic Design, September 9, 2004 products in the a/v system vary greatly in price from manufacturer to manufacturer as well, although not typically as drastically as the projectors. An estimate for labor, installation, and programming is also included. Costs associated with the electrical infrastructure changes recommended for the a/v system is not included and should be sought from an electrical contractor based on our recommendations. An estimate of the projector screen support structure is not included as well. Please call if there are any questions or comments regarding the audio-visual system design presented in this report. Although this is a preliminary system design, we would be happy to develop a more detailed design as this renovation project moves forward. Sincerely, Brian R. Smith, Senior Engineer Approved by, Steve Pettyjohn, Principal Certified: Institute of Noise Control Engineers-1981 REFERENCES 1. B. Smith & S. Pettyjohn, Preliminary Results of Acoustical Analysis and Evaluation of U.C. Davis Freeborn Hall, The Acoustics & Vibration Group, Project No. R04142, July 26,2004. 33

> UC Davis - Freeborn Hall Production Systems Improvements Master Plan Work Scope Key - Reference SK's l 2 Item Area Description Notes Demolition Remove-all acoustic reflectors installed during 1980's renovation including wall panels, ceiling light troffers and lights, and stage ceiling reflectors. / Salvage lighting electrical circuiting. O / Provide Acoustical Material at Audience Ceiling Overhead Support Truss Rigging Attachment Points Overhead Support Trusses Provide 5,700 square feet of 2" thick fabric wrapped fiberglass panels applied to the underside of the ceiling over the audience area. Minimum Noise Reduction Coefficient (NRC) of 0.85 per ASTM C423 using mounting Type A per ASTM E795. Manufacturers: Wall Technologies, Conwed, Deacoustics, Lamvin, LBI/Boyd. Provide penetrations in audience ceiling for the support cables for overhead support truss. Cut ceiling and provide trim in 100 places. Event industry standard truss overhead support system as shown in example drawing SK's 1 & 2, dead hung. Finish: custom powder coated a selected color. Engineered and installed. Architectural Lighting (96) incandescent 8" diameter theatrical "par" down lights (1) Q250PAR38/FL lamp (fixture unit cost est. at $200); clamp mount to overhead support trusses. (72) fluorescent "high-bay" fixtures with an approximate 24" diameter, Utilize salvaged circuits where available. Fluorescent fixtures connected to "non-dims" within the event lighting control system. Incandescent fixtures are cord and plug to wiring devices each with (8) 42-watt triple compact fluorescent lamps; "Sportlite LX-800 and dimmers incorporated into the event lighting control series" fixtures with custom louvers (fixture unit cost est. at $500); system described below. pendant mount from ceiling. Proscenium Improvements Smoke Vents / Q WS&bOCP Stage Floor Refinishing / P y Fire Sprinkler Upgrade Stage "Dead Hung" Battens Pick-up Points & Chain Hoists Event Lighting System Provide allowance for aesthetic improvements to the proscenium walls facing the audience. "Gravity" smoke venting required in the amount of 5% of the stage area. Verify fitness and operation of existing vents. Re-rig for compliant operation by fusible link and from stage floor level. Existing stage floor to be stripped and refinished with penetrating ebony stain and non-reflective urethane sealer. Provide sprinklers over the audience area if mandated by the Campus Fire Marshall [10) dead hung pipes and (12) beam clamps for attachment of stage elements; (4) l-ton chain hoists; (4) 1/4-ton, 3-phase chain hoists; control system Complete control system consists of a control console, control electronics, dimmers, circuit outlet boxes ("distribution"), portable fixtures and cable. Stage Draperies An inventory of replacement stage draperies will be included. These would include a decorative bi-parting motor operating main curtain, a main border, black masking legs and borders, a eye, and a black backdrop. Provide Acoustical Material at Stage Side Walls Production Lighting Control and AV System Infrastructure Provide 400 square feet of 1" thick fabric wrapped fiberglass panels applied to the side walls of the stage. Minimum Noise Reduction Coefficient (NRC) of 0.85 per ASTM C423 using mounting Type A per ASTM E795. Manufacturers: Wall Technologies, Conwed, Deacoustics, Lamvin, LBI/Boyd. Refer to Report for details of scope +/-200 dimmers. Fixture inventory includes: (12) ETC 1 Revolution moving ellipsoidals, (50) fixed ellipsiodals, (16) \ borderlights Event AV System Refer to Report for details of scope Budget provided by Acoustics & Vibration Group. See report for details. The Shalleck Collaborative inc. '6/21/2005

APPENDIX G