PVC Failures. Russ Dueck, P.Eng. City of Calgary, Water Resources UDI Breakfast Seminar September 8, 2010

Similar documents
SECTION POLYVINYL CHLORIDE (PVC) PIPE

SECTION 5: SANITARY SEWER SYSTEM DESIGN

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

Diamond LOK-21 Assembly Information

Royal Seal Gasketed Sewer Pipe

Beacon Hill Sewer District Standard Specifications

EXHIBIT "A. Technical Specifications for Water and Sewer Service Lines

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

SECTION GRAVITY SANITARY SEWERS

Wastewater Capital Projects Management Standard Construction Specification

PVC Installation and Tapping For Potable Water and Sanitary Sewer. Handling and Installation Practices Manual

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

WATER MAIN CONSTRUCTION TECHNIQUES DEPARTMENT OF PUBLIC WORKS WATER & WASTEWATER DIVISION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SECTION 6A STORM DRAIN DESIGN Mar S E C T I O N 6A STORM DRAIN - DESIGN

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

PVC Gasketed & Solvent Weld Pipe

LS 2540 SEWER LATERALS AND INSPECTION TEES

Force Main Condition Assessment: New Technologies & Case Studies

INDEX. Sec. No. Items Page Nos.

The Most Advanced Name in Drainage Systems. Sanitary Sewer Pipe

DESIGN AND CONSTRUCTION GUIDELINES AND STANDARDS DIVISION 33 UTILITIES SITE UTILITIES

Table of Contents 2.1 INTRODUCTION MATERIALS IN USE...2-1

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

SEPARATION OF WATER MAINS, SEWERS, STORM DRAINS, AND UNDER DRAINS

WATER SERVICE 2

SECTION STORM DRAINAGE TABLE OF CONTENTS

Native InDesign 2890 SaniTite Brochure 1/8" CMYK April 17, 07

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

LEE S SUMMIT USES PIPE BURSTING TO BROADEN ITS ASSET MANAGEMENT TOOLBOX AND REHABILITATE POTABLE WATER DISTRIBUTION SYSTEM

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

OAR52 A-1 (September, 1981)

Mechanical Joint Restraints

Replacement Project of Aged Pipes in Tokyo

SANITARY SEWER SPECIFICATIONS

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

Carlon Bore-Gard and Boreable Multi-Gard Raceway

SECTION 300 SANITARY SEWER CONSTRUCTION SPECIFICATIONS

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION STORM DRAINAGE SYSTEM

Pro-Lift Steel Pile Foundation Repair

900 SEWERAGE WORK ITEM PIPE SEWERS COMPLETE IN PLACE

Superseded. The average time for a normal repair after a crash is approximately 1.5 to 2 hours for a 3- person crew.

Section Installation of pipe and casing for sanitary sewer by methods of augering.

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 603 SANITARY SEWER FORCE MAINS

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

SECTION NONREINFORCED CONCRETE SEWER PIPE

AMERICAN Mechanical Joint Pipe For Water, Sewage or Other Liquids

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

due to uncertainty. This, in turn, has a direct impact on equipment availability and maintenance costs. Unfortunately, due to misconceptions and

SECTION 724 PIPE CULVERTS

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

Model Specification 509 DRISCOPLEX 4200 and DRISCOPLEX 4300 Gravity Flow Sanitary Sewer

Section 2100-Trenching and Tunneling

Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING

Value Engineering Considerations for Cast Iron Soil Pipe and PVC in Commercial Sanitary and Storm Drainage Applications

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 21

Installation Guide For PVC Sewer Pipe

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

3A General Information A. Concepts... 1 B. Conditions... 1

CCTV INSPECTION OF SEWER LINES. A. Section Sanitary Gravity Sewer Lines. B. Section Sanitary Gravity Sewer Line Testing

Module 3: Sewer Material Lecture 3: Sewer Material

DIVISION 4300 STORM DRAINAGE

ASTM C76, Class III, Wall B, except as modified herein. Clean natural sand, ASTM C33. Artificial or manufactured sand will not be permitted.

SECTION 3 SANITARY SEWER DESIGN

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

Elev. A = , Elev. B = , horizontal distance = 1625 feet a. 7.7 b..077 c d. 1.28

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Memorandum. PROJECT: Postmark Emergency Storm Repair Alternative Analysis

CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST

Pipeline Replacement using Relining

SEWER STANDARDS SECTION 2 SECTION TWO - SEWER STANDARDS CITY OF ELLENSBURG

PART 1 GENERAL 1.1 SECTION INCLUDES

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines

C. Section TESTING LABORATORY SERVICE.

Whitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

CITY OF MELISSA MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

TABLE OF CONTENTS SECTION 500 SANITARY SEWER AND FORCE MAIN

Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

Impacts of Tunnelling on Ground and Groundwater and Control Measures Part 1: Estimation Methods

Transcription:

PVC Failures Russ Dueck, P.Eng. City of Calgary, Water Resources UDI Breakfast Seminar September 8, 2010

PVC Watermain Reliability Distribution System is 50% PVC PVC breaks account for 1-3% of total annual break count PVC failures are typically catastrophic, leading to substantial water loss and sinkholes.

PVC Watermain Reliability PVC Failures Last 30 Years 157 Failures Failures on All Pipe Materials Within 30 Years of Installation 10,495 Failures

PVC Watermain Reliability

Recent Failures Northwest Calgary December 2008 Repair Cost = $82,000 Southeast Calgary July 2009 Repair Cost = $57,800 Southwest Calgary September 2009 Repair Cost = $182,500 Average repair cost of watermain breaks in 2009 = $14,000

Northwest Failure December 2008 Installation Year: 2001 Size: 250 mm Class: DR-18 Failure Mode: Split initiating at bell Probable Causes: - Longitudinal bending combined with joint deflection. - Joint deflection above maximum accepted deflection of three degrees. - Over-insertion of spigot into bell - Soil movement (bedding conditions)

Northwest Failure December 2008 Note depth of insertion of spigot in bell

Northwest Failure December 2008 Note deflection

Northwest Failure December 2008 Note spigot impressions on bell

Southeast Failure July 2009 Installation Year: 1981 Size: 300 mm Failure Mode: Split Probable Causes: - No clearance between 1800 mm storm duct and PVC pipe, thus causing longitudinal bending. 300 mm vertical separation is required at crossings. - Soil settlement

Southeast Failure July 2009 Note lack of vertical separation

Southeast Failure July 2009

Southwest Failure September 2009 Installation Year: 2004 Size: 250 mm Class: DR-18 Failure Mode: Split initiating at bell Probable Causes: - Longitudinal bending either due to improper installation or insufficient bedding - Joint deflection above maximum accepted deflection of three degrees - Over-insertion of spigot into bell

Southwest Failure September 2009 Note road sub-grade damage

Southwest Failure September 2009 Note how the pipe as sprung after being cut

Southwest Failure September 2009 Note longitudinal deflection

Southwest Failure September 2009 Note depth of spigot in bell

Southwest Failure September 2009 Note spigot impressions (partially highlighted in black)

Root Cause Analysis The causes of the failures were one or a combination of the following: Over insertion of the joint. Joint deflection above maximum accepted deflection guidelines. Pipe stress due to longitudinal bending. Lack of vertical separation from an existing utility.

Root Cause Analysis Over insertion of the joint: Uni-Bell Recommendations: A gap should exist between the inside of bell and spigot. Spigot should not bottom in bell. Over-inserted pipe will cause point load and bell distortion.

Root Cause Analysis Joint deflection above maximum accepted deflection guidelines: Manufacturer s Installation Guide (In accordance with Uni-Bell, AWWA C-900, and AWWA M23) Joint deflection and longitudinal bending shall not be combined on the same pipe. Joint deflection requires assembly ½ less than insertion line Maximum joint deflection for 250 mm pipe = 3 degrees

Root Cause Analysis Pipe stress due to longitudinal bending: Manufacturer s Installation Guide (In accordance with Uni-Bell, AWWA C-900, and AWWA M23) Joint deflection and longitudinal bending shall not be combined on the same pipe. Longitudinal deflection of 250 mm DR-18 pipe and larger is not recommended.

Root Cause Analysis Lack of vertical separation from an existing utility City of Calgary Standard Specifications for Waterworks Construction Sec 504.16.00 (2009) requires a vertical separation of 300 mm between water, sanitary and storm main crossings. The same 300 mm requirement existed in 1981, as it was implemented after PVC was approved as a water pipe material. Prior to PVC approval, 150 mm was the distance required when ductile iron was the primary material used.

Summary In all three cases, aspects of the installations did not conform to the relevant City of Calgary Waterworks Specifications, Uni-Bell recommendations or Manufacturer guidelines. It is apparent that the failures resulted from design or construction errors that were never rectified. Although the piping designs did not appear to be the primary cause of failure, designers should be cognisant of the complications that tight tolerances create in field conditions. For example, Consultants need to ensure that where pipe designs include curved alignments or cross other utilities, that it is noted on the drawings that the installation of deflection bends may be required. As well, simple details such as pipe wall thickness need to be taken into consideration in designs. By identifying potential conflicts and limitations at the design stage, Contractor s will be better prepared to install the pipe within specifications. Contractors and Consultants need to ensure that workers are educated on Standard Construction Specifications and install pipe according to the manufacturers guidelines. This includes educating workers on the potential consequences of improperly installed PVC pipe, such as catastrophic pipe failures and sinkholes. Manufacturers should ensure that installation guidelines state a maximum insertion distance, and that factory insertion lines are marked for all sizes and classes of pipe. Manufacturers play an important role in continually educating designers and installers on the proper methods of PVC pipe installation.