Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System

Similar documents
North American Society for Trenchless Technology (NASTT) NASTT s 2014 No-Dig Show. Orlando, Florida April 13-17, 2014

Prestressed Concrete Pipe Fitness for Service and Repair

External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902

Meeting the Challenge of Pipeline Emergency Repair

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

Measuring the Condition of Prestressed Concrete Cylinder Pipe

WSSC Ad-Hoc Committee on Large Diameter Water Mains. August 2, 2013

Section SEWER PIPE INSTALLATION AND TESTING

Condition Assessment of a 48 PCCP Water Main Within an Abandon Subway Tunnel

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

Industrial Pipeline Integrity Management & Remote Polyurea Pipe Lining Systems.

Rehabilitation of corroded pipelines and pipes with FibaRoll

Flowtite Jacking Pipe

Force Main Condition Assessment: New Technologies & Case Studies

Pipeline Asset Management: From Assessment to Prioritized Projects List

AGENDA ITEM C9. COST/FUNDING SOURCE: $431,847.40/ Uniform Rate

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

APE T CFRP Aslan 500

SECTION STORM DRAINAGE SYSTEM

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

Wastewater Capital Projects Management Standard Construction Specification

Session: HDPE Pipe Test Rafael Ortega, Vice President, Lockwood, Andrews & Newnam

Chesapeake Section AWWA Symposium

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

The Original Carbon Fiber Reinforced Polymer System

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

Rehabilitation or Replacement? That Is The Question

Relining of Water Mains with. Flexible High Pressure Pipelines. Raedlinger Primus Line, Inc. Ivan Zubiaga Executive Vice President 2014

SECTION PRECAST CONCRETE UTILITY STRUCTURES

Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

Bridge Structural Rehabilitation Using FRP Laminates

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

Guide Specification STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM

WEKO-SEAL Internal Joint Sealing WEKO-SEAL. internal pipe-joint sealing

Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets

REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC

Rehabilitation of Large Diameter PCCP: Relining and Sliplining with Steel Pipe

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

Water Main Lining A Sustainable Alternative to Open Cut Replacement

HYDRAULIC ANALYSIS OF PIPE LINED WITH MADISON S 100% SOLIDS STRUCTURAL POLYURETHANE COATINGS

SEWER CLEANING, INSPECTION AND ASSESSMENT

Introduction to Pressure Pipe Rehabilitation with CIPP

PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY

Experimental assessment of concrete damage due to exposure to high temperature and efficacy of the repair system

ICS: Strengthening retrofitting of reinforced concrete structures by gluing of fibre reinforced polymeric fabrics (FRP fabrics)

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

High Density Polyethylene Liners for Rehabilitation of Corroded Pipelines

CHAPTER 6 - SANITARY SEWER

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

Retrofit Design of Damaged Prestressed Concrete Cylinder Pipes

INDEX. Sec. No. Items Page Nos.

DEPARTMENT OF DEFENSE ALLIED NATIONS TECHNICAL CORROSION CONFERENCE. November 15-19, 2015 Pittsburgh, PA, USA. Technical Program

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

CLEANING, INSPECTION, AND TESTING OF SEWERS

SOLVING SECONDARY CONTAINMENT PROBLEMS

A Decade of Performance of FRP-Repaired Concrete Structures

Fire-Damage or Freeze-Thaw of Strengthening Concrete Using Ultra High Performance Concrete

STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District

Strengthening and Repair of Reinforced Concrete Structures. Ian Wienholt Business Development Manager

Section Four: Linings and Coatings

CIPP for Large Diameter Pressure Pipes. Water Research Foundation Large Diameter Pipe Rehabilitation Seminar 20 January 2016 George Bontus, P.Eng.

ENGINEERING SPECIFICATION PULTRUDED DYNARAIL FIBERGLASS LADDER & LADDER CAGES

BLADDER SURGE CONTROL SYSTEM

Ultraviolet (UV) Light Cured Fiberglass Reinforced Cured-In-Place Pipe (CIPP) It is not just for sanitary sewer rehabilitation

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

Structural Rehabilitation of the Kenilworth PCCP Transmission Main with Steel Slipliner

Fiberglass Rebar (GFRP Rebar)

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

Safe & Sound Bridge Terminology

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

Green Thread Product Data

SECTION SANITARY SEWER AND STORM DRAIN SYSTEMS

Concrete Repair. Applications and Procedures

CONSTRUCTION OF NON-CIRCULAR SEWER REHABILITATION PROJECTS IN LOS ANGELES

C. Section TESTING LABORATORY SERVICE.

CA-48 TECHNICAL SPECIFICATION

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES

SECTION SANITARY SEWER PIPE

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

High Capacity Helical Piles Limited Access Projects

SOCALGAS APROACH TO PIPELINE INTEGRITY

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

HIGHWAYS DEPARTMENT GUIDANCE NOTES ON THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE DECKS

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

REHABILITATION OR REPLACEMENT? THAT IS THE QUESTION

PIPE REHABILITATION. Industrial Wastewater Municipal Wastewater Drinking Water Pressure Pipes

City of Lincoln, Nebraska STEVENS CREEK BASIN TRUNK SEWER TECHNICAL MEMORANDUM NO. 5 PIPE MATERIAL SELECTION TABLE OF CONTENTS

SECTION PVC PRESSURE PIPE AWWA C900

Transcription:

Using StrongPIPE Hybrid FRP for PCCP Rehab in Miami-Dade System Luis Aguiar Miami-Dade Water & Sewer Department Anna Pridmore, PhD Structural Technologies

PROJECT BACKGROUND Miami-Dade Water & Sewer Department (MDWASD): 7,900 miles of water mains from 2-120 in diameter across 400 square miles 1,400 miles of sanitary sewer mains

PROJECT BACKGROUND In response to a series of high profile catastrophic failures in 2010 & 2011: MDWASD implemented a comprehensive asset management program, and established the Infrastructure Assessment and Rehabilitation Program (IAARP) Ruptured 54-inch PCCP water transmission main

INFRASTRUCTURE ASSESSMENT & REHABILITATION PROGRAM (IAARP) Routine rotating inspections of pipeline Adoption of best industry practices Precision inspection Replacement Structural upgrade

ELECTROMAGNETIC INSPECTION Identifies pipe segments with broken wires

Pressure (psi) Large Pressure Pipe Structural FAILURE RISK ANALYSIS & REPAIR PRIORITIZATION Failure risk analysis performed Prestressing wire pitch and spacing Cylinder thickness Concrete core thickness Internal and external loads on pipe Facilitates prioritizing repairs or replacements before failures occur Serviceability Strength with contribution of soil Strength w/o contribution of soil Damage Number of Broken Wires

OPTIONS ANALYSIS Factors: Many MDWASD s pipelines are located underneath major roadways making trenchless rehabilitation advantageous. For 5 years MDWASD has used FRP for PCCP upgrades Established an on-call emergency response team of prequalified contractors Construction alongside roadways

PROJECT SCOPE 13 Segments of 54 inch PCCP 10 Segments of FRP repair 3 Segments of Hybrid FRP Constituents CFRP System Hybrid FRP System Primer, saturating resin, intermediate filler, topcoat Longitudinal reinforcement 2 part 100% solids epoxy 2 part 100% solids epoxy Hand applied layers of GFRP & CFRP Hand applied layers of GFRP & CFRP Hoop reinforcement Hand applied layers of GFRP & CFRP Robotically installed continuous steel wire embedded in epoxy

DESIGN REQUIREMENTS Both FRP and Hybrid FRP systems are stand alone systems designed to resist the following loads without reliance on the host pipe: Working pressure 150 psi Working plus transient pressure 225 psi Vacuum pressure -14.7 psi Soil Cover 5.5 ft Ground water height above crown 5.5 ft Surface live load HS-20

StrongPIPE Hybrid FRP System Overview StrongPIPE is fully structural repair system comparable to the use of carbon fiber reinforcement. Two (2) installations for Miami-Dade Water & Sewer completed in past 18 months. One installation was inspected after 10 months in service with no issues. Objective is to utilize for extended runs of pipe because it is more cost effective than other structural repair systems.

StrongPIPE inspection @ Miami-Dade after 10 months in service

StrongPIPE Hybrid FRP System Overview Basic composition for Hybrid FRP system

HYBRID FRP INSTALLATION PROCESS Dewatering Surface preparation Adhesion testing verifying surface prep Installation of longitudinal FRP Application of thickened epoxy Installation of steel reinforcement Application of thickened epoxy Installation of longitudinal FRP Application of topcoat

Prepared concrete substrate 54-inch PCCP Large Pressure Pipe Structural

Drilling the holes to set the test pucks for adhesion tests

Mechanical saturation equipment Large Pressure Pipe Structural

Installation of longitudinal layer of fiber reinforced polymer

Truck mounted unit for Hybrid FRP System Large Pressure Pipe Structural

Hybrid FRP System Steel reinforcement installation

Longitudinal & Hoop FRP Layers Epoxy mortar Existing spigot end Existing bell end Epoxy Primer Longitudinal FRP Layers Epoxy mortar Steel Embedded in Thickened Epoxy Longitudinal FRP Layers Top coat END TERMINATION DETAIL Stainless steel expansion ring

HYBRID FRP INSTALLATION VIDEO Large Pressure Pipe Structural

MAJOR STEPS IN QA/QC PROCESS: Monitor temperature and humidity Verification of surface prep Calibration of mechanical saturator Adhesion testing Preparation of witness panels for tensile testing Verification of FRP alignment Verification of FRP overlaps Verification of spacing of steel reinforcement Verification of embedment of steel in epoxy

Verification of steel wire placement Large Pressure Pipe Structural

CONTACT INFORMATION QUESTIONS? Luis Aguiar Miami-Dade Water & Sewer Department lagui@miamidade.gov 786.552.8185 Anna Pridmore, PhD Structural Technologies apridmore@structuraltec.com 714.869.8824