Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant



Similar documents
Black Canyon Hydroelectric Project FERC Project No. P Proposed Fish Passage Study Plan September 2012

Section 2. Mono Basin Operations

Year Post Restoration Monitoring Summary Rock Creek Project Monitoring and Analysis conducted by Bio-Surveys,LLC. Contact: strask@casco.

WATER STORAGE, TRANSPORT, AND DISTRIBUTION Multi-Dam Systems and their Operation - J.J. Cassidy MULTI-DAM SYSTEMS AND THEIR OPERATION

UPPER DESCHUTES R-EMAP TEMPERATURE SUMMARY

Hydropower. Corps Hydro Plants Non-Federal Plants


ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage

Penticton Creek May 4, 2015 Council Meeting

Ruby River Grayling - Gravel Spawning Beds Monitoring Report January 2008

DISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, Values Statements.

BIG CREEK Nos. 1 AND 2 (FERC Project No. 2175) VOLUME 1 (BOOK 1 OF 27 BOOKS) INITIAL STATEMENT, EXHIBITS A, B, C, D AND H (PUBLIC INFORMATION)

COMPLIANCE REPORT MUDDY HOLLOW CULVERT REMOVAL FILE NUMBER 25358N

ROGUE RIVER SPRING CHINOOK SALMON CONSERVATION PLAN. Evaluation of spring Chinook salmon spawning in Big Butte Creek, 2008

Skaguay Reservoir. FISH SURVEY AND MANAGEMENT DATA Greg A. Policky - Aquatic Biologist (Salida) greg.policky@state.co.

October 11, Sharon Stohrer State Water Resources Control board P.O. Box 2000 Sacramento, CA

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P Turbidity Monitoring Plan

Background Information: The Mamquam River Floodplain Restoration Project

CHAD R. GOURLEY SPECIALTY EMPLOYMENT

CITY UTILITIES DESIGN STANDARDS MANUAL

121 FERC 62,167 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Public Utility District No. 1 of Project No Chelan County

Sand and Silt Removal from Salmonid Streams

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration

Bull Run River. Water Temperature Evaluation. Prepared by: City of Portland Bureau of Water Works Portland, Oregon

AN INITIATIVE TO IMPROVE

NID statement Agreement Disagreement Auburn Ravine: During irrigation and nonirrigation

Frequently Asked Questions (FAQs) on Hydropower

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

May 29, Mr. Tom Howard Executive Director State Water Resources Control Board P.O. Box 100 Sacramento, CA

LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN

Recreational Enhancements on the Lehigh River Public Information Workshop February 2013

UTILITIZATION OF ECOHYDROLOGIC MODELS IN FLOODPLAIN FISH PASSAGE AND HABITAT RESTORATION EVALUATION

NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand

Prattsville Berm Removal Project. 1.0 Project Location

Environmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization

Youghiogheny River From Confluence, Pa to Indian Creek Fayette and Somerset Counties

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN

Subject: Prospect 3 Hydroelectric Project (FERC ) Comments on Preliminary Application Document and Scoping Document; and Study Requests

Walla Walla Bi state Stream Flow Enhancement Study Interim Progress Report. Department of Ecology Grant No. G

Project Theory-Climate Change and Traditional Ecological Knowledge Adaption in the Klamath Basin

Gold Ray Dam Interagency Technical Team Meeting

ENVIRONMENTAL ISSUES AND MANAGEMENT FOR HYDROPOWER PEAKING OPERATIONS

Restoring Ecosystems. Ecosystem Restoration Services

Executive Summary: PA No. 12 Micro-hydro at Graham Hill Water Treatment Plant

General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title]

Introduction to Architecture. Lesson 13: Hoover Dam

Earth Science. River Systems and Landforms GEOGRAPHY The Hydrologic Cycle. Introduction. Running Water. Chapter 14.

HCP Team Meeting. November 18, icfi.com

TENNESSEE GAS PIPELINE COMPANY, L.L.C.

CHAPTER I: INTRODUCTION. Background

6.0 Results of Risk Analyses

Arkansas River Corridor Vision & Master Plan

Kevin Kennedy Natural Gas and Special Projects Office

Tie CornrnonweaGti of Massaciusetts Wecutive Ofiice of Energy andenvironmentacpfiairs 100 Cam6ndjge Street, Suite 900 Boston, NP

Prepared By: Tom Parker Geum Environmental Consulting, Inc.

LR 314 Working Group 5 Final Report

1.7.0 Floodplain Modification Criteria

STANDARDS FOR RANGELAND HEALTH ASSESSMENT FOR SAGEHEN ALLOTMENT #0208

Monitoring Riparian Areas With a Camera

Proposal to the Trinity Adaptive Management Working Group (TAMWG)

Ponds- Planning, Design, Construction

Stream Restoration Post-Implementation Annual Monitoring Report Year 2: 2013 Covering the Period of July 2012 to July 2013

Floodplain Connectivity in Restoration Design

CARLSON CREEK HYDROELECTRIC PROJECT PRELIMINARY FEASIBILITY EVALUATION AEA GRANT #

HUDSON RIVER-BLACK RIVER REGULATING DISTRICT BOARD MEETING JUNE 10, 2014

Re: Preliminary Permit Application for the Rose Creek Pumped Storage Project

The Teton Creek Restoration Project Summary:

Solar PV panels fitted to roofs. Solar PV panels produce electricity from energy provided by sunlight. 3.5 MWh per system

Request Number 11: Fish and Fish Habitat Compensation Plan

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA

Addendum D. Nomination of Moody Wash ACEC

Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan

How To Check For Scour At A Bridge

Final Report. Dixie Creek Restoration Project. Funded by Plumas Watershed Forum

SPA Annual Report for 2002 September, 2003 Montgomery County Department of Environmental Protection Page 125. Evaluation and Recommendations

Chapter 11. Costs and Funding

HEADWATERS CONTROL STRUCTURE MANAGEMENT POLICY AND OPERATING PROCEDURES

JOB DESCRIPTION. GS-11 $46,006 - $59,801 Annual/Full Benefits GS-12 $55,138 - $71,679 Annual/Full Benefits

Water Extraction Permitting Policy

9.1. Adequacy of Available Data and Monitoring Efforts

How To Plan A Buffer Zone

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure

How To Manage Water Resources In The Yakima Basin

Habitat Quality, Rainbow Trout Occurrence, and Steelhead Recovery Potential Upstream of Searsville Dam

Oxbow Restoration for Fish Habitat and Water Quality

NPLOTH7 GIS Database Development Mission (2619), Bryson (2601), Franklin (2603), Dillsboro (2602) Final Report

RESTORATION AND ENHANCEMENT OF SOUTHERN CALIFORNIA LAGOONS

Steelhead Recovery in San Juan and Trabuco Creeks Watershed

2013 Hardwater Lake Aquatic Vegetation Control Plan LDWF, Inland Fisheries

STATE OF CALIFORNIA STATE WATER RESOURCES CONTROL BOARD

5.14 Floodplains and Drainage/Hydrology

Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002

Outlet stabilization structure

DeWitt Pipeline Rehabilitation/Replacement Project Environmental Assessment

Resolving complex issues with large scale river restoration; a case study: the San Joaquin River in California

Restoration Planning and Development of a Restoration Bank

Plan Groundwater Procurement, Implementation and Costs, prepared for the Brazos River Authority, July 2005.

Addendum. Use Attainability Analysis for Site Specific Selenium Criteria: Alkali Creek. February 23, 2009

Transcription:

Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant By Ginger Gillin, John Pizzimenti, and Doug Foss, GEI Consultants, Inc., USA, and Jon Jourdonnais, PPL Montana, USA. Abstract The Mystic Lake Project is a high elevation hydroelectric project adjacent to a pristine Rocky Mountain wilderness. On December 17, 2007 the Federal Energy Regulatory Commission issued PPL Montana (PPLM) a new License to continue operating Mystic under FERC s new Integrated Licensing Process. This high head project diverts water from Mystic Lake via pipeline, surge tower and penstocks across steep and geologically active terrain. PPLM needed to demonstrate that it had historically protected the fishery in the two-mile bypass reach and tailwaters and would continue to do so in the future. Additionally, PPLM needed to demonstrate they could protect the aquatic resources in the event of failure of the flowlines. This paper describes how the utility (1) effectively studied the aquatic resources, (2) assessed past effectiveness of their operations and (3) improved the reliability of the project to protect those resources in the future. They accomplished this by building trust Figure 1. Mystic Lake Dam and Reservoir. and consensus with a large stakeholder group who amazingly achieved its collective goals without sacrificing any of the energy or capacity benefits nor the environmental attributes the project has provided since 1927. PPLM and stakeholders found ways to maintain the Mystic Project s renewable and peaking power resources and simultaneously meet other important public goals of protecting the natural resources and providing recreational opportunities. Overview Constructed in 1927 in an extreme environment not far from Yellowstone National Park, Mystic Lake is a remarkable example of early 20th century hydropower. Mystic Lake Dam at elevation 7673 feet is in the headwaters of West Rosebud Creek. It took tenacity to overcome the steep, dangerous topography and snowy winters at this high elevation Rocky Mountain site. The 10 Mw powerhouse is 2.3 miles downstream of the dam at elevation 6550 feet. This project develops 1100 feet of head and operates in a peaking mode during the low flow seasons. The elevated storage lake can be drawn down up to 60 feet for winter capacity and energy use. 1

On December 17, 2007 the Commission issued the Mystic Project a new license, the first under FERC s new Integrated Licensing Process, or ILP. The bypass reach of West Rosebud Creek between the dam and powerhouse contains a valuable rainbow and brown trout recreational fishery. Previous studies in the bypass reach established a minimum instream flow of 10 cfs between June 1 and September 1, and a 3 cfs flow the rest of the year. They also established a minimum flow of 20 cfs downstream of the Figure 2. 2.3 Mile Bypass Channel. Elevational profile of the West Rosebud Creek bypass reach. The yellow square at approximately 7,100 ft represents where Maxie Creek enters West Rosebud Creek. project and re-regulated power discharges to reduce peaking fluctuations in the lower river. The project is also a target destination of white water boaters for the June-July runoff. Using consensus based study approaches in the ILP and negotiated settlements based on data, the participants and FERC agreed, to maintain the same historic instream flows to protect the healthy fishery. The aquatic study team however also recognized a failure of the flow line could impact the fishery and aquatic habitats of both the bypass and mainstem river downstream of the hydro. Rock and Ice avalanches are known in the area and could rupture the penstock and cutoff flows to the powerhouse as well as the bypass reach and lower river. Should disruption occur at normal pool elevation the spillway would operate to protect the instream flows. In winter however, when Mystic Lake is below spillway elevation, the project has no mechanism to quickly restore instream flows to the bypass or tailwaters. PPLM s engineers have come up with a solution to bypass the flow line with a new valve at the outlet of the rock tunnel not far from the dam. A 60-inch flow line emerges from the tunnel onto a narrow rock ledge. The site and conditions create numerous Figure 3. Doug Foss inspecting Mystic Lake Penstock via Cable Car Rail Line. 2

challenges to design and construct a sufficiently large valve system that would operate under the extreme conditions of a runaway failure under sub-freezing conditions without power. Challenges include (1) potential need for the largest of air cranes (Sikorsky helicopters) for up to a 15 ton valve system; (2) need for erection and maintenance cranes; (3) need for protection from avalanches and rock falls and (4) a remotely controlled but automated system capable of closing under runaway mode. Instream Flow Concerns West Rosebud Creek-Mystic Lake hydrology has an early summer snowmelt driven peak with a low flow winter condition that can actually reach zero discharge due to total freeze up in the upper elevations. The hydropower operations reduce the peak discharge by refilling the reservoir after a gradual 60-foot winter drawdown. Downstream of the project there are two recreational lakes, West Rosebud Lake which has a re-regulating dam and spillway and Emerald Lake downstream of that. Under the previous FERC License PPL had committed to a minimum flow of 20 cfs all year downstream of West Rosebud Lake. Thus historically there was 20 cfs continuously from winter power operations when natural flows might otherwise drop to a fraction of this amount due to freezing conditions. The project was also diverting flows around a steep two-mile section of West Rosebud Creek known as the bypass reach. The key aquatic resource questions were then: what effects, positive or negative were these historic operations having on the resources in the bypass? Historic instream flows in the bypass in the previous license were 10 cfs summer (June 1 - August 31) and 3 cfs all other times. This is significantly less flow than would be present without the project. But there were times when the natural winter inflows may have dropped to zero due to extremely low temperatures. Therefore, two key questions were (1) what affects if any, was is the historic instream flow having and (2) had the project maintained its required flows during the past 30 years? In addition, concerns were raised about a lack of ramping rates in the bypass reach, particularly on August 31, when flows would be adjusted from 10 cfs to 3 cfs potentially stranding fish and dewatering macroinvertebrates. Study Plans and Results Hydrologic Records The consulting team digitized all the minimum flow, USGS hydrology and powerhouse discharge records from the past 30 years. When averaged, the project was diverting close to an average of 5 cfs during the low flow season and more than 10 cfs during the summer season. They identified that with the exception of about a total of 52 days during the past quarter century, the project had met its minimum 3 cfs flow bypass requirements. It met nearly all of its 10 cfs summer minimum flow records and any transgressions were minor. Detailed study of the 3 cfs flow violations occurred during two extreme events in two separate winters when the entire system froze and there were no flows entering Mystic 3

Lake. There was no evidence that flows had ever dropped to zero in the bypass at any time. Flows of 20 cfs downstream of West Rosebud Lake were likewise historically being met consistently by the project since the construction of the re-regulating dam. The automated re-regulating gate system enabled excess flows to pass. The storage in West Rosebud Lake was sufficient to maintain a minimum discharge of 20 cfs during periods when the powerhouse was not generating. Fishery Populations and Aquatic Habitat The Aquatic Resource Team debated the need for hydraulic models of the bypass habitat and concluded that assessment of the condition of the actual fishery would be the first indicator of the health of the fishery. In addition, the Team agreed to sample and assess the physical habitat of riffles and pools under low flow conditions to determine the extent of usable trout habitat in the bypass reach. Data showed that rainbow trout occupied lower, middle and upper reaches of the bypass wherever slopes were sufficient to create pool habitat (Table 1). Minimum flows appeared adequate to keep these pools full given the hydraulic gradients and geology of the streambed. Total Length Inventoried (ft) Width (ft) Pool Depth (ft) Crest Depth (ft) Riffle Depth (ft) Pocket Pool Depth (ft) Available Spawning Gravel ft^2 Pool to Riffle Ratio Lower Reach 1788.00 16.73 2.68 0.91 1.29 2.05 243.00 1.58:1 Middle Reach 2043.00 20.85 1.74 0.84 0.67 1.47 270.50 0.95:1 Upper Reach 1743.00 16.76 2.48 1.12 0.70 1.58 127.00 3.47:1 Total 5574.00 NA NA NA NA NA 640.50 NA NA 18.11 2.30 0.96 0.89 1.70 NA NA Table 1. Summary statistics for the November modified R1/R4 habitat survey conducted in the bypass reach of West Rosebud. Creek. Rainbow trout inhabited Mystic Lake and presumably could and did colonize the upper bypass reaches via the spillway. Brown trout which were extant only downstream of the powerhouse were able to colonize the lower bypass areas up to the first major waterfall barrier. Impassable waterfalls occurred throughout sections of the bypass and restricted brown trout to the lower most reach of the bypass Sampling showed healthy populations of rainbow trout in Mystic Lake and rainbow and brown trout in the two lakes downstream of the powerhouse. They also showed densities among the highest known for the state for a stream of this size in the bypass reach. The presence of all life history stages from juvenile through reproductive size adults demonstrated that the system was self-sustaining. These fishery data led to conclusions that instream flows had been protective and that power operations including re-regulation had been prudent in protecting the fisheries around the project area since the last license conditions were imposed. 4

Downstream of the re-regulating dam in the mainstem river, habitat assessment showed good trout habitat at low flow conditions. Historic data on the fishery from Montana Fish, Wildlife, and Parks data indicated that this population was healthy, self sustaining and being protected if not enhanced by the 20 cfs minimum flows provided by re-regulated discharges. Herpetology experts conducted aquatic habitat surveys for herptile species around the project and determined no critical habitat exists for sensitive species. At the request of the U.S. Forest Service, the consulting team conducted an analysis of project affects on overall system hydrology using the Nature Conservancy method known as Indicators of Hydrologic Alteration or IHA (Smythe Scientific, version 7, 2005: www:weba.viawest.net/users/csmythe). The greatest change in hydrologic regime below the project was determined to be slightly lowered average peak discharge as a result of storage operations. Therefore, no change in the minimum instream flow was proposed. Riparian biologists conducted plant surveys downstream of the project also to determine if the altered hydrology was affecting habitat. The riparian habitats were found to contain healthy populations of native cottonwoods and other species. Those few altered areas were correlated with land disturbances from livestock and other ranching activities. Plans to monitor riparian conditions were included in the FERC License conditions. Figure 4. View of Mystic Lake and Absorkee. Conclusions The historic and existing minimum flow operations both in the bypass and the reregulated reach of the river were judged by the Aquatic Resource Team to have been protective of the natural aquatic resources. Due to the methodology of measurement and to historic records, it was clear that the Mystic Project had on average contributed closer to 5 cfs on average to the bypass during the minimum flow season. In order to maintain the actual historic flows that have supported the excellent fishery, PPLM agreed to maintain the historic levels which were judged to be typically 5 cfs with the allowance to reduce flows to 4 cfs 11 days each month (September through May). Although this appears to increase in the required bypass flow, in actually it codified continuation of PPLM s actual historic operation which was enhanced due to natural 5

inflows augmenting controlled releases. During summer months (June through August) the minimum bypass reach flow was kept to 10 cfs. This healthy fishery approach avoided the need to conduct costly and often debatable hydraulic habitat studies. This led to rapid resolution of what is often the most costly aspect of relicensing projects with bypassed instream reaches. PPLM also agreed to ramping the descending bypass minimum flow below 10 cfs to a maximum of 2 cfs per hour when the minimum flow is changed from summer to fall operations August 31 each year. Fish Valve Design PPLM showed good faith and stewardship of the river by recognizing the potential for dewatering the stream even though it might be an unlikely event. PPLM is continuing to work on the design elements of the emergency fish valve and has committed to installing the valve by 2011. As envisioned, the valve will provide a means of releasing a minimum of 5 cfs during the low flow season and 10 cfs during the summer season. Most importantly, the new valve will be ready to also maintain instream flows of 20 cfs to the entire river should any catastrophic event prevent water from flowing to the powerhouse. We will report at a future date on the successful implementation of this important safety element of the new Mystic Lake project. Figure 4. Existing configuration of the Mystic Lake flow line and penstock system Authors Ginger Gillin is a Senior Environmental Scientist with GEI Consultants in Sacramento, California. She works on FERC licensing and aquatic biological issues on regulated rivers in the western USA and served as lead aquatic scientist and project manager for this project. 6

John Pizzimenti is a Vice President at GEI Consultants in Portland, Oregon. John served as project manager and senior principal consultant for this project. Doug Foss was a Mechanical Engineer and lead engineer for this project from GEI Consultants Bozeman, Montana office. Doug passed away shortly before Mystic received its new license. We dedicate this paper to Doug s memory. He was instrumental in many of the successful elements in this and so many other hydro projects. He will be missed. Jon Jourdonnais is Hydro Licensing and Compliance Manager for PPL Montana in Butte, Montana. Jon led the entire Mystic Lake Relicensing effort and he and PPL Management empowered this team to be the first to successfully license a project under the ILP. 7