Plan Groundwater Procurement, Implementation and Costs, prepared for the Brazos River Authority, July 2005.
|
|
|
- Alexis Parker
- 9 years ago
- Views:
Transcription
1 6 Conjunctive Use 6.1 Lake Granger Augmentation Description of Option Rapid population growth and development in Williamson County require additional water supplies throughout the planning period. The total need for new supplies in Williamson County is about 19,700 acft/yr in the year 2020, increasing to about 167,200 acft/yr by year Much of the increased demand is in the southwestern portion of the county in and adjoining the Cities of Round Rock, Leander and Georgetown. This alternative will add 53,361 acft/yr (7,096 from Phase I in ,265 acft/yr from Phase II 1 ) by augmenting the long-term firm yield of Lake Granger with groundwater pumped from the Trinity Aquifer and the Carrizo-Wilcox Aquifer. In the initial phase of the project, water from the Trinity Aquifer in eastern Williamson County would be blended with treated water from the East Williamson County Regional Water Treatment Plant (EWCRWTP). In the second phase of the project, additional groundwater would be developed from the Carrizo-Wilcox Aquifer in areas east of Williamson County, in Milam, Lee and Burleson Counties. At this time, specific locations for these supplies have not been identified. For the purposes of this plan, it is assumed that these supplies will come from Milam County. Facilities for Phases 1 and 2 are depicted in Figure and Figure 6.1-2, respectively. Conceptual designs for the various components of these projects are based on studies performed for the Brazos River Authority in , and Two alternatives have been studied previously for the second phase of the project. In the first alternative, referred to as the Comingling Option, Carrizo-Wilcox Aquifer water is first pumped into Lake Granger and comingled with natural runoff in the reservoir. The comingled water is subsequently diverted and all of the water is treated at the EWCRWTP. In the second alternative, referred to here as the Bypass Option, groundwater is blended with treated Lake Granger water rather than comingling the water in the reservoir. Because of concerns about blending groundwater in Lake Granger and the additional cost and treatment capacity associated with treating the blended water, current Brazos River Authority planning assumes that the Bypass Option will be used rather than the Comingling Option. The Comingling Option produces a more consistent water quality to the customers than does the Bypass Option. As an alternative or complement to using blended Trinity Aquifer and Lake Granger water, the Trinity Aquifer could be used for aquifer storage and recovery (ASR). Treated 1 Parsons Brinkerhoff Quade and Douglas, Inc. and Espey Consultants: Williamson County Water Supply Plan Groundwater Procurement, Implementation and Costs, prepared for the Brazos River Authority, July R.W. Harden and Associates and Freese and Nichols, Inc.: Assessment of the Use of Trinity Groundwater in Williamson County, Texas, prepared for the Brazos River Authority, July R.W. Harden and Associates and Freese and Nichols, Inc.: Results of Test Hole Drilling and Conceptual Design of Permanent Facilities, Trinity Aquifer, Williamson County, prepared for the Brazos River Authority, November May
2 surface water could be stored in the Trinity Aquifer during times of low demand or high flows and recovered for use at a later date. Pending further study ASR is not included as an option in Phase I at this time Available Yield Using the Brazos G WAM, the firm yield of Lake Granger is projected to decline from a yield of 17,017 acft/yr in the year 2020 to 14,192 acft/yr by Reservoir sedimentation is depleting conservation storage from its original permitted volume of 65,500 acft to a projected volume at year 2070 of 36,271 acft. Water from the Trinity Aquifer in the Lake Granger area is relatively high in dissolved solids. Phase I envisions blending Trinity Aquifer water with treated water from the EWCRWTP to reduce dissolved solids concentration. A ratio of 2 parts Lake Granger water to 1 part Trinity Aquifer water should meet drinking water standards. As a result, the amount of water available from the Trinity Aquifer is limited by the yield of Lake Granger. Table shows the potential supply from the first phase of this project, which ranges from about 8,500 acft/yr of additional supply in 2020 to about 7,100 acft/yr in This strategy could potentially be provided supply under the BRA System Operation permit (See Section 7.12), currently pending at the Texas Commission on Environmental Quality. If an entity other than the BRA were to sponsor and pursue this strategy, then an agreement with the BRA would be required to address concerns related to the potential subordination of the System Operation strategy. Table Potential Supply from First Phase of Lake Granger Augmentation Project (Values in acft/yr) Source Granger Lake Firm Yield 17,017 16,452 15,887 15,322 14,757 14,192 Amount of Trinity Aquifer Groundwater 8,509 8,226 7,944 7,661 7,379 7,096 Total 25,526 24,678 23,831 22,983 22,136 21,288 * assumes a 2:1 mixing ratio of Granger to Trinity water May 2015
3 Figure Phase I Conjunctive Use with Trinity Aquifer May
4 Figure Phase II Conjunctive Use with Carrizo-Wilcox Aquifer The second phase of the project calls for overdrafting Lake Granger during times of high flow, utilizing interruptible surface water from BRA System Operations. Surface water supplies will be supplemented by water from the Carrizo-Wilcox Aquifer when interruptible water from Lake Granger is not available. The conjunctive use project would develop a total supply of 53,361 acft/yr (7,096 acft/yr from Phase I in 2070 plus 46,265 acft/year from Phase II). A portion of the water from Phase II is used to firm up the 19,840 acft/yr of permitted diversions out of Lake Granger, of which only 14,192 acft/yr are firm in 2070 without the conjunctive use project. EWCRWTP customers and other water utilities in the distribution system are likely candidates for this additional water supply. The Brazos G WAM was utilized to simulate operations of Lake Granger supplemented with the groundwater pumping. In the WAM, it was assumed that all of the demand (less the Trinity Aquifer water from Phase I) was taken from Lake Granger when the reservoir was full and spilling. When the reservoir is less than full, demands on the reservoir are reduced as the storage declines and the remainder of the demand is met by pumping from the Carrizo-Wilcox Aquifer. Figure shows the storage trace for Lake Granger modeled with these assumptions. Based on these assumptions, the average pumping from the Carrizo-Wilcox Aquifer is 28,118 acft/yr with a maximum pumping of 51,831 acft/yr (Figure 6.1-4) May 2015
5 Figure Lake Granger Storage 2070 Conditions 40,000 35,000 Lake Granger Storage (acft) 30,000 25,000 20,000 15,000 10,000 5, Year Figure Annual Carrizo-Wilcox Pumping 2070 Conditions Groundwater Use Average 60,000 Carrizo-Wilcox Groundwater Pumping (acft/yr) 50,000 40,000 30,000 20,000 10, Year May
6 A review of groundwater availability for the Trinity Aquifer in Williamson County and the Carrizo-Wilcox Aquifer in Milam County shows that existing demands are equal to are greater than the Modeled Available Groundwater (MAG). Thus, the groundwater supply for the Lake Granger Augmentation Project may not be available as presented Environmental Issues Environmental impacts could include: Possible reduction in flood releases to the San Gabriel River downstream of Lake Granger Possible moderate impacts on riparian corridors depending on specific locations of pipelines Possible low impacts on instream flows due to slight decrease in groundwater discharges from the Carrizo-Wilcox Aquifer A summary of environmental issues is presented in Table Table Environmental Issues: Groundwater/Surface Water Conjunctive Use (Lake Granger Augmentation) Water Management Option Implementation Measures Environmental Water Needs/Instream Flows Bays and Estuaries Fish and Wildlife Habitat Cultural Resources Threatened and Endangered Species Comments Groundwater/Surface Water Conjunctive Use Construction of well fields, collection systems, pump stations, pipelines, and expansion of existing water treatment plant Possible impacts on instream flows Negligible impact Possible moderate impacts on riparian corridors and upland habitats depending on specific locations of pipelines Possible low impact Possible low impact Assume institutional transfer agreements among water rights owners, suppliers, and users Engineering and Costing Facilities for this option are shown in Figures and 6.1-2, and Table and Table For costing purposes, it is assumed that in Phase I potable water supply will be delivered to a point just north of the City of Taylor. In Phase II, delivery would be extended to a point between the Cities of Taylor and Georgetown. For Phase I, the Trinity Aquifer well field is assumed to require four wells located near the EWCRWTP. Because there is little current use from the Trinity Aquifer in this area, one test well was drilled in 2013 to verify productivity and water quality. Based on the results, it is concluded that the Trinity Aquifer near the EWCRWTP has greater productivity and a lower concentration of dissolved minerals than projected from the information available in the last plan. Other facilities include a well field collection system, May 2015
7 cooling towers (the water will most likely be hot), expansions to the EWCRWTP, and a 3.7-mile 36-inch treated water pipeline from EWCRWTP to an existing customer delivery point. This option also required a larger intake structure in Lake Granger, a new pump station and a 3.8-mile 48-inch raw water pipeline that have already been built by BRA. Conceptual designs and costs for the various components of these projects are based on studies performed for the Brazos River Authority between 2005 and The construction costs were updated to September 2013 prices and reformatted to be consistent with Brazos G practices. No evaluation was made to determine consistency of these costs with results from Unified Costing Tool, which is used by all regional planning groups. The total capital costs for Phase I is $59.4 million as shown in Table Additional costs for professional services, land acquisition, well mitigation, and interest during construction add $25.7 million for a total project cost of $85.1 million. Annual debt service on this principal amount, calculated on the basis of 5.5 percent interest for 20- year debt is $7.1 million. Operation and maintenance costs for pumping, transmission, and treatment to deliver a total annual supply of 25,526 acft (17,017 acft from Lake Granger in 2020 plus 8,509 acft from the Trinity Aquifer), as well as groundwater leasing and surface water purchase contracts must be accounted for to arrive at a unit cost of produced water. These additional costs of $7.8 million added to the annual debt service gives a total annual cost for the full project of $14.9 million. For Phase I, the unit cost of water is $584 per acft/yr or $1.79 per 1,000 gallons. Phase II will provide an additional 46,265 acft/yr of supply. The location of the well field for Phase II has not been identified. For the purposes of this study, it is assumed that the well field will be located in Milam County, although all or part of the required well field may be located in Burleson, Lee or other counties to the east of Williamson County. Carrizo-Wilcox groundwater will be gathered by a well-field collection system and transported by parallel 36-inch and 48-inch pipelines (built in phases) to a blending facility near the EWCRWTP. An additional 42-inch treated water pipeline will be built from the blending facility to the Phase I delivery point. Two parallel 38-inch and 42-inch pipelines (also built in phases) would deliver the water to a new customer delivery point between the cities of Taylor and Georgetown. Customers such as Chisholm Trail Special Utility District, Georgetown or Round Rock would need to build treated water pipelines to the delivery point. The Phase II total capital cost is $360.6 million as shown in Table Additional costs for professional services, land acquisition, well mitigation, and interest during construction add $276.5 million for a total project cost of $637.1 million. Annual debt service on this principal amount is $53.3 million. Annual costs for the new supply of 46,265 acft/yr, as well as groundwater leasing, regulatory groundwater withdrawal fees, and surface water purchase contracts must be accounted for to arrive at a unit cost of produced water. These additional costs of $21.2 million added to the annual debt service gives a total annual cost for the full project of $74.5 million. For Phase II, the unit cost of water is $1,611 per acft/yr or $4.94 per 1,000 gallons. Compensation to BRA may be required if this strategy were developed by another entity other than BRA to compensate for any subordination of the System Operations strategy. May
8 Table Cost Estimate Summary for Phase I of Lake Granger Augmentation (September 2013 Prices) Item Estimated Costs for Facilities Trinity Aquifer Well Field (4 wells) $24,369,000 EWCRWTP Expansions (12.5 MGD) $28,670,000 Treated water pipeline (36 in. dia., 3.7 miles) $4,453,000 Transmission Pump Station(s) $1,925,000 TOTAL COST OF FACILITIES $59,417,000 Engineering, Legal Costs and Contingencies $20,573,000 Environmental & Archaeology Studies and Mitigation $713,000 Land Acquisition and Surveying (37 acres) $219,000 Interest During Construction (1.5 years) $4,248,000 TOTAL COST OF PROJECT $85,170,000 ANNUAL COST Debt Service (5.5 percent, 20 years) $7,127,000 Operation and Maintenance $5,050,000 Pumping Energy Costs ( $/kw-hr) $1,191,000 Purchase of Water (25,526 $60.50/acft) $1,544,000 TOTAL ANNUAL COST $14,912,000 Available Project Yield (acft/yr) 25,526 Annual Cost of Water ($ per acft) $584 Annual Cost of Water ($ per 1,000 gallons) $ May 2015
9 Table Cost Estimate Summary for Phase II of Lake Granger Augmentation (September 2013 Prices) Item Estimated Costs for Facilities Carrizo-Wilcox Well Field (30 wells) $33,848,000 Pipeline from Well Field to EWCRWTP (36 & 48 in. dia. each 44 miles) $128,311,000 Blending Facility $9,993,000 EWCRWTP Expansions (83 MGD) $83,485,000 Treated water pipeline from delivery to customers (various dia., 68 miles) $68,617,000 Transmission Pump Stations $33,895,000 Treated water storage $2,417,000 TOTAL COST OF FACILITIES $360,566,000 Engineering, Legal Costs and Contingencies $116,765,000 Environmental & Archaeology Studies and Mitigation $4,322,000 Land and/or Groundwater Rights Acquisition $100,000,000 Land Acquisition and Surveying $4,371,000 Interest During Construction (3 years) $51,033,000 TOTAL COST OF PROJECT $637,057,000 ANNUAL COST Debt Service for Infrastructure (5.5 percent, 20 years) $53,309,000 Operation and Maintenance $10,990,000 Pumping Energy Costs 0.09 $/kw-hr) $5,725,000 Annual Cost to Purchase Water (Assumed $60.50 per acft) $2,799,000 Annual Groundwater Permitting Cost (Assumed $60.50 per acft) $1,701,000 TOTAL ANNUAL COST $74,524,000 Available Project Yield (acft/yr) 46,265 Annual Cost of Water ($ per acft) $1,611 Annual Cost of Water ($ per 1,000 gallons) $ Implementation Issues Early significant activity toward implementation of this startegy has been accomplished by the Brazos River Authority via its ownership of Lake Granger water supply, application for a systems operation permit, ownership of the existing water treatment plant on Lake Granger, and pursuit of nearby groundwater supplies. Developing a suitable approach to the evaluated level of groundwater pumping requires additional cooperative agreements May
10 with local groundwater districts and landowners. However, for purposes of regional planning, both Phase 1 and 2 projects overdraft the groundwater supply, which is inconsistent with required procedures as implemented by the TWDB. This water supply option has been compared to the plan development criteria, as shown in Table Potential Regulatory Requirements: Requirements for permits to use surface water and groundwater, as well as for pipeline construction, will require permits as follow: Local groundwater district pumping permits as needed. TCEQ water rights permit (pending) for BRA System Operations (Phase II) U.S. Army Corps of Engineers Section 404 permits for pipeline stream crossings, discharges of fill into wetlands and waters of the U.S. for construction, and other activities NPDES Stormwater Pollution Prevention Plans TP&WD Sand, Shell, Gravel, and Marl permit for construction in state-owned stream beds May 2015
11 Table Comparison of Lake Granger Augmentation to Plan Development Criteria Impact Category Comment(s) A. Water Supply 1. Quantity 1. Sufficient to meet needs 2. Reliability 2. Uncertain, dependent on acquiring groundwater 3. Cost 3. Reasonable (moderate to high) B. Environmental factors 1. Environmental Water Needs 1. Low impact 2. Habitat 2. Low to moderate impact 3. Cultural Resources 3. Low impact 4. Bays and Estuaries 4. Low impact 5. Threatened and Endangered Species 5. Low impact 6. Wetlands 6. Low impact C. Impact on Other State Water Resources No apparent negative impacts on state water resources; no effect on navigation D. Threats to Agriculture and Natural Resources E. Equitable Comparison of Strategies Deemed Feasible Low to None No. Groundwater availability does not consider MAG as other Options do F. Requirements for Interbasin Transfers Not applicable G. Third Party Social and Economic Impacts from Voluntary Redistribution None May
12 This page intentionally left blank May 2015
Update on Aquifer Storage and Recovery
Update on Aquifer Storage and Recovery Dean Powell Bureau Chief Water Supply Bureau Governing Board Workshop September 2013 Objectives Discuss the basics of aquifer storage and recovery (ASR) technology
RESTRICTING GROUNDWATER WITHDRAWALS TO PROTECT WATER RESOURCES: ECONOMIC IMPACT ASSESSMENT
CHAPTER 14 RESTRICTING GROUNDWATER WITHDRAWALS TO PROTECT WATER RESOURCES: ECONOMIC IMPACT ASSESSMENT Grace Johns and Lisa A. McDonald Economic analysis methods have been used in Florida to identify positive
City of Fort Collins Water Supply and Demand Management Policy
City of Fort Collins Water Supply and Demand Management Policy The City of Fort Collins Water Supply and Demand Management Policy provides a foundational framework for water supply and demand management
Clean Water Services. Ecosystems Services Case Study: Tualatin River, Washington
Viewed broadly, the concept of ecosystem services describes the many resources and services provided by nature. Typically, traditional planning and development practices do not adequately represent the
Michigan Wetlands. Department of Environmental Quality
Department of Environmental Quality Wetlands are a significant component of Michigan s landscape, covering roughly 5.5 million acres, or 15 percent of the land area of the state. This represents about
COMMUNITY CERTIFICATIONS
National Flood Insurance Program Community Rating System COMMUNITY CERTIFICATIONS Public reporting burden for this form is estimated to average 4 hours for annual recertification, per response. The burden
Series 2016A-2 (Green Bonds) Final Proceeds Allocation April 2016
Series 2016A-2 (Green Bonds) Final Proceeds Allocation April 2016 James L. McIntire Washington State Treasurer Summary The State of Washington offered green bonds to investors in September 2015, with approximately
COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES. April 20, 2010 EXHIBIT 1
COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES April 20, 2010 EXHIBIT 1 ELEMENT 4 WATER RESOURCES TABLE OF CONTENTS 4.1 INTRODUCTION 4.2 GOALS AND POLICIES 4.2.A General Goals and Policies 1 4.2.B
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers
Appendix A. Lists of Accomplishments and Project Costs. UMRWD 10 Year Plan Update. Appendix A UPPER MINNESOTA RIVER WATERSHED DISTRICT
UPPER MINNESOTA RIVER WATERSHED DISTRICT Lists of Accomplishments and Project Costs 10 Year Plan Update UMRWD 10 Year Plan Update Page A 1 UMRWD LIST OF ACCOMPLISHMENTS Since its inception in 1967, the
Flood Risk Management
Flood Risk Management Value of Flood Risk Management Every year floods sweep through communities across the United States taking lives, destroying property, shutting down businesses, harming the environment
Flood Risk Management
Flood Risk Management Value of Flood Risk Management Value to Individuals and Communities Every year floods sweep through communities across the United States taking lives, destroying property, shutting
1 INTRODUCTION. Kayenta Complex Page 9 December 2011 Cumulative Hydrologic Impact Assessment
1 INTRODUCTION The Office of Surface Mining Reclamation and Enforcement (OSMRE) is the regulatory authority for coal mining operations under the Surface Mining Reclamation and Control Act of 1977 that
INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY
ORDER NO. R5-2011-XXXX INFORMATION SHEET Background Triangle Rock, Inc. (Discharger) submitted a Report of Waste Discharge (RWD) on 23 August 2010. The Discharger is expanding the mining operations at
LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN
1 AUGUST 2011 LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN KEY ELEMENTS OF THE PLAN: 1. Replace the existing unsafe Ragged Mountain dam with a new dam and raise the reservoir pool level initially
CHECKLIST FOR FILING AN APPLICATION FOR A GROUND AND/OR SURFACE WATER WITHDRAWAL PROJECT IN THE DELAWARE RIVER BASIN
CHECKLIST FOR FILING AN APPLICATION FOR A GROUND AND/OR SURFACE WATER WITHDRAWAL PROJECT IN THE DELAWARE RIVER BASIN PLEASE COMPLETE CHECKLIST AND ENCLOSE WITH THE APPLICATION. If you need assistance,
Facing The Challenges In Houston s Water System: Past, Present, and Future
Facing The Challenges In Houston s Water System: Past, Present, and Future Jun Chang, P.E. D.WRE Deputy Director Department of Public Works and Engineering Presented to HCEC February 17, 2012 Past Regulatory
2011 MAJOR PROJECTS UPDATE - EAST WELLFIELD EXPANDED HYDROGEOLOGICAL STUDY AND WASTEWATER TREATMENT PLANT ZERO IMPACT ANALYSIS
Council November 28, 2011 2011 MAJOR PROJECTS UPDATE - EAST WELLFIELD EXPANDED HYDROGEOLOGICAL STUDY AND WASTEWATER TREATMENT PLANT ZERO IMPACT ANALYSIS ISSUE As a component of the Town s 2011 Major Projects
Proposed General Plan Update Goals, Policies, and Implementation Actions
Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental
1. INTRODUCTION 5. THE PERMIT PROCESS
1. INTRODUCTION Laws of the United States and the State of Iowa have assigned the US Army Corps of Engineers and the Iowa Department of Natural Resources with specific and different regulatory roles designed
How To Manage Water Resources In The Yakima Basin
Yakima Basin Integrated Water Resource Management Plan October 23, 2014 Presented by Derek Sandison, Director Office of Columbia River Photo Courtesy of Tom Ring Basin size: 6,155 sq. miles Population:
Roosevelt Water Conservation District ROOSEVELT WATER CONSERVATION DISTRICT
ROOSEVELT WATER CONSERVATION DISTRICT RESPONSE TO ARIZONA POWER AUTHORITY REQUEST FOR INFORMATION DATED SEPTEMBER 12, 2012 PRESENTED OCTOBER 24, 2012 RWCD is an irrigation district that was established
GOALS, OBJECTIVES AND POLICIES
GOALS, OBJECTIVES AND POLICIES The following goal, objective and policy statements have been developed for the use of local policy makers in guiding and directing the decision making process as it relates
General Frost-Freeze FAQs
General Frost-Freeze FAQs Groundwater Pumping: 1) Why do farmers use water to protect their crops during frost-freeze events? a. During frost-freeze events, farmers spray water onto their crops to protect
DISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, 2014. Values Statements.
DISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, 2014 Values Statements. The Board opposes any new transfers of water from the
Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1
Strategy Name: Reduce Existing Potential for Flood Damages LRSW-S3C1. Develop and implement a program to: Minimize flood damages through the use of structural measures. Minimize flood damages through the
2008 Compensatory Mitigation Rule: Overview and Highlights. Jenny Thomas U.S. Environmental Protection Agency Wetlands Division July 2014
2008 Compensatory Mitigation Rule: Overview and Highlights Jenny Thomas U.S. Environmental Protection Agency Wetlands Division July 2014 Outline Background Rule goals Rule structure 8 sections Highlight
ARIZONA DEPARTMENT OF WATER RESOURCES
ARIZONA DEPARTMENT OF WATER RESOURCES WATER MANAGEMENT REQUIREMENTS FOR SOLAR POWER PLANTS IN ARIZONA ADWR CONTACT: Jeff Tannler, Statewide Active Management Area Director Arizona Department of Water Resources
Section 5: Conserve to Enhance Program Goals What is Conserve to Enhance All About?
Section 5: Conserve to Enhance Program Goals What is Conserve to Enhance All About? Conserve to Enhance (C2E) was originally conceptualized as an approach to giving the environment a seat at the table
PUBLIC NOTICE Application for Permit
PUBLIC NOTICE Application for Permit 30-Day Notice Issue Date: June 20, 2016 Expiration Date: July 20, 2016 US Army Corps of Engineers No: NWP-2010-535 Oregon Department of State Lands No: 58311-RF Interested
Vista Ridge Water Transmission & Purchase Agreement
Vista Ridge Water Transmission & Purchase Agreement Doug Evanson Senior Vice President/Chief Financial Officer Rates Advisory Committee Concentric Sources of Supply Canyon Lake Trinity Aquifer CRWA Lake
Water Utility Financial Plan and Rates Study
FINAL March 2015 Prepared for City of Fresno, California Water Utility Financial Plan and Rates Study Submitted by F I N A L Water Utility Financial Plan and Rates Study Prepared for City of Fresno, California
Coldwater Heritage Partnership Implementation Grant Final Report Morrison Run Watershed Restoration Project Western Pennsylvania Conservancy Project Summary The goal of the Morrison Run Watershed Restoration
Chapter 9. Selected Watershed Initiatives in the Great Basin Region
Chapter 9 Selected Watershed Initiatives in the Great Basin Region The Great Basin contains vast areas of sparsely populated desert lands. Lacking an ocean drainage, the Great Basin is a hydrologic sink
LR 314 Working Group 5 Final Report
LR 314 Working Group 5 Final Report I. Nebraska Department of Natural Resources Table 1. NDNR and NATURAL RESOURCES COMMISSION WATER/INTEGRATED MANAGEMENT PLANNING RELATED RESEARCH, STUDIES AND RELATED
Natural Resource-Based Planning*
Natural Resource-Based Planning* Planning, when done well, is among the most powerful tools available to communities. A solid plan, based on good natural resource information, guides rational land-use
Section 4 General Strategies and Tools
Section 4 General Strategies and Tools Key planning issues for WRIA 35 have been identified in Sections 5 and 6 in the areas of water supply, instream flow, water quality, and aquatic habitat. General
DEQ Response to Comments regarding the Public Notice for a Coal Mining Project in the Panther Creek watershed In Craig and Nowata Counties.
DEQ Response to Comments regarding the Public Notice for a Coal Mining Project in the Panther Creek watershed In Craig and Nowata Counties. There were 10 comments received in response to an April 14, 2014
Wildlife Habitat Conservation and Management Program
Wildlife Habitat Conservation and Management Program Manual for Counties and Cities Oregon Department of Fish and Wildlife 2015 Table of Contents 1. Introduction Purpose of the habitat program Objective
CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE
1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,
Building Resilient Infrastructure for the 21 st Century
Building Resilient Infrastructure for the 21 st Century 1 Maria Mehranian Cordoba Corporation & Los Angeles Regional Water Quality Control Board October 19, 2014 24 th Annual Lake Arrowhead Symposium:
How To Plan A Buffer Zone
Backyard Buffers Protecting Habitat and Water Quality What is a buffer? A buffer (also called a riparian buffer area or zone) is the strip of natural vegetation along the bank of a stream, lake or other
Comparative Evaluation of Generalized River/Reservoir System Models. by Ralph A. Wurbs Civil Engineering Department Texas A&M University
Comparative Evaluation of Generalized River/Reservoir System Models by Ralph A. Wurbs Civil Engineering Department Texas A&M University TR-282 Texas Water Resources Institute College Station, Texas April
U.S. Army Corps of Engineers Tulsa District
U.S. Army Corps of Engineers Tulsa District Mike Abate, PMP. Chief, Civil Works Branch, PPMD April 17, 2015 US Army Corps of Engineers Civil Works Mission Water Supply 50% of Corps water supply contracts
Water Extraction Permitting Policy
Water Extraction Policy 1 Water Extraction Permitting Policy Department of Environment, Labour & Justice January 2013 Water Extraction Policy 2 EXECUTIVE SUMMARY This document establishes a new policy
SPECIAL USE PERMIT 22-01. JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing
SPECIAL USE PERMIT 22-01. JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing This report is prepared by the James City County Planning Division
REFERENCE. All National Grid personnel who plan and perform work involving protected water resources are responsible for:
EG-30NY ENVIRONMENTAL GUIDANCE PAGE 1 of 9 DATE 10/1/10 EP 3 Natural Resource Protection 1.0 SCOPE AND RESPONSIBILITIES National Grid s New York service territory encompasses thousands of wetlands, lakes,
Briefing Paper on Lower Galveston Bay and Bayou Watersheds Lower Bay I: Armand Bayou to Moses Lake and Adjacent Bay Waters
Briefing Paper on Lower Galveston Bay and Bayou Watersheds Lower Bay I: Armand Bayou to Moses Lake and Adjacent Bay Waters Jim Lester, PhD. and Lisa Gonzalez Houston Advanced Research Center Galveston
4. Environmental Impacts Assessment and Remediation Targets
4. Environmental Impacts Assessment and Remediation Targets 4.1 Environmental Impacts Significant additional development in the Alder Creek watershed is not anticipated at this time; however, there are
Addressing Declining Elevations in Lake Mead
Integrated Resource Planning Advisory Committee July 23, 2014 Addressing Declining Elevations in Lake Mead 1 Meeting Topics Drought update Attribute finalization Interbasin Cooperation Intake Pumping Station
A Long-Range Plan: Melbourne s Drinking Water Supply
April 2002 A Long-Range Plan: Melbourne s Drinking Water Supply The long-term water supply of South Brevard County must be dependable, flexible, and affordable. With those goals in mind, we continue to
Upper Des Plaines River & Tributaries, IL & WI Feasibility Study
Upper Des Plaines River & Tributaries, IL & WI Feasibility Study Jeffrey Zuercher Project Manager Chicago District February 19, 2014 Study Partnership: US Army Corps of Engineers Agenda Background Study
As stewards of the land, farmers must protect the quality of our environment and conserve the natural resources that sustain it by implementing
N A T U R A L R E S O U R C E C O N S E R V A T I O N As stewards of the land, farmers must protect the quality of our environment and conserve the natural resources that sustain it by implementing conservation
Recycled Water for Cooling Towers
Recycled Water for Cooling Towers City of Santa Clara Alan Kurotori, P.E. Director of Water & Sewer Utilities Critical Facilities Round Table April 15, 2010 Presentation Overview Water Supply Where do
Prepared By: Eric Chamberlain
Prepared By: Eric Chamberlain Drainage 101 So, What s a Municipal Drain??? It is a Drainage System either open ditch or enclosed pipe system or any other water control structure Petitioned for by landowners
Greater Los Angeles County Region
Attachment 6 Greater Los Angeles County Region IRWM Implementation Grant Proposal Monitoring, Assessment, and Attachment 6 consists of the following items: Monitoring, Assessment, and. The purpose of this
United States Depmiment of the Interior Bureau of Reclamation Western Colorado Area Office Grand Junction, Colorado
WCAO-GJ-FONSI -14-01 United States Depmiment of the Interior Bureau of Reclamation Western Colorado Area Office Grand Junction, Colorado FINDING OF NO SIGNIFICANT IMPACT SPURLIN MESA LATERAL OF THE CRAWFORD
Flood Plain Reclamation to Enhance Resiliency Conserving Land in Urban New Jersey
Flood Plain Reclamation to Enhance Resiliency Conserving Land in Urban New Jersey Rutgers Cooperative Extension Water Resources Program Christopher C. Obropta, Ph.D., P.E. Email: [email protected]
Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002
Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed Summary Report 2002 DOE/BP-00005268-5 November 2002 This Document should be cited as follows: "Restoring Anadromous Fish Habitat in Big Canyon
NAPA COUNTY WATERSHED SYMPOSIUM
Planning, Building, and Environmental Services NAPA VALLEY GROWTH NAPA COUNTY WATERSHED SYMPOSIUM Plunging Forward May 15, 2015 1 YOU CAN T CROSS THE SEA MERELY BY STANDING AND STARING AT THE WATER. Rabindranath
Urban Stream Restoration Defining the Full Benefits of a Project. Warren C. High MACTEC Engineering and Consulting
Urban Stream Restoration Defining the Full Benefits of a Project Warren C. High MACTEC Engineering and Consulting Economics in the Decision Process Return on Investment Willingness to Pay Municipal Growth
LDPCSD Water Supply Emergency Response Plan Status Update 2-4-15
LDPCSD Water Supply Emergency Response Plan Status Update 2-4-15 1 EMERGENCY OVERVIEW The Lake Don Pedro Community Services District (LDPCSD) provides domestic potable water service to 1450 connections
CALIFORNIA AMERICAN WATER LOS ANGELES DISTRICT 2009 GENERAL RATE CASE CHAPTER: 1 INTRODUCTION AND SUMMARY OF APPLICATION
DISCUSSION OF INFORMATION PRESENTED IN THIS CHAPTER This chapter contains information regarding the operation of the Los Angeles District of California American Water as well as tables that summarize the
QUESTIONS AND ANSWERS WATERS OF THE U.S. PROPOSAL
QUESTIONS AND ANSWERS WATERS OF THE U.S. PROPOSAL Key Background Congress enacted the modern Clean Water Act in 1972 to address pollution entering the nation s waters to complement statutes such as the
TEXAS UTILITY LAWYERS 2015 ANNUAL MEETING SAN ANTONIO, TX OCTOBER 15, 2015 CHARLES R. YARBROUGH, II AND JAREN A. TAYLOR
TEXAS UTILITY LAWYERS 2015 ANNUAL MEETING SAN ANTONIO, TX OCTOBER 15, 2015 CHARLES R. YARBROUGH, II AND JAREN A. TAYLOR The views expressed in this presentation represent those of the author only and are
~xccuti\lc :Bcpertmcnt
~xccuti\lc :Bcpertmcnt ~tote of ~lifornia EXECUTIVE ORDER B-29-15 WHEREAS on January 17, 2014, I proclaimed a State of Emergency to exist throughout the State of California due to severe drought conditions;
Arkansas River Corridor Vision & Master Plan
A r k a n s a s R I v e r C o r r I d o r P l a n Arkansas River Corridor Vision & Master Plan July 2005 Indian Nations Council of Governments A r k a n s a s R I v e r C o r r I d o r P l a n Partnership
Hydrologic Engineering Techniques for Regional Water Resources Planning
US Army Corps of Engineers Hydrologic Engineering Center Hydrologic Engineering Techniques for Regional Water Resources Planning October 1969 Approved for Public Release. Distribution Unlimited. TP-17
Table 2: State Agency Recommendations Agency of Agriculture, Food and Markets
SUPPORTING INFORMATION ASSOCIATED WITH THE ALLOCATION PRIORITIES FOR CLEAN WATER FUND BOARD Table 2: State Agency Recommendations Agency of Agriculture, Food and Markets 1 Agriculture AAFM On-Farm Implementation
HCP Team Meeting. November 18, 2015. icfi.com
HCP Team Meeting November 18, 2015 icfi.com 1 Welcome and Introductions Where are we in the HCP process Hydrology modeling update Native fish survey Fish translocation Finalize covered activities Next
The Everglades & Northern Estuaries; St. Lucie River Estuary, Indian River Lagoon & Caloosahatchee Estuary. Water Flows & Current Issues
The Everglades & Northern Estuaries; St. Lucie River Estuary, Indian River Lagoon & Caloosahatchee Estuary Water Flows & Current Issues Florida Governor Rick Scott August 20, 2013 Upper Chain of Lakes
Peace River Basin Resource Management Plan - Action Items Status Report for the Peace River Basin Management Advisory Committee Meeting
Peace River Basin Resource Management Plan - Action Items Status Report for the Peace River Basin Management Advisory Committee Meeting December 2010, Mid-Meeting Update (October 15, 2010) In its Peace
5. Environmental Analysis
5.11 The potential for adverse impacts on utilities and service systems was evaluated based on information concerning current service levels and the ability of the service providers to accommodate the
Evaluation of Site-Specific Criteria for Determining Potability
Evaluation of Site-Specific Criteria for Determining Potability and Cleanup Goals for Impacted Groundwater This paper presents considerations used to evaluate site-specific criteria for determining groundwater
Susan Iott U. S. General Accounting Office. Restoration of the South Florida Ecosystem
Susan Iott U. S. General Accounting Office Restoration of the South Florida Ecosystem Presented at The Aspen Global Change Institute June 5-10, 2003 Summer Science Session I Learning from Regions: A Comparative
The Dungeness Water Exchange Mitigation Guidance Document. April 2013
The Dungeness Water Exchange Mitigation Guidance Document April 2013 Prepared by Washington Water Trust 1530 Westlake Avenue N, Suite 400 Seattle, WA 9810 Table of Contents- Dungeness Water Exchange Mitigation
A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1
A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1 J. Bonham 2 and K. Stephenson Abstract Recently the US Army Corps of Engineers (the Corps) has increased
STATEMENT OF SHARON BUCCINO SENIOR ATTORNEY NATURAL RESOURCES DEFENSE COUNCIL WASHINGTON, DC
STATEMENT OF SHARON BUCCINO SENIOR ATTORNEY NATURAL RESOURCES DEFENSE COUNCIL WASHINGTON, DC Good morning. My name is Sharon Buccino. I am an attorney with the Natural Resources Defense Council (NRDC).
Leveraging Ohio s Clean Water SRF Program to Fund Stream and Wetland Restoration and Protection Projects
Leveraging Ohio s Clean Water SRF Program to Fund Stream and Wetland Restoration and Protection Projects Association of State Wetland Managers 2014 State/Tribal/Federal Coordination Meeting Shepherdstown,
