Collapse of Flying Formwork During Concrete Placement

Similar documents
Formwork for Concrete

Collapse of Underground Storm Water Detention System

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

POST AND FRAME STRUCTURES (Pole Barns)

6 RETROFITTING POST & PIER HOUSES

Handling, Erection and Bracing of Wood Trusses

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Structural Failures Cost Lives and Time

Wisconsin Building Products Evaluation

The Analysis of Open Web Steel Joists in Existing Buildings

COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

Page & Turnbull imagining change in historic environments through design, research, and technology

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

Technical Assignment 2 TABLE OF CONTENTS

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Joist. Reinforcement. Draft 12/7/02

Steel joists and joist girders are

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

609 West Rock Road, Radford,VA / (fax) RECOMMENDED ATTACHMENTS & CONNECTION DETAILS

The Collapse of Building 7 by Arthur Scheuerman December 8, 06

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

Chapter 3 - Structural Design

Engineering for Stability in Bridge Construction: A New Manual and Training Course by FHWA/NHI

Stability. Security. Integrity.

PART 1 GENERAL 1.1 SECTION INCLUDES

EAST LYME HIGH SCHOOL

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

Residential Deck Safety, Construction, and Repair

SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED

Ceiling Mounted Folding Attic Ladders Installation Instructions

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

Rigid and Braced Frames

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

Optimum proportions for the design of suspension bridge

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

Safe & Sound Bridge Terminology

Chapter 3 Pre-Installation, Foundations and Piers

4B The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

Construction Laborer Dies after Falling off Collapsed Precast Concrete Floor Slab

U.S. Department of Labor Occupational Safety and Health Administration Directorate of Construction. April 2015

Breakaway Walls

bi directional loading). Prototype ten story

9.3 Two-way Slabs (Part I)

Elevating Your House. Introduction CHAPTER 5

Analysis and Repair of an Earthquake-Damaged High-rise Building in Santiago, Chile

Optimising plate girder design

CE591 Lecture 8: Shear Walls

High Strain Dynamic Load Testing of Drilled Shafts

FORMWORK INTRODUCTION

DESIGN OF BLAST RESISTANT BUILDINGS IN AN LNG PROCESSING PLANT

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

FLAT ROOF BOX SPAN CARPORTS

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

What is Seismic Retrofitting?

FLAT ROOF CARPORT RECOMMENDED INSTRUCTION MANUAL

How to Design Helical Piles per the 2009 International Building Code

16. Beam-and-Slab Design

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SEISMIC DESIGN. Various building codes consider the following categories for the analysis and design for earthquake loading:

Overhang Bracket Loading. Deck Issues: Design Perspective

Chapter 3 DESIGN AND CONSTRUCTION FEATURES IMPORTANT TO SEISMIC PERFORMANCE

MEZZANINE SPECIFICATIONS PART 1 GENERAL 1.1 SCOPE 1.2 APPROVED MANUFACTURER 1.3 REGULATORY ORGANIZATIONS AND GROUPS 1.4 QUALITY ASSURANCE

Dr. K.N.Jha Department of Civil Engineering Indian Institute of Technology Delhi Block V, Room No. 322

COMMONLY USED RESIDENTIAL BUILDING CODES

METHOD OF STATEMENT FOR STATIC LOADING TEST

[TECHNICAL REPORT I:]

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

Design and Construction of Cantilevered Reinforced Concrete Structures

Investigation of the November 2, 2013 collapse of concrete beams at Fort Lauderdale-Hollywood Airport runway project

TEST REPORT. Rendered to: HOMELAND VINYL PRODUCTS, INC. For:

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

FORM DESIGN. easy to work with, and generally available.

The Stabilizer TM. Benefits. Supplemental support system for sagging beams and floor joists within a crawl space

Brandangersundet Bridge A slender and light network arch

Steel and composite bridges in Germany State of the Art

Owner's Manual & Assembly Instructions

K. D. FRAME ASSEMBLY FOR CLOSED STEEL STUD WALLS...Ins 10. FRAME INSTALLATION DETAILS FOR CLOSED STEEL STUD WALLS...Ins 11

PUMP JACK SYSTEM AND ACCESSORIES

TECHNICAL NOTE. Design of Diagonal Strap Bracing Lateral Force Resisting Systems for the 2006 IBC. On Cold-Formed Steel Construction INTRODUCTION

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

SECTION PIPE HANGERS AND SUPPORTS

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

Approximate Analysis of Statically Indeterminate Structures

ARCH 331 Structural Glossary S2014abn. Structural Glossary

MHI. Overview of Manufactured Home Installation MANUFACTURED HOUSING INSTITUTE. This guide contains an overview. of the HUD-Code manufactured home

INSTALLATION. General. Important Note. Design. Transport

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

T-14 Tilt-Up Wall Braces

Section A Roof Truss

HORIZONTAL INSTALLATION

Beginning on Friday, Jan 22, and on subsequent investigations, the following issues were identified:

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

TEST REPORT. Rendered to: LMT-Mercer Group, Inc. For: PRODUCT: 4" x 4" and 5" x 5" PVC Porch Posts with Aluminum Reinforcing

Transcription:

Collapse of Flying Formwork During Concrete Placement No. 8 July 2002 A formwork collapse occurred during the construction of a new manufacturing building which was being built in suburban Boston for a large electronics manufacturer. The building is multileveled, and for the most part has a structural steel frame with composite concrete and metal deck floors. However, there is one section of the building which has a deep reinforced concrete waffle floor slab supported on reinforced concrete columns and peripheral reinforced concrete walls. During the initial placement of the concrete for the waffle slab, the supporting formwork collapsed, resulting in injury to a number of construction workers. The waffle floor construction is 430 feet by 184 feet in plan. Figure 2 (next page) is a part plan at the southwest corner of the floor, showing representative construction; Figure 3 is a section through the west side of the floor, showing the floor and the supporting walls and columns. The formwork for the waffle slab consisted of fiberglass pans supported by flying forms. A flying form is a large section of flat floor formwork, called a table, which is reused many times. It is handled by a crane which "flies" it into place. The table is supported on previously completed construction, either by legs onto a floor below, or by supports on the sides of columns. In order for the flying form system to be of practical use, there has to be a method to drop the large tables down, after the concrete it is supporting has achieved its proper strength, and to either roll the tables to its Figure 1. View of collapse from below. Photo taken from under flying formwork that did not collapse. next position, or to roll the tables to the edge of the slab so it can be moved out and picked up by a crane for its next use. For this project the tables were supported on the east and west sides of the concrete columns, and by temporary steel columns adjoining the ends of the concrete buttresses shown on Figure 3. Figure 4 (page 3) shows a cross-section through the formwork, taken at the same location as Figure 3. There are proprietary support fixtures attached to the columns by high-strength bolts. At the concrete columns, the bolts pass through sleeves cast into the columns. Figure 5 shows a side elevation of a support fixture. Figure 6 shows support fixtures mounted on a column. Due to the heavy load of the concrete, there are two supports on each side of the concrete columns and two supports on the steel columns. (Continued on page 3) 1998 and 2002 Zallen Engineering

2 Figure 2 Part plan showing the southwest corner of the waffle floor slab. Adjacent floor construction is not shown. Figure 3 Section through waffle floor slab. Reinforcing steel and adjacent floor construction are not shown.

3 Figure 4. Section through formwork for waffle floor, taken at the same location as Figure 3. Waffle pan forms and side forms are not shown. Figure 5. Side view of support fixture. (Continued from page 1) Each support fixture at the columns has a screw jack with a bearing plate at the top; the screw jacks are turned to bring the bearing plates to the proper elevation and the form tables are flown in on top of them. Filler pieces of formwork are then placed at the buttresses and between the tables, and the formwork is then ready to receive the requisite reinforcing steel, other accessories, and finally the concrete. When the concrete has achieved its proper strength, the jacks are lowered until the steel support girders rest on top of rollers on the support fixtures (see Figure 5), and the filler pieces at the buttresses and between the tables are removed. The tables are then rolled out to the next position or are rolled out and picked up by the crane. The design of the flying form system was by the supplier of the system, and it was shown on erection and shop drawings prepared by the supplier. The formwork was erected by the concrete subcontractor, who generally erected it in accordance with the formwork erection drawings. Figure 6. Support fixtures for flying forms. Figure 4 shows details of the temporary steel columns at the ends of the buttresses, at the time of the collapse. The formwork erection drawings showed no detail for the support of the base plate of the steel columns adjoining the buttresses; they just indicated that the bottom of the base plate would be at the level of

4 (Continued from page 3) the top of the ground floor slab on grade. (The slab would be installed at a later time). The wood blocking supporting the column base plate was added in the field by the concrete subcontractor. See Figure 7. The flange of the temporary steel columns adjoining the ends of the buttresses was attached to the buttresses with two pair of 5/8 inch diameter expansion anchors. See Figures 4 and 8. One purpose of these anchors was to hold the column and the supported formwork in-place; a second purpose was to provide lateral support to the column so as to prevent lateral buckling of the column perpendicular to the web of the column. N, O The length of each table (and its girders) was 40 feet and the width was set to clear the concrete columns or the ends of the buttresses. The girders of the table thus spanned over three supports, with each end of the girders being simply supported on a single screw jack, and the center of the girders being supported on two screw jacks (see Figure 6). = = Figure 7. Wood blocking supporting base plate of temporary steel column on Line 5; believed to be at the most northerly end of the formwork that collapsed. (The column shown did not collapse). The Collapse The concrete pour started at the southwest corner and proceeded north to fill the first bay, between Lines 5 and 6. See Figure 2. The collapse occurred when the concrete in the first bay extended to Line 6 to the east, and approximately 70 feet to the north. Figure 9 (page 5) is a view of the collapse. (Continued on page 5) Notes for Non-Engineers 1. These notes explain structural engineering jargon and concepts for non-engineers. 2. A column becomes unstable when the axial load on the column reaches a critical level. Due to this instability, the column suddenly bends laterally, causing it to collapse. This behavior is called buckling. (Continued on page 5) Figure 8. Top of temporary steel column showing one of the top pair of 5/8 inch diameter expansion bolts.

5 (Continued from page 4) When the load from the concrete was imposed onto the steel columns adjoining the buttresses, the columns pushed down on and compressed the wood blocks, and at the same time loaded the expansion anchors in shear. A basic structural principle is that when load is shared between various elements, it will be transferred to the elements in proportion to their respective stiffnesses; the stiffer the element, the greater the percentage of load it will support. Relative to the steel column itself and to the expansion anchors, the wood blocking in compression is flexible, thus a substantial portion of the column load was transferred to the expansion bolts. Since the reaction (the resisting force) of the expansion bolts on the column is eccentric to (i.e., not in line with) the load on the top of the column, the top pair of expansion anchors were subjected to tension in addition to the shear on these anchors. P= The failure was initiated at the temporary steel column at grid location W-5, which was one of the two most heavily loaded temporary columns, when the top pair of expansion bolts pulled out of the concrete in a concrete cone mode of failure, and the bottom pair of bolts sheared off. The vertical load was then completely transferred to the wood blocks; however, at the same time the column buckled laterally and collapsed, since, with the failure of the expansion anchors, it lost its intermediate lateral support. The failure of Column W-5 precipitating the collapse of the whole bay with most of the other temporary columns failing in a similar mode. The estimated load on the column when it failed was 90,000 lbs. The calculated ultimate capacity of the column with one flange braced laterally by the expansion anchors is 118,000 lbs. However, the calculated ultimate capacity without that flange being braced is only 40,000 lbs. Figure 9. View of collapse, looking eastward. Notes for Non-Engineers (Continued from page 4) 3. The eccentricity causes the column to try to rotate away from the end of the buttress. This rotation effect, which is called a moment, is resisted by an opposite moment created by tension in the top expansion anchors and an equal and opposite compression of the column against the end of the buttress at the bottom of the column. (Continued on page 6) The form designer, the concrete subcontractor, and the general contractor all made errors: 1) the form designer did not specify how the steel columns were to be supported at their base, 2) the form designer did not detail the columns to prevent vertical load transfer to the expansion anchors, 3) the concrete subcontractor did not request and obtain a support detail for the steel columns, and 4) the general contractor did not insist that the concrete subcontractor request and obtain said support detail. (Continued on page 6)

6 (Continued from page 5) The form designer used a slender steel shape for the column which is intended for use as a beam, which resulted in the requirement for intermediate lateral support to prevent buckling of the column perpendicular to the web. Had the designer provided a column that did not need intermediate lateral support, a shape that is normally used for columns, the wood blocks may have crushed, but the column would not have buckled. Q There would have been a downward displacement of the form table with the concrete along Line 5, but the form probably would not have collapsed. Principal Rubin M. Zallen, P.E. investigated this collapse. Notes for Non-Engineers (Continued from page 5) 4. A simple beam under load will have compression on the top flange and tension on the bottom flange. The compression flange will have a tendency to buckle whereas the tension flange will not. The compression flange of most beams will be supported laterally by the floor construction so that the flange cannot buckle; thus a slender deep cross-section is efficient for beams. A column on the other hand will normally have both flanges in compression. Column sections are usually proportioned as stocky members so that bracing is unnecessary between their ends. is published by Zallen Engineering, 1101 Worcester Road, Framingham, MA 01701. Comments are welcome. Please direct comments to Rubin M. Zallen, P.E., by telephone at 508-875-1360 or by e-mail at rmzallen@zallenegineering.com.