SECTION BRIDGE CRANES

Size: px
Start display at page:

Download "SECTION 14 6300 BRIDGE CRANES"

Transcription

1 PART 1 GENERAL 1.01 SECTION INCLUDES SECTION A. CMAA Class C bridge crane complete system including runway beams, ASCE rails, bridge beam, end trucks, hoist, trolley, runway support columns and operating system. B. Materials and labor for complete installation. C. Sequencing and coordination of work with other disciplines RELATED SECTIONS 1.03 REFERENCES A. CMAA No Crane Manufacturers Association of America. B. ASME Crane Standards, B30 Series. C. ASME HST , "Performance Standard for Overhead Electric Wire Rope Hoists". D. NEMA - National Electric Manufacturers Association. E. NEC - National Electrical Code. F. OSHA - Occupational Safety and Health Administration. G. HMI - Hoist Manufacturers Institute. H. AISC - American Institute of Steel Construction. I. AWS - American Welding Society SYSTEM DESCRIPTION A. One bridge crane with the following features: 1. Single-girder, top running, dual motor ton capacity '-3" span with 0'-6" +/- overhangs /25 fpm +/- dual-speed bridge [100 fpm +/- VFD bridge]. 5. C-track power festoon. 6. (2) push button remote controls with key switch shutoff, and back up pendant control on hoist. 7. Five-ton electric wire rope hoist. a. 18'-0" +/- available lift with 20/3.3 fpm +/- 2-speed lift operation. b. Motor driven trolley with 65 fpm w/ VFD. 8. Top of crane runway ASCE rail to top of bridge not to exceed 1'-5" 9. Top of bridge to throat of hook to be approximately 3'-0" bar enclosed mainline electrification for runway. a. Includes: conductor bars, power feeds, mounting brackets, hangers, end caps, and connecting tool. 11. Runway beams. a. Includes: channel cap (if required), splice plates, end stops and attachment hardware. b. Runway beams for 36 foot foot, continuous bay lengths. See plan for runway support information 12. Runway Columns: a. Columns at grids 1C, 1,d 3D, 5D and 7D b. Attachment of columns to existring concrete piers. B. Installation, mechanical and electrical hookup of above equipment. LHB Project No

2 1.05 DESIGN REQUIREMENTS A. Runway monorail beams, complete with connections to the building structural system, and any required splices shall be designed, supplied, and erected by the Contractor as shown in the drawings. Runway beam design including sizing and all connections shall be per CMAA standards. B. All equipment furnished under this section shall comply in all respects with the requirements of OSHA, the standards of the Crane Manufacturer's Association of America (CMAA) and the Hoist Manufacturer's Institute (HMI) SUBMITTALS A. See Section Administrative Requirements, for submittal procedures. B. Product Data: Provide Manufacturer's catalog data confirming rated capacity, equipment speeds, horsepower electrical requirements, and component sizes and dimensions. C. Shop Drawings 1. Each submittal shall be complete in all respects, incorporating all information and data listed herein and all additional information required for evaluation of the proposed equipment's compliance with the Contract Documents. Partial, incomplete or illegible submissions will be returned to the Contractor without review for resubmission. 2. Shop drawings shall include but not be limited to: a. Equipment specifications and data sheets identifying all materials used and methods of fabrication. b. Complete assembly, layout and installation drawings with clearly marked dimensions. c. Manufacturer's installation and startup instructions. d. Weights of all component parts, assembled weight of units and approximate total shipping weight. e. Example equipment nameplate data sheet. f. Interconnecting ladder-type wiring diagrams for power and control wiring required for final connections. Clearly differentiate between portions of wiring that are factory installed and portions to be field installed. g. List of recommended spare parts. h. Voltage (120V or 208V), phase (1 or 3), load (in amperes, watts, or hp), and maximum overcurrent protection rating (in amperes for either a circuit breaker or fused switch) of each electrical supply connection. D. Certificates: Certify that products of this section meet or exceed specified requirements. Provide factory test certificates. E. Calculations: Provide calculations for bridge and runway beams by Engineer licensed in the state which the project is located. F. Factory testing and inspection certificates. G. Operation and maintenance manuals. H. Manufacturer's instructions. I. Installation, testing and commissioning certificates. J. List of manufacturers and model numbers. K. Special tools list. L. List with a minimum of four manufacturers' standard lubricants, which may be used interchangeably for each type of lubricant required. M. Warranty: Submit manufacturer warranty and ensure that forms have been completed in Owner's name and registered with manufacturer QUALITY ASSURANCE A. Manufacturer shall be regularly engaged in the business of designing, building, and repairing bridge cranes of the type specified in this Section. All bridge crane components and LHB Project No

3 appurtenances furnished for this contract shall be designed, coordinated, and supplied by a single supplier. The Contractor shall be responsible for ensuring the proper components are incorporated in the package and that the requirements of other specification sections are satisfied. B. Products Requiring Electrical Connection: Listed and classified by UL as suitable for the purpose specified and indicated DELIVERY, STORAGE, AND PROTECTION A. Units shall be packaged, shipped and stored in such a way as to prevent rust or damage PROJECT CONDITIONS A. Sequence installation to ensure utility connections are achieved in an orderly and expeditious manner WARRANTY A. See Section Closeout Submittals, for additional warranty requirements. B. Correct defective Work within a one year period after Date of Substantial Completion. C. Provide five year manufacturer warranty for the complete system, including accessories and components. Each component shall be warranted by the manufacturer having unit responsibility. PART 2 PRODUCTS 2.01 MANUFACTURERS A. Shaw-Box, Detroit Crane and Hoist, Columbus McKinnon Corporation, Harrington, R&M, or equal, modified to provide the specified features and to satisfy the specified operating conditions. B. Substitutions: See Section Product Requirements MATERIALS A. Runway beams: ASTM A992 Grade 50 or ASTM A572 Grade 50. B. Bridge beam: ASTM A992 Grade 50 or ASTM A572 Grade 50. C. Wire rope: Extra flexible plow steel cable for crane service COMPONENTS A. Crane Bridge: 1. The crane shall be assembled and tested at the point of manufacture prior to shipment and disassembled only to the extent required to facilitate shipment and installation. 2. The rated capacity of the crane shall be the load that the crane is designed to carry as specified by the manufacturer and shown in tons on large capacity plates located on each side of the crane bridge. 3. Materials shall be free from all defects and imperfections that may affect the finished product. All parts shall be new and unused. 4. End trucks shall be fabricated from structural steel shapes and plates welded into an integral unit and in-line bored to receive the wheel axles. 5. The bridge shall be designed and fabricated as a complete integral structure with only such parts removable as required to facilitate the erection and maintenance of equipment. 6. The bridge girder shall be constructed of standard structural shapes or boxed sections, reinforced and welded as required. Connections between the girder and end trucks can be either welded or bolted after installation and squaring. 7. The end trucks shall have a minimum wheel base of 1/8 of the crane's span. Each truck will be carried on two (2) wheels running on anti-friction bearings. Wheels shall be of machined, hardened steel, double-flanged and capable of running on ASCE runway rails. The end trucks will be provided with rubber bumpers at each end to engage end stops on the crane runway. LHB Project No

4 B. Bridge Drive: The crane bridge shall be driven by two drives. One located on and driving one pair of wheels on each end truck. Each drive shall consist of a drive gear reducer, a TENV, crane duty, 30-minute rated motor with class F insulation and means of braking to meet the requirements of OSHA. C. Bridge Control Panel: 1. The bridge motions control shall be located in a bridge-mounted NEMA 4 enclosure. The bridge control is to be provided with a mainline contactor controlled from the bridge control station and a door-mounted disconnect that turns off power to the bridge panel and drives and the hoist and trolley panel and drives before the panel door can be opened. 2. The control shall be designed and built per the National Electric Code (NEC) standards with color-coded and match-marked wires. The panel shall also meet appropriate UL standards. D. Crane Motion Control: 1. All motions of the crane (hoist, trolley and bridge) shall be operated through a single cable suspended pendant pushbutton type control. The pendant shall have two buttons for the control of each motion plus power on/off buttons: a. Hoist - up/down. b. Trolley - left/right. c. Bridge - forward/reverse. d. Power - on/off. 2. The pendant shall be suspended from a festoon cable pendant track system running the length of the bridge. 3. Pushbutton station shall be of molded contour grip type and supported from the hoist by strain relief cable to avoid damage from pull on the control wires. The enclosure is to be NEMA 12. Controls pendant shall be 115 volt AC, supported by a strain cable. Pendant shall hang to a point 1067 mm (3'-6") above the operating floor elevation as shown on the drawings. The pushbuttons shall return to the off position when the operator releases the pressure. The magnetic contactors for all motions shall be mechanically or electrically interlocked. Control voltage at the pushbutton stations shall be grounded to the hoists. E. Crane Bridge Electrification: 1. Power and control voltage will be provided to the moving trolley and hoist through means of a festoon flat cable system. There will be separate cables for the motor power supply (line voltage) and control and these cables will be provided with separate connecting fittings and plugs. The cable connecting fittings and plugs shall be of the type easily repairable or modified in the field without special tools. The power and control cables will be carried from trolleys with four (4) steel wheels running in a track suspended off the bridge girder running the full length of the crane span. 2. The bridge will be provided with a main power pick-up (collector pole) and sliding shoe collectors that will contact and run in the shielded bar runway conductor system. F. Crane Runway System: 1. Runway beams shall be provided and attached to the building framing system as noted on the drawings. The beams shall be capped or uncapped as required to achieve maximum hook lift and to handle the crane's loading (Equivalent Center Loading, ECL) at full capacity load and closest hook approach possible. The ends of the runway beams are to be jointed together by means of bolted splices. 2. Runway power electrification shall be provided running the full length on one side of the runway. The electrification shall be of the shielded bar type supported at proper intervals to prevent sag or excessive vibration and with power feeds located to minimize voltage drop so as to provide adequate power to operate at least the hoist and one traverse motion at the extreme ends of the runway. G. Electric Wire Rope Hoist: 1. Wire rope hoist shall meet the requirements of ASME B30.16 "Overhead Hoists". Hoist shall be heavy duty meeting H4 Service classification as defined in ANSI/ASME HST-4M LHB Project No

5 "Performance Standard for Overhead Electric Wire Rope Hoists". Hoist shall meet the following requirements: a. Frame shall be fabricated from rolled steel to form a one-piece weldment. b. Gear case is to be machined aluminum alloy casting with sealed construction allowing the gears and load brake to operate in a bath of oil. c. Bearings shall be high quality anti-friction type of either needle or ball design and used throughout the hoist. Bearings not considered lifetime lubricated by the manufacturer, shall be provided with a means for lubrication. d. Hoist brakes: DC electrical multiple disc motor brake spring set electrically released, or self-adjusting Weston type mechanical load brake located in the gear case. Brakes shall have the capability of holding rated load in the event of failure of either brake system. e. Overload devices shall be provided to prevent lifting excessive overloads. This load-limiting device shall be preset at the factory to disengage the hoist motor form the gearing in event of excessive overload condition. Overload device is to be located between the motor and load brake, so that the load brake will hold the load in event of overload device failure. f. Motors shall be of high starting torque type designed specifically for hoist duty services with permanently lubricated ball bearings, rated for 30-minute duty cycle. The motor enclosure is to be totally enclosed non-ventilated, TENV. Motor insulation shall be class F minimum. If hoist is to be two-speed, it shall have a high speed to low speed ratio of 3:1 or 6:1. Motor is to have automatic reset temperature actuated switch (TAS) in motor windings to provide motor running over current protection. g. Gearing shall be a combination of spur and/or helical, precision cut and heat treated to ensure quiet, efficient operation. Gears shall be totally enclosed and run in a bath of oil to provide maximum lubrication. Gears are either splined or keyed to shafts. h. Deep grooved, large diameter rope drum that helps prevent over wrap of cable for longer rope life. i. The diameter of the rope drum shall not be less than 18 times the diameter of hoisting cable, running sheaves not less than 16 times, and idler sheaves not less than 12 times the diameter. Hoisting cable shall be 6x37 improved plow steel. j. Geared upper and lower limit switch shall be provided that allows the upper and lower limits to be set to accommodate the application. k. Controls to be centralized and designed per NEC standards and housed in a panel with a hinged door. The controls are to be provided with a step-down transformer within the panel that provides 120 volts power to the control circuits. Control circuit voltage to push the button station shall not exceed 120 volts. In addition, the panel shall meet appropriate UL standards. l. All controls, including power transformer, shall be housed in a NEMA 1 enclosure mounted in an easily accessible location on the hoist. Controls shall include trolley travel and hoist raising and lowering. Motors shall be fully enclosed 30-minute duty cycle motors in a NEMA frame rated for 208 volts, 3-phase, 60 Hz power supply. m. Motor driven trolleys shall have heavy section rolled steel side frames. The wheels shall be steel with heat-treated tread. Motor driven trolleys shall have totally enclosed non-ventilated (TENV) motors with right angle gear reducers. Trolley wheel gears and pinions shall have machined cut gear teeth. Spacer washers shall be provided for trolley adjustments to various beam sizes. H. Electrical: 1. Furnish and install all wiring and controls from the wall-mounted disconnect switch. 2. The sizing and selection of electric crane motors shall be the responsibility of the crane manufacturer in order to ensure complete coordination of components and to provide unit responsibility. 3. Any reference to motor size or power requirements for the crane motors contained in the Contract Documents is preliminary and shall not be relied on by the Contractor. The Contractor shall be responsible for any changes to the electrical system that may result LHB Project No

6 from final sizing and selection of the crane motors by the crane manufacturer at no additional cost to the Owner. 4. All motors shall be furnished and installed under this Section. All motors shall be of the standard efficiency totally enclosed non-ventilated squirrel cage type for 208 volts, 3-phase, 60 Hz. All motors shall be of ample size and construction to carry continuously all loads which may be imposed through their full range of operation. The maximum motor loading shall not exceed the nameplate horsepower rating, exclusive of service factor. Motor horsepower is to be determined by the crane supplier. All motors shall operate at speeds not greater than described herein. 5. Furnish and install all motors and drives specified in this Section. The Contractor shall also furnish all necessary wiring diagrams and instructions for proper wiring of equipment. I. Spare Parts and Special Tools: Spare parts and any special tools required for disassembly or maintenance shall be provided. One complete set of manufacturer's standard spare parts for each component size shall be provided SHOP FINISHING A. Except for touchup, all painting shall be done in the shop. The crane and runway beams shall be primed and finish coated in accordance with Section Paints and Coatings SOURCE QUALITY CONTROL AND TESTS A. Fabrication Tolerances: Per CMMA requirements. B. Factory tests shall be performed by the manufacturer prior to delivery in order to verify the accuracy and performance of the systems specified. The manufacturer shall certify and provide copies of the tests and warranty the equipment's performance specified in this Section. All certifications of factory tests shall be submitted to and reviewed by the Owner before the equipment is shipped. PART 3 EXECUTION 3.01 EXAMINATION A. The Contractor is advised to carefully examine the drawings prior to bidding to make an evaluation of interferences and obstructions that might impose additional limitations upon the equipment INSTALLATION A. The Contractor shall install the complete systems in the general arrangement and where shown on the drawings and as specified. The Contractor shall install and test each complete system and each system component in strict conformance with the manufacturer's written recommendations. Installation shall be performed by mechanics skilled in work of this kind. The equipment shall be checked, aligned, and approved for start-up by the manufacturer's factory trained representatives. Each system component shall be reviewed and approved by the applicable manufacturer prior to start-up of the complete system. The manufacture having unit responsibility shall arrange and coordinate such reviews between component manufacturers and the Contractor ERECTION TOLERANCES A. Erection tolerances shall meet the requirements of the manufacturer and all referenced standards FIELD QUALITY CONTROL A. The Contractor shall arrange and schedule testing and commissioning with the Owner. B. After completion of installation, the bridge crane, trolley and hoist shall be completely tested to ensure compliance with the performance requirements as specified. As a minimum, testing shall be by operating the equipment through a complete lift and lowering cycle and through a complete travel of the bridge and runway or monorail beams to determine that the equipment performs smoothly and safely without failure. Such tests shall be carried out with the hoisting equipment loaded at 125 percent of specified capacity. After load testing, the overload limit LHB Project No

7 switch is to be reset at the rated load. Any defects shall be corrected or replaced immediately by the Contractor at no expense to the Owner. All testing and the costs of all required certification shall be at the Contractor's expense STARTING EQUIPMENT AND SYSTEMS A. The Contractor shall include in the Contractor's bid all costs associated with providing the services of the Manufacturer's field representative for checking, aligning, testing placing in operation, and Owner Training. B. The Contractor shall not use cranes or hoists to perform any of the Work for this Contract without prior written authorization by the Owner. Any use of cranes or hoists by the Contractor shall be at the Contractor's risk. Any damage done to cranes or hoists by Contractor shall be repaired by Contractor at Contractor's expense CLEANING A. Clean all installed materials, equipment and related areas after final installation. END OF SECTION LHB Project No

TOP RUNNING SINGLE GIRDER BRIDGE CRANE

TOP RUNNING SINGLE GIRDER BRIDGE CRANE SECTION 14630 TOP RUNNING SINGLE GIRDER BRIDGE CRANE 1.01 SUMMARY PART 1- GENERAL A. The work required under this section shall include the designing, manufacturing, shipping, installing and field testing

More information

Glossary of Common Crane Ter ms:

Glossary of Common Crane Ter ms: Glossary of Common Crane Ter ms: 26 Adjustable brakes: Electro-mechanical device to control crane deceleration. Bridge beam: Traveling beam connected to end trucks - supports trolley hoist and load. Bumpers:

More information

EMH, Inc. Specifications for

EMH, Inc. Specifications for EMH, Inc. Specifications for Top Running Cranes Under Running Cranes Wire Rope Hoists DISCLAIMER These SPECIFICATIONS ARE INTENDED AS GENERAL GUIDELINES ONLY for technical procedure. Questions concerning

More information

INSTRUCTIONS AND PARTS LIST SINGLE GIRDER UNDERHUNG CRANE BRIDGE KITS 1/2 THRU 10 TON HAND GEARED AND MOTOR DRIVEN

INSTRUCTIONS AND PARTS LIST SINGLE GIRDER UNDERHUNG CRANE BRIDGE KITS 1/2 THRU 10 TON HAND GEARED AND MOTOR DRIVEN INSTRUCTIONS AND PARTS LIST SINGLE GIRDER UNDERHUNG CRANE BRIDGE KITS 1/2 THRU 10 TON HAND GEARED AND MOTOR DRIVEN JUNE, 1999 COPYRIGHT 1999, Columbus Mckinnon Corporation PART NO. 113533-71 Page 1 COLUMBUS

More information

LOADING DOCK EQUIPMENT. A. Section 03100 - Concrete Forms and Accessories: Placement of anchors into concrete.

LOADING DOCK EQUIPMENT. A. Section 03100 - Concrete Forms and Accessories: Placement of anchors into concrete. LOADING DOCK EQUIPMENT PART 1 GENERAL 1.1 SECTION INCLUDES A. Loading dock equipment of the following types: 1. Dock lifts. 2. Control stations. 1.2 RELATED SECTIONS A. Section 03100 - Concrete Forms and

More information

DESIGN CLARIFICATION (DC)

DESIGN CLARIFICATION (DC) DESIGN CLARIFICATION (DC) Owner: Victor Valley Wastewater Reclamation Authority Date: 03/03/2015 Contractor: W M Lyles Carollo Project No.: 8299A.20 Project Name: Subregional WRPs DC No.: 001 DC Title:

More information

N E R / E R T H R E E P H A S E ELECTRIC C H A I N H O I S T S

N E R / E R T H R E E P H A S E ELECTRIC C H A I N H O I S T S N E R / E R T H R E E P H A S E ELECTRIC C H A I N H O I S T S W o r k i n g H a r d e r F o r Yo u In 1876, Edwin Harrington dramatically improved the self-sustaining hoist by introducing the worm-gear

More information

Architectural Specifications* MODEL HDE

Architectural Specifications* MODEL HDE MODEL HDE 200 Fairview Road, Unit #2, Barrie, Ontario L4N 8Z8 Tel: 866-792-9968 or 705-792-9968 Fax: 705-735-9564 www.tnrdoors.com email: [email protected] TNR Model HDE Tech Specs September 4, 2012 Page

More information

CHESTER HOIST LISBON, OHIO, U.S.A. 44432 PHONE (330) 424-7248 FAX (330) 424-3126

CHESTER HOIST LISBON, OHIO, U.S.A. 44432 PHONE (330) 424-7248 FAX (330) 424-3126 BULLETIN WD-100-06 The only complete line of worm-gear driven hoists, Chester Worm Drive Hoists are available in more than 1200 different models for lifting and moving loads from 1 to 15 tons. They may

More information

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations. DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,

More information

Cleveland Tramrail Bridge Components

Cleveland Tramrail Bridge Components Cleveland Tramrail Bridge Components 1 Tarca Rail Tarca Track features specially rolled high-carbon alloy steel rail with raised treads welded to a steel flange and web. Tarca is designed to provide maximum

More information

Mechanical Installation

Mechanical Installation Page -1-1. INTRODUCTION AND PURPOSE 1.1. This specification covers the installation, testing and precommissioning of mechanical equipment. Work is to be performed in conjunction with the manufacturer s

More information

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches

SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches SUGGESTED SPECIFICATION for Series 185 Service Entrance Rated Automatic Transfer Switches PART 1 GENERAL 1.01 Scope Optional Standby Power Generator Systems A. Furnish and install automatic transfer switches

More information

SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS

SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier by using Tools / Options / View / Hidden Text. On newer versions of Microsoft Word

More information

SPECIFICATIONS FOR TENDER NO: PSNR/SCP/VKS/E 1635 ANNEXURE I TECHNICAL SPECIFICATIONS FOR LIGHTING HIGH MAST

SPECIFICATIONS FOR TENDER NO: PSNR/SCP/VKS/E 1635 ANNEXURE I TECHNICAL SPECIFICATIONS FOR LIGHTING HIGH MAST TECHNICAL SPECIFICATIONS FOR LIGHTING HIGH MAST ANNEXURE I Sl.No. Description for BHEL Requirement Offered Deviation Scope of supply, erection and commissioning: 1 The scope of this specification covers

More information

Pump Specifications 250 Series Submersible Sump / Effluent Pump 2 Solids handling

Pump Specifications 250 Series Submersible Sump / Effluent Pump 2 Solids handling Pump Specifications 250 Series Submersible Sump / Effluent Pump 2 Solids handling 250_P1 R10/7/2015 Copyright 2015 Liberty Pumps Inc. All rights reserved. Specifications subject to change without notice.

More information

Pump Specifications 405 Series Commercial Drain Pump (High-Temp) 2 Solids handling

Pump Specifications 405 Series Commercial Drain Pump (High-Temp) 2 Solids handling Pump Specifications 405 Series Commercial Drain Pump (High-Temp) 2 Solids handling 405_P1 R1/27/2012 Copyright 2012 Liberty Pumps Inc. All rights reserved. Specifications subject to change without notice.

More information

SECTION 26 09 26 LOW VOLTAGE LIGHTING CONTROLS

SECTION 26 09 26 LOW VOLTAGE LIGHTING CONTROLS SECTION 26 09 26 LOW VOLTAGE LIGHTING CONTROLS PART 1 - GENERAL 1.01 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Division 1, "General Requirements", and Section

More information

MODEL HSR-007 Direct Drive Rolling Steel

MODEL HSR-007 Direct Drive Rolling Steel MODEL HSR-007 Direct Drive Rolling Steel 200 Fairview Road, Unit #2, Barrie, Ontario L4N 8Z8 Tel: 866-792-9968 or 705-792-9968 Fax: 705-735-9564 www.tnrdoors.com email: [email protected] Model HSR-007

More information

Specification. Safelift Overhead Travelling Cranes

Specification. Safelift Overhead Travelling Cranes Specification Safelift Overhead Travelling Cranes Safelift overhead travelling cranes are Safelift products, produced by the Rossendale Group, backed by the Safelift Guarantee. GENERAL PRODUCT DESCRIPTION

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

Architectural Specifications MODEL HDXL 9. 200 Fairview Road, Unit #2, Barrie, Ontario L4N 8Z8

Architectural Specifications MODEL HDXL 9. 200 Fairview Road, Unit #2, Barrie, Ontario L4N 8Z8 MODEL HDXL 9 200 Fairview Road, Unit #2, Barrie, Ontario L4N 8Z8 Tel: 866-792-9968 or 705-792-9968 Fax: 705-735-9564 www.tnrdoors.com email: [email protected] Model HDXL 9 Tech Specs September 4, 2012

More information

SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT

SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT PART 1 - GENERAL 1.1 DESCRIPTION A. The Work specified in this Section consists of designing, furnishing and installing factory-assembled

More information

P.A.L. S SPECIFICATIONS

P.A.L. S SPECIFICATIONS PART 1- GENERAL 1.1 SCOPE To furnish all labor, materials and equipment necessary or required to complete the installation of the lift as indicated on the Drawings and Specifications. This specification

More information

INSTALLATION AND MAINTENANCE INSTRUCTIONS FOR THREE PHASE INDUCTION MOTORS

INSTALLATION AND MAINTENANCE INSTRUCTIONS FOR THREE PHASE INDUCTION MOTORS INSTALLATION AND MAINTENANCE INSTRUCTIONS FOR THREE PHASE INDUCTION MOTORS Frames 143T - 449TZ 5100 North IH 35 Round Rock, Texas 78681 Phone: 800-451-8798 512-255-4141 Fax: 512-244-5512 RECEIVING 1. Check

More information

LOAD TEST PROCEDURE. Bridge, Gantry and Jib Cranes & Monorail Systems B001-R05/07

LOAD TEST PROCEDURE. Bridge, Gantry and Jib Cranes & Monorail Systems B001-R05/07 LOAD TEST PROCEDURE Bridge, Gantry and Jib Cranes & Monorail Systems B001-R05/07 Introduction: Load testing and inspection of overhead cranes is required by many safety regulations, national consensus

More information

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES SECTION 26 29 23 VARIABLE FREQUENCY DRIVES PART 1 GENERAL 1.01 SCOPE A. Furnish and install individual freestanding variable frequency AC drives (VFD) as shown on the Drawings and specified herein. 1.02

More information

SEWER CHEWER Wastewater / Sludge Grinder Submersible Gearmotor

SEWER CHEWER Wastewater / Sludge Grinder Submersible Gearmotor INSTALLATION, OPERATION AND MAINTENANCE MANUAL For SEWER CHEWER Wastewater / Sludge Grinder Submersible Gearmotor Yeomans Chicago Corporation 3905 Enterprise Court P.O. Box 6620 Aurora, IL 60598-0620 Phone:

More information

Roped Hydraulic Residential Elevator Specifications

Roped Hydraulic Residential Elevator Specifications January 1, 2004 Roped Hydraulic Residential Elevator Specifications P.O. Box 749, 5191 Stump Rd., Plumsteadville, PA 18949 Toll Free: 888-443-2800, Phone: 215-766-3380, Fax: 215-766-3385 CONTENTS Part

More information

Maxi-Stamper. 200 to 1,000 Tons STAMPING OUT DOWNTIME

Maxi-Stamper. 200 to 1,000 Tons STAMPING OUT DOWNTIME TM Maxi-Stamper 200 to 1,000 Tons STAMPING OUT DOWNTIME Standard Features Steel Fabricated Construction Drive Capacity Rated 1/2 Above Bottom of Stroke Self-Diagnostic Solid State Controller Moveable Operator

More information

Installation Manual Version 7.3 IMPORTANT:

Installation Manual Version 7.3 IMPORTANT: Installation Manual Version 7.3 IMPORTANT: READ ENTIRE MANUAL CAREFULLY, THIS PHASE CONVERTER MUST BE INSTALLED BY A INDUSTRIAL LICENSED ELECTRICIAN 230 VOLTS MODEL ONLY READ FIRST!!!!!! DANGER: HIGH VOLTAGE

More information

26 3213.13 Diesel Engine Driven Generators Page 1 of 6

26 3213.13 Diesel Engine Driven Generators Page 1 of 6 Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at

More information

SECTION 11 78 13 MORTUARY REFRIGERATORS

SECTION 11 78 13 MORTUARY REFRIGERATORS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 11 78 13 MORTUARY REFRIGERATORS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable in

More information

HPC500 Series Top Running and Underhung End Trucks

HPC500 Series Top Running and Underhung End Trucks EFFECTIVE: May 2, 2012 HPC500 Series Top Running and Underhung End Trucks ½ Ton, 1 Ton, and 2 Ton Capacity Code and Serial No. This equipment should not be installed, operated or maintained by any person

More information

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances

More information

ETZGAR CONVEYOR COMPANY Controls Section v12.05

ETZGAR CONVEYOR COMPANY Controls Section v12.05 Section 7 Controls Page Description 7-1 Controls Index 7-2 Motor Data, Enclosure Rating and Abbreviations 7-3 Controls Safety Guidelines 7-4 Fixed Speed Controls Packages 7-5 Three Phase AC Variable Speed

More information

CLEAR-DIVISIONS CENTERFOLD

CLEAR-DIVISIONS CENTERFOLD CLEAR-DIVISIONS CENTERFOLD Introduction: The following three (3) part specification offers the Standard and Optional features for the CLEAR-DIVISIONS CENTERFOLD moveable The yellow highlighted areas in

More information

Rules for Construction of Overhead and Gantry Cranes (Top Running Bridge, Multiple Girder)

Rules for Construction of Overhead and Gantry Cranes (Top Running Bridge, Multiple Girder) ASME NOG-1 2015 (Revision of ASME NOG-1 2010) Rules for Construction of Overhead and Gantry Cranes (Top Running Bridge, Multiple Girder) AN AMERICAN NATIONAL STANDARD ASME NOG-1 2015 (Revision of ASME

More information

James M. Pleasants Company

James M. Pleasants Company James M. Pleasants Company SUBMITTAL DATA GAINESVILLE MECHANICAL DECEMBER 20, 2013 PROJECT: GSU: J-183 HUMANITIES LAW BLDG. QUOTE NO:12116 ENGINEER: STEVENS & WILKINSON GASKETED PLATE HEAT EXCHANGER Tag:

More information

ATS Overhead Table Shelf System INSTRUCTION MANUAL

ATS Overhead Table Shelf System INSTRUCTION MANUAL ATS Overhead Table Shelf System INSTRUCTION MANUAL ATS Overhead Table Shelf System Instruction Manual Warranty Newport Corporation warrants this product to be free of defects in material and workmanship

More information

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. 2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to

More information

Installation and Maintenance Manual for SPANCO Freestanding Modular Bridge Cranes & Monorails

Installation and Maintenance Manual for SPANCO Freestanding Modular Bridge Cranes & Monorails Manual No. 103-0045 REV. 12/08 Installation and Maintenance Manual for SPANCO Freestanding Modular Bridge Cranes & Monorails ISO 9001 REGISTERED 2 TABLE OF CONTENTS Important Dimensions for Modular Bridge

More information

SECTION 11014 WINDOW WASHING SYSTEMS

SECTION 11014 WINDOW WASHING SYSTEMS SECTION 11014 WINDOW WASHING SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section includes, but is not limited to, design and furnishing portable davits, davit sleeves, dvit bases, four (4) removable outriggers,

More information

Memberships. W.F. Welding & Overhead Cranes Ltd. Since 1986. W.F. Welding & Overhead Cranes. 1-200 Ton Overhead Cranes. Jib Cranes.

Memberships. W.F. Welding & Overhead Cranes Ltd. Since 1986. W.F. Welding & Overhead Cranes. 1-200 Ton Overhead Cranes. Jib Cranes. Memberships Canadian Standards Association (CSA) W.F. is approved by the Canadian Welding Bureau and certified to CSA standard W47.1-03-Division 1. Other memberships include: W.F. Welding & Overhead Cranes

More information

Commercial Gas Furnace Upflow

Commercial Gas Furnace Upflow Commercial Gas Furnace Upflow Model G24-200 80% A.F.U.E. 200,000 Btuh Input Heating Cap. 7.5 or 10 Tons Nominal Add-On Cooling GUK FEATURES Certified by A.G.A./C.G.A. Laboratories. Heavy gauge painted

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

I BEAM TRACK INSTALLATION

I BEAM TRACK INSTALLATION PDQ 0/700 FESTOON SYSTEM INSTALLATION AND MAINTENANCE INSTRUCTIONS INTRODUCTION The PDQ Festoon System was designed to run on one of three sizes of I-beams: S x., S8 x 8. and S x.. System trolleys must

More information

RT100 ROUGH TERRAIN CRANE DATASHEET - IMPERIAL. Features:

RT100 ROUGH TERRAIN CRANE DATASHEET - IMPERIAL. Features: ROUGH TERRAIN CRANE DATASHEET - IMPERIAL Features: Rated capacity: 100 ton @ 10 ft working radius Maximum boom length: 174 ft Maximum tip height: 183 ft Maximum hook height: 174.5 ft CONTENTS Key............................................................................................

More information

Safety Manual For Overhead Crane Operators

Safety Manual For Overhead Crane Operators Safety Manual For Overhead Crane Operators Contents Forward ---------------------------------------------------------------1 Qualifications---------------------------------------------------------1 Certification

More information

8500 SERIES POWER & FREE CONVEYORS

8500 SERIES POWER & FREE CONVEYORS 8500 SERIES POWER & FREE CONVEYORS Founded in 1958 in Pickering, Ontario, Allied Conveyors Limited established a reputation as an industry leader in the design, manufacture and installation of premium

More information

Cable/Conduit Conversion

Cable/Conduit Conversion Cable/Conduit Conversion Busway can be used in many applications where cable and conduit are more commonly used. The question arises, Why use busway instead of conventional cable and conduit? Benefits

More information

Display hidden notes to specifier. (Don't know how? Click Here) A. Advanced Upcoiling Security Grilles, power operated.

Display hidden notes to specifier. (Don't know how? Click Here) A. Advanced Upcoiling Security Grilles, power operated. SECTION 08333 ADVANCED UPCOILING SECURITY GRILLE MODEL 600 ADV Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Advanced Upcoiling Security Grilles,

More information

Rating when used as a weight carrying hitch without spring bars:

Rating when used as a weight carrying hitch without spring bars: BOLT-TOGETHER WEIGHT DISTRIBUTING HITCH SYSTEM Rating when used as a weight distributing hitch with spring bars: Part Number 48051 4805 48053 48054 Max Tongue Weight 550 Ibs. 750 Ibs. 1000 Ibs. 1400 lbs.

More information

Vehicle Restraint Installation Manual

Vehicle Restraint Installation Manual Vehicle Restraint Installation Manual SHR-5000 9 Carriage SHR-5000 12 Carriage MADE IN U.S.A. This Manual Covers Restraints Built After Serial Numbers: 4487000001 and up PRINTED IN U.S.A. RITE-HITE PRINT

More information

SWITCHGEAR Section 16. SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less.

SWITCHGEAR Section 16. SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less. PART 1 - GENERAL SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less. RELATED SECTIONS Division 16 Section "Basic Electrical Materials and Methods" for general

More information

INTER PLANT STANDARD STEEL INDUSTRY

INTER PLANT STANDARD STEEL INDUSTRY INTER PLANT STANDARD STEEL INDUSTRY CODE OF PRACTICE FOR REVAMPING OF EOT CRANES IPSS:3-02-014-03 IPSS Corresponding IS does not exist 0. FOREWORD 0.1 This Inter Plant Standard has been prepared by the

More information

2. Division 05 Structural Steel Framing for steel framework requirements

2. Division 05 Structural Steel Framing for steel framework requirements SECTION 131200 - CLIMBING WALLS PART 1 GENERAL 1.1 SUMMARY A. This section includes the following: 1. GFRC Rock Realistic Climbing Wall System B. Related Sections 1. Division 04 Unit Masonry 2. Division

More information

Recirculating Roof Fans Models ESRMD, ESRMDF and ERD

Recirculating Roof Fans Models ESRMD, ESRMDF and ERD Recirculating Roof Fans Models ESRMD, ESRMDF and ERD Four-Way Fan Exhaust Supply Mix Recirculate BUILDING VALUE IN AIR. October 2005 Recirculating Roof Fans Exhaust/Supply/Recirculation/Mix Model ESRMD

More information

THE RIGHT LIFT FOR EVERY STATION

THE RIGHT LIFT FOR EVERY STATION INDUSTRIAL CRANES NUCLEAR CRANES PORT CRANES HEAVY-DUTY LIFT TRUCKS SERVICE MACHINE TOOL SERVICE WORKSTATION LIFTING SYSTEMS WORKSTATION LIFTING SYSTEMS THE RIGHT LIFT FOR EVERY STATION Workstation Lifting

More information

Engineered Material Handling. Overhead Bridge Cranes and Gantry Cranes

Engineered Material Handling. Overhead Bridge Cranes and Gantry Cranes TM Engineered Material Handling Overhead Bridge Overhead and Gantry Bridge Cranes and Gantry Cranes Custom Engineered Crane Systems Gantry Cranes EMH builds a complete range of gantry cranes including

More information

Section M POWER LIFTS

Section M POWER LIFTS Section M POWER LIFTS December 2009 1M Index 1. 53-520244-000 Poly V Idler Assembly 2. 53-520205-000 N.A. Mounting Bracket 3. 53-520212-000 Cable Assembly 4. 53-600149-000 Wire Harness Assembly 5. 53-860322-010

More information

CLEAR-DIVISIONS VARIOFOLD

CLEAR-DIVISIONS VARIOFOLD CLEAR-DIVISIONS VARIOFOLD Introduction: The following three (3) part specification offers the Standard and Optional features for the CLEAR-DIVISIONS VARIOFOLD moveable The yellow highlighted areas in the

More information

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built

More information

TECHNICAL SPECIFICATION FOR PROJECTION WELDING MACHINE (Qty. 2 Nos.)

TECHNICAL SPECIFICATION FOR PROJECTION WELDING MACHINE (Qty. 2 Nos.) TECHNICAL SPECIFICATION FOR PROJECTION WELDING MACHINE (Qty. 2 Nos.) 1. Requirement: Two (02) Nos. DC Type, 3 phase, 3 wire Projection Welding Machine is required for welding of ventilation M.S. / Stainless

More information

Operating Manual. Los Angeles Abrasion Machine HM-70A & HM-70AF

Operating Manual. Los Angeles Abrasion Machine HM-70A & HM-70AF Operating Manual Los Angeles Abrasion Machine HM-70A & HM-70AF Rev: 07/19/2012 PHONE: 800-444-1508 P.O. Box 200, Lewis Center, Ohio 43035-0200 FAX: 800-255-5314 740-548-7298 E-mail: [email protected]

More information

The Contractor shall furnish and install all shielded power cable suitable for use on this project.

The Contractor shall furnish and install all shielded power cable suitable for use on this project. Section 16122 PRIMARY POWER CABLES PART 1 GENERAL: WORK INCLUDED The Contractor shall furnish and install all shielded power cable suitable for use on this project. RELATED WORK Section 16020: Tests SUBMITTALS

More information

DUMP TARP KITS MANUAL TARP KITS ELECTRIC TARP SYSTEMS MECHANICAL CRANK ARM TARP SYSTEMS

DUMP TARP KITS MANUAL TARP KITS ELECTRIC TARP SYSTEMS MECHANICAL CRANK ARM TARP SYSTEMS ELECTRIC TARP & MANUAL SYSTEMS DUMP TARP KITS MECHANICAL CRANK ARM TARP SYSTEMS MANUAL TARP KITS ELECTRIC TARP SYSTEMS MECHANICAL CRANK ARM TARP SYSTEMS MANUAL TARP KITS TRAILER TARP KITS PARTS & ACCESSORIES

More information

Bussmann. All-In-One Module. Bussmann Power Module Switch. How to configure Part Numbers: Step 1: Select Switch Amperage 1

Bussmann. All-In-One Module. Bussmann Power Module Switch. How to configure Part Numbers: Step 1: Select Switch Amperage 1 How to configure Part Numbers: Step : Select Switch Amperage Power Module Switch Rating (Amps) Power Module Switch Catalog No. 30 3 60 6 00 200 2 400 4 Step 2: Select Options Needed 5 Bussmann Power Module

More information

1. Lay out 2 pieces of 7/8" tubing and mark for bending as shown. Remember that the bend is in the shaded area as shown below in Figure 1.

1. Lay out 2 pieces of 7/8 tubing and mark for bending as shown. Remember that the bend is in the shaded area as shown below in Figure 1. MINI BIKE PLANS Page 1 INTRODUCTION Before starting to build your Mini-Bike, be sure that you have all the parts shown on the material list. You will note that tubing has been used in the construction.

More information

Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank

Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank Recommended Product Specifications Fuel Day Tank System Tramont UTRS Fuel Day Tank This specification describes requirements for a Diesel Fuel Day Tank System consisting of one or more fuel tanks, an Electronic

More information

32:(5#5$7,1* 4833#USP283#+] 4;33#USP293#+] 3ULPH 113 kva, 90 kw 124 kva, 99 kw 6WDQGE\ 114 kva, 91 kw 125 kva, 100 kw

32:(5#5$7,1* 4833#USP283#+] 4;33#USP293#+] 3ULPH 113 kva, 90 kw 124 kva, 99 kw 6WDQGE\ 114 kva, 91 kw 125 kva, 100 kw ,1'8675,$/#*(16(7 6HULHV#'9#448 32:(5#5$7,1* 4833#USP283#+] 4;33#USP293#+] 3ULPH 113 kva, 90 kw 124 kva, 99 kw 6WDQGE\ 114 kva, 91 kw 125 kva, 100 kw Generator set consisting of engine and alternator mounted

More information

IRRIGATION PUMPING Table of Contents - Section 900

IRRIGATION PUMPING Table of Contents - Section 900 IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS

More information

MCC Ratings. Voltage Rating

MCC Ratings. Voltage Rating MCC Ratings In addition to the various ratings of individual components used in motor control centers, the overall ratings of the motor control center must also be considered. Voltage Rating Motor control

More information

Work Smart - Not Hard with a Blue Giant Lift Table

Work Smart - Not Hard with a Blue Giant Lift Table Lift Tables Hydraulic Lift Tables Eliminate the need to bend, twist and pick up heavy loads manually. Let BLUE GIANT Lift Tables increase productivity and decrease costly injuries caused by overexertion

More information

8146/5 Series Breaker Panelboards

8146/5 Series Breaker Panelboards 8146/5 Series Breaker Panelboards DISTRIBUTION BREAKER PANELBOARDS FOR HAZARDOUS & CORROSIVE ENVIRONMENTS Breaker Panels Features: Wide variety of Flameproof branch circuit breakers for Zone 1 & Division

More information

TENDER DOCUMENT. NIT No.: WEX/SP/CH/Crane/2012-13 Dt.20.12.2012 BHARAT HEAVY ELECTRICALS LIMITED, HEEP, RANIPUR, HARIDWAR-249403

TENDER DOCUMENT. NIT No.: WEX/SP/CH/Crane/2012-13 Dt.20.12.2012 BHARAT HEAVY ELECTRICALS LIMITED, HEEP, RANIPUR, HARIDWAR-249403 TENDER DOCUMENT Retrofitting of existing 10 MT Chain Wheel Operated Overhead Double Girder Crane by Electric Wire Rope Hoist of 10MT in Compressor House, HEEP, BHEL, Hardwar NIT No.: WEX/SP/CH/Crane/2012-13

More information

CLEAR-DIVISIONS APERTO

CLEAR-DIVISIONS APERTO CLEAR-DIVISIONS Introduction: The following three (3) part specification offers the Standard and Optional features for the CLEAR-DIVISIONS moveable glass wall system. The yellow highlighted areas in the

More information

TABLE OF CONTENTS DT7K INSTRUCTION MANUAL TABLE OF CONTENTS 1-19-00E DT7K

TABLE OF CONTENTS DT7K INSTRUCTION MANUAL TABLE OF CONTENTS 1-19-00E DT7K TABLE OF CONTENTS DT7K INSTRUCTION MANUAL SECTION 100 DESCRIPTION & SPECIFICATIONS 17459 INSTALLATION DIMENSIONS - DT7K 17384 MOUNTING HOLE TEMPLATE S14930 INSTALLATION DRAWING - 14930 MOUNTING PEDESTAL

More information

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation MTE SERIES RLW World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930 2009 MTE Corporation IMPORTANT USER INFORMATION NOTICE MTE Series RLW reactors are components designed to improve the reliability

More information

BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS

BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS PLEASE READ COMPLETE INSTRUCTIONS BEFORE YOU BEGIN LEAVE INSTALLATION INSTRUCTIONS AND USER'S GUIDE WITH OWNER ALL ELECTRIC WIRING AND PLUMBING MUST BE DONE

More information

We will discuss common industrial applications with guides for the proper use of electric motors on these.

We will discuss common industrial applications with guides for the proper use of electric motors on these. INTRODUCTION: Baldor Electric Company has prepared this Specifiers Guide to help you cover all the bases when you are specifying electric motors. It will cover in a generic way most of the subjects which

More information

SELF-STEERING AXLE TABLE OF CONTENTS

SELF-STEERING AXLE TABLE OF CONTENTS SELF-STEERING AXLE TABLE OF CONTENTS Section 1 - Introduction Section 2 - Pre-Installation Check List Section 3 - Ride Height Adjustments Section 4 - Suspension Mount Section 5 - Axle Mount Section 6 -

More information

1.02 SYSTEM DESCRIPTION

1.02 SYSTEM DESCRIPTION 1 OF 7 MODULAR MEZZANINES GUIDE SPECIFICATIONS FOR PART 1 - GENERAL 1.01 RELATED WORK A. SECTION 03 30 00: Cast in Place Concrete (and Concrete Finishing) 1. The area where mezzanine is installed shall

More information

DENVER MODEL 30 X 30 SPECIFICATIONS

DENVER MODEL 30 X 30 SPECIFICATIONS DENVER MODEL 30 X 30 SPECIFICATIONS Dimensions: Roof Dimensions 30-0 x 30-0 (4) Columns (Center to Center) 25-6½ x 25-6½ Minimum Clearance 8-0 Roof Height @ Peak Dependent on Col. Ht. Hip Roof 4:12 pitch

More information

Owner s Manual Gantry Cranes

Owner s Manual Gantry Cranes Owner s Manual Gantry Cranes Fixed Height Gantry Crane MODEL NUMBER: SERIAL NUMBER: CAPACITY IN TONS: Telescoping Gantry Crane Bushman AvonTec 262-790-4200, 800338-7810, Fax 262-790-4200 www.bushmanavontec.com

More information

Ceiling-Mounted Workstation Steel Bridge Crane

Ceiling-Mounted Workstation Steel Bridge Crane SPANCO PRODUCT SPECIFICATIONS 1 Ceiling-Mounted Workstation Steel Bridge Crane This guide can be used to prepare a bid specification for the incorporation of a Ceiling-Mounted Workstation Steel Bridge

More information

INSTALLATION and OPERATION RANGE BALL CONVEYOR MODEL NO: BC-001AN

INSTALLATION and OPERATION RANGE BALL CONVEYOR MODEL NO: BC-001AN Easy Picker Golf Products, Inc. 415 Leonard Blvd. N., Lehigh Acres, FL 33971 PH: 239-368-6600 FAX: 239-369-1579 Service: 800-982-4653 SALES: 800-641-4653 www.easypicker.com [email protected] INSTALLATION

More information

SECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM

SECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM SECTION 13850 (28 31 00) FIRE DETECTION AND ALARM SYSTEM ENGINEERING SPECIFICATION INTELLIGENT REPORTING FIRE DETECTION SYSTEM PART 1 GENERAL 1.1 DESCRIPTION A. This specification includes the furnishing,

More information

Pipe Cutting and Beveling Clamshells

Pipe Cutting and Beveling Clamshells Pipe Cutting and Beveling Clamshells Who We Are One Company, Total Support, Complete Solutions For more than a century, Hydratight has provided world-class bolted joint solutions and continues to set international

More information

Specification Guide. for RVAC. Direct Replacement. AC Medium Voltage. Circuit Breakers

Specification Guide. for RVAC. Direct Replacement. AC Medium Voltage. Circuit Breakers Specification Guide for RVAC Direct Replacement AC Medium Voltage Circuit Breakers Table of Contents 1.0 General Work Scope...3 2.0 Standards...3 3.0 Supplier Qualifications...4 4.0 Circuit Breaker Element

More information

AFE424 SERVICE PARTS

AFE424 SERVICE PARTS This is the parts list for the AFE. When looking up part numbers, always check the complete model and serial numbers to be certain of ordering the correct parts. The Air Cooled model has also been manufactured

More information

SERVICE PARTS LIST PAGE 1 OF 6 BASE ASSEMBLY SPECIFY CATALOG NO. AND SERIAL NO. WHEN ORDERING PARTS 12" DUAL BEVEL COMPOUND MITER SAW B27A

SERVICE PARTS LIST PAGE 1 OF 6 BASE ASSEMBLY SPECIFY CATALOG NO. AND SERIAL NO. WHEN ORDERING PARTS 12 DUAL BEVEL COMPOUND MITER SAW B27A PAGE 1 OF 6 BASE ASSEMBLY 00 0 EXAMPLE: Component Parts (Small #) Are Included When Ordering The Assembly (Large #). SPECIFY CATALOG NO. AND NO. WHEN ORDERING PARTS 1 02-80-0050 Thrust Bearing (1) 2 05-80-0510

More information

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 READ CAREFULLY These instructions are intended to cover good practices in

More information

INSTRUCTION MANUAL AND PARTS LIST MODEL 14-10

INSTRUCTION MANUAL AND PARTS LIST MODEL 14-10 VERTICAL BAND SAWS INSTRUCTION MANUAL AND PARTS LIST MODEL 1-10 DAKE/PARMA WHEN ORDERING PARTS GIVE COMPLETE SERIAL NUMBER OF MACHINE GIVE PART NUMBER AND NAME GIVE AMOUNT REQUIRED Unless the above data

More information