Experiences of Irrigation Rehabilitation and. Modernisation in Viet Nam

Similar documents
Technical Consultant

Module 3. Irrigation Engineering Principles. Version 2 CE IIT, Kharagpur

Organization Chart for Design Organization

Ex-Ante Evaluation (for Japanese ODA Loan)

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road,

VEHICLE CROSSOVER INFORMATION PACK

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM

Broad Crested Weirs. I. Introduction

Exercise (4): Open Channel Flow - Gradually Varied Flow

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.

Lecture 24 Flumes & Channel Transitions. I. General Characteristics of Flumes. Flumes are often used:

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure

Corporate Social Responsibility (CSR) for Responsible Agricultural Investments (RAI)

Ponds- Planning, Design, Construction

Madagascar: Betsiboka Rice Project, Phases I-V

Cambodia: Flood Damage Emergency Reconstruction Project

Cambodia: Extension of rural roadways (TRIP I-III) and removal of flood damage on rural roads and other infrastructure (FRP)

Problem Tree Analysis

Global water resources under increasing pressure from rapidly growing demands and climate change, according to new UN World Water Development Report

IE principal dimensions

Viet Nam Da Nang Waste water management

Micro-Hydro. Module Introduction. Tokyo Electric Power Co. (TEPCO)

CHAPTER 3 RESEARCH DESIGN

Flood mitigation program for Gatun lake. Programa de mitigación de inundaciones del lago Gatún

IRRIGATION PROJECTS IMPLEMENTED BY FAO IN LEBANON

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

Management of Water and Fisheries Resources to Improve Community Livelihoods in Battambang

Progress of Water Environmental Governance/Management and Future Challenges in Vietnam

APPLICATION OF GIS AND REMOTE SENSING IN IRRIGATION NETWORKS MANAGEMENT

PRSENTATION ON DRAINAGE SYSTEM DELHI EAST DELHI MUNICIPAL CORPORATION

How To Build A Road Into A Lake In The North Of The Korean Island Of Hongkoon

TANZANIA. The land area of Tanzania is about 1 million square kilometres. This includes the offshore islands of Zanzibar, Pemba and Mafia.

HOW TO FUND BASIN MANAGEMENT PLANS? Invest in IWRM - it pays back!

Design of Bridges. Introduction. 3 rd to 4 th July Lecture for SPIN Training at the University of Dar es Salaam

RICE CULTIVATION: ENVIRONMENTAL ISSUES AND WATER SAVING APPROACHES

Public private partnerships in agricultural insurance

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

SCALING UP AGRICULTURAL FINANCE

Flow Measurement Calibration and Measurement

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa

Water Mains Rehabilitation Framework (NI) Northern Ireland Water

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

CHAPTER 2 QUANTITY TAKE-OFF

Mahmood Ahmad, EXPERT GROUP MEETING ON ACHIEVING FOOD SECURITY IN MEMBER COUNTRIES IN A POST CRISIS WORLD

Ex-Ante Evaluation (for Japanese ODA Loan)

Safe & Sound Bridge Terminology

MINUTES of a meeting of CABINET held on 16 April 2013 at County Hall, Matlock. PRESENT Councillor A I Lewer (in the Chair) Councillors J A Allsop, J

AGRICULTURAL PROBLEMS OF JAPAN

Cost Benefits analysis

Emergency Spillways (Sediment basins)

DESIGN CONSIDERATIONS OF SSI SCHEMES FOR THEIR SUSTAINABILITY AND FARMERS MANAGEMENT SIMPLICITY

SECTOR ASSESSMENT (SUMMARY): AGRICULTURE AND NATURAL RESOURCES 1

California Energy Commission Agricultural Peak Load Reduction Program. For Water Agencies Administered by the Irrigation Training and Research Center

Modelling of Urban Flooding in Dhaka City

Highlights of Organic Issues within National Agric Policy (20013)

1 Introduction. 1.1 Key objective. 1.2 Why the South Esk

GENERAL ASSEMBLIES OF ANBO AND INBO JOHANNESBURG (RSA) KOPANONG HOTEL & CONFERENCE CENTRE 4 7 MARCH 2007

National Electric Power Regulatory Authority

NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand

How To Understand And Understand The Flood Risk Of Hoang Long River In Phuon Vietnam

ICOLD POSITION PAPER ON DAM SAFETY AND EARTHQUAKES

HYDRAULICS. H91.8D/C - Computerized Open Surface Tilting Flow Channel - 10, 12.5, 15 and 20 m long

Meeting Urban Development Challenges

Reforming the Malawi Agricultural Development and Marketing Corporation (ADMARC): Poverty and Social Impact Analysis (PSIA)

Emmanuel Tumusiime-Mutebile: The challenge of modernising smallholder agriculture in East Africa

River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a

PJ 24/ February 2012 English only. Projects Committee/ International Coffee Council 5 8 March 2012 London, United Kingdom

ARCHITECTURE OF INDUSTRIAL AUTOMATION SYSTEMS

PJ 22/12. 7 February 2012 English only. Projects Committee/ International Coffee Council 5 8 March 2012 London, United Kingdom

WATER RESOURCES MANAGEMENT IN THE REPUBLIC OF AZERBAIJAN: OVERVIEW AND OUTLOOK

What do you need to know about effective writing in civil engineering practice?

Elevated Roads for Sri Lanka

HOUSE BUILDING DIGEST

Exploring the Possibilities of Small Hydropower Development Utilizing NRCS-Assisted Flood Control Dams

Toward Sustainable Regional Development through Renewable Energy

China s experiences in domestic agricultural support. Tian Weiming China Agricultural University

Your guide to the Energy Company Obligation (ECO) How we can make it work for you. A5_ECOguide_AW.indd 2 24/10/ :04

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

AUTOMATED SCHEDULING OF OPEN-CHANNEL DELIVERIES: POTENTIAL AND LIMITATIONS

Viet Nam: Rural Infrastructure Sector Project

London Borough of Merton Local Flood Risk Management Strategy

Culvert Rehabilitation A presentation by ms consultants, inc. engineers, architects, planners

RECYCLED MICRO HYDROPOWER GENERATION USING HYDRAULIC RAM PUMP (HYDRAM)

TOWARDS AN AUCTION SYSTEM FOR RENEWABLE ENERGY REMUNERATION: KEY POINTS PAPER PUBLISHED

2. Mahatma Gandhi National Rural Employment Guarantee Act (MGNREGA)

Chapter 9. Steady Flow in Open channels

Training Materials for Scaling-up Climate Change Adaptation and Modified Procedures

PERSONAL LEARNING PLAN- STUDENT GUIDE

1. Carry water under the canal 2. Carry water over the canal 3. Carry water into the canal

WATER RESOURCES OF MAHARASHTRA STATE The geographical area of the state is 30.7Mha. Cultivable area is 22.5 Mha.(73%GA). Out of this 40% area is

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

The World Bank DRC - Agriculture Rehabilitation and Recovery Support (P092724)

CLIMATE CHANGE ADAPTATION ACTIVITIES

PRESENTATION. Improving the performance of Public Water Utilities A case study of Bangalore N.C. MUNIYAPPA, Chairman, BWSSB LOCATION MAP OF BANGALORE

Chapter 2 Basis of design and materials

Monitoring and control of openchannel flow in irrigation canals

Performance Evaluation of Community Based Irrigation Management in the Tekeze Basin

Ex-Ante Evaluation (for Japanese ODA Loan)

Lodge Grass Creek Add-on Project Overview

By Manitoba Hydro, March 4 th 2013

Transcription:

Experiences of Irrigation Rehabilitation and Modernisation in Viet Nam

Viet Nam Overview of Irrigation Infrastructure and Rice Production Salient Facts and Figures (2012) Gross Area of Viet Nam: 331,210 km 2 Population: 88.8 M Arable area: ~7.0 Mha (21.1% of land) of which: Irrigation infrastructure (80%) 5.6 Mha Irrigation functioning well: 2.8 Mha Poor / partial / no irrigation: 4.2 Mha Area of rice land: 3.8 Mha Cropped rice area: 7.8 Mha Average cropping intensity: 205% Average rice yield: 5.6 t/ha Rice production: 43.4 Mt Rice exports: 8.1 Mt Agricultural sector: 21.5% GDP

Viet Nam Water Resources Assistance Project (VWRAP) In its Strategy of Socio-Economic Development 2001-2010, the GOVN made agricultural modernisation a top priority to increase growth and reduce poverty. VWRAP was a WB-funded US$ 176 M programme (2005-2012) of irrigation rehabilitation and modernisation on six irrigation schemes, designed to pilot the GOVN s strategy of agricultural modernisation and improved water resources management. VWRAP s objective was Fostering agricultural diversification and gains in productivity through irrigation system modernisation, and thereby raising farm household incomes and reducing rural poverty. Priority was major improvement of water delivery service.

VWRAP IRRIGATION SCHEME LOCATIONS Cau Son 21,800 ha Yen Lap 6,800 ha Ke Go 19,000 ha Phu Ninh 17,400 ha Da Ban 7,300 ha Dau Tieng 57,600 ha Total area: 130,000 ha 0 500 km

Modernisation of Irrigation Infrastructure

VWRAP - Scope of Civil Works Generally, scheme capacities were not significantly increased from original 1980s design. Excavation / filling carried out to restore / modify original canal cross-sections, as required. Canals lined in selected areas (permeable soils, perched reaches, weak eroded banks). Canal structures rehabilitated, modified or replaced. New long-crested weirs and measurement flumes constructed at strategic locations. SCADA systems installed in 5/6 schemes (excl. Da Ban).

Rehabilitation and Modernisation Design Process Design carried out by 3 sets of consultants, but with limited international staff time, used up too early. There was a 1½ year delay in appointing design consultants, thus delaying the start of construction. In general, the original feasibility study proposals were adopted. Original schemes had been designed in 1980s on u/s control basis, which was mostly retained as too costly to change to d/s control. Only East main canal of Dau Tieng scheme was converted to d/s control, with SCADA actuators connected to 6 cross-regulators.

Canal lining - Construction Majority of canal systems were built during the 1980s, following the American war, and were unlined due to budget constraints; the most vulnerable reaches were lined in subsequent years. Under VWRAP, significant lengths of the main, primary, secondary and tertiary systems were lined. Choice of lining type was influenced by the length of construction windows and type of embankment material, and included; a) insitu concrete panels, b) precast slabs, c) small precast units, d) dry stone pitching in rc frames Geomembrane was laid in some reaches (Yen Lap and Ke Go) where canals were perched on permeable soils.

Canal lining added under VWRAP Type of Canal Length km Lined before VWRAP km / % Lined after VWRAP km / % Main canals 196 4.8 Primary canals 647 52 Secondary and tertiary canals 2,004 39 2.5% 8.0% 2.0% 116 59.1% 384 59.4% 688 34.4% Approximately 40% of civil works costs were on canal lining

Canal Lining Types Dau Tieng insitu concrete panels Yen Lap precast slabs with geomembrane Phu Ninh rectangular flume Phu Ninh dry stone pitching in rc frames

Improvements in Canal Conveyance Efficiency Scheme Increase in Flow Parameters Reduction in Water Delivery Times Cau Son No data provided by PMU/IMC Middle Canal: 48 hrs >> 30 hrs East Main Canal: 72 hrs >> 50 hrs West Canal: 24 hrs >> 16 hrs Phan Dam Canal: 12 hrs >> 9 hrs Secondary Canals: Reduced by 50% Fill canal system: 4 days >> 2 days Yen Lap Main canal flow: 5.5 >> 8.0 m 3 /s Main Canal: Reduced by 4 hrs Ke Go Main canal water level at tail: 4.80 >> 5.47 m - 67 cm increase Main Canal: 3 days >> 1 day Phu Ninh No data provided by PMU/IMC North Main Canal: 40 hrs >> 19 hrs Secondary Canals: Reduced by 50% Da Ban No data provided by PMU/IMC West Main Canal: East Main Canal: Branches N3, N4: 40 hrs >> 6 hrs 36 hrs >> 5 hrs 5 hrs >> 4 hrs Dau Tieng No data provided by PMU/IMC Main canal to field: 2 days >> 1 day

New Structures - Long-crested weirs and Measurement Flumes Yen Lap Ha Bach main canal Yen Lap Ha Bach main canal head Phu Ninh Primary canal N18 Ke Go Primary canal head N2

Need for Supervisory Control and Data Acquisition (SCADA) to modernise system operation Typical SCADA Layout Reservoir or river intake Irrigation HQ Control centre X-regulator gates Offtake gates Local station. Supports data transmission from sensors monitoring water levels u/s and d/s of gates, flow measurement d/s of gates, gate openings, and water quality (if required). Data transmission

SCADA Installation on Dau Tieng Scheme K34 Cross-regulator - East main canal Gate Actuator (Electric motor) Acoustic water level monitor Display monitor in Control Centre

Was Infrastructure Modernisation Achieved? Whilst additional lining has much improved canal conveyance efficiency, this is not irrigation modernisation per se. Insufficient water control and measuring structures were built, in particular long-crested weirs to maintain water levels at strategic offtakes - their unit cost was comparatively small, and many could have been constructed by reducing small lengths of more expensive canal lining. Only in Phu Ninh & Yen Lap have reasonable numbers been built, and their benefits are now appreciated by IMC staff and farmers. It is understood that long-crested weirs were not listed in GOVN s irrigation structures design manual, despite many recommendations. Maybe some local IMC managers didn t have the confidence to approve the designer s proposals. SCADA installation in Dau Tieng was successful but is not being used properly. In the other 4 schemes, installation was so late that the project had finished before the systems were completed, so no feedback so far.

Lessons Learned Design/Construction Inappropriate designs caused additional costs and delays Designers must spend more time consulting local people to avoid wasting cost and time on abortive design and bidding. Canal closure periods For canal rehabilitation, contractors have limited construction windows due to canal closure periods. Appropriate design and construction planning is vital. Dry / Rainy seasons Canal earthworks must be done in dry season so contract award timing is important but difficult to achieve as period for tendering, bid evaluation, approval and contract award is unpredictable so first dry season may be lost.

Lessons Learned Design/Construction Cau Son Contractors were delayed due to insufficient details on how to deal with minor problems, such as small pumping stations, protecting bridge abutments, or modifications to drainage culverts. Contract drawings need the full details. Cau Son Yen Lai canal bed width was reduced from 10 to 8 m in one short reach. Bank-filling of eroded canal profiles to achieve straight sections, added more cost and delay, especially with limited construction windows, and added little significant benefit to the canal s hydraulic performance.

Lessons Learned Design/Construction Phu Ninh Some soils on North main canal, known to be weak at design stage, caused several bank failures. Alternative lining methods could have been provided on the drawings for these weak sections. Dry stone pitching in an rc grid frame proved successful. Cau Son Completion of contracts 18 & 19 were delayed due to poor design decisions. Trapezoidal design encroached on householders land so design was changed, mid-contract, to a flume section, with a large cost increase needing a rebid and thus even further delay.

Modernisation compromised Cau Son, Guia canal Existing bridge with debris caught on central pier, causing large head losses. Problem made worse because new canal profile is now wider than bridge, which was not scheduled to be replaced. Modernisation objective compromised. Dau Tieng, Primary Canal N18, K7+600 Construction of gated long-crested weir. Two orifices had been made through weir walls, at IMC s request who said gate width was not sufficient to pass flow. Thus, some IMC staff didn t understand the main function of long-crested weirs.

Missed Opportunities Ke Go main canal aqueduct, K3+329 A long-crested weir could have been built u/s of aqueduct inlet to regulate water levels for u/s offtakes. Existing central gate could have been used for fine tuning of water levels. Cau Son Need for long-crested weirs IMC staff were asked about the usefulness of long-crested weirs in canal operation. Agreed were useful - the designers had wanted to put in more, but PMU said existing system was functioning ok and did not agree to more than two weirs.

Missed Opportunity Ke Go - main canal tail, K16+900 At Ke Go main canal tail are two gated regulators, feeding N8 & N9 sec. canals. PMU staff said a long-crested weir had been constructed at end of main canal. However, a new side-spill escape weir had been built into the left bank instead. The designer said a long-crested weir had been designed, but was rejected by PMU and a side-spill escape weir built instead. An opportunity to improve operational control was lost a long-crested weir could have been built in front of N8, using its existing gate to fine tune water levels.

Missed Opportunity Ke Go N6-7 tertiary canal This photo is 1 of 20 new long-crested weirs on the tertiary network. A side spill weir had been formed in left side wall, just u/s of gate; water should flow around gate and rejoin canal d/s. Gate was not fully closed so water flowed under the gate and not over the side spill weir. A cheaper solution would put simple longcrested weirs diagonally across flume, to maintain water levels.

Incorrect Operation Dau Tieng - N8 primary canal, K2+506 A W long-crested weir operated with the gate open, rather than shut, with water passing over the crests. Gate operators didn t understand the reasons for introducing longcrested weirs, and need training. Senior IMC staff explained when periods of least irrigation demand the operators like to keep canal water levels low, so canal banks are not stressed. With canal lining this argument is no longer valid.

Wrong design? Construction error? New long-crested weir submerged and ineffective. At the time, it was not established whether wrong design or construction error. Crests could easily be raised to make weir functional. Phu Ninh North main canal K12+590

Civil Works Costs Scheme Area ha Cost US$/ha Cau Son 21,800 970 Yen Lap 6,800 1,500 Ke Go 19,000 1,040 Phu Ninh 17,400 1,310 Da Ban 7,300 730 Average cost ~US$ 970/ha (2009-10 prices), say ~US$ 1,180/ha (2013-14 prices @ 5% pa). Add 5% for design consultants. Costs shown do not include land compensation and resettlement costs which are often significant. Dau Tieng 57,600 810 Average 2009-10 2013-14 $ 970/ha $ 1,180/ha

Modernisation of Irrigation Operations and Institutional Reform

Institutional Issues / Water Management Institutional modernisation and reform is equally as important as rehabilitating and modernising civil works. However, it usually takes second place in donor-funded projects, with need to finish design and construction works to keep up with the loan disbursement schedule. For 5-7 years of a typical project life, insufficient time is available to reform institutions needs maybe >10 years. For a successful outcome it s essential that the leaders (eg. IMC directors) are enthusiastic about reform if not, then little will be achieved.

Participatory Irrigation Management (PIM) A 3-year PIM programme was funded by a Japanese grant - 66 WUOs were set-up in 13 pilot areas in the 6 schemes and were running well when VWRAP ended. However, lack of continuity in funding when the project finished meant that several WUOs stopped operating, due to lack of financial resources, even though the members wanted to continue, Continuity budget should be applied for and be in place when the donor-funded project finishes. This would demonstrate that the authorities were serious about institutional reform.

Irrigation Management Transfer (IMT) IMT aims to transfer responsibility for O&M of secondary canal networks to WUOs. IMT programme was not introduced into VWRAP until its last year so not enough time for any significant progress. Some WUOs don t have the legal status to have irrigation infrastructure transferred to them. One major problem is that current WUOs are based on either administrative or hydraulic boundaries, which are incompatible.

Irrigation Benchmarking Benchmarking programme not introduced into VWRAP until its last year. Initial findings highlighted many institutional obstacles to starting benchmarking, such as... IMCs are not obliged, under their charter, to measure and monitor water use but function only as a water service provider. GOVN legislation on M&E of irrigation infrastructure exists but is not specific enough.

Lessons Learned - Acceptance of Irrigation Modernisation There was reluctance from some IMCs to accept modernisation in the way that canals would be operated and controlled. East main canal of Dau Tieng now designed for d/s control - SCADA can set levels at cross-regulators to match flows taken off into primary canals. Thus, operational staff have no need to adjust cross-regulator gates but they continue to do so as it s what we ve always done. Cau Son: the reluctance to build long-crested weirs may be because IMC continue to operate canals on an on/off basis, not necessary but it s what we re used to doing. Unless senior IMC management wish to modernise, little will happen in practice, despite training programmes.

VWRAP.. How Successful Was It?

Viet Nam Academy of Water Resources Guidelines on Irrigation Modernisation The overall lesson learned from VWRAP is that principles of modernisation were not fully understood by the main stakeholders - consultants, PMU and IMC managers.. 1) Although infrastructure has been improved it has not yet met all operational requirements e.g. damaged gates of some cross regulators were replaced but are still operated manually rather than electrically, so difficult and time-consuming for operators. 2) Local managers have not yet properly put new infrastructure into use due to their poor understanding of the principles of modernisation to meet operational requirements. 3) Implementation was not fully in accordance with project objectives due to wrong design in some places, some unnecessary longcrested weirs built (Yen Lap), no institutional changes, and keeping the traditional modes of operation thus the expected benefits have not yet been fully achieved.

Conclusions in WB Completion Report Final WB rating was Moderately Satisfactory. Modernisation is a continuous process - initial phase was completed but more years needed to fully achieve the objective envisaged at appraisal. Future projects could concentrate on fewer changes with enhanced sustainability. Delays in design process delayed start of construction, so IMC reform was neglected. Much staff training provided on improved system operation but not generally implemented in the field by IMC staff. Project lacked an agricultural component in its preparation.

Da Ban Dam THE END