Design and Construction of Auger Cast Piles



Similar documents
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Piling Datasheets. Continuous flight auger (CFA) Driven Rotary

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

BUTE Department of Construction Management and Technology

PILE FOUNDATIONS FM 5-134

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

High Capacity Helical Piles Limited Access Projects

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SECTION 411 DRILLED PIERS

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

Table of Contents 16.1 GENERAL Overview Responsibilities

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

ALLOWABLE LOADS ON A SINGLE PILE

GLOSSARY OF TERMINOLOGY

Federation of Piling Specialists July 2010

A DEEP FOUNDATION COMPARISON: DRIVEN vs BORED PILES. Professor s Driven Pile Institute Logan, UT June 26, 2013

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

DESIGNING STRUCTURES IN EXPANSIVE CLAY

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

High Strain Dynamic Load Testing of Drilled Shafts

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY

SECTION ABANDONMENT OF SEWER MAINS

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

Caltrans Geotechnical Manual

Page B-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2014 LOAD TESTS

SECTION 1 GENERAL REQUIREMENTS

Safe & Sound Bridge Terminology

IH-635 MANAGED LANES PROJECT, SEG. 3.2

The advantages and disadvantages of dynamic load testing and statnamic load testing

METHOD OF STATEMENT FOR STATIC LOADING TEST

vulcanhammer.net This document downloaded from

ATLAS RESISTANCE Pier Foundation Systems

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

KWANG SING ENGINEERING PTE LTD

COSMOS 2012: Earthquakes in Action COSMOS 2012

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Pro-Lift Steel Pile Foundation Repair

hs2 Ground A non-technical guide

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

SECTION SHEETING, SHORING AND BRACING

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

How To Design A Foundation

COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

POST FOUNDATION REPAIR PERFORMANCE RESIDENTIAL AND OTHER LOW-RISE BUILDINGS ON EXPANSIVE SOILS. The Repair Committee of

Step 11 Static Load Testing

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

Specification Guidelines: Allan Block Modular Retaining Wall Systems

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

Quality Assurance Concepts. Outline

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Designed and Engineered to Perform

Lighthouse Engineering, L.L.C.

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

PILE TESTING SPECIFICATION

The International Workshop on Micropiles, 2007

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

System. Stability. Security. Integrity. 150 Helical Anchor

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

MICROPILE FOUNDATIONS IN KARST: STATIC AND DYNAMIC TESTING VARIABILITY

Pavements should be well drained both during and upon completion of construction. Water should not be allowed to pond on or near pavement surfaces.

Construction sites are dewatered for the following purposes:

APPENDIX A PRESSUREMETER TEST INTERPRETATION

C. Section TESTING LABORATORY SERVICE.

Moving Small Mountains Vesuvius Dam Rehab

BRIDGES ARE relatively expensive but often are

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Load Testing of Drilled Shaft Foundations in Limestone, Nashville, TN Dan Brown, P.E., Ph.D.

Geotechnical Investigation using Standard Penetration Test (SPT) in Rangamati, Bandarban and Khagrachari Towns

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

How To Check For Scour At A Bridge

EN Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland

The demand for new roadway

Anirudhan I.V. Geotechnical Solutions, Chennai

Jack-in Piling Environmental Friendly Piling System

DIRECTIONAL DRILLING

Emergency repair of Bridge B421

SECTION 700 STRUCTURES SECTION 701 DRIVEN PILING MATERIALS Materials Materials shall be in accordance with the following:

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

PDCA Driven-Pile Terms and Definitions

product manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer

Instrumentations, Pile Group Load Testing, and Data Analysis Part II: Design & Analysis of Lateral Load Test. Murad Abu-Farsakh, Ph.D., P.E.

Geotechnical Building Works (GBW) Submission Requirements

Transcription:

Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com

CONTENTS 1. Auger Cast Pile Types 2. Construction Sequence 3. Applications For Transportation Projects 4. Common Materials 5. Construction Equipment 6. Procedures Used In This 7. Static Axial Capacity, Case History 8. Group Effects For Axial Capacity Lateral Load And Settlement, Case History 9. Quality Control (QC)/ Quality Assurance (QA) Technology

Example of Foundations Failure 1

Example of Foundations Failure 2

Example of Foundations Failure 3

Example of Foundations Failure 4

Auger Cast Pile Types Auger Cast Pile (ACP) Continuous Flight Auger (CFA) Piles Augered-Cast-in-Place (ACIP) Auger Pressure Grout Screw Piles Drilled Displacement (DD) Piles

Auger Cast Pile Types Auger cast piles are a type of drilled foundation in which the pile is drilled to the final depth in one continuous process using a continuous flight auger. Auger Cast Piles

Auger Cast Pile Types A) During drilling the flights of the auger are filled with soil, providing lateral support and maintaining the stability of the hole. B) At the same time the auger is withdrawn from the hole, concrete or a sand/cement grout is placed by pumping the concrete/grout mix through the hollow center of the auger pipe to the base of the auger that provides continuous support of the hole. C) Then Steel-reinforcement is placed into the hole.

Auger Cast Pile Types Drilled Displacement (DD) Piles

Auger Cast Pile Types

Auger Cast Pile Types Auger cast piles are typically installed with diameters ranging from 12 to 36 in. and lengths of up to 100 ft. In Europe with more recent powerful rigs, diameters could go up to 60 in. The reinforcement is in the upper portion of the pile for ease of installation and low bending stresses are transferred below these depths. In some cases, full-length reinforcement is used, as is most common with drilled shaft foundations. Auger cast piles can be constructed as single piles like for soundwall or light pole foundations For bridges or other large structural foundations, auger cast piles are most commonly installed as part of a pile group in a manner similar to that of driven pile foundations Auger Cast Piles

Auger Cast Pile Types Drilled Shaft vs. CFA Foundation Use of casing or slurry to temporarily support the hole is avoided. Drilling the hole in one continuous process is faster than drilling a shaft excavation. Because of torque requirement the diameter and length of CFA piles are generally less than drilled shafts. Continuous auger for installation also limits CFA piles to soil or very weak rock profiles. Auger Cast Piles

Auger Cast Pile Types Drilled Shaft vs. CFA Foundation Auger Cast Piles

Auger Cast Pile Types Driven Piles vs. CFA Foundation Noise and vibration due to pile driving are minimized. CFA piles eliminate splices and cutoffs. Soil heave due to driving can be eliminated when non-displacement CFA piles are used. A disadvantage of CFA piles compared to driven piles is that the available QA methods to verify the structural integrity and pile bearing capacity for CFA piles are less reliable than those for driven piles. CFA piles generate soil spoils that require collection and disposal especially if it is contaminated. Auger Cast Piles

Construction Sequence - Drilling Balanced auger rotation and penetration rates The auger having an excessively slow penetration rate and an insufficient base feed to keep the auger flights full Effect of Over- Excavation using CFA Piles

Construction Sequence - Drilling When a soil profile being drilled has mixed soil conditions (e.g., weak and strong layers), difficulties may arise. If the rig cannot penetrate the strong soil stratum at the proper rate, the augers can mine the overlying weak soil to the surface and cause subsidence. One solution to properly balance soil removal and penetration rate is to use Drilled Displacement (DD) piles.

Construction Sequence - Grouting Grout Delivered to Pump When the drilling stage is complete and the auger has penetrated to the required depth, the grouting stage must begin immediately. Grout or concrete is pumped under pressure through a hose to the top of the rig and delivered to the base of the auger via the hollow center of the auger stem.

Construction Sequence - Grouting Hole at Base of Auger for Concrete

Construction Sequence Grouting Sequence Upon achieving the design pile tip elevation, the auger is lifted a short distance typically 6 to 12 in. and grout is pumped under pressure to expel the plug at the base of the internal pipe and commence the flow. The auger is then screwed back down to the original pile tip elevation to establish a small head of grout or concrete on the auger and to achieve a good bearing contact at the pile tip. The grout is pumped continuously under pressure typically up to 150 to 300 psi measured at the top of the auger while the auger is lifted smoothly in one continuous operation. Simultaneously, as the auger is lifted, the soil is removed from the flights at the ground surface so that soil cuttings are not lifted high into the air (potential safety hazard). After the auger has cleared the ground surface and the grouting/concrete procedure is completed, any remaining soil cuttings are removed from the area at the top of the pile and the top of the pile is cleared of debris and contamination. The reinforcement cage is lowered into the fluid grout/concrete to the required depth and tied off at the ground surface to maintain the proper reinforcement elevation.

Construction Sequence

Construction Sequence Sometime the top of the pile can be difficult to find among the surface disturbance. Attention to detail in the final preparation of the surface is critical to ensure that structural integrity is maintained. Grout at Surface after Auger Withdrawal

Construction Sequence Finishing Pile and Reinforcement Placement

Construction Sequence - Grout vs. Concrete Grout Majority of work is using a sand/cement grout mixture because of the fluidity and ease of installation of reinforcement. The typical range of compressive strength of grout (4,000 to 5,000 psi). In the grout mix, fly ash and slag are often substituted for a portion of the cement for 24% to 30% to produce mixes with higher workability and pumpability, reduced bleeding, and reduced shrinkage. Grout is so fluid that the workability is typically measured using a flow cone. Concrete For concrete a pea-gravel size aggregate with around 42% sand used in the mix. Concrete is cited as being less costly than grout, less prone to overrun volume, and is considered to be more stable in the hole when constructing piles through soft ground. Concrete slump for CFA construction is similar to that of wet-hole drilled shaft construction, with target slump values in the 8 in. ± 1 in. range.

Applications For Transportation Projects Bridge Piers and Abutments. Soundwalls. Earth Retaining Structures. Pile-Supported Embankments.

Advantages And Limitations of CFA Piles Speed of installation of CFA piles and lower cost over other pile types. Increased requirements to minimize noise and vibrations from pile installation in heavily populated areas. A reluctance by many owners to utilize CFA piles because of concerns about quality control and structural integrity. Demand on bridges for uplift and lateral load capacity, scour considerations, and/or seismic considerations, require pile diameters and possibly lengths

Advantages And Limitations of CFA Piles Favorable Geotechnical Conditions Medium to very stiff clay soils. Cemented sands or weak limestone. Medium dense to dense silty sands and well-graded sands. Rock overlain by stiff or cemented deposits. Unfavorable Geotechnical Conditions Very soft soils. Loose sands under groundwater. Geologic formations containing voids. Hard soil or rock overlain by soft soil or loose, granular soil.

Applications For Transportation Projects When to Select and Use the CFA Piles Favorable geotechnical conditions available. Projects where speed of installation is important. Batter Piles Required. Projects where large numbers of piles are required. Low headroom conditions.

Applications For Transportation Projects Bridge Piers and Abutments Types of bridge most suited for the use of CFA Interchange structures (where scour is not a major issue). Approach structures. Or those involving bridge widening.

Applications For Transportation Projects Bridge Piers and Abutments Crosby, Texas

Applications For Transportation Projects Bridge Piers and Abutments Crosby, Texas Twelve production piles were instrumented and monitored during construction and load testing using trucks. The results from the pile instrumentation suggest that the piles supported the fully loaded bridge entirely by mobilizing side friction alone and with very small around 0.1 in. movements.

Applications For Transportation Projects Low Headroom Conditions

Applications For Transportation Projects CFA piles can be a viable alternative to drilled shafts or slurry walls. A structural steel section may be used for pile reinforcement rather than a reinforcing cage. Needs heavy drilling equipment. Secant or Tangent Pile Walls

Applications For Transportation Projects Secant or Tangent Pile Walls

Applications For Transportation Projects Drilling CFA Piles for Secant Wall

Applications For Transportation Projects Secant or Tangent Pile Walls New Haven, Connecticut

Applications For Transportation Projects Secant or Tangent Pile Walls New Haven, Connecticut

Applications For Transportation Projects Soundwalls in Favorable Soil

Applications For Transportation Projects Pilecaps on CFA Piles for a Pile-Supported Embankment The use of CFA piles for a pile-supported embankment may represent a cost-effective alternative to ground modification

Applications For Transportation Projects Pilecaps on CFA Piles for a Pile-Supported Embankment Foundation strata consist of weak and compressible subsoils, which would take a long time to consolidate. Accelerating construction. fill supporting a transportation facility that is particularly sensitive to settlements (such as a high-speed rail). Accelerated construction is required for projects where additional cost due to traffic shifts, geotechnical instrumentation, and related time delays present an unacceptable situation to project owners

Construction Cost ($20 to $28 per linear foot Many Variables Affect Pile Costs Costs relating to performance and integrity testing are likely to be higher on transportation projects. Length, diameter, reinforcement, and grout strength. Size of the project. Mobilization cost

Construction Equipment Crane-Attached CFA System Hydraulic CFA System

Construction Equipment Augers for Different Soil Conditions: Auger for CFA Piles in Sandy Soil (Top) and Augers for DD Piles (Bottom)

Construction Equipment Auger for Use in Clay, with Auger Cleaner Attachment

Construction Equipment Cutter Heads for Hard Material (left) and Soil (right)

Construction Equipment Double Rotary CFA Piles

Construction Equipment Trucks Discharging into Pump Close up View of Grout Pump

Construction Equipment In-Line Flowmeter

Construction Equipment Sensor for Concrete Pressure at Auger Tip

Reinforcement Machine-Welded Reinforcement Cage on Project Site

Reinforcement Use of Steel Pipe to Reinforce a CFA Pile for a Wall

Reinforcement Installation of Reinforcement Cage into Battered CFA Pile

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 12 Floors Building in Downtown Fort Wayne, Indiana

Static Axial Capacity and Group Effects, Case History 14 Floors Tower in Downtown Indianapolis, Indiana

Static Axial Capacity and Group Effects, Case History 14 Floors Tower in Downtown Indianapolis, Indiana

Static Axial Capacity and Group Effects, Case History 14 Floors Tower in Downtown Indianapolis, Indiana

Quality Control (QC) / Quality Assurance (QA) Monitoring and Control of the Drilling Phase The operator and inspector should observe and record the depth of the auger, the speed of the auger, the rate at which the auger penetrates into the ground, and the torque with which the auger is rotated. Operator with Cab Mounted Display Used to Control Drilling

Quality Control (QC) / Quality Assurance (QA) Monitoring and Control of the Grouting/Concreting Phase Control of the grouting / concreting phase of construction may be the most important aspect of QA/QC for CFA piles. In-line Flowmeter

Quality Control (QC) / Quality Assurance (QA) Monitoring and Control of the Grouting/Concreting Phase Display Panel for Observation by Inspector

Quality Control (QC) / Quality Assurance (QA) Example Data Sheet from Project

Quality Control (QC) / Quality Assurance (QA) Cubes for Grout Testing

Quality Control (QC) / Quality Assurance (QA) Use of Integrity Testing Integrity Testing by Surface Methods -Sonic Echo Testing

Quality Control (QC) / Quality Assurance (QA) Use of Integrity Testing Integrity Testing using Downhole Techniques Downhole Single-Hole Sonic Logging (SSL) Concept

Quality Control (QC) / Quality Assurance (QA) Load Testing Static Load Test Setup on CFA Piles

Quality Control (QC) / Quality Assurance (QA) Load Testing Proof Testing of Production Piles with Statnamic

Questions? Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com