Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models. Martin Hopkinson
|
|
|
- Hilary Reed
- 9 years ago
- Views:
Transcription
1 Page 1 of 13 Monte Carlo Schedule Risk Analysis - a process for developing rational and realistic risk models Martin Hopkinson Abstract Monte Carlo schedule risk analysis has become a widely practiced technique in project management and can be very useful if conducted to high standards. However, its results can be misleading unless care has been taken to ensure that the structure of models and the input estimates produce realistic simulations of project delivery. This paper describes a process that can be used to develop realistic and useful schedule risk models. The process is also designed to avoid a number of common practices that can produce irrational models and unrealistic estimates. Monte Carlo Schedule Risk Models Monte Carlo Schedule risk analysis is described in a number of guides to project risk management including the Project Management Institute (PMI) Practice Guide and the Association for Project Management (APM) Project Risk Analysis and Management (PRAM) Guide. This support for the technique reflects its increasingly wide usage. There are also a number of commercial software tools that support the technique including Primavera Risk (previously marketed as Pertmaster) for Projects. These tools support a number of common features of Monte Carlo schedule risk models as well as a number of other features that can be used as appropriate. Figure 2 illustrates common features of Monte Carlo schedule risk models. Uncertain outcome of activity durations estimated with probability distributions Min Mode Max Uncertain effects of risk events estimated with probabilities and impact probability distributions Min Mode Max Variation of milestone dates is driven by Monte Carlo simulation, with results typically shown using s-curves X% Typically, probability distributions are defined using a shape (e.g. Beta Pert) and a three-point estimate Figure 2: Common features of Monte Carlo schedule risk models
2 Page 2 of 13 Common features of schedule risk networks include activities, risk events, milestones and network dependencies. A working-time calendar (or combination of calendars) is also required. In addition to these features, some risk models may include one or more of the following: Probabilistic dependencies Conditional dependencies Resource constraints and/or resource uncertainties Calendar risk profiles (e.g. to simulate date-dependent weather risk) Purposes of Schedule Risk Analysis Schedule risk analysis may have a number of purposes. The primary purpose is often to provide risk-based confidence forecasts for the achievement of key milestones, including the project s end milestone. Typically, these forecasts are presented in the form of histograms or cumulative probability (S-curve) graphs. Figure 2 is an example of the latter, identifying 80 th percentile confidence (P80) dates for the completion of two milestones. 100% 80% Cumulative probability Interim Milestone Project End Milestone Achievement Date Interim Milestone P80 date Project End P80 date Figure 2: Illustration of risk-based schedule confidence forecasts Forecasts such as that illustrated in Figure 2 convey useful information about overall project schedule risk to stakeholders. They can therefore be used in connection with project approval points. For example, the UK s Ministry of Defence requires P10, P50 and P90 confidence forecasts to be included in the business case for any major project at the point of Main Gate approval. This allows project sponsors and project approval boards to assess whether or not the degree of risk associated with the project is commensurate with the organisation s risk appetite. Risk-based confidence forecasts can also help to quantify a project s schedule contingency requirements and position schedule contingencies appropriately. Moreover, schedule risk models can be varied to reflect the implications of options for project delivery in order to determine which are most likely to achieve the best results. Both of these approaches can contribute towards making plans risk-robust.
3 Page 3 of 13 Finally, statistics from Monte Carlo simulation can be used to generate metrics such as criticality and schedule sensitivity index which identify the activities and risks that contribute most to a project s overall schedule risk. This provides a risk prioritisation approach that is superior to common, but more simplistic, techniques such as the Probability-Impact Matrix. All of these purposes of schedule risk analysis have been proven to be useful in practice. However, they are only useful if the analysis is based on a realistic model. As with any quantitative modelling technique, the validity of the results is critically dependent upon the quality of the input data. If model inputs, are of poor quality, the results may be misleading. It is thus important to understand what constitutes a good quality schedule risk model and how to develop one. Characteristics of a Good Quality Schedule risk model A good quality schedule risk model is one that simulates the important implications of all significant sources of risk in a realistic and rational manner. The aim should be to use as simple a model as is possible whilst still achieving these objectives. A key first test when validating a risk model is to consider whether or not the implications that it simulates are important and the right focus for management interest. In essence this means that the purposes of conducting the analysis should have been identified. There is no point, for example in conducting analysis on milestones that are unimportant, using assumptions that are unrealistic or in circumstances where the results will not influence decisions. It should also be remembered that the analysis can have different purposes. In his book on Quantitative Risk Analysis (3 rd Ed 2008), David Vose notes that The biggest uncertainty in risk analysis is whether we started off analysing the right thing and in the right way. Second, the model should take account of all significant sources of schedule risk. There may exist sources of risk that govern whether or not events will occur that would giver rise additional activities to those planned. Such event risks are often to be found in a project risk register. They can be included in schedule risks models as activities that may or may not occur. Alternatively some event risks might be better represented using techniques such as probabilistic dependencies or calendar risks. However, not all risks are event risks. Some risks are attributable to sources of uncertainty that drive activity duration over a continuous range i.e. variability risks. The implications of such risks can be reflected in the probability distributions assigned to activities in the risk network. An important feature of good quality risk models is that all significant sources of risk have been identified, understood and appropriately simulated. Third, the input risk estimates must be realistic. This requires an unbiased and appropriately structured approach to the risk estimating process. In the absence of a structured approach, estimates will be based on intuition and thus exposed to the effects of heuristics (mental shortcuts) that tend to produce risk estimates that are both biased and too narrow. A frequent indication of unrealistic estimates is the de facto use of the project s deterministic schedule to obtain Mode estimates for variability risk and the estimation of distribution extremes using a standard +/- percentage (e.g. +/- 10%) metric. Making realistic risk estimates requires time and care. Resorting to
4 Page 4 of 13 +/- percentage estimates is often the result of a project having too many estimates to make. The solution is to ensure that risk models are restricted to a manageable number of activities and risks. This is one reason for recommending that no risk model should include more than 200 activities and that this should be regarded as a ceiling for large and complex projects. Most schedule risk models should be much simpler. Finally, for a risk model to be considered rational, there should be evidence that the combination of its parts should be capable of a correct simulation of overall schedule risk. Since risks often interact in complex ways, it is usually difficult to provide such evidence unless the model has been developed iteratively in a top down manner. It should also be noted that it is easy to produce irrational schedule risk models unintentionally. The modelling verification process should therefore provide assurance that known common causes of irrational models have been avoided. Irrational risk models may be the consequence of: 1. Modelling at low levels of activity detail, using activities and dependencies that are not unlikely to evolve during the course of project delivery (thus assuming a degree of certainty about the network that is not rational in the context of simulating the implications of uncertainty). Most risk models with more than 200 activities are irrational for this reason, as are many with fewer than 200 activities. 2. Using inappropriate schedule constraints on activities (e.g. must finish by ) that override the Monte Carlo simulation. 3. Using network dependencies inappropriately such that affected activities fail to influence the simulation results. Finish-Finish dependencies can result in this fault if used to represent partially overlapping activities. 4. Using dependencies with leads or lags that mask the significance of risk associated with missing activities. 5. Including activities in the network that do not directly drive schedule risk (e.g. project management or routine meetings). 6. Unquestioning use of information from the project s deterministic schedule in circumstances when it is known to be immature, faulty or biased. 7. Using ambiguous activities and/or risk events that provide an inadequate basis for estimating. 8. Duplicating the implications of risks e.g. by adding event risks to the model when their implications are already simulated by dependencies. 9. Pulling across risk estimates from a risk register that have not been made in the context of the schedule risk model. In practice, the most frequent cause of irrational risk models is electronic copying of the project s deterministic schedule (often referred to as the plan). It should be noted that the first five points in the above list refer to techniques that may be legitimate in the context of planning but irrational if pulled through to risk analysis. Hence, even if the project s schedule is of good quality, it is usually a mistake to simply copy it for the purpose of risk modelling. Since good quality risk models cannot usually be produced by copying a project s schedule, there is a need for a process for doing so.
5 Page 5 of 13 A Process for Monte Carlo Schedule Risk Models Figure 3 illustrates a process for developing and using a project Monte Carlo schedule risk model. The subsequent sections of this paper describe why each stage of the process is important and how it should be implemented. Identify purpose(s) of analysis Identify Key Milestones Identify assumptions that frame the model Develop Activity Network Validate key milestone dates Introduce event risks to network Make Risk Estimates Analysis of alternative planning scenarios Preferential development of detail as part of an iterative multi-pass process Run Model / Obtain results Identify responses Report implications, together with framing assumptions Figure 3: Process for developing and using a Monte Carlo schedule risk model Identify purpose(s) of analysis The function of any risk model is to support decisions that might be taken in response to the insights that it produces. Since schedule risk analysis may have one or more purposes, it important to identify what those purposes are and who will use the analysis results. This will help scope the analysis appropriately and identify the key milestones around which the model structure should be built. Clarifying these points with decision makers will also help to convey assurance that their requirements have been understood thus making it more likely that they will act on the analysis results. Identify Key Milestones Identifying the purpose of the analysis should help identify the milestones that are the subject of the analysis results, as depicted, for example in Figure 2. It may also help to identify other key milestones in order to structure and validate the model as it is developed. Typically, there might be 4 and 10 key milestones, with the number reflecting the project s size and complexity. Key milestones might be selected on the basis that they: can be associated with well-defined products or events; represent points at which activity paths in the schedule converge; are known e.g. from previous experience, to be exposed to schedule risk;
6 Page 6 of 13 are relatively evenly spread over time, and are of significant interest to decision makers and project stakeholders; Develop Activity Network The product of this step of the process is an activity network that models how key milestones are driven. It is good practice to use simple Finish-Start logic unless there are good reasons for doing otherwise. It is also good practice to start with the simplest possible network, working with the minimum number of high level activities commensurate with this aim. Further detail using lower level activities can be added in later passes of the model s development. The reasons for this are that: Working with a complex network often makes it easier to overlook the fact that fundamental assumptions are being made to frame the model. Starting with a simple network can help to clarify which dependencies override others. In practice, there are usually only a limited number of dependencies are unalterable. Differentiating between these and other dependencies can be a useful way of identifying where the merits of different plans could be compared using risk analysis and where the use of lower level activities might be irrational. Key areas of risk and ways in which they interact are sometimes easier to identify when working with a high level schedule. One of the arts of good risk modelling is to preferentially develop detail in areas of the model that matter most from a risk perspective. As the model is developed, insights gained from the each stage of its development can be responded to with either further development of detail or the production of alternative versions that allow different planning scenarios to be compared. Validate Key Milestone Dates It should be possible to compare the deterministic version of the risk model activity network with the project s schedule. The dates for key milestones provide a convenient check that they are aligned. A lack of alignment can indicate the presence of issues with either the risk model or the schedule. Errors in either can be corrected during this step of the process. Decision makers who use the analysis results are more likely to be persuaded on the risk model s validity if it aligned with dates that they recognise from the project schedule. Equally, however, it should be appreciated that an advantage of developing a separate schedule risk model is that provides a health check on the project plan. Introduce risk events to the network The activity network developed by previous steps should be augmented so that it is able to simulate the implications of event risks. Event risks are potential step changes to the underlying plan that may or may not occur. Many event risks can be simulated as activities that may or may not exist risk probability is effectively the probability of task existence. Such risks are connected into the network using dependencies in the same way as activities which can be assumed to exist. However, there may be circumstances in which certain event risks can only be simulated using other means
7 Page 7 of 13 such as probabilistic dependencies, calendar-related risk or resource availability variance. In practice, a project s risk register is often a good starting point for the identification of event risks. However, it should be noted that some risks in the risk register might already be inherent to the risk model s activity network e.g. the risk that manufacturing might be delayed by late issue of drawings. Care thus needs to be taken when selecting risks to be modelled as events. Make Risk Estimates Having developed a complete risk network, estimates are required to drive the Monte Carlo simulation. As a minimum estimates will be required for: Probability distributions associated with the duration of activities, often defined using a probability distribution shape and three-point estimate. Probability and impact estimates for risk events simulated as activities that may or may not occur, with impact estimates usually estimated in the form of a probability distribution rather than single value. These estimates are crucial to the simulation results; care is required to ensure that they are realistic and unbiased. The issues involved in achieving this aim are complex and discussed in a number of works. The notes below provide a brief summary of how some of the most important factors can be addressed. 1. Estimates should be made by subject matter experts (SMEs) with the aid of a risk management specialist who can guide them in the use of an appropriately structured approach. For example, SMEs should understand the implications of the probability distribution shapes that being used. 2. Risks should be understood clearly before estimates are made. For example, in order to estimate an event risk probability there should be clarity about the sources of uncertainty that influence whether or not the risk would occur. 3. Sources of uncertainty that affect activity or risk impact variance may combine in complex or compound ways. One cause of unrealistically narrow three-point estimates is that the relevant sources of uncertainty are not identified explicitly or that insights from this information are not used appropriately. 4. When making three-point estimates, it is good practice to estimate the High estimate first, then the low estimate and finally the mode (most likely), in each case taking care to understand the circumstances in which these could arise. This approach avoids the anchoring bias inherent to the oft used assumption that planned deterministic durations are the same as the mode. 5. It may be possible to use quantitative historical data from previous projects to help validate the estimates. However, care needs to be taken to ensure that such projects are genuinely representative of the new project for which estimates are being made. It should also be remembered that the number of projects may not provide a statistically valid sample. The realistic range of uncertainty is thus usually wider than would be indicated by the outcomes of any of the previous projects.
8 Page 8 of Estimators must be committed to the principle of making unbiased estimates. It is likely to help if estimators are accountable for outcomes. If the nature of the project environment is one that could foster bias, estimates should be subject to independent scrutiny. Dependent upon the structure and development stage of the model, estimates may also be required to: Simulating the effects of covariance between associated activities and risks (usually using correlation inputs). Specify relative probabilities for probabilistic dependencies. Identify assumptions that frame the model As any risk model is developed, assumptions have to be made in order to structure the model and simplify the ways in which the implications of uncertainty are simulated. Some assumptions may be explicitly built into the model, for example an assumed start date or dependencies representative of contractual obligations. Other assumptions, such as the project s purpose, objectives and contracting strategy, may be implicit to the risk network and estimates. Key assumptions should be recorded as the model is developed. They include assumptions that are fundamental to the project or the context in which the analysis results should be interpreted. Other key assumptions may imply the exclusion of risks from the model that cannot rationally be modelled e.g. potential showstoppers. If the people who act upon the analysis results are not made aware of key assumptions, they might misinterpret the results and take inappropriate action. The primary reason for recording assumptions is thus to ensure that they are disclosed in conjunction with the reporting of results. However, it should also be noted that records of assumptions that imply constraints may lead to the identification of opportunities for schedule improvement. Run model and obtain results With modern computer software and processing power, running a Monte Carlo simulation now takes little more than seconds. As a result, the question of how many iterations of the simulation are required to in order to produce reliable results has become a less important issue than it used to be. For the purposes of project schedule risk analysis, 3000 iterations are usually more than sufficient, although there is little time penalty for using a higher number. The more important issue is how the results are used and whether or not they can be used to identify appropriate responses. Schedule risk analysis results are generally of two types: 1. Risk-based forecasts, e.g. as illustrated in Figure Statistical analysis of the relative importance of the model s constituent activities and event risks e.g. as illustrated in Figure 4.
9 Page 9 of 13 Results of both types can be used to identify risk responses and report the implications of schedule risk to stakeholders and project decision makers. Identify responses In cases where there are relationships between the project s risk register and its schedule risk model, some schedule risk responses may already be identified in the risk register. However, schedule risk analysis results can provide a sharper focus on the importance of certain activities or risks, thus leading to further consideration as to how associated risks responses could be made more effective. Typically, this focus is provided through Tornado charts based on metrics such as criticality, cruciality or schedule sensitivity index (SSI). Figure 4 illustrates the Tornado chart format. The activities and event risks with the longest bars are those that have the greatest influence on overall schedule risk. 0 Cruciality Activity 14 Activity 23 Event risk F Activity 3 Activity 30 Event risk B Activity 9 Event risk E Figure 4: Illustration of a Schedule Risk Analysis Tornado Chart Schedule risk analysis can also lead to the identification of risk responses that might not be identified or assessed using a risk register. Such responses include: 1. Making provisions for schedule contingency in the project plan, in response to the risk-based forecasts obtained for key milestones; 2. identification of further modelling actions that may be required to obtain a more detailed analysis of risk (preferential development of detail as part of an iterative multi-pass process), and 3. Using variants to the schedule risk model to assess the effect of potential risk mitigation activities or other options that would alter delivery plans. The second and third of these types of response require further cycles of modelling represented by feedback loops in the process illustrated in Figure 3.
10 Page 10 of 13 Preferential development of detail as part of an iterative multi-pass process A number of the most respected academic works in the field of project risk management recommend the use of an iterative top-down process. For example Chapman and Ward (2002) uses ten case studies to show how key insights and rational risk models can be developed iteratively from a constructively simple initial model. This principle of using top-down iterative process is also inherent to the APM s guides to project risk. It is tempting to develop modelling detail preferentially in areas of the schedule that are best understood and that can be estimated with the most precision. Indeed, this makes good sense in the context of project planning. However, in the field of risk management it makes more sense to focus preferentially on areas of the schedule that have the greatest degrees of risk exposure. One approach to identifying these areas is to run a high-level schedule risk model in order to identify the activities that have the most influence on overall risk e.g. using Tornado diagram results as illustrated in Figure 4. These activities can then be addressed as being composite risks that might be better understood if broken down into a more detailed risk network for modelling purposes. The other key reason for using a top-down approach to schedule risk model development is that (for reasons detailed earlier in this paper) it provides assurance that the model is rational. In contrast, the common-practice single pass approach in which a detailed risk register is merged with a detailed project schedule frequently produces an irrational risk model. The importance of using an iterative process for risk model development is reflected in the solid feedback line in the process diagram in Figure 3. This indicates that an iterative process should be used in all cases, whereas the other feedback loop (analysis of alternative planning scenarios), represented with a dashed line, is sometimes not required, although it is often very useful. Analysis of alternative planning scenarios One of the advantages of developing a schedule risk model is that it becomes possible to run the analysis with different planning scenarios. This allows what if? planning issues to be assessed from a risk perspective. Techniques for analysing different planning scenarios include: Substituting one part of the schedule with an alternative combination of activities that would achieve the same ends. Investigating the opportunity for schedule enhancement by using management interventions e.g. committing more resources to the project. Quantifying the benefits of implementing risk mitigation actions that reduce the probability and/or schedule impact of event risks (pre and post mitigation analysis). The implications of alternative planning scenarios are reflected in different versions of the risk model that can be run so as to compare results with a view to choosing the
11 Page 11 of 13 optimal solution. Figure 5 illustrates a comparison of the results produced by two scenarios. 100% Cumulative probability 80% Planning Scenario 2 Planning Scenario 1 Figure 5: Example of the comparison of alternative planning scenarios In the case of Figure 5, Scenario 2 would probably be preferred to Scenario 1 since, on average, it is likely to achieve an earlier project completion date. However, if the organisation was risk averse, Scenario 1 might be preferred since it there is less uncertainty about the date by which the project would be complete and because there is at least a possibility that Scenario 2 would achieve a later completion date. The example in Figure 5 illustrates how schedule risk analysis forecasts can be used to clarify the implications of project design decisions. Report implications, together with framing assumptions Achievement Date The last step in process described by this paper is to report results, insights and recommendations to the relevant interested parties. Depending upon the purpose of the analysis these parties might include the members of the project management team, the project sponsor, other people project governance roles or external stakeholders such as the project customer. Each report should provide data relevant to the relevant purposes of risk analysis established during the first step of the process. Analysis reports are likely to include graphical outputs such as those shown in Figures 2 and 4. However, for the purposes of clarity, it is important that the key assumptions used for risk modelling purposes are also disclosed. It is also good practice to summarise the actions taken to verify that an appropriate process has been used for risk model development and to validate the model(s) in terms of their fitness for purpose. Martin Hopkinson October 2011
12 Page 12 of 13 A link to download free copies of this paper and other useful project risk management resources found at References 1. Association for Project Management (2004). Project Risk Analysis and Management (PRAM) Guide (2nd Edition). Princes Risborough, UK, Association for Project Management. 2. Chapman, C & Ward, S. (2002) Managing Project Risk and Uncertainty; a Constructively Simple Approach to Decision Making. Chichester, UK, John Wiley & Sons Ltd. 3. Chapman, C & Ward, S. (2003) Project Risk Management; Processes, Techniques and Insights (2 nd Edition). Baffins Lane, Chichester UK: John Wiley & Sons Ltd. 4. Comptroller and Auditor General (2008). Ministry of Defence Major Projects Report Buckingham Palace Road, London, UK National Audit Office. 5. Earned Value Specific Interest Group. Earned Value Management APM Guidelines. 6. GoPM Specific Interest Group (2004) Directing Change, A guide to governance of project management. Association for Project Management. (available at 7. GoPM Specific Interest Group (2007) Co-directing Change, A guide to governance of multi-owned projects. Princes Risborough, UK, Association for Project Management. 8. Hillson, D and Murray-Webster, R. (2005). Understanding and Managing Risk Attitude. Farnham, UK, Gower Publishing. 9. Hopkinson, M (2001) Schedule Risk Analysis: Critical Issues for Planners and Managers. London, UK, PMI Europe Conference. 10. Hopkinson, M et al (2008). Prioritising Project Risks. Princes Risborough, UK, Association for Project Management. 11. Hopkinson, M (2011) The Project Risk Maturity Model; measuring and improving risk management capability. Farnham, UK, Gower Publishing. 12. Hulett, D (2009). Practical Schedule Risk Analysis. Farnham, UK, Gower Publishing. 13. Lichtenberg, S (2000). Proactive Management of Uncertainty using the Successive Principle. Copenhagen, Denmark, Polyteknisk Press.
13 Page 13 of Murray-Webster, R and Hillson, D. (2008). Understanding and Managing Group Risk Attitude. Farnham, UK, Gower Publishing. 15. Project Management Institute (2009). Practice Standard for Project Risk Management. Pennsylvania, USA, Project Management Institute Inc. 16. Vose, D (2008). Risk Analysis a Quantitative Guide (3 rd Edition). Chichester UK: John Wiley & Sons Ltd.
Managing Overall Project Risk. Abstract
Managing Overall Project Risk Dr David Hillson, PMI Fellow, PMP, HonFAPM, FRSA, FIRM, FCMI, CMgr, MIOD The Risk Doctor Partnership, [email protected] Abstract Leading project risk management guidelines
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
INT 3 Schedule Risk Analysis
INT 3 Schedule Risk Analysis David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12, 2015 1 Agenda Add uncertainty to the schedule,
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D.
Schedule Risk Analysis Simplified 1 by David T. Hulett, Ph.D. Critical Path Method Scheduling - Some Important Reservations The critical path method (CPM) of scheduling a project is a key tool for project
Project Risk Management Single Subject Certificate Syllabus Levels 1&2 4 th Edition
Project Risk Management Single Subject Certificate Syllabus Levels 1&2 4 th Edition The Single Subject Certificates in Project Risk Management (Risk SSC) are designed to build on the knowledge gained in
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model - 12419
Integrated Cost and Schedule using Monte Carlo Simulation of a CPM Model - 12419 ABSTRACT David T. Hulett, Ph.D., Hulett & Associates, LLC Michael R. Nosbisch, CCC PSP, Project Time and Cost, Inc. This
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT
RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.
Risk Workshop Overview. MOX Safety Fuels the Future
Risk Workshop Overview RISK MANAGEMENT PROGRAM SUMMARY CONTENTS: Control Account Element Definition ESUA Form Basis of Estimate Uncertainty Calculation Management Reserve 1. Overview 2. ESUA Qualification
Net Present Value Risk Analysis
an example of using risk management to shape a project s solution Martin Hopkinson CI05 M01 I02 Slide No. 1 Common-practice Project Risk Management Single Pass Process Project Objectives Brainstorm, Checklists
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
A Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Overview.
A Comparison of System Dynamics (SD) and Discrete Event Simulation (DES) Al Sweetser Andersen Consultng 1600 K Street, N.W., Washington, DC 20006-2873 (202) 862-8080 (voice), (202) 785-4689 (fax) [email protected]
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Project Risk Management
Support of Project Risk Management Development of Risk Based Contingency Values for a Baseline Project Budget Estimate Panama Canal 3rd Lane Locks Atlantic and Pacific Locks, Pacific Access Channel, and
Understanding risk exposure using multiple hierarchies. Introduction
Understanding risk exposure using multiple hierarchies David Hillson PhD PMP FAPM FIRM MCMI FRSA Director, Risk Doctor & Partners Introduction Risk management is recognised as an essential contributor
Unit 4: Time Management (PMBOK Guide, Chapter 6)
(PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
An Oracle White Paper June 2009. The Benefits of Risk Assessment for Projects, Portfolios, and Businesses
An Oracle White Paper June 2009 The Benefits of Risk Assessment for Projects, Portfolios, and Businesses Executive Overview... 1 Introduction... 1 Why Do Projects Fail?... 3 The Effects of Optimism and
How To Design A Project
Introduction to Procurement Why is procurement important? Client needs are unique and consequently each project meeting those needs has unique characteristics. This means that achieving the right project
PROJECT RISK MANAGEMENT
11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
Software Project Scheduling under Uncertainties
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
PROJECT RISK ANALYSIS AND MANAGEMENT
PROJECT RISK ANALYSIS AND MANAGEMENT A GUIDE BY THE ASSOCIATION FOR PROJECT MANAGEMENT (formerly The Association Of Project Managers) Compiled from information provided by members of the Special Interest
UK Sport Gold Event Series Investment Guide 2013-2019
Gold Event Series Investment Guide 2013-2019 Introduction The guide outlines UK Sport s current approach to making investment decisions as part of its Gold Event Series. In the Guide we outline: > > The
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
A collection of Safran Project report samples for project professionals
A collection of Safran Project report samples for project professionals Safran Software Solutions Global Offices: Houston, London, Oslo, Stavanger www.safran.com Contents Introduction... 2 About the Reports
Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Integrated Risk Management:
Integrated Risk Management: A Framework for Fraser Health For further information contact: Integrated Risk Management Fraser Health Corporate Office 300, 10334 152A Street Surrey, BC V3R 8T4 Phone: (604)
8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
In initial planning phases In monitoring and execution phases
Project management What is it? Project management is a framework for a range of tools for helping plan and implement development and change projects. A range of tools exist, including: Gantt charts (bar
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire
P3M3 Portfolio Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction
Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
Project Management Process
Project Management Process Description... 1 STAGE/STEP/TASK SUMMARY LIST... 2 Project Initiation 2 Project Control 4 Project Closure 5 Project Initiation... 7 Step 01: Project Kick Off 10 Step 02: Project
Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis
Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt Programme, Project & Service Management Analysis Table of Content 1 Executive Summary... 3 1.1 Scope of Work... 3 1.2 Methodology for
Schedule Risk Analysis Simulator using Beta Distribution
Schedule Risk Analysis Simulator using Beta Distribution Isha Sharma Department of Computer Science and Applications, Kurukshetra University, Kurukshetra, Haryana (INDIA) [email protected] Dr. P.K.
PMI Risk Management Professional (PMI-RMP) Exam Content Outline
PMI Risk Management Professional (PMI-RMP) Exam Content Outline Project Management Institute PMI Risk Management Professional (PMI-RMP) Exam Content Outline Published by: Project Management Institute,
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM) February 2010 Version 1.12 Copyright: Australian Institute of Project Management Document
ESKITP7145.01 Manage IT service delivery performance metrics
Overview This sub-discipline covers the competencies required to manage the monitoring, analysis and communication of IT service delivery performance metrics. Monitoring service level performance is a
PROJECT AUDIT METHODOLOGY
PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit
Contents. Project Management: August 2005 Page 2 Clinical Research Operational Standards for Professional Practice for Professional Practice
Project Management: August 2005 Contents Introduction........................................................... 4 About this standard: what is the importance of project management?................. 4
PROJECT RISK ASSESSMENT & MANAGEMENT
PETROSYNC S PROJECT MANAGEMENT SERIES PROJECT RISK ASSESSMENT & MANAGEMENT Your Key To Analyse & Identify Risk In Project Risk Management 1 March 4 March 2016 Bali, Indonesia Supported By Course Overview
Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations
Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations December 2011 Contents Contents... i Introduction... 1 Executive Summary... 1 Background...
ISO, CMMI and PMBOK Risk Management: a Comparative Analysis
ISO, CMMI and PMBOK Risk Management: a Comparative Analysis Cristine Martins Gomes de Gusmão Federal University of Pernambuco / Informatics Center Hermano Perrelli de Moura Federal University of Pernambuco
White Paper. PPP Governance
PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting
Composite performance measures in the public sector Rowena Jacobs, Maria Goddard and Peter C. Smith
Policy Discussion Briefing January 27 Composite performance measures in the public sector Rowena Jacobs, Maria Goddard and Peter C. Smith Introduction It is rare to open a newspaper or read a government
Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman
Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Best Practices in Model Development and Maintenance Adam Rose ([email protected]), Product Manager, XP Solutions
Best Practices in Model Development and Maintenance Adam Rose ([email protected]), Product Manager, XP Solutions adopted from Best practices for software development projects Mike Perks ([email protected]),
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
A Risk Management Standard
A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management
Portfolio Management 101:
THOUGHT LEADERSHIP WHITE PAPER In partnership with Portfolio Management 101: Moving from Just Project Management to True PPM A lot of organizations claim that they carry out project & portfolio management
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
1. Background and business case
1. Background and business case This section explains the context and why the project is being undertaken. It provides the justification for investing the time and resources in the project. 1.1 Reasons
Benefits Realization from IS & IT, and Change Management of roles and the working practices of individuals and teams.
: Delivering Value from IS & IT Investments John Ward and Elizabeth Daniel John Wiley & Son Ltd ISBN: 9780470094631, 399 pages Theme of the Book This book explores a process and practical tools and frameworks
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview
PMI Risk Management Professional (PMI-RMP ) - Practice Standard and Certification Overview Sante Torino PMI-RMP, IPMA Level B Head of Risk Management Major Programmes, Selex ES / Land&Naval Systems Division
Quantitative Risk Analysis with Microsoft Project
Copyright Notice: Materials published by Intaver Institute Inc. may not be published elsewhere without prior written consent of Intaver Institute Inc. Requests for permission to reproduce published materials
Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry
CIB World Building Congress 2007 549 CIB2007-370 Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry Dr Tabarak Ballal 1, Dr Taha Elhag 2 and Mr Salim Ambusaidy 3 1
PROJECT RISK MANAGEMENT
PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized
The Cost of Risks. Essence of Risk Quantification. PALISADE @RISK Forum Calgary 2008
PALISADE @RISK Forum Calgary 2008 The Cost of Risks Essence of Risk Quantification Disclaimer: This presentation material is provided for general information. The author shall not be held accountable for
The principles of PRINCE2
The principles of PRINCE2 The project management framework known as PRINCE2 is based upon a set of principles. These principles are the bedrock and foundations upon which everything else in the framework
Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
The Transport Business Cases
Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business
EXAM EXEMPLAR QUESTIONS
Level 6 Professional Diploma in Procurement and Supply PD5 - Programme and project management EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 10 QUALIFICATIONS 2013 QUESTIONS
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
PMOs. White Paper. 1 www.mosaicprojects.com.au. 1 For more papers on PMOs see: http://www.mosaicprojects.com.au/resources_papers.
s A 1 will have various roles and responsibilities according to whether the service (or support) is focused at the project, program or portfolio level. Project management offices (PjMO) provide centralised
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Schedule Compression
Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual
Insights. Did we spot a black swan? Stochastic modelling in wealth management
Insights Did we spot a black swan? Stochastic modelling in wealth management The use of financial economic models has come under significant scrutiny over the last 12 months in the wake of credit and equity
Practical guide to IFRS
pwc.com/ifrs Practical guide to IFRS The art and science of contingent consideration in a business combination February 2012 Contents Introduction 1 Practical questions and examples 3 1 Initial classification
IFRS 10 Consolidated Financial Statements and IFRS 12 Disclosure of Interests in Other Entities
May 2011 (updated January 2012) Project Summary and Feedback Statement IFRS 10 Consolidated Financial Statements and IFRS 12 Disclosure of Interests in Other Entities At a glance We, the International
Monte Carlo Simulations for Patient Recruitment: A Better Way to Forecast Enrollment
Monte Carlo Simulations for Patient Recruitment: A Better Way to Forecast Enrollment Introduction The clinical phases of drug development represent the eagerly awaited period where, after several years
ORACLE S PRIMAVERA RISK ANALYSIS
ORACLE S PRIMAVERA RISK ANALYSIS KEY FEATURES Risk Analysis Guide Schedule Check Templated Quick Risk Risk Register Wizard Risk Register Risk Analysis Every project has risks. The organizations that succeed
Project Governance a board responsibility. Corporate Governance Network
Project Governance a board responsibility Corporate Governance Network November 2015 1 Contents Page Introduction 3 Board responsibilities 3 What is project governance? 4 The boards duties in respect of
Sample Examination Questions
Sample Examination Questions The following questions are examples of the type of questions that appear on the PMP Certification Examination. Disclaimer: These questions are intended for study purposes
Chapter 11 Project Management
Chapter 11 Project Management Managing and Using Information Systems: A Strategic Approach by Keri Pearlson & Carol Saunders Introduction What are the elements of a good project? Why do so many IT projects
ENGINEERING COUNCIL. Guidance on Risk for the Engineering Profession. www.engc.org.uk/risk
ENGINEERING COUNCIL Guidance on Risk for the Engineering Profession www.engc.org.uk/risk This guidance describes the role of professional engineers and technicians in dealing with risk, and their responsibilities
IRSG Opinion on Joint Discussion paper on Key Information Document (KID) for Packaged Retail and Insurance-based Investment Products (PRIIPs)
EIOPA-IRSG-15-03 IRSG Opinion on Joint Discussion paper on Key Information Document (KID) for Packaged Retail and Insurance-based Investment Products (PRIIPs) Executive Summary It is of utmost importance
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane [email protected] Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
APM web briefing - Use of Product Breakdown Structures and Work Breakdown Structures
APM web briefing - Use of Product Breakdown Structures and Work Breakdown Structures Introduction Product Breakdown Structures and Work Breakdown Structures look very similar and both have important roles
Use project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
Specialists in Strategic, Enterprise and Project Risk Management. PROJECT RISK MANAGEMENT METHODS Dr Stephen Grey, Associate Director
BROADLEAF CAPITAL INTERNATIONAL PTY LTD ACN 054 021 117 23 Bettowynd Road Tel: +61 2 9488 8477 Pymble Mobile: +61 419 433 184 NSW 2073 Fax: + 61 2 9488 9685 Australia www.broadleaf.com.au [email protected]
Measurement of Banks Exposure to Interest Rate Risk and Principles for the Management of Interest Rate Risk respectively.
INTEREST RATE RISK IN THE BANKING BOOK Over the past decade the Basel Committee on Banking Supervision (the Basel Committee) has released a number of consultative documents discussing the management and
Data gathering for Schedule Risk Analysis
DEGREE PROJECT, IN PROJECT MANAGEMENT AND OPERATIONAL DEVELOPMENT, SECOND LEVEL STOCKHOLM, SWEDEN 2015 Data gathering for Schedule Risk Analysis MARTIN MORY KTH ROYAL INSTITUTE OF TECHNOLOGY INDUSTRIAL
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
Technology management in warship acquisition
management in warship acquisition A J Shanks B.Eng(Hons) MIET BMT Defence Services Limited SYNOPSIS Today s warship designers and engineers look to technology to provide warships and systems better, cheaper
Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
Introduction. http://www.alexsbrown.com/ Page 1
Modeling Tough Scheduling Problems with Project Management Software Alex S. Brown, PMP, Strategic Planning Manager, Mitsui Sumitomo Marine Management (U.S.A.), Inc. Introduction Despite year-over-year
Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500
Project Training Company Comparing PMBOK Guide 4 th Edition, Edition and STS Sauter Training & Simulation S.A. Avenue de la Gare 10 1003 Lausanne Switzerland Web: www.sts.ch E-mail: [email protected] Phone:
Document management concerns the whole board. Implementing document management - recommended practices and lessons learned
Document management concerns the whole board Implementing document management - recommended practices and lessons learned Contents Introduction 03 Introducing a document management solution 04 where one
Report. by the Comptroller and Auditor General. Ministry of Defence. Army 2020
Report by the Comptroller and Auditor General Ministry of Defence Army 2020 HC 263 SESSION 2014-15 11 JUNE 2014 4 Key facts Army 2020 Key facts 82,500 trained regular Army personnel planned in December
10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.
PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition
Strategies to successfully manage your major project
PROJECT ADVISORY Strategies to successfully manage your major project Whitepaper 1 Thought Leadership Series 10 kpmg.com/nz About this whitepaper KPMG s Project Advisory thought leadership series is aimed
