Risk Assessment of Plan Schedule by Monte Carlo Simulation



Similar documents
A Robustness Simulation Method of Project Schedule based on the Monte Carlo Method

Monte Carlo analysis used for Contingency estimating.

Risk Analysis and Quantification

Amajor benefit of Monte-Carlo schedule analysis is to

CRASHING-RISK-MODELING SOFTWARE (CRMS)

Software Project Scheduling under Uncertainties

Quantitative Risk Analysis with Microsoft Project

Chapter 11 Monte Carlo Simulation

Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.

INT 3 Schedule Risk Analysis

Schedule Risk Analysis Simulator using Beta Distribution

RISK MITIGATION IN FAST TRACKING PROJECTS

PROJECT RISK MANAGEMENT

Project Scheduling: PERT/CPM

Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model

Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson

COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS

PROJECT RISK MANAGEMENT

OTC Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc.

ORACLE S PRIMAVERA RISK ANALYSIS

Risk Workshop Overview. MOX Safety Fuels the Future

Simulation and Lean Six Sigma

DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I

Unit 4: Time Management (PMBOK Guide, Chapter 6)

PROJECT TIME MANAGEMENT. 1 Powered by POeT Solvers Limited

Profit Forecast Model Using Monte Carlo Simulation in Excel

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Negative Risk. Risk Can Be Positive. The Importance of Project Risk Management

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

Project Time Management

Scheduling Resources and Costs

One-Minute Spotlight. The Crystal Ball Forecast Chart

USING QUANTITATIVE RISK ANALYSIS TO SUPPORT STRATEGIC DECISIONS 1

Project Cost Management

PROJECT TIME MANAGEMENT

Project Time Management

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18

Better decision making under uncertain conditions using Monte Carlo Simulation

Project Risk Management

Overseas Investment in Oil Industry and the Risk Management System

A. O. Odior Department of Production Engineering University of Benin, Edo State.

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

The work breakdown structure can be illustrated in a block diagram:

CORPORATE FINANCE RISK ANALYSIS WITH CRYSTAL BALL ARE WE ADDING VALUE?

TEACHING SIMULATION WITH SPREADSHEETS

A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry

PROJECT RISK ANALYSIS AND MANAGEMENT

IMPORTANCE OF QUANTITATIVE TECHNIQUES IN MANAGERIAL DECISIONS

Project Planning and Scheduling

Application Survey Paper

Cumulative Diagrams: An Example

Priori ty

Rehabilitation Scenarios for Sustainable Water Mains. University, Montreal, Quebec, Canada, PH (514) ext. 8779; FAX (514) ;

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

Critical Path Method (CPM)

The Cost of Risks. Essence of Risk Quantification. Forum Calgary 2008

Prof. Olivier de Weck

PROJECT RISK ASSESSMENT & MANAGEMENT

Risk Analysis Overview

Introduction to project management and concepts

Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions

CRITICAL CHAIN AND CRITICAL PATH, CAN THEY COEXIST?

CHAPTER 1. Basic Concepts on Planning and Scheduling

Project Time Management

CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL

Extensive operating room (OR) utilization is a goal

Project Time Management Activity Definition Activity Sequencing Duration Estimating Schedule Development Schedule Control

Event Chain Methodology in Project Management

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort

Project Scheduling: PERT/CPM

VIII. Project Management Glossary

Representing Uncertainty by Probability and Possibility What s the Difference?

Risk Management Primer

Multiproject Scheduling in Construction Industry

Project Scheduling & Tracking

Project Risk Management Handbook: A Scalable Approach

Project Time Management

Time Management. Part 5 Schedule Development. Richard Boser

A Short Introduction to Project Management

Operational Research. Project Menagement Method by CPM/ PERT

Guidelines for a risk management methodology for product design

Chapter 6. (PMBOK Guide)

Business Valuation under Uncertainty

21. Earned Value deals with: a. EV Scope b. PV Time c. AC Cost 22. Portfolios are organized around business goals. 23. Take stern action against

TRADING SYSTEM EVALUATION By John Ehlers and Mike Barna 1

Project Management Planning

Descriptive statistics Statistical inference statistical inference, statistical induction and inferential statistics

Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:

Risk Review Process Basics

Module 3: The Project Planning Stage

PROJECT MANAGEMENT PLAN CHECKLIST

Session 4. System Engineering Management. Session Speaker : Dr. Govind R. Kadambi. M S Ramaiah School of Advanced Studies 1

SWEN 256 Software Process & Project Management

25Project management

Technology A Risk Prevention / Mitigation Tool

Transcription:

International Conference on Information Technology and Management Innovation (ICITMI 2015) Risk Assessment of Plan Schedule by Monte Carlo Simulation Zhaoni Kong 1, a, Jianping Zhang 1, b *, Chao Li 1, Xiaoying Zheng 1 and Qingqing Guan 2 1 Faculty of Civil Engineering and Architecture, Kunming University of Science and Technology, P.R. China 2 Faculty of Environmental Science and Engineering, Kunming University of Science and Technology, P.R. China a 237071828@qq.com, b 1181557223@qq.com Keywords: risk assessment, Monte Carlo simulation, triangular distribution, schedule control. Abstract: With an increasingly complex and rapidly changing construction circumstance, owners and their contractors are confronting challenges from risk management while maintaining control and improving performance. With great capabilities for project management solution, Monte Carlo simulation was used to forecast projects execution results. In this paper, a practical example, construction and installation engineering in cargo area of Kunming Changshui international airport project is studied to show explicitly the benefits of using Monte Carlo simulation to assess risk in practical scheduling. Introduction Plan schedule is one of the most important responsibilities of construction project management. A success in managing a project requires a complete and realistic project schedule that plans and coordinates various activities. Also, a reasonable schedule should predict the completion and milestone dates of the project. But reasonable project schedule is difficult to achieve because the rules of project scheduling is unclear to the scheduler with unrealistic deadlines, uncertainty of activity durations [1]. No two activities among projects are exactly same, thus even well experienced project managers could not precisely estimate the completion of a project. Moreover modern construction projects are often complex in characteristics. There are unforeseen reasons that make the majority of construction projects often overrun scheduled completion time and even miss targets [2]. Laufer & Howell [3] find that about 80 projects have high degree of uncertainty at the beginning of constructions. More and more project managers therefore begin to realize the importance of uncertainties in project schedule. Challenged by unforeseen reasons, project managers begin to treat risk management as their routine requirement. Project Management Institute defined a project risk as an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective [4]. As can been seen, a risk has two parts--probability of occurrence and the effect of each occurrence. Risk management can be categorized as technical, external, internal and organizational work. The process of risk management includes risk identification, risk assessment, risk response and risk documentation [5]. Modeling and quantifying risk are crucial parts of risk management. In 1950s, quantitative network modeling techniques were used to simulate the construction process. Network diagram techniques can find activity relationships, and help the establishment of durations and coordination of construction projects. However, Birrell [6] noticed that the critical path method (CPM) uses a single value to estimate each activity and even the entire construction without considering the effects of uncertainty. CPM assumes that each activity has only one possible outcome and will be completed successfully. In fact, there are numerous possible results for an activity with different consequences. Besides, in most cases the probability of activity durations calculated by critical path methodology (CPM) to achieve the plan was less than 25. Recently, Hulett [1] found program evaluation and review technique (PERT) also always underestimated schedule risk, ignoring the possible risk that may be caused by PERT-slack paths. 2015. The authors - Published by Atlantis Press 509

PERT only focused on the one longest or PERT-critical path. According to Bonny [7] and Li et al. [8], activity durations calculated by PERT were almost always less than actual statistic mean with deviation up to 30. Besides, traditional scheduling processes ignore the uncertain and risky nature of the environment of a project. So, network-based planning processes have been proven inadequate to conduct practical risk analysis in scheduling. To produce an effective schedule, a more thorough scheduling process is required with formal recognition and assessment of project uncertainty. To improve accuracy, brainstorming, sensitivity analysis, the Delphi method, or decision tree analysis are also used as typical existing analyzing risk methods. Recently, as a useful modeling technique to monitor risk, Monte Carlo simulation has great potential and the convenience [9]. Many results show that Monte Carlo simulation produces the correct answers without abovementioned flaws. As a modern way to evaluate project schedule risk, Monte Carlo simulation can overcome the deterministic limitations of traditional scheduling processes. In this paper, a practical example is studied to show explicitly the benefits of using Monte Carlo simulation to assess risk in practical scheduling. Simulation and results Monte Carlo simulation Monte Carlo simulation was developed in the 1940s and became available under the help of personal computers and associated software, e.g. Primavera Risk, Primavera Crystal Ball, @RISK for Projects and so on. Monte Carlo has been involving in many industrial, scientific, logistical and social fields in many years. Recently project managers have used Monte Carlo to simulate the project completion date and the project cost estimate. Through computing the CPM schedule many times, Monte Carlo simulation can determine the project completion date on the basis all possible combinations of the uncertain activity durations. In Monte Carlo simulation, the project model is computed many times (iterated) with the input values (e.g., activity durations) chosen at random for each iteration from the probability distributions of these variables. Monte Carlo simulation follows certain steps [10] a. Creation of the quantitative model of the form of y=ƒ(x 1, x 2,...,x n ), b. Selection of the random variables x i1, x i2,, x in, c. Evaluation of the model and output storage in y i, d. Repeat steps (b) and (c) as many times needed (for i=1 to k), e. Analysis of results. A case study A practical case, construction and installation engineering in cargo area of Kunming Changshui international airport project is presented in this section to illustrate the proposed method. In this scenario, the Oracle Crystal Ball software was used to analyze the schedule, while it was assumed that schedule values follow a triangular distribution with the 99 confidence interval. In order to meet the abovementioned requirement of accuracy, the number of simulation should be greater or equal to 4096 [11]. So, the number of runs was set to 10,000. To improve probability of activity durations, the Monte Carlo simulation actually allows the recalculation of the model over and over again, each time using different randomly selected sets of values from the input probability distributions, while using all valid combinations of the possible inputs, in order to simulate all possible outcomes. The spreadsheet of stochastic scheduling model and relevant Gantt chart can be found in Table 1 and Figure 1. 510

Table 1. Critical Path-Stochastic Scheduling Model Task Predecesso r O ptimisti c Expected Pessimist ic Sim Value EST EFT LST LFT Slack Crit Pat h Start A Start 103 153 199 153 0 153 0 153 0 1 74.51 B A 44 59 65 59 153 212 153 212 0 1 74.51 C B 49 61 70 61 212 273 212 273 0 1 74.51 D Start 152 182 233 182 0 182 30 212 30 0 25.49 E D 53 61 69 61 182 243 212 273 30 0 25.49 F C, E 73 92 109 92 273 365 273 365 0 1 100 G F 49 61 73 61 365 426 395 456 30 0 2.54 H G, I 80 121 161 121 456 577 486 607 30 0 2.61 I F 56 91 111 91 365 456 365 456 0 1 97.46 J G, I 48 62 93 62 456 518 456 518 0 1 97.39 K J 70 89 124 89 518 607 518 607 0 1 97.39 L H, K 52 61 78 61 607 668 637 698 30 0 9.22 M H, K 111 153 187 153 607 760 607 760 0 1 90.78 N L 47 62 78 62 668 730 698 760 30 0 9.22 1=yes,0=no Project Completion Time= 760 Prob. O n CP Figure 1. Gantt chart containing the deterministic time [Oracle Primavera P6] Fig. 2 Frequency view As is shown in Fig. 2, axis X depicts the completion date and axis Y stands for the probability of the given value to occur. The blue-colored area represents the positive values of the project completion time and the pink-colored area represents the negative values. It plots the distribution curve of all of the dates when the project is going to end and replace a firm date with a range of dates. Fig. 2 also exhibits that the probability that the completion date of September 30, 2011 can be met is only 47.02. Thus, the completion date calculated in CPM scheduling is not very likely to occur, given the risks that have been specified. Since there is only about 47.02 likelihood that this project can be finished on September 30, 2011 or earlier, the probability of schedule completion on this project without risk mitigation is problematic. It should be noted that the date of September 30 is not even the most likely completion date for this project. From the histograms, it seems that the most likely duration (the tallest column in Figure 2) is closer to 770 than to 760. This finding indicates that it is unwise to put confidence on the sum of even the most likely durations as a predictor of the duration. As a common value for a conservative target is a date that has an 80 percent probability of success, abbreviated often as P-80, the table shows the results that P-80 date is about 788.29 according to Table 2. 511

Tab. 2 Percentiles Percentile 0 10 20 30 40 50 60 70 80 90 100 Forecast values 663.37 724.23 736.86 746.59 754.62 762.64 770.23 778.52 788.29 802.15 860.68 Tab.3 Sensitivity Analysis Activity Name Percentage A 25.2 M 24.7 I 14.6 K 13.4 J 11.3 F 5.9 D 2.1 B 1.7 C 0.8 E 0.2 L 0.1 N 0 H 0 G 0 The risk analysis by Monte Carlo simulation also can identify the major risk and find a way to the unfavorable outcomes. In order to find the key factors that can impact the completion date, sensitivity analysis was conducted. Table 3 shows which factors have the most potential impact on the distribution of possible outcomes and how the variations in project s objectives correlate with variations in different uncertainties. From sensitivity analysis, it is clear that A (Design) has the highest uncertainty and impact on the distribution of possible outcomes. M (construction of second floor) and I (Decoration) also have high uncertainties and impacts, some due to long construction duration and key construction period. In this scenario, it is necessary for a project manager to find causes of variances and take some corrective actions. To create a schedule contingency allowance, the move-in for the next available window would be postponed. If the project completion date is immovable, schedule should be compressed and improved with the expectation of 80 or 90 percent probability of completion. Although this compression always cause a general rise in price, risk assessment is not cost but an investment in terms of actual money saved, since resources are used more efficiently and the consequence of a delay to the project can be avoided. Through Monte Carlo simulation, the project risks and their potential consequences can be identified for practical case. A balance between the precisely planning a project schedule and the scarce resources also can be achieved. The results confirm that risk assessment by Monte Carlo simulation can assist in planning decision, setting contingency time and taking corrective action. Conclusion As an advanced data mining method in project management, Monte Carlo simulation can provide wealthy informations, including the criticality path report, the criticality distribution, and the duration probability curves for risk management. As seen from a practical case, compared with firm date given by CPM, Monte Carlo simulation can provide a range of date for risk analysis. By Monte Carlo simulation, risk analysis can help refine the schedule, identify and monitor risk events, and respond with corrective actions in case of unfavorable outcomes. In short, Monte Carlo simulation can provide direct pictorial information to assist the decision makers in selecting a realistic yet acceptable project completion time. References [1] D. Hulett, Practical Schedule Risk Analysis, Farnham, Surrey, United Kingdom, 2009. [2] K.G. Cooper, The $2,000 hour: How managers influence project performance through the rework cycle, PM J. 4(1994) 11 24. [3] A. Laufer, G.A. Howell, Construction planning: Revising the paradigm, PM J. 3(1993) 23 33. 512

[4] Project Management Institute, A Guide to the Project Management Body of Knowledge, Project Management Institute, Pennsylvania, 2004. [5] A. Basu, Practical risk analysis in scheduling, AACE International Transactions, West Virginia, 1998. [6] G.S. Birrell, Construction planning-beyond the critical path, J. Constri. Div. ASCE. 106(1980) 389-407. [7] J.B. Bonny, Handbook of construction management and organization, VanNostrand Reinhold Company, Vancouver, WA, 1973. [8] R.G. Li, G.X.Wang, Y. Li, J.L. Ren, Study on uncertainty of activity duration in PERT, Systems Engineering and Electronics, 19(1997) 40-45(chinese). [9] Y.Reuven, Simulation and the Monte Carlo method, Wiley, New York, 2008. [10] D. Vose, Quantitative risk analysis, a guide to Monte Carlo simulation modelling, Wiley, New York, 1996. [11] N. Duan, H.M. Xue, Y. Pan, A method for determining the number realizations in the calculation of reliability by Monte Carlo simulation method, Coal Mine Machinery, 3(2002) 13-14. 513