SHORT-CIRCUIT LEVELS FOR THE VICTORIAN ELECTRICITY TRANSMISSION NETWORK TO

Similar documents
SHORT TERM TRADING MARKET: SETTLEMENT RECONCILIATION MAPPING

NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET

Tasmanian Transmission Revenue Proposal

FACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

Operating Security Standards

National Electricity Amendment (Network Support Payments and Avoided TUoS for Embedded Generators) Rule 2011

MARKET EVENT REPORT. Scheduling Error Affecting Dispatch of Mintaro Gas Turbine Station. Electricity Market Operations Performance PREPARED BY:

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE

G8 - Contracts for Difference Metering

Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions

NETWORK PLANNING REPORT - P002. BALLARAT (Planning)

16 West Coast Regional Plan

Network Consulting for Power Grid Optimization

FACTS. Solutions to optimise network performance GRID

Wide Area Monitoring Current Continental Europe TSOs Applications Overview

INTRODUCTION TO HARMONIC ASSESSMENT IN POWER SYSTEMS

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

6. The estimated costs here do not include any applicable ITCC tax

2014 Residential Electricity Price Trends

HEATWAVE JANUARY DATE: 26 January 2014

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

New South Wales State and Regional Population Projections Release TRANSPORT AND POPULATION DATA CENTRE

PRELIMINARY DECISION CitiPower distribution determination

Executive Summaries Bursary Vacation Placements in VICTORIA. List of Executive Summaries. Student Company Page Bursary Holders

Load Dispatcher (Class Code 5223) Task List

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

(2) Words and expressions used and not defined in these regulations but defined in the Act shall have the meaning assigned to them in the Act.

FACT SHEET. NEM fast facts:

Renewable Energy in Victoria

Actual capital expenditure during the current regulatory period. Project summary

EPCOR Distribution & Transmission Inc.

Chapter 9 Balanced Faults

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

Revenue proposal 2014/ /19. responsive efficient price aware

RELIABILITY PLANNING CRITERIA

Wind farm Developments in South Australia: Select Committee Inquiry

The stable way. Synchronous condenser solutions. siemens.com/energy/facts

2012 San Francisco Colloquium

Asset Management Plans

EXECUTIVE SUMMARY. Key observations. AEMO to include rooftop PV generation in annual forecasting reports

Preliminary Feasibility Assessment For. The Rio Tinto Alcan to BCH Transfer Limit of 460 MW. With 50% Series Compensation on Both KMO KIT lines

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas

Kent Active System Management (KASM) Oct 2015 / Matthieu Michel

ELECTRICITY FROM RENEWABLE ENERGY IN VICTORIA 2011 June 2012

Energex. Statement of expected price trends. 1 July 2014 to 30 June /15 Statement of expected price trends

Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION

Asset Management Strategy

POWER TRANSMISSION FROM OFFSHORE WIND FARMS

Western Australia and the Northern Territory are not connected to the NEM, primarily due to the distance between networks.

IESO Supply Deliverability Guidelines

FRCC Standards Handbook. FRCC Automatic Underfrequency Load Shedding Program. Revision Date: July 2003

General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System

Possible future retail electricity price movements: 1 July 2012 to 30 June 2015

Brochure Introducing HVDC

Australian Accounting Standards Board (AASB)

VICTORIAN ELECTRICITY DISTRIBUTION NETWORK SERVICE PROVIDERS ANNUAL PERFORMANCE REPORT 2010

HVDC 2000 a new generation of high-voltage DC converter stations

POWER FACTOR CORRECTION

Instructions for use:

AusNet Transmission Group Pty Ltd

APRIL 2014 ELECTRICITY PRICES AND NETWORK COSTS

Guidelines on the Short Circuit Current Rating for Industrial Control Panels

Engineering innovation

Hyperlinks are Inactive

Knowing the FACTS. FACTS that enhance power quality in rail feeder systems

NATIONAL ELECTRICITY FORECASTING REPORT. For the National Electricity Market

Product brochure Multi Functional Switchgear PASS M kv Flexible and compact switchgear solutions for windfarms

APPROVED AMENDED PRICING METHODOLOGY FOR PRESCRIBED SHARED TRANSMISSION SERVICES FOR 1 JULY 2014 TO 30 JUNE 2019.

A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES

APPENDIX 15. Review of demand and energy forecasting methodologies Frontier Economics

Tech Talk. Smart metering update Successful rollout. Connection Standards newsletter December Contents. To all Registered Electrical Contractors

2012 San Francisco Colloquium

DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS

A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division

ENERGY RETAILERS COMPARATIVE PERFORMANCE REPORT PRICING

Appendix D Justification for Recovery of Regulated Inventory Costs September 2011

The Economic Impact of Dominion Capital Expenditure Projects

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Asset Management Plan

A Live Black-start Capability test of a Voltage Source HVDC Converter

COMPARISON OF THE FACTS EQUIPMENT OPERATION IN TRANSMISSION AND DISTRIBUTION SYSTEMS

Power System review W I L L I A M V. T O R R E A P R I L 1 0,

Jemena Electricity Networks (Vic) Ltd

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK

Magnus Callavik, ABB Power Systems, HVDC, Västerås, Sweden Phone: +46(0)

Non-Network Options Report

Specific amendments to the Capacity Allocation and Congestion Management Network Code

Power Transmission and Distribution. Shunt reactors for medium and highvoltage. From development to use

Distribution Annual Planning Report (DAPR) to

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

WE RE HERE TO CHANGE BUSINESS ENERGY IN AUSTRALIA FOREVER.

ENERGY RETAILERS COMPARATIVE PERFORMANCE REPORT PRICING

Service Power Technologies. Retrofitting A future-oriented concept in lifecycle management

Earth Fault Detection Basics in Theory

DESCRIPTION DWG DESCRIPTION DWG

1. a) How effective is the current Climate Change Act 2010 in driving climate change action by:

Transcription:

SHORT-CIRCUIT LEVELS FOR THE VICTORIAN ELECTRICITY TRANSMISSION NETWORK 2014 15 TO 2018 19 Published: June 2015

IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information relating to AEMO s planning and development functions for the Victorian electricity transmission network, as at the date of publication. Disclaimer This document or the information in it may be subsequently updated or amended. This document does not constitute legal or business advice, and should not be relied on as a substitute for obtaining detailed advice about the National Electricity Law, the National Electricity Rules, or any other applicable laws, procedures or policies. AEMO has made every effort to ensure the quality of the information in this document but cannot guarantee its accuracy or completeness. Accordingly, to the maximum extent permitted by law, AEMO and its officers, employees and consultants involved in the preparation of this document: make no representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of the information in this document; and are not liable (whether by reason of negligence or otherwise) for any statements or representations in this document, or any omissions from it, or for any use or reliance on the information in it. Acknowledgement AEMO acknowledges the support, cooperation and contribution of all electricity industry participants in providing data and information used in this publication. 2015. The material in this publication may be used in accordance with the copyright permissions on AEMO s website. Australian Energy Market Operator Ltd ABN 94 072 010 327 www.aemo.com.au info@aemo.com.au NEW SOUTH WALES QUEENSLAND SOUTH AUSTRALIA VICTORIA AUSTRALIAN CAPITAL TERRITORY TASMANIA

CONTENTS 1. INTRODUCTION 2 2. SHORT-CIRCUIT LEVELS APPROACHING STATION LIMITS 2 3. SHORT-CIRCUIT LEVEL MITIGATION 3 3.1 Hazelwood Power Station 3 3.2 Moorabool Terminal Station 3 3.3 Richmond Terminal Station 220 kv 4 3.4 Richmond Terminal Station 22 kv 4 3.5 West Melbourne Terminal Station 4 APPENDIX A. COMMITTED PROJECTS AND CLOSURES 5 APPENDIX B. NETWORK MODELLING ASSUMPTIONS 6 B.1 Summary of modelling assumptions 6 B.2 representation 6 B.3 data 6 B.4 Loads 6 B.5 Pre-fault voltage profile 6 B.6 switching modes and outage conditions 6 B.7 Reactive plant and HVDC 7 B.8 development plan 7 APPENDIX C. SHORT-CIRCUIT LEVEL ASSESSMENTS 8 MEASURES AND ABBREVIATIONS 9 Units of measure 9 Abbreviations 9 GLOSSARY 9 AEMO 2014 1

1. INTRODUCTION This report provides information relating to the Victorian electricity transmission network s capability to withstand short-circuit currents over a five-year outlook period (2014 15 to 2018 19). This information is useful for: Stakeholders who intend to connect to the Victorian electricity transmission network. They can use it as a basis for a preliminary assessment of the network s capability to accommodate an intended connection. Stakeholders who own equipment that may be affected by transmission network current flows (or who plan to invest in such equipment). They can assess the impact of high network current flows during faults. 2. SHORT-CIRCUIT LEVELS APPROACHING STATION LIMITS Due to fewer new large generators being forecast to connect compared to last year, as well as the closure of Morwell power station, maximum short-circuit levels have reduced slightly on the transmission network. AEMO s modelling for this report shows that the following 14 terminal stations have maximum shortcircuit levels forecast greater than 95% of their short-circuit limits during the five-year outlook period. Brooklyn Terminal Station 66 kv East Rowville Terminal Station 66 kv Geelong Terminal Station 66 kv Hazelwood Power Station 220 kv Jeeralang Terminal Station 220 kv Keilor Terminal Station 66 kv Moorabool Terminal Station 220 kv Red Cliffs Terminal Station 22 kv Richmond Terminal Station 220 kv, 66 kv, and 22 kv Ringwood Terminal Station 66 kv Rowville Terminal Station 66 kv Templestowe Terminal Station 66 kv Thomastown Terminal Station 66 kv West Melbourne Terminal Station 220 kv & 66 kv. AEMO will continue to monitor these locations to make sure their maximum short-circuit levels remain within the limits set by the National Electricity Rules and the Use of System Agreements (UoSA) for circuit breaker capabilities. Short-circuit levels are affected by network configurations such as new connections and network augmentations. AEMO 2015 2

3. SHORT-CIRCUIT LEVEL MITIGATION Of the 14 locations where short-circuit levels are approaching limits, the following four are forecast to exceed the existing short-circuit limits within the five-year outlook. Hazelwood 220 kv Moorabool 220 kv Richmond 220 kv and 22 kv West Melbourne 220 kv. Specific mitigation measures for each of the locations identified are outlined in Sections 3.1 3.5. Options for reducing short-circuit currents in the Victorian electricity transmission network include: Operational switching, where selected transmission network circuit breakers may be switched to open, to reduce short-circuit current contributions into critical buses. This is already being undertaken at several locations in the Victorian network, including Hazelwood Power Station 220 kv, Thomastown 220 kv, Rowville 220 kv, Keilor 220 kv, and several 66 kv buses. redevelopment, such as further bus splits at critical buses or taking circuits out of service during select periods. Installing short-circuit current limiting reactors. Upgrading the short-circuit capability of terminal stations by replacing affected plant (such as earth grids, civil structures, circuit breakers, and other switchgear). Preferred short-circuit level mitigation options are developed on a case-by-case basis, with each project undergoing a comprehensive technical and economic justification. 3.1 Hazelwood Power Station AusNet Services has commenced a staged process to replace aged and limiting circuit breakers at Hazelwood Power Station as part of their asset refurbishment program. Following completion of the fourth stage, scheduled for 2017, this station will be fully rated for shortcircuit levels up to 40 ka. Last year s short-circuit level report calculated the short-circuit level at the Hazelwood B2 220 kv to exceed the 40 ka circuit breaker limit under certain system configurations. However given Morwell power station closure, Hazelwood B2 220 kv is now forecast to remain under the 40 ka circuit breaker limit. AEMO will continue to manage prospective short-circuit levels at Hazelwood Power Station through operational switching arrangements to ensure that short-circuit levels remain within network asset limits. 3.2 Moorabool Terminal Station In March 2015, AEMO and AusNet Services re-designated this station as a Metro station, rather than a Country station. This has increased the station limit from 26.2 ka to 40 ka, in line with National Electricity Rules (NER) limits. All 220 kv circuit breakers at Moorabool Terminal Station are rated for short-circuit levels up to 40 ka. AusNet Services will be investigating the short circuit level withstand capability of substation equipment at Moorabool Terminal Station as part of its Capability Incentive Parameter Action Plan (NCIPAP) for 2014 2017. AEMO 2015 3

3.3 Richmond Terminal Station 220 kv The maximum short circuit current is expected to exceed the lowest circuit breaker rating of 26.3 ka at Richmond 220 kv. However, only part of the bus short-circuit current flows through the limiting circuit breaker. Based on the short-circuit current expected to flow through individual circuit breakers, AEMO calculates that the equivalent bus short-circuit level limits could be as high as 29.3 ka for three phase and 28.8 ka for single phase-to-ground faults before the circuit breaker reaches its limit. Richmond 220 kv short-circuit levels are forecast to remain within these equivalent bus short-circuit level limits, and no mitigation measures are required at this stage. 3.4 Richmond Terminal Station 22 kv Richmond 22 kv bus short-circuit levels are forecast to be within 95% of NER limits from 2014 15 onwards. AEMO will continue to monitor short-circuit levels at Richmond and will implement appropriate short-circuit level mitigation measures if required. 3.5 West Melbourne Terminal Station The maximum short circuit current is expected to exceed the lowest circuit breaker rating of 26.3 ka at West Melbourne 220 kv. However, only part of the bus short-circuit current flows through the limiting circuit breaker. AEMO calculates that the equivalent bus short-circuit level limits could be as high as 27.1 ka for single phase-to-ground before the circuit breaker reaches its limit. Although West Melbourne 220 kv bus short-circuit levels are still forecast to reach the circuit breaker limit in 2014 15, these short-circuit levels will be controlled to remain within the circuit breaker limits operationally as required. West Melbourne Terminal station is scheduled to have four existing 220/66 kv transformers replaced with three 220/66 kv transformers in 2018 19. This will reduce the short circuit levels on the 66 kv network. AEMO 2015 4

APPENDIX A. COMMITTED PROJECTS AND CLOSURES Date Type Project 2014 15 Generation Bald Hills Wind Farm Establishment Bendigo Terminal Station Rebuild (Stage 2) Closure Dederang Terminal Station Transformer Replacement Geelong Terminal Station Rebuild Morwell Terminal Station Rebuild Morwell Power Station Closure 2015 16 Brunswick Terminal Station Redevelopment Stage 1 Glenrowan Terminal Station Rebuild 2016 17 Heywood Terminal Station Third Transformer Installation Generation Ararat Wind Farm Establishment South Morang Terminal Station Rebuild 2017 18 Ballarat Terminal Station to Moorabool Terminal Station Third Circuit Installation Deer Park Terminal Station Establishment Heatherton Terminal Station Redevelopment Richmond Terminal Station Redevelopment 2018 19 West Melbourne Terminal Station Redevelopment Ringwood Terminal Station Rebuild AEMO 2015 5

APPENDIX B. NETWORK MODELLING ASSUMPTIONS B.1 Summary of modelling assumptions B.2 representation Short-circuit levels in this report are based on a network model with all generators, transmission plant, and relevant sub-transmission lines included and in service. Victoria s neighbouring transmission networks (in New South Wales and South Australia) are represented by simplified equivalent networks that represent the committed generation and transmission projects in those regions. Generation and transmission plant changes in Tasmania will not affect short-circuit levels in Victoria as the two regions are connected through a high-voltage direct current (HVDC) link. B.3 data Transmission connection assets, sub-transmission assets, and distribution network embedded generators included in the model are based on information supplied by the distribution businesses and AusNet Services. B.4 Loads The Victorian loads at individual terminal stations have been set to equal the diversified maximum demand from the 2014 Victorian Terminal Station Demand Forecasts, as this condition maximises short-circuit currents. The total Victorian regional demand is set to the medium-growth, summer 10% probability of exceedance (POE) demand forecasts in the 2014 National Electricity Forecasting Report. 1 B.5 Pre-fault voltage profile The short-circuit currents are proportional to pre-fault voltage, which is reported alongside the shortcircuit levels calculated at each location. B.6 switching modes and outage conditions The transmission network is assumed to be normally operated in one of six switching modes: R0, R1, R2, R5, R5M, and R6. These normal switching modes are detailed in the supporting spreadsheet. 2 AEMO calculated short-circuit levels under each of these modes, and the highest short-circuit level at each location is presented in this report. AEMO also assessed short-circuit levels under select outage conditions where automatic control schemes or manual changes in bus configuration are known to result in increased short-circuit levels. 1 AEMO. 2014 National Electricity Forecasting Report. Available at: http://www.aemo.com.au/electricity/planning/forecasting/~/media/files/other/planning/nefr/2014/2014%20updates/nefr_final_published_no v_2014.ashx 2 AEMO. Short-Circuit Levels for The Victorian Electricity Transmission 2014-15 to 2018-19 (Spread sheet). Available at: http://www.aemo.com.au/electricity/planning/victorian-annual-planning-report/vapr-supporting-information. AEMO 2015 6

B.7 Reactive plant and HVDC Short-circuit levels presented in this report include contributions from shunt capacitor banks and HVDC interconnectors (Basslink and Murraylink). The assumptions of reactive plant and HVDC applied in the short-circuit calculation are described in the supporting spreadsheet. 3 Before calculating the short-circuit levels, static VAR compensators (SVC) are converted from their synchronous condenser model, typically used in steady state assessments, to an equivalent maximum shunt capacitance. This represents the behaviour of an SVC shortly after inception of a short circuit. B.8 development plan Committed and proposed network augmentations and generation connections to the transmission and distribution networks affect short-circuit levels. The supporting data3 describes the transmission network developments considered in this short-circuit level assessment. AEMO is aware of other connection proposals, but these were not sufficiently advanced at the time this assessment was prepared, so AEMO did not consider them in this report. Such proposals will affect short-circuit levels if they proceed. Outside Victoria, only new generation developments in South Australia and New South Wales located near the Victorian border affect Victorian short-circuit levels. AEMO is not aware of any such developments over the five-year outlook period. 3 AEMO. Short-Circuit Levels for The Victorian Electricity Transmission 2014-15 to 2018-19 (Spread sheet). Available at: http://www.aemo.com.au/electricity/planning/victorian-annual-planning-report/vapr-supporting-information. AEMO 2015 7

APPENDIX C. SHORT-CIRCUIT LEVEL ASSESSMENTS AEMO determined the short-circuit levels for three phase and single phase-to-ground faults for the five-year outlook period based on the assumptions described in Appendix B. The supporting data 4 presents the short-circuit levels and limits for each bus under system normal conditions and selected outage conditions. Short-circuit level information for each bus throughout the five-year outlook period comprises: Pre-fault voltage level (kv). Three phase-to-ground short-circuit level (3-phase ka) and the related switching mode that delivers the highest short-circuit level. Single phase-to-ground short-circuit level (1-phase ka) and the related switching mode that delivers the highest short-circuit level. The switching modes and outage conditions include: Normal switching modes: R0, R1, R2, R5, R5M, and R6. Outage conditions, identified by normal switching modes plus ID followed by a number, corresponding to the specific outage condition. Short-circuit level bus and limit information is also provided for each bus, comprising: Base voltage (kv), which is the nominal bus voltage level. Three phase short-circuit level limit (3-phase ka) and its basis. Single phase-to-ground short-circuit level limit (1-phase ka) and its basis. Where short-circuit limits are specified in a Use of System Agreement (UoSA), the basis for each limit is the lesser of: The lowest circuit breaker rating. The limit stated in the UoSA with the distribution business. Where short-circuit limits are not specified in the UoSA, the basis for each limit is the lesser of: The lowest circuit breaker rating. The National Electricity Rules limit. 4 AEMO. Short-Circuit Levels for The Victorian Electricity Transmission 2014-15 to 2018-19 (Spread sheet). Available at: http://www.aemo.com.au/electricity/planning/victorian-annual-planning-report/vapr-supporting-information. AEMO 2015 8

MEASURES AND ABBREVIATIONS Units of measure Abbreviation ka kv Unit of measure Kiloamps Kilovolts Abbreviations Abbreviation AEMO HVDC NCIPAP NER POE SVC UoSA Expanded name Australian Energy Market Operator High Voltage Direct Current Capability Incentive Parameter Action Plan National Electricity Rules Probability of Exceedance Static VAR Compensator Use of System Agreement GLOSSARY Term Committed Augmentation Phase-to-ground fault Short-circuit level Three-phase fault Definition Any network project that has advanced to the point where proponents have secured land and planning approvals, entered into contracts for finance and generating equipment, and either started construction or set a firm date. A contingency event where a single phase becomes short-circuited to ground. The maximum current that is expected to flow in response to a short-circuit at a given point in the power system. Short-circuit levels are generally measured in kiloamps (ka). A contingency event where all three phases become short-circuited together. AEMO 2015 9