INTER PLANT STANDARD STEEL INDUSTRY



Similar documents
Rules for Construction of Overhead and Gantry Cranes (Top Running Bridge, Multiple Girder)

LOAD TEST PROCEDURE. Bridge, Gantry and Jib Cranes & Monorail Systems B001-R05/07

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

Joist. Reinforcement. Draft 12/7/02

INSTRUCTIONS AND PARTS LIST SINGLE GIRDER UNDERHUNG CRANE BRIDGE KITS 1/2 THRU 10 TON HAND GEARED AND MOTOR DRIVEN

Memberships. W.F. Welding & Overhead Cranes Ltd. Since W.F. Welding & Overhead Cranes Ton Overhead Cranes. Jib Cranes.

Hand chain 6,0m 1000kg

TENDER DOCUMENT. NIT No.: WEX/SP/CH/Crane/ Dt BHARAT HEAVY ELECTRICALS LIMITED, HEEP, RANIPUR, HARIDWAR

TOP RUNNING SINGLE GIRDER BRIDGE CRANE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

INSTALLATION. General. Important Note. Design. Transport

The mechanics finish work on time today...

SAFE HANDLING OF PRECAST CONCRETE PRODUCTS

Glossary of Common Crane Ter ms:

SCAFFOLDING RUNWAY SYSTEM

TARIFF CODE and updates standard

Crane Runway Girder. Dr. Ibrahim Fahdah Damascus University.

Installation and Maintenance Manual for SPANCO Freestanding Modular Bridge Cranes & Monorails

Safety Manual For Overhead Crane Operators

ERIKKILA INDUSTRIAL CRANES

Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since.

Safe & Sound Bridge Terminology

CMTI TENDER DOCUMENT FOR 10 TON CRANE. Central Manufacturing Technology Institute Tumkur road, Bangalore

Structural welding is a process by which the parts that are to be connected are heated and

How To Ensure Safety Of Lifting Equipment

Owner s Manual Gantry Cranes

US 51 Ohio River Bridge Engineering and Environmental Study


Engineered Material Handling. Overhead Bridge Cranes and Gantry Cranes

SPECIFICATIONS FOR TENDER NO: PSNR/SCP/VKS/E 1635 ANNEXURE I TECHNICAL SPECIFICATIONS FOR LIGHTING HIGH MAST

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

1. Lay out 2 pieces of 7/8" tubing and mark for bending as shown. Remember that the bend is in the shaded area as shown below in Figure 1.

Bolt-on castor set B

SECTION WINDOW WASHING SYSTEMS

Operator Training Questionnaire

DESIGN PROCEDURE JOINT CONFIGURATION

I BEAM TRACK INSTALLATION

SERIES NG 1800 STRUCTURAL STEELWORK

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

MODEL HSR-007 Direct Drive Rolling Steel

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

WARNING! Failure to follow these inspection procedures can cause personal injury and property damage.

\ srl High Technology Gear Reducers and Cardan Shafts CERTIFIED QUALITY SYSTEM: UNI ISO EN 9001:2008 ICIM 2779/2; IQNET N. IT UNIVERSAL SHAFT

Properly Install, Inspect, and Load Test Overhead Patient/Resident Track Lifts

10 TON HYDRAULIC PRESS

Pressure vessel basics for all engineers

Guidance on Load Testing Suspended Access Equipment

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT

ENGLISH FORK GUIDE 2013

TANK FABRICATION. Automated Solutions for Your Tank Fabrication Project. Bug-o Systems

TECHNICAL SPECIFICATION FOR PROJECTION WELDING MACHINE (Qty. 2 Nos.)

STANDARD PRACTICE INSTRUCTION

These Installation Instructions are valid for antennas in the following version:

Statutory Inspection, Examination and/or Testing of Specified Equipment:

TELESCOPE Motorized Lighting Suspension

EMH, Inc. Specifications for

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

Overhang Bracket Loading. Deck Issues: Design Perspective

SCAFFOLDING PRODUCT TECHNICAL GUIDE. Scaffold Couplers General Technical and Application Manual. Genuine Safety. Outstanding Service.

Structural Failures Cost Lives and Time

ABOUT CWB CERTIFICATION/ QUALIFICATION The work CWB does on behalf of our clients can be divided into five main categories:

7. PRINCIPAL STEPS 8. POTENTIAL HAZARDS 9. RECOMMENDED CONTROLS

Most Asked Action Alerts

Procedures for Inspection, Maintenance, Repair, and Remanufacture of Drilling Equipment

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013

V1504 Vertical Platform Lift OWNER S MANUAL

SLAB DESIGN. Introduction ACI318 Code provides two design procedures for slab systems:

Slings, Rigging and Lifting Equipment

INSTRUCTIONS THOROUGHLY BEFORE BEGINNING***************

PLM series Permanent load lifting magnets

FIELD ACCEPTANCE OF FIELD WELDING GUIDE

WE-350 Series ¼ Turn Electric Actuator

Drew University Ladder Safety Program Policy and Inspection Procedure Draft 0412

METHOD OF STATEMENT FOR STATIC LOADING TEST

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

ATS Overhead Table Shelf System INSTRUCTION MANUAL

CHAPTER 13 LOAD HOOKS

1.1 DIMENSIONS AND WEIGHT PAG LOAD CENTRE FOR LIFTING PAG STORAGE CONDITIONS PAG. 2

Section A. GENERAL INFORMATION

Course available 24/7 for up to six months from the date of purchase or until completion

SECTION BRIDGE CRANES

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

Hamilton Form Company, Ltd Custom Designs, Flexible Solutions

Manufacturing & Servicing Capabilities

BEST PRACTICES TOWARDS ENERGY EFFECIENCY. UltraTech Cement Limited. (Unit -Kotputli Cement Works)

P.A.L. S SPECIFICATIONS

Specification. Safelift Overhead Travelling Cranes

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar

SECTION SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS

STANDARD SPECIFICATION FOR STORAGE TANKS

ATLANTA MODEL SPECIFICATIONS

Whitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada

AIR-SUSPENSION. Art. nr.: L.L C.M. Auxiliary Air Suspension. Designed for: Mitsubishi L200. From: 2007& UP RDW 71/

A: SIGNIFICANT RISKS Initial Risk Rating H/M/L B: KEY CONTROL MEASURES ACTION

ABR Brake Rectifier Instruction Manual

INTERNATIONAL LABOUR ORGANISATION. REGISTER OF LIFTING APPLIANCES and ITEMS OF LOOSE GEAR

HPC500 Series Top Running and Underhung End Trucks

TLILIC3003A Licence to operate a bridge and gantry crane

Examining rails in detail. Rail inspection: Rail testing Rail measurement Welding monitoring and vehicle testing Consulting

Architectural Specifications MODEL HDXL Fairview Road, Unit #2, Barrie, Ontario L4N 8Z8

Transcription:

INTER PLANT STANDARD STEEL INDUSTRY CODE OF PRACTICE FOR REVAMPING OF EOT CRANES IPSS:3-02-014-03 IPSS Corresponding IS does not exist 0. FOREWORD 0.1 This Inter Plant Standard has been prepared by the Standards Committee on Operation & Maintenance, IPSS 3:2 with the active participation of the representatives of steel plants and was adopted in April 2003. 0.2 Inter Plant Standardization for steel industry primarily aims at achieving rationalisation and standardization of procedure. For effective control it is advisable to follow strictly the procedure mentioned in the standard and not to make any deviations as per convenience. 0.3 This standard is intended to provide the criteria for selection of crane for revamping and standard revamping procedure. 1. SCOPE 1.1 This Inter Plant Standard deals with general purpose double box type bridge girder EOT cranes and is divided into two parts. Part A : Covers procedure for selection of crane for revamping and Part B : Covers the standard practice for crane revamping. 1.2 The application of this standard requires (i) Visual inspection of crane structure condition. (ii) Measurement of camber & bowing of bridge girders. (iii) Measurement of plate thickness of critical structural members. (iv) Measurement of vibration level of cabin, bridge girder. (v) Study of records of inspection of important structural member and repair done earlier. 1.3 Based on above study, the condition of crane structures are categorised in the following categories. Category 3 Category 2 General defects in structure. e.g. cracks in weld, failure of weld joints. ------ Recommendation - In situ repair. Major structural defects in the crane structures. e.g. cracks & distortion of structures of End girder, trolley, failure of bridge girder, End girder joints and LT wheel bracket failure. ------ Recommendation - Revamping of crane. Page 1/6

Category 1 IPSS:3-02-014-03 Serious defects in crane structures. e.g. cracks perpendicular to line of stress in Bridge girders which are fatigue cracks and serious sources of danger. Buckling of compression member of girder (top flange) due to over stress resulting in short wave kink in the flange. ------ Recommendation - Revamping along with replacement of the bridge girder. 1.4 This standard does not cover new cranes under construction / yet to be commissioned since they are governed by respective clauses of design / statutory code / indent specification. 2. REVAMPING a) Revamping implies process of giving new lease of life to the crane which cannot be revitalized by normal periodic repair. b) Normal periodic repair / capital repair are done in-situ whereas during revamping the crane is taken out of circuit normally by lowering and the job is done in Engineering Shop / suitable place and original geometry of the equipment is restored back within norms. c) Revamping of crane is done when repeated structural repair does not improve condition of crane structures. d) While structural revamping of crane is being carried out, all mechanical and electrical defects shall also be attended to. e) Modification like conversion of angle trolley line to Festoon cable system for ATL (Auxiliary Trolley Line). Extension of girder platform to facilitate layout of panels, etc for ease maintenance shall be taken up during revamping. f) Modifications are also carried out to enhance the performance and maintainability of the crane. g) Revamping cost advantage : Cost advantage = (CN / LN CR / LR) x LR Where CR = Cost of revamped equipment in Rs. LR = Life of revamped equipment in years. (Generally 70% of LN) CN = cost of new equipment in Rs. LN = life of new equipment in years. Page 2/6

IPSS:3-02-014-03 PART A CRITERIA FOR SELECTION OF CRANE FOR REVAMPING : Following criterias are applied for selection of crane for revamping : a) Frequency of failure and downtime of crane : Crane shall be taken for revamping : When the availability of particular crane comes down to 50 to 60% of availability of the similar type of crane; Repeated repairs do not improve the availability of the crane Frequent LT /CT wheel changing is happening due to structural deformation. b) Designed life of crane structures : As per IS 4137-1985, given below : Running time in a year Total designed life of crane Class-I 1000 hours 30 years Class-II 2000 to 3000 hours 30 years Class-III Over 3000 hours 20 years Class-IV Over 4000 hours 20 years When a crane has worked for its designed life in its class, it shall be taken up for revamping. c) Deflection of Bridge girder When the deflection of Bridge girder exceeds 1/900 of span by applying safe working load with trolley in the centre without taking impact factor into consideration, crane shall be taken up for revamping. d) Camber in Bridge girder For new Bridge girder, camber is kept at 1 mm / metre of span, and negative camber shall not be allowed. If any crane has developed negative camber, crane shall be put down for revamping. However, based on practical experience for negative camber upto 12 mm in bridge span of more than 20 mtr, the packing plate can be provided below the trolley / CT rails. e) Bowing of girder Bowing of girder shall be limited to span/2000 mm as per IPSS:2-02-002-01 (first revision). If bowing is between 20-40 mm for any Bridge girder, the crane shall be put down for revamping and girders shall be interchanged by providing platform at the other face of the girder. For bowing more than 40 mm, girder shall be replaced. Page 3/6

IPSS:3-02-014-03 f) Cracks in Bridge Girder structures If Bridge Girder is developing cracks, crane shall be lowered and girder shall be changed. g) Failure of Bridge an End girder connections h) Condition of trolley structure When the condition of the trolley structure does not improve even after having regular maintenance/repair, trolley shall be replaced. i) Condition of equipment foundations. j) Modifications in Mechanical & Electrical systems for improvement in the performance and maintainability of the crane. k) Electrical failure in panels or cable faults caused by long usage of the crane. PART B STANDARD REVAMPING PRACTICES FOR DOUBLE BOX TYPE BRIDGE GIRDER EOT CRANE Standard steps of revamping procedure are as follows : A) PREPARATION OF DETAILED DEFECT LIST Detailed defect list is to be prepared under following heads Structural, Mechanical, Electrical : I) STRUCTURAL : Repair, replacement, modification of the following : a) Bridge girder b) End girder c) Trolley d) Operator s cabin e) Side platform f) Electrical structures like bus bar, etc II) MECHANICAL : Repair, overhauling, replacement of the following : a) Hoist reducer b) Hoist drum c) Bridge reducer d) Trolley reducer e) Bridge wheels f) Trolley wheels Page 4/6

g) Trolley rails h) Alignment of equipment i) Brake assembly j) Pulleys & buffer etc. IPSS:3-02-014-03 III) ELECTRICAL : Repair, revisioning, replacement, modification of electrical equipment / accessories of the following : a) Motors b) Panels c) Resistance boxes d) Cables e) Limit switches f) Lights g) Bus bar/trailing cable h) Controllers B) PREPARATION OF DRAWINGS Drawings shall be done as per requirement of defect list. For any modification or any improvement, detailed designing shall be done and drawing shall be prepared. Important improvement during revamping are changing of Bridge and End girder side connection to overriding design, change in plateform size to accommodate Festoon cable system, change in operator s cabin for operator comfort / better visibility, L-type foundation for bridge drive. C) DISMANTLING OF CRANES a) After shut down, all major parts - motor, trolley, operator cabin, etc shall be dismantled. b) By cutting End girder at suitable place, girder shall be lowered with the help of mobile/rail crane. c) Bridge girder shall be shifted to suitable place for revamping jobs. D) ACTIVITIES DURING CRANE REVAMPING a) Damaged ends portion of Bridge girder shall be cut by gas cutting b) New fabricated bridge portion shall be aligned with old bridge girder c) Wheel shall be aligned in new fabricated End girder d) End girder shall be placed over elevated bridge rail kept over 600 I-beam e) End girder shall be levelled, aligned and kept at designed span of the crane f) Bridge girder shall be placed over the End girders g) Crane control assembly shall be surveyed and made as per IPSS:2-02-002-01 Deviations in important parameters are : Wheel base + 6 mm Wheel span + 6 mm upto 40 metre Wheel diagonal + 5 bridge ( + 3 mm trolley) Wheel vertical deviation + 1 mm in 1000 wheel dia. Wheel skew deviation + 1 mm in 1000 wheel dia. Trolley rail level difference + 4 mm for 2.5 metre trolley gauge. Page 5/6

IPSS:3-02-014-03 h) Erection of trolley rails and its alignment i) Welding of bridge piece shall be done by low hydrogen MS electrode, after providing back-up strip in the joint. Weld joint in a girder shall be kept staggered. Tested Welders shall be engaged. Weld quality shall be tested by DP test and ultrasonically. j) Old plateforms shall be rectified or new plateforms shall be erected. Bridge reducers shall be erected and aligned. k) Panels, pipes, conduits and trailing cable structure parts shall be erected over platform. l) Trolley : All equipment shall be overhauled and erected after repair of equipment foundations. m) Operator s cabin : All controllers shall be erected and conduiting/cabling shall be done. E) ERECTION OF CRANE a) Erection of End girder on LT rails and arresting them suitably. b) Erection of first bridge over End girder. c) Move one bridge and two End girders assembly away to make space for erection of second bridge girder. d) Lift second girders, bring earlier assembly below the lifted girder and lower second girder. e) Check dimensions by survey, connect End girder and Bridge girder joint firmly. f) Erect trolley and operator s cabin g) Fixing of hoist rope and pulley blocks h) Piping, conduiting, cabling and other electrical jobs. F) LOAD TESTING & COMMISSIONING OF CRANE (Ref. IPSS:2-02-008-97) a) Check control and power circuit, set all limit switches. b) Record no-load and load current of all mechanisms. c) Check bridge girder deflection at the middle at rated load. d) Check for permanent set of Bridge girder at 125% of rated load. e) Record hoisting and lowering speed of hook, bridge travel and trolley travel speed at a rated load. f) Check all limit switches. G) PAINTING AND HANDING OVER OF CRANE Back Crane shall be painted as per IPSS:1-07-064-03. All reports of survey of control assembly, load test and ultrasonic weld test are compiled and handed over to the user department at the time of handing over of the Crane. Page 6/6