Requirements for an Effective Fault Detection and Diagnostic System for Automated Continuous Commissioning of Building HVAC Systems

Similar documents

Building Analytics Improve the efficiency, occupant comfort, and financial well-being of your building.

Example Retrocommissioning Measure: Opening Throttled Discharge Valves

Scope of Work. See for resources available

Fundamentals of HVAC Control Systems

REAL OPERATING COST SAVINGS FROM RETRO- COMMISSIONING OPPORTUNITIES FOR SAVINGS IN ACADEMIC MEDICAL CENTERS

KU DESIGN GUIDELINES APPENDIX XVI RECOMMENDED BAS I/O CONTROL POINTS BY EQUIPMENT / SYSTEM

Case Study. Crown Melbourne & BUENO Systems: Energy and Operational Savings Across a Multi-Use Entertainment Complex.

CONTROL STRATEGIES FOR HVAC SYSTEMS

Central Plant Air Systems: Keeping the Heart and. Title Style. Better Buildings Summit May 2016

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Sample - Existing Building Commissioning Plan

Modeling and Simulation of HVAC Faulty Operations and Performance Degradation due to Maintenance Issues

Automated Commissioning for Energy (ACE) Platform for Large Retail Property. Overview

ULTRA-EFFICIENT HVAC DESIGN AND CONTROL

Find what matters. Information Alchemy Turning Your Building Data Into Money

Company name Date submitted. Building address City State ZIP. * Building Sq. Ft.

Variable Air Volume - VAV

Using Time-of-Day Scheduling To Save Energy

Continuous Commissioning of the Dallas/Fort Worth International Airport

NEBB STANDARDS SECTION-8 AIR SYSTEM TAB PROCEDURES

Chapter-5 Introduction to Building Automation System (BAS)

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) March

Building Diagnostic Market Deployment Final Report

for Plans Examiners and Building Inspectors

Impact of Control System Technologies on Industrial Energy Savings

5178 EOI Direct Digital Controls Systems Strategic Plan Schedule A. Technical Submission. City of Richmond

Rev. No. 0 January 5, 2009

Criteria for Building Automation Dashboards

Introduction to Building Automation Systems (BAS)

Commissioning - Construction Documents (Page 1 of 6)

Continuous Energy Management at UC San Diego. Anna Levitt, P.E. Assistant Energy Manager June 13, 2013

Guide Specification SECTION COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

Wireless Pneumatic Thermostat Technology Demonstration Test. Los Angeles Unified School District 333 S. Beaudry Ave.

HVAC Processes. Lecture 7

Building Commissioning

Collaborative Laboratory Commissioning and Sustaining the Optimal Building. By E. Lon Brightbill, P.E Facility Dynamics

CATALYST Frequently Asked Questions

Demand Based Static Pressure Reset Control for Laboratories

Building Energy Systems. - HVAC: Heating, Distribution -

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues

SUCCESS STORY ENERGY TO CARE UF HEALTH SHANDS VISTA REHAB & UF HEALTH SHANDS CANCER HOSPITAL (SOUTH TOWER)

Printing and Publishing Energy Savings Guide

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

Applying Pressure Independent Control Valves in H.V.A.C. Systems. A Presentation to: Orange Empire ASHRAE Santa Ana Nov. 17, 2009

Automated Equipment Data Analytics to Detect Issues, Trends, Faults & Anomalies

Mechanical Systems Proposal revised

Temperature Controls Design

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT

Comparing Energy Savings of Different VAV Systems

HVAC Simplified Approach Option

SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP

BEST PRACTICE GUIDE TO MAXIMIZE ROI OF ENERGY MANAGEMENT SYSTEMS. Bob Zak SVP, Facility Solutions Ecova

The sample report format is applicable to many different building types and systems and the examples provided cover a variety of applications.

Dual Maximum VAV Box Controls

Transactive Controls: Market-Based GridWise TM Controls for Building Systems

Pilot Program Description: Building EMIS

Managed Services - How to Manage Your Site Controls Energy System

HEATING, VENTILATION & AIR CONDITIONING

Trade Professional Alliance EE Programs Training. Napa, CA January 20, 2015 Mark Salavitch Trade Professional Manager, Bay Region

Energy Design Resources Commissioning Plan Outline Template

Model-Based Performance Monitoring: Review of Diagnostic Methods and Chiller Case Study

HVAC Systems: Overview

COMPARATIVE LIFE-CYCLE ANALYSIS OF ENERGY-EFFICIENCY MEASURES AT TVA S CHATTANOOGA OFFICE COMPLEX: PHASE II RESULTS & FINAL DESIGN

New Approaches in Automating and Optimizing Demand Response to Solve Peak Load Management Problems

CHAPTER 8 HVAC (Heating, Ventilation, and Air-Conditioning)

ENERGY SAVING STUDY IN A HOTEL HVAC SYSTEM

Frequently Asked Questions

Leveraging the Power of Intelligent Motor Control to Maximize HVAC System Efficiency

Analysis of HVAC Control Strategies

Building Energy Management: Using Data as a Tool

Building Re-Tuning Training Guide: AHU Heating and Cooling Control

C-Bus Application Messages & Behaviour Chapter 25 Air Conditioning

DABO ADDS INTELLIGENCE AND MEMORY TO A BUILDING S OPERATING SYSTEM

Seven Steps to Maximizing Central Plant Efficiency

DTE Energy Pilot Programs DTE Insight & Retro-Commissioning MPSC Collaborative Joint Workgroup

Air Side Economizers and Energy Recovery - Improvements and New Regulations. Richard Lord

DATA CENTER COOLING INNOVATIVE COOLING TECHNOLOGIES FOR YOUR DATA CENTER

The Business Case Annual fuel cost savings of 26% worth more than 28,000 Annual fuel savings of 1.3million kwh Annual CO2 savings of over 245 tonnes

Air Conditioning Clinic

School District Gives Andover Infinity TM High Marks

Insider. Customer Success Stories

Features. Emerson Solutions for Abnormal Situations

ENERGY SAVING BY COOPERATIVE OPERATION BETWEEN DISTRICT HEATING AND COOLING PLANT AND BUILDING HVAC SYSTEM

J O U R N A L. Energy Performance for. Proper Specification of Air Terminal Units Future Climate Impacts on Building Design

The main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building.

Agenda. Part I: Introduction to OptimumHVAC. Part II: Initial Energy Savings Analysis for MCO Main Terminal. Part III: Case Studies & Conclusion

Greenhouse Gas Implications of HVAC Upgrades in Multi-Unit Residential Buildings

Case Study. Redmond Middle School: Advanced Analytics to Detect Energy Waste in HVAC System

Impacts of Static Pressure Set Level on the HVAC Energy Consumption and Indoor Conditions

Sample Company SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

CHILLER PLANT CONTROL MULTIPLE CHILLER CONTROLS

ISA108 Intelligent Device Management (IDM)

Presentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks

Using Big Data Analysis as part of the Commissioning Process

Outline. CC objectives Site and building description Typical data floor overview CC measures Results Lessons learned

AUDITING (WITH) BAS AEE-NY APRIL 2015

HVAC Checklist - Long Form

Riverside City College. Math & Science Building HVAC Investigation. May 23, 2013

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings

Transcription:

Requirements for an Effective Fault Detection and Diagnostic System for Automated Continuous Commissioning of Building HVAC Systems Prepared by: Adrian Armstrong, EIT Prism Engineering Ltd.

o Agenda -FDD System Overview -Distinction between Alarms and FDD -Building Requirements -Review of Key Characteristics 2

Fault Detection Opportunity Correcting sub-optimal equipment operation represents a significant opportunity to reduce building energy consumption and provide improved occupant comfort Based on information published by ASHRAE in 2012, faults relating to HVAC systems represent between 1-2.5% of total commercial building consumption 1 3 1. M. Wiggins, J. Brodrick, HVAC Fault Detection, ASHRAE Journal, February 2012

FDD System Overview Use information from the existing building automation system to identify faults / suboptimal operation of equipment. Trend data from the DDC system is run through an analytics engine 4 4

Typical FDD System Architecture 5 5

FDD System Goals Increase energy efficiency Improve occupant comfort Reduce maintenance costs All the FDD systems in the marketplace have the same goals however systems vary in their approach and sophistication objective is to generate actionable tasks that can be addressed by the facilities team 6 6

Rules based approach One of the main approaches used to identify faults is applying If/Then logic to appropriately mapped points Simple economizer rule example: If a system is operating in 100% outside air and MAT is greater than OAT by 2 C then trigger a fault recommending sensor calibration and verification of proper damper actuation. Extension of the previous example: Trigger a fault If a system is operating in economizer mode AND calculated MAT differs from sensed OAT by 2 C Equipment maintenance example: If a heat pump cycles more than a maximum number of times per hour, trigger a fault recommending setpoint or deadband revision. 7

Example Faults AHU with simultaneous heating and cooling Excessive ventilation air supply System not using free cooling System operating outside of schedules hours Manual overrides Excessive equipment cycling Equipment hunting due to inappropriate control loop tuning 8

Faults vs. Alarms Most FDD systems include deviation from setpoint Duplication of existing functionality, such as space temperature setpoint alarms Often better left in the DDC systems FDD focus is primarily on gaining deeper insights ex: space is over setpoint, flow setpoint is being achieved, may indicate sensor mis-calibration 9

Faults vs. Alarms A large focus of FDD is identifying noncritical problems before they would reach a DDC alarm state Allow for pro-active maintenance by identifying equipment which is short cycling, out of calibration, etc. Identifying equipment which is functioning as programmed, but where additional savings opportunities exist 10

Suitability for FDD Is there enough DDC / trending capability to provide meaningful insights? Greater value at sites with terminal equipment on the DDC system Is there enough equipment and usage at the site? Fixed cost for onboarding, hardware, licensing Generally best suited to sites 100,000 ft 2 or greater Are appropriate resources available to follow through on recommended corrective action. People & Funding 11

Features of an Effective FDD System 1. Vendor experience and developed rules appropriate to your site 2. Appropriate level of rules sophistication 3. Hierarchical relationship between equipment 4. Fault Suppression / filtering 5. Fault Prioritization 6. Beyond If/Then statistical / Peer based approaches 12

Vendor Experience & Developed Rules Is the suite of rules already developed by the vendor appropriate to your requirements of your site? Large amount of variation exists in the marketplace in terms of number of developed rules for different vendors and the extent of their deployment of some rules Main emphasis is on cooling from some products Need to ensure that the FDD system under consideration has appropriate development appropriate for the HVAC topology in place Dual duct systems Data Centers 13

Fault Sophistication Basic Fault Simultaneous heating and cooling Fan operating outside of scheduled hours What about sub-optimal sequences / opportunities for optimization? 14 14

Fault Sophistication Typical Operation 15 15

Fault Sophistication Basic Fault Simultaneous heating and cooling 16 16

Fault Sophistication Advanced Fault Opportunity to increase SAT 17 17

Fault Sophistication Reduced Cooling load while still meeting space loads 18 18

Fault Sophistication Other advance faults AHU Static Pressure reset Pump speed reset Chilled water / heating water supply reset Generally speaking these types of faults are moving towards optimizing the sequence of operations for the site 19

Hierarchical Relationship Hierarchy / parent child relationship between systems Associate plant equipment with terminal equipment served. Chiller and distribution pumps with all the served cooling coils AHU with all the downstream terminal devices such as reheats, VAVs or mixing boxes 20 20

Hierarchical Relationship- Example AHU is operating with the preheat coil as well as all terminal reheats 100% open 21

System Hierarchy - Example Possible root causes: Failed sensor(s) Boiler supply water temperature below setpoint (or setpoint is too low) Heating water plant not operating (either boilers or distribution pumps) If a hierarchical structure in in place additional options in place to identify root causes at the plant level which may be affecting served systems. 22

System Hierarchy An effective strategy to link plants together with served systems is key to a scalable FDD system. Many of the more sophisticated faults require looking at the bigger picture in order to diagnose faults and identify optimization opportunities. 23

Fault Suppression For an FDD systems to be effective, it must include provisions to minimize false positives / nuisance faults. Comes back to generating actionable items This item can be closely related to the hierarchical relationship previously noted. Provisions should be in place to prevent a fault within a plant level system from triggering dozens or hundreds of faults within the served system. Alternatively, faults in the served systems should be grouped or connected with the parent system. 24 24

Fault Suppression - Example 25

Fault Suppression Example (cont d) AHU is operating at 100% speed but not achieving static pressure setpoint VAV is showing reduced HD flow relative to setpoint (typical for 15+ units) Root cause is at the AHU VAV faults should either be suppressed or linked to the AHU level fault 26

Fault Suppression By including provisions to either suppress the faults in the served terminal devices, or link those faults to the fault in the parent system, key information is brought to building operators attention This is critical to ensuring that timely corrective action can be undertaken More signal, less noise 27

Fault Prioritization This is key to giving the facilities team an actionable fault list Basic approach undertaken by some vendors is to flag main systems (AHUs, boilers, distribution pumps) as high priority More sophisticated approach involves prioritizing in some or all of the following areas: Energy impact GJ, kwh, $ Occupant comfort impact Equipment wear / maintenance impact 28 28

Fault Prioritization Allows you to tackle the biggest problems first Typically provides options to sort reports based on some or all of the different options. 29

Fault Prioritization Energy Impact approaches Projecting savings forward Quantifying what s been lost already over a pre-determined time scale. 30

Fault Prioritization Projecting savings forward Takes the amount of energy wasted over a pre-determined period and projects that forward End result in a prediction of the energy that will be wasted if some corrective action is not undertaken. Due to the complex interactions of systems, accuracy of this approach is suspect. Ex: Predicted savings from simultaneous heating and cooling during summer would most likely not account warm weather shut down of the heating water system. Quantifying what s been lost already Tracks the energy lost either since the fault was first detected or over a predetermined period. Rely on basic engineering thermodynamic calculations. ex: Fan HP and runtime to estimate energy cost 31

Beyond If/Then The main tool used in most of the marketplace is based on IF/Then logic. Additional approaches include: Peer analysis Comparison to KPIs and past performance Snapshot of proper system operation after building commissioning which becomes the benchmark the building is compared to Comparison to past performance implies that past performance was correct. This may not be the case Alternatively, space requirements may have changed. 32

Conclusion FDD is an emerging area in the building controls sector. Pilot deployments have in some cases identified substantial savings which have resulted in short paybacks for some installations. When considering if FDD is appropriate for your site consider some of the following: Building size DDC system complexity Is there a plan in place to take corrective action based on the identified faults. 33

Conclusion Key items to consider when selecting an FDD system for your site: The amount of rule development, and their applicability to your HVAC systems The level of fault sophistication Hierarchical structure Fault suppression Fault prioritization Capabilities beyond IF/Then style rules 34

Questions? Thank you. T 604-298-4858 adriana@prismengineering.com www.prismengineering.com #320-3605 Gilmore Way, Burnaby, BC V5G 4X5