Quantity Takeoff. Dr. Ahmed Elyamany



Similar documents
Quantity Take-off. Quantity Take-off

CHAPTER 2 QUANTITY TAKE-OFF

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No May 15, 2013

The Task. for. PERI Construction-Exercise 2003

TABLE OF CONTENTS. INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE...

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans

PROJECT COST ESTIMATES & FEASIBILITIES

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.

HOUSE BUILDING DIGEST

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Technical Notes 3B - Brick Masonry Section Properties May 1993

Elevating Your House. Introduction CHAPTER 5

Requirements for Building Application Submission

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME

PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE

Technical Assignment 2 TABLE OF CONTENTS

SECTION TABLE OF CONTENTS. H Proposed Material, Product or Equipment Substitution Request

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

Chapter 16. Mensuration of Cylinder

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

Excerpts from the Canadian National Building Code (NBC)

VOLUME AND SURFACE AREAS OF SOLIDS

The unit costs are based on the trend line of the 3 low bids for the average quantity.

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE

Project : CONSTRUCTION OF BUILDING(including electrical and plumbing works) FOR NATIONAL CENTRE FOR SUSTAINABLE COASTAL MANAGEMENT,CHENNAI

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

LAYING BLOCK AND BRICK

Aluminium systems profile selection

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SOMETIMES the cost of installing a landscape plan

Superform Products Ltd.

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

Building Cost Estimates-Beef Related Facilities

Area is a measure of how much space is occupied by a figure. 1cm 1cm

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY

High Strain Dynamic Load Testing of Drilled Shafts

1. Concrete: T W L / 27 = Concrete C.Y. Multiply Feet Thickness x Feet Width x Feet Length / 27 = Cubic Yards.

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

King Post Wall Information

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Construction Technologies Career Field Pathways and Course Structure

Design and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 6 Bill of Quantities

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

Lighthouse Engineering, L.L.C.

PROJECT TITLE : 2-STOREY RESIDENCE LOCATION : ALONG DAANG HARI,MOLINO.BACOOR,CAVITE OWNER : CUEVASVILLE REALTY

SECTION STORM DRAIN SYSTEM

SIMULATION PRE-INSTALLATION GUIDELINES CONTRACTOR REQUIREMENTS FOR ROOM PREPARATION

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

FY08 SEWER POINT REPAIRS BID TABULATION

Estimating with Microsoft Excel

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:

ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

How To Build A Luxury Apartment Complex In London

WORK SCOPE. Domains in which we work:

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

SUCF PROJECT COST REPORTING GUIDE

Olilo's AEC Design Services. SrinSoft Inc, Partners of

APPLICANT / CONTACT:_

Uncovered Decks & Porches

If stepping is required, step at 180mm as seen in this picture.

Hanson Building Products. precast basement solutions

BILL OF QUANTITY FOR THE WORK OF "REPAIRING OF CIVIL & PLUMBING WORKS INSIDE AND OUTSIDE OF THE WORKSHOP"

Section 600 Incidental Construction

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

Detailing of Reinforcment in Concrete Structures

Seattle Public Schools Building Excellence IV Projects Under Construction

PAVER JOB INFORMATION SHEET

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

FDOT Specifications List

CONSTRUCTION SUMMARY OF THE PEREIRA HOUSE AT MADOL, VERNA GOA.

QS 004 DEPARTMENT OF PUBLIC WORKS REPUBLIC OF SOUTH AFRICA BUILDING COST DATABASE

Attachment G-1: Pit Latrine Diagram. Fig E.1a: Pit Latrine. Fig E.1b: Plan View of Twin Pits

Simplifying design and construction. Alan Tovey, Director The Basement Information Centre

Buildings Construction Procurement Strategy

Gas Meter Clearances and Service Installation Requirements

1. A plane passes through the apex (top point) of a cone and then through its base. What geometric figure will be formed from this intersection?

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No December 2014

2. What building projects are exempted? (permit not required)

NAHB PRODUCT DEFINITION

Special Use Commercial Properties

Built to Last. Built for Beauty. Good. Solid. Logix. TM

EAST LYME HIGH SCHOOL

Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 ( N, E)

While RS Means is a useful estimating tool, it must be used as intended, coupled with regional knowledge.

Transcription:

Quantity Takeoff Dr. Ahmed Elyamany 1

Outline Importance of Quantity Takeoff Preparation of Quantity Takeoff Measurement Units Measuring excavation, P.C footings, Beams, Columns, slabs, and stairs. Solved Example 2

Quantity Takeoff Quantity takeoff is an activity performed by General Contractors, Subcontractors, Cost Consultants, and Quantity Surveyors as part of the construction process. It involves counting the number of items associated with a particular construction project 3

Quantity Takeoff Quantity Takeoff is performed by: General Contractors, Subcontractors, Cost Consultants, Quantity Surveyors Counting the number of items associated with a particular construction project Determining the associated materials and labor costs Preparing an estimate as part of the bidding process. Applied to the pricing process. 4

Quantity take-off: Why? Owner perspective: Initial estimate of the project costs at the different stages of the project. Preparing the BOQ as a requirement of the contract documents. Estimating the work done for issuing the contractor payments. Contractor perspective: Pricing different work items. Identifying the needed resources (Labor, Equipment, etc.). Project schedule. Preparing invoices for work done. Subcontractors payments. Review and control of crews production rates. 5

Quantity Takeoff The quantity takeoff process is typically done manually using a printout, a pen, and a calculator. 6

Quantity Takeoff New Trend is Building Information Modeling (BIM) Provide a solution that generates a set of takeoff elements (counts, measurements, conditions that affect cost) enables estimators to more quickly and more accurately perform takeoff for bidding or pricing. 7

Quantity Takeoff Important to specify the type of ; Imported materials Suppliers Equipment Labors Work in project Important to know project budget Important to know activities logic 8

Quantity Takeoff Criteria It must be as accurate as possible Should be based on all available engineering and design data. Use of appropriate automation tools is highly recommended. The Quantity Takeoff is an important part of the cost estimate. 9

Quantity Takeoff Input Documents Input from the client (task description). Conditions (general, special, supplementary). Drawing and specifications. Addenda. Agreement form. Modifications. 10

Quantity Development Guidelines Coordinate the quantity takeoff process and plan with the estimator. Include a list of materials in quantity takeoffs. Utilize a process that easily records the quantity Check scales and dimensions on each drawing sheet. Highlight drawing areas where quantities have been determined to ensure all elements is captured but not double counted. 11

Quantity Development Guidelines Consider items that have no material but still require cost, e.g., job office overhead, task setup, training and certifications. Add a certain amount of waste, loss, drop off, or length related to the material purchases for a bulk order. Coordinate with designers if the design appears in error.. 12

Takeoff Sheet & Bill Of Quantities Quantity Takeoff Sheet مقايسات كميات Estimated Quantities Actual Quantities Bill Of Quantities (BOQ) مقايسات أعمال تقديرية مقايسات أعمال فعلية مقايسات تثمينية 13

Quantity Takeoff Sheet Item Item Unit Quantity Length Dimension Width Height Part Subtraction Addition Total 1 2 3 4. 14

Bill Of Quantities Price Notes Item Item Unit Quantity Unit Total 1 2 3 15

Bill of Quantities classification The Bill of Quantities is classified into the following work groups: Civil works Sanitary works Electrical works Mechanical works 16

Bill of Quantities classification Civil works: Earth works: leveling, excavation, backfilling, transportation of excavated soil) Foundation works: plain concrete reinforced concrete piling foundations 17

Bill of Quantities classification Civil works: Brick works: Internal brick work External brick work Skelton reinforce concrete: Columns, Beans, Slabs Stairs 18

Bill of Quantities classification Civil works: Finishing: Water proofing Staircases Plastering Flooring Painting Metal works: Windows Doors Accessories 19

Bill of Quantities classification Sanitary works: Water feeding systems Internal and external plumbing works Finishes of plumbing works Electrical works: Electrical cables Wiring; Accessories Internal connections Mechanical works: Air conditioning systems Elevators 20

Work order Items in takeoff sheets are organized in the same construction sequence. Order of items in the same chapter: Items estimated in (m3) Items estimated in (m2) Items estimated in (m) Items estimated in (unit) Items estimated in (ton) Items estimated in (L.S.) 21

Measuring Units The units of measurements for civil engineering works are mainly categorized for their: Nature Shape Size and Payments to the contractor. There are a number of standard codes and methods of measurement that are available. 22

Measuring Units Cubic meter (m 3 ) Used for items such as: Excavation Backfilling Concrete Brick walls ( 25 cm thick) Square meter (m2) Used for items such as: Brick walls (<25 cm thick) Plastering Flooring Painting 23

Measuring Units Linear meter (m) Used for items such as: Pipe lines Canals Stair steps Windows sills Number (unit) Used for items such as: Electric outlets Doors and windows Sanitary fixtures Precast concrete 24

Measuring Units Lump sum(l.s.) Item is subcontracted when the contractor does not have enough experience to construct it or there is an item which has a small quantities of many work items such as: Manholes Lifts Some electrical and plumbing works Weight (Ton): Metallic works Reinforcement steel 25

Preparation of Quantity Takeoff Check the availability of drawings Check the axis and dimensions Check building levels and link it to structural drawings. Check doors and windows model numbers Check ground water levels 26

Preparation of Quantity Takeoff Check architectural against structural drawings Check foundation design and foundation levels Check construction members dimension and reinforcement. Review the contract conditions and specifications 27

Formulas Square Rectangle Parallelogram Trapezoid Trapezium 28

Formulas Triangles Regular Polygons Circle Parabola Ellipse 29

Formulas 30

Formulas 31

Formulas 32

Formulas 33

Formulas 34

Formulas 35

Earth works Excavation Quantities are calculated based on the dimensions of the foundation in plans from the owner perspective. Contractors should consider the excess of material excavated to all for safe operations. Prices differ based on the soil type, deep of excavation, ground water level, site location, shoring system, Equipment used, etc. Unit of measurement is cubic meter (volume). Consider the example in the following slide: 36

Earth works Excavation The length of excavation = 5.4 2 + (4.4 2) 2 = 15.6 m Depth of excavation = 1.8 m Width of excavation = width of plain concrete footing = 1.0 m Volume = 15.6 1.8 1.0 = 18.8 m3 37

Earth works Backfilling Unit of measurement is cubic meter (volume) Consider the example shown in previous slide, the volume of backfilling could be calculated as follow: Volume of backfilling = excavation concrete brick Volume of concrete = 15.6 1 0.4 = 6.24 m3 Volume of brick = 15.6 0.4 1.4 = 8.736 m3 Volume of backfilling = 18.8 (6.24 + 8.736) = 3.824 m3 38

Earth works Site leveling & Soil transportation Site leveling: Measured in m2 (area) if thickness < 30cm. Measured in m3 (volume) if thickness > 30cm. Soil transportation: Transported soil = Vol. of exc. Vol. of backfilling + additional soil at site Add swelling factor based on the soil type: 5% sandy soil. 15% clayey soil and 25% for demolition material. (owner or contractor) 39

Concrete works Plain concrete & Reinforced concrete Plain concrete (PC): Measured in m2 (area) if thickness < 20 cm. Measured in m3 (volume) if thickness 20 cm. Average thickness should be mentioned when measurement is done by area. Reinforced concrete (RC): All RC elements measured by volume (m3) except hollow block slabs measured by area (m2). Domes, cylindrical roofs and shells measured by area in the horizontal projection. 40

Concrete works Plain Concrete Footing Quantity of P.C footing = No. of footings for a specific model * length * width * depth Total quantity of P.C footings = summation of P.C footing models RC Footing PC Footing 41

Concrete works Ground Beams Quantity of ground beam = No. of ground beams for a specific model * length * width * depth Total quantity of ground beams = summation of ground beam models Ground Beam RC Footing PC Footing 42

Concrete works Columns Quantity of columns = No. of columns for a specific model * length * width * height Total quantity of columns = summation of columns models Columns RC Footing PC Footing 43

Concrete works Slabs Solid slabs: Quantity of slab = length * width * thickness Flat slab: Quantity of slab = length * width * thickness Beams: Quantity of beam = length * width * height 44

Brick works Measured in m2 (by area) if thickness <25 cm. Measured in m3 (by volume) if thickness 25cm. Deduct all openings. Deduct half the area (volume) of arches. Deduct all Concrete elements. Separate item for each brick type 45

Stairs Quantity of stairs = inclined length * width * height + stair section area * stair width * No. of stairs stair section area 46

Plastering Internal Plaster: Engineering measurement by area (m2). All openings are deducted. All openings sides are added. Inclined slabs are calculated based on their horizontal projection. 47

Plastering External plaster: Measured by area (m2). Openings with areas < 4 m2 are kept with deduction. Deduct half the area of the openings 4 m2. Openings with areas < 4 m2 are kept with deduction. Cantilever slabs < 1 m projection not added. Add half the area of cantilever slabs 1 m. 48

EXAMPLE 1 Substructure Taking-off List Site preparation Removing trees and shrubs Lifting turf Top soil/removing/preserving Excavation Reduce levels/disposal of excavated material Excavating trenches/disposal of excavated Material/Filling/Surface treatments Concrete Foundations Beds/formwork/damp-proof membrane Masonry Brick walls Forming cavities Filling to cavities 49

EXAMPLE 1 Substructure Site levels Top soil cannot be used for backfilling as it would, over time, cause damage to the substructure. The usual default depth for topsoil is 150 mm Next figure is a 5 m grid of a survey of levels taken on a site. The site is required to be reduced to a level of 35.62 and in order to calculate the volume of excavation required the average level of the site must be determined. This can be easily done by weighting the levels as follows starting at the top left-hand corner of the site (35.90) and working from left to right. 50

EXAMPLE 1 Substructure Site levels Level Total Level 35.90 35.90 35.86 2 71.72 35.89 2 71.78 35.92 2 71.84 35.90 2 71.80 35.89 35.89 35 86 2 71.72 35.84 4 143.36 35.88 4 143.52 35.90 4 143.60 35.90 4 143.60 35.86 2 71.72 35.84 35.84 35.85 2 71.70 35.87 2 71.74 35.90 2 71.80 35.88 2 71.76 35.78 35.78 Total 1435.07 Number of Points = 40 Average site level = 1435.07 / 40 = 35.87 Reduced level = 35.62 Average Excavation depth = 35.87-35.62 = 0.25 51

Example 5.6m ع ١ ك ٢ ع ١ 15cm 7ɸ10/m 4.8m ك ١ 7ɸ12/m ك ١ A A ع ١ ك ٢ ع ١ 52

ك Example سفلي عدل و الكانات 6ɸ8/m الغطاء الخرساني 4ɸ16+ علوي 2ɸ16 ٢.٥ سم 0.3m x 0.5m قطاع الكمرات ك ١ ٢ 0.3m x 0.3m 3.0m قطاع العمود ع ١ ارتفاع العمود ع ١ قطاع السمالت 0.3m x 0.5m منسوب األرض الطبيعية 1.2 m القواعد المسلحة 1m x 1m x 0.4m 53 Section A-A القواعد العادية 1.6m x 1.6m x 0.3m

Example It is required to estimate the quantities of the following jobs: (كميات الحفر) Excavation (خرسانة القواعد العادية) Plain Concrete Footings (خرسانة القواعد المسلحة) Reinforced Concrete Footings (خرسانة السمالت) Ground Beams concrete (كميات الردم) Filling (خرسانة األعمدة) Columns concrete (خرسانة البالطة وكمرات السقف) Slab and beams Concrete حديد تسليح البالطة وكمرات ( Reinforcement Slab and beams (السقف 54

Excavation 1.6 m 4.8 m 1.2 m 1.6 m.15 m 5.6 m.15 m 1.6 m 5.3 55 0.8 m 3.7 m

Excavation No. Item Unit Number Length Width Depth Total 1 Excavation m3 4 1.6 1.6 1.2 12.288 2 3.7 0.3 0.5 1.11 2 2.9 0.3 0.5 0.87 56

PC Concrete Footings No. Item Unit Number Length Width Depth Total 2 PC Concrete m3 4 1.6 1.6 0.3 3.072 1.6 m 0.3 m 1.6 m 57

RC Concrete Footings No. Item Unit Number Length Width Depth Total 3 RC Concrete m3 4 1 1 0.4 1.6 1.0 m 0.4 m 1.0 m 58

Ground Beams No. Item Unit Number Length Width Depth Total 4 Ground Beams m3 2 5.3 0.3 0.5 1.59 2 4.5 0.3 0.5 1.35 0.5 m السمالت 4.8 m 4.5 m 0.3 m 0.15 m 5.6 m 5.3 0.15 m 0.3 m 59

Filling No. Item Unit Number Length Width Depth Subtotal Total 1 Excavation m3 14.27 2 PC Concrete m3 3.07 3 RC Concrete m3 1.60 4 Ground Beams m3 2.94 Total Concrete m3 7.61 5 Filling m3 6.66 60

Columns No. Item Unit Number Length Width Depth Total 6 Columns Concrete m3 4 0.3 0.3 3 1.08 3.0 m 3.0 m االعمدة 3.0 m 61

Slab & Beams No. Item Unit Number Length Width Depth Total 7 Slab & Beams m3 2 5.3 0.3 0.5 1.59 2 4.5 0.3 0.5 1.35 1 5 4.2 0.15 3.15 0.15 m 5.0 m 0.5 m 4.2 m 15 cm 4.8 m 4.5 m 0.3 m 62 0.15 m 5.6 m 5.3 0.15 m

Take-off Summary Table No. Item Unit Number Length Width Depth Total 1 Excavation m3 14.27 2 PC Concrete m3 3.07 3 RC Concrete m3 1.60 4 Ground Beams m3 2.94 5 Filling m3 6.66 6 Columns Concrete m3 1.08 7 Slab & Beams m3 6.09 Total Concrete 14.78 63

ك Reinforcement Takeoff 30cm 0.3m x 0.5m 4ɸ16+ علوي 2ɸ16 قطاع الكمرات ك ١ ٢ سفلي عدل و الكانات 6ɸ8/m الغطاء الخرساني ٢.٥ سم 2.5cm 2.5cm 25cm 7ɸ10/m 7ɸ12/m 50cm 45cm 64

Reinforcement Takeoff Unit No. of Length Total Unit Total (kg) bars length Weight Weight 16 upper (beams) 4 4.8 19.2 1.63 31.296 4 5.6 22.4 1.63 36.512 16 lower (beams) 8 4.8 38.4 1.63 62.592 8 5.6 44.8 1.63 73.024 10 long (Slab) 34 5.6 190.4 0.63 119.952 12 short (Slab) 40 4.8 192 0.92 176.640 8 stirrup (beams) 60 1.55 93 0.41 38.130 51 1.55 79.05 0.41 32.411 Total Steel 570.557 65

66 Questions?