Pole Guying More Complicated Than Meets the Eye. NRECA TechAdvantage 2014 Presented by Jason Settle, P.E. jason.settle@gdsassociates.



Similar documents
V.A PJM Design and Application of Overhead Transmission Lines 69kV and Above

Requirements for the Attachment of Communication Cable Facilities on PPL Poles

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

System. Stability. Security. Integrity. 150 Helical Anchor

Chapter 3 Pre-Installation, Foundations and Piers

Schedule-4(A3) Page 1 of 5. Specification No.: JPL/KWTL/A3 (Package-A3) To: Bidder's Name & Address

Transmission Foundations. helical piles and guy anchors for transmission structures.

When power interruptions happen.

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

PRESTRESSED CONCRETE POLES The Solid Alternative to Wood

Figure A-1. Figure A-2. continued on next page... HPM-1. Grout Reservoir. Neat Cement Grout (Very Flowable) Extension Displacement Plate

CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION

Stability. Security. Integrity.

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars

AERIAL FIBER OPTIC CABLE PLACEMENT

BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE

ENCE 4610 Foundation Analysis and Design

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

TECHNICAL MEMORANDUM

The minimum reinforcement for the stem wall is the placement of:

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

load on the soil. For this article s examples, load bearing values given by the following table will be assumed.

Please check with your local inspection authority for any additional requirements before installation.

SUPPLEMENT TO SPECIFICATIONS FOR ELECTRICAL INSTALLATIONS

Installation Instructions Hustler 6-BTV Trap Vertical

Activity 2.3b Engineering Problem Solving Answer Key

EMERGENCY HOME PROTECTION. Homeowner's Guide for Emergency Flood Control. Contents INTRODUCTION

International Greenhouse Company

Hendrix Spacer Cable

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

5/1/2013. Topics. The challenge is to better maintain native characteristics of soils during and after construction

PUMP JACK SYSTEM AND ACCESSORIES

IRRIGATION PUMPING Table of Contents - Section 900

SECTION UNDERGROUND ELECTRIC SERVICE

Spool Tie. RUS Accepted NOMENCLATURE GENERAL RECOMMENDATIONS (440)

Screw Thread Design. Rev

Vertical Break Parallel (VBP) / Vertical Break Slant (VBS)

TS 813 GROUNDING AND BONDING TTD TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD CONTROLLER CABINET GROUNDING

Residential Deck Safety, Construction, and Repair

POLE MOUNT SYSTEM-3 INSTALLATION

STANDARD OPEN PATIO COVER

The Stabilizer TM. Benefits. Supplemental support system for sagging beams and floor joists within a crawl space

Transmission Silicone Insulators Line Post 69 kv to 161 kv

INSTALLATION INSTRUCTIONS HUSTLER 4-BTV, 5-BTV TRAP VERTICAL WARNING INSTALLATION OF THIS PRODUCT NEAR POWER LINES IS DANGEROUS

How to Design Helical Piles per the 2009 International Building Code

6 RETROFITTING POST & PIER HOUSES

POLE MOUNT SYSTEM EX-3 INSTALLATION

EZ-48-3AB Weather Station Mounting Tripod and Mast

By SP Partners, LLC. INSTALLATION GUIDE. Prestige

MOBILE HOME SERVICE REQUIREMENTS GAS

Veri*Lite Silicone Rubber Line Post Insulators for 15-69kV Applications

Shaft- Mounted Speed Reducers

C O N V E Y O R C O M P O N E N T S C H A I N S B E L T S B E A R I N G S

Rating when used as a weight carrying hitch without spring bars:

The Verdura Wall check with your local building department

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

March 14, Installation of Bay, Bow and Garden Windows

Dynamic Load Testing of Helical Piles

DISTRIBUTION SYSTEMS INDEX NOV 06 SECTION 2. Detroit Ann Arbor Mt. Clemens Port Huron

Ceiling Mounted Folding Attic Ladders Installation Instructions

758 Heavy-duty Ratchet Guy Wire Cutter

Trundle Bed Plans (For Use Under Twin or Full-Size Standard Length Beds)

Helical Pier Foundation System U.S. Patents 5,011,336; 5,120,163; 5,213,448

POST AND FRAME STRUCTURES (Pole Barns)

SECTION GUARDRAILS

Design of Steel Structures Prof. S.R.Satish Kumar and Prof. A.R.Santha Kumar. Fig some of the trusses that are used in steel bridges

1 Town of Lyons Electrical Distribution System Design Standards

Type of Force 1 Axial (tension / compression) Shear. 3 Bending 4 Torsion 5 Images 6 Symbol (+ -)

c. Borehole Shear Test (BST): BST is performed according to the instructions published by Handy Geotechnical Instruments, Inc.

ALLOWABLE LOADS ON A SINGLE PILE

COMMERCIAL CONDUIT RULES AND REGULATION

RPS - sales@rpssolar.com San Bruno Cove, San Diego, CA 92130

Steel Bridge Design E90 Project Proposal

Transmission Foundations Case History : Helical piles Hydro One Networks Inc.

Residential Foundations and Basements

LAYING BLOCK AND BRICK

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Mobile Home Pre-Inspection Checklist

Electrical Service Guidelines

MAST ARMS & POLES. Ornamental Pole Top & Bases

Quick fix for frost heave:

Additions and Alterations

TYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

3M Mobile SkyWalk Series Horizontal Lifeline Product Return Form

Building Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County

STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13

Hi*Lite XL Transmission Insulators

GUY-GRIP Dead-end NOMENCLATURE GENERAL INFORMATION SAFETY CONSIDERATIONS (440)

Aerial Fibre Optics. Complete One Stop Solution for Aerial Fibre Optics. OPGW Cable and Fittings for OPGW

ANTENNA PARTS CATALOG

MERCHANTS METALS SECTION ARMORLINK ALUMINIZED CHAIN LINK FENCE AND GATES 2014!

This mount uses concrete parking bumpers and a Davis tripod to create a mounting solution for nonpenetrable

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

SERIES ASM NEOPRENE/EPMD FLANGED SINGLE SPHERE CONNECTOR CONNECTORS. Pressures to 225 PSIG (15.51 barg) Temperatures to 230ºF (110ºC)

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

SECTION CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

ATS Overhead Table Shelf System INSTRUCTION MANUAL

Transcription:

Pole Guying More Complicated Than Meets the Eye NRECA TechAdvantage 2014 Presented by Jason Settle, P.E. jason.settle@gdsassociates.com

Pole Guying Strength of components NESC vs. RUS Guy Factor Grounding 2

Pole Guying Purpose Support fully loaded design tension of conductors Applied wind and ice load 3

The Components of a Guyed Structure Guy Attachment Guy Attachment Height Guy Pole Anchor Guy Lead 4

The strength of the guy-anchor assembly is dependent on: Strength of the guy wire de-rated to 90% of the RBS (NESC Table 261-1) Strength of the guy attachment including the bolt and washer Strength of the anchor and rod Holding power of the soil in which the anchor is installed Only as Strong as the Weakest component 5

Guy Hardware 6

Thimble-eye Bolt 7

Johnny Ball & Guy Strain Insulator 8

Guy Wire Strength Data 9

RUS Guy Assemblies & Strength Assembly Item Material E1.1 E1.1L E1.2 b Bolt, machine 5/8 (12,400 lbs) 3/4 (18,350 lbs) None d Washer, curved 3 square (7,800 lbs) v Guy attachment Standard (6,600 lbs) y Guy wire 3/8 SM (6,255 lbs) 4 square (14,200 lbs) Heavy Duty (8,500 lbs) 3/8 HS steel (9,720 lbs) None 90% of guy wire 7/16 SM (8,415 lbs) Total Guy Strength 6,255 lbs 8,500 lbs 8,415 lbs 10

11

RUS Standard Washer Allowed Load RUS standards allow no more than 910 pounds per square inch of compression for washers on wood poles and crossarms. 12

13

14

RUS Standard Distribution Anchor Assemblies Anchor Type Expanding Screw (Power Installed) RUS Designation Maximum Holding Power (lbs)* F1.8 8,000 F1.10 10,000 F1.12 12,000 F2.8 8,000 F2.10 10,000 F2.12 12,000 *Maximum Holding Power based on installation in Class 5 Soil 15

Types of Soils for Anchor Placement Class Description Soil Class Descriptions 1 Solid rock 2 Dense sand, hard silts, course gravel 3 Compact clay & gravel mixed, shale, hardpan 4 Compacted sand, clay-pan, compacted gravel 5 Loose sand, gravel & clay, compacted course sand 6 Clay loam, damp clay, compacted fine sand, loose course sand 7 Silt loam, loose sand fines, wet clay, miscellaneous fill 8 Swamp, saturated loam, marshland 16

Expansion Anchors Rating (pounds) 6,000 8,000 10,000 12,000 Item Anchor Rod F1.6 F1.8 F1.10 F1.4 x Anchor Rod 5/8 x 7 5/8 x 7 N/A N/A Thimble Eye x Anchor Rod N/A N/A 3/4 x 8 3/4 x 8 Twin Eye z Anchor (sq. in.) 90 100 120 135 17

Expansion (Bust) Anchors Un-expanded Anchor Expansion Tool Illustration courtesy of Hubble Power Systems (Chance) 18

Screw Anchors Single Helix Double Helix Illustration courtesy of Hubble Power Systems (Chance) 19

20

Spacing of Anchors 5 feet 5-ft for standard duty 8-ft for heavy duty 21

Guying Situations Change in conductor size New wire sagged against old wire Line angles Dead-ends Grade B Crossings Spans that exceed the ruling span by 150% Long crossings 22

Guy & Anchor Selection Depend on: Horizontal pull at the guy attachment Guy resultant tension in the down guy Soil type in which the anchor is installed Available materials and assemblies 23

Standard Guy and Anchor Assemblies Guys Anchors E1.1 ( 6,255 lbs) F1.6 (6,000 lbs) E1.1L (8,500 lbs)* F1.8 (8,000 lbs) E1.2 (9,720 lbs)* F1.10 (10,000 lbs) * 3/8 HS steel 24

Guy & Anchor Grade of Construction RUS requires Minimum Grade C on distribution Must match highest Grade of construction on pole Transmission underbuild Grade B Railroad, Limited Access Hwy Grade B 25

Type of Guy Loads Transverse Forces acting perpendicular to the line Wind blowing on ice loaded conductors Tension in the wire Longitudinal Forces acting parallel to the line Maximum loaded design tension 26

Deadend Guying Calculations Tension A,B,CΦ Height Neutral Height Guy Height (Hg) Guy Lead (Lg) 27

Dead-end guying Gh = Mt/Hg Gh = Horizontal pull at guy attachment Mt = Sum of moments due to tension in the wire Hg = Average guy attachment height NESC construction grade = C NESC loading district = Light Primary cond. = 1/0 ACSR 6/1, Neutral cond. = 2 ACSR 7/1 Pole height and class = 40 ft, Class 4, SYP Pole-top assembly = C5.71L (RUS Assembly) 28

*NESC Load factors for deadend guyed structures defined in Rule 250B Type of Loading Grade B Grade C Crossing Elsewhere Transverse wind 2.50 2.20 1.75 Transverse wire tension Longitudinal load at dead-ends 1.65 1.10 1.10 1.65 1.10 1.10 *Adapted from NESC Table 253-1, 2012 Edition 29

*NESC Load factors for Extreme Weather when applicable Type Loading Rule 250 C Extreme Wind Grade B Crossing Grade C Elsewhere Wind Loads 1.00 0.87 0.87 All other loads 1.00 1.00 1.00 Rule 250D Extreme ice with concurrent wind 1.00 1.00 1.00 *Adapted from NESC Table 253-1, 2012 Edition Applied to NESC 250B load if a structure or its supported facilities exceed 60 feet above ground or water. 30

Transverse Wind Load for 1-ft of Conductor Conductor Physical Data Transverse Wind Name Size/Strand Dia. (in) RBS (lb) Light (lb/ft) Medium (lb/ft) Heavy (lb/ft) Sparate Raven Penguin Merlin 2 ACSR 7/1 1/0 ACSR 6/1 4/0 ACSR 6/1 336 ACSR 18/1 0.325 3640 0.2438 0.2750 0.4417 0.398 4380 0.2985 0.2993 0.4660 0.563 8350 0.4223 0.3543 0.5210 0.684 8680 0.5130 0.3947 0.5613 31

Step 1: Moment Due to Tension (Mt) Mt = Σ(Dt Hc Ft) Mt = Moment due to tension in the wire DT = Fully loaded design tension DT = 50% RBS 1/0 ACSR = 0.50(4,380 lbs) = 2,190 lbs 2 ACSR = 0.50(3,640 lbs) = 1,820 lbs Hc = Height of conductor above grade (RUS C5.71L) Ft = NESC wire tension load factor = 1.10 (grade C) 32

Step 1: Moment due to tension (Mt) Wire DT(lb) x Hc (ft) x Ft (ft) = Mt(ft-lb) A-phase 2190 x 32.5 x 1.10 = 78,293 B-phase 2190 x 32.5 x 1.10 = 78,293 C-phase 2190 x 32.5 x 1.10 = 78,293 Neutral 1,820 x 28.5 x 1.10 = 57,057 Σ(Dt Hc Ft) = 291,936 Mt = 291,936 ft-lbs 33

Step 2: Horizontal Pull (Gh) Gh Mt Hg Hg = Height of guy attachment = 31.75-ft (RUS drawing C5.71L) Mt = 291,936 ft-lbs Gh = 291,936/31.75 = 9,195 Gh = 9,195 lbs 34

Guy Resultant or Total Guy Load (Gr) Gr Gh Lg 2 Lg Hg 2 Gr = Guy resultant tension (lbs) Gh = Horizontal pull at guy attachment (lbs) Hg = Height of guy attachment (ft) Lg = Guy lead length (ft) 35

Guy Resultant for Example 1 (Equation Method for 1:1 Guy Lead) Gr Gh Lg 2 Lg Hg 2 Gr 9,195 2 31.75 31.75 31.75 2 13003.69lbs Total Guy Load (Gr) = 13,004 lbs 36

Guy Factors Gf Lg2Hg2 Lg Hg Gf = Guy Factor Lg = Guy lead length Hg = Guy attachment height Lg 37

Guy Factors 30 30 30 Gf 30 302 302 30 1.414 Gf 20 202 302 20 1.803 Gf 15 1 to 1 2 to 3 1 to 2 152 302 15 2.236 38

Guy Resultant for Example 1 (Guy Factor Method) Gr Gh * Gf 1:1 Guy Lead Gr 9,195*1.414 13,001lbs 2:3 Guy Lead Gr 9,195*1.803 16,579 lbs 1:2 Guy Lead Gr 9,195* 2.236 20,560 lbs 39

Guy Leads Specify and stake adequate guy leads Not based on truck setup Short guy leads can cause Significant increase in total guy load Pole buckling due to the vertical component of guy tension Buckling Guy Lead 40

Pole Buckling Short Guy Leads Small Pole Class Heavy Wire Tension Specify a larger class pole 41

Guy Factors Guy Lead (ft) Guy Attachment Height (ft) 30 32 34 36 38 40 42 10 3.16 3.35 3.54 3.74 3.93 4.12 4.32 15 2.24 2.36 2.48 2.60 2.72 2.85 2.97 20 1.80 1.89 1.97 2.06 2.15 2.24 2.33 25 1.56 1.62 1.69 1.75 1.82 1.89 1.96 30 1.41 1.46 1.51 1.56 1.61 1.67 1.72 35 # # # 1.43 1.48 1.52 1.56 40 # # # # # 1.41 1.45 42

43

Clearance from Guys to Other Conductors Adapted from NESC Table 235-6 Bare Guy Wire Insulator Link Secondary and Neutral 6 inches 4.5 inches 12 kv Primary 6 inches 4.5 inches 25 kv Primary 10 inches 7.5 inches 44

Code Violation! 45

Grounding Anchor Guys and Span Guys Rule 215C2 All anchor guys and span guys shall be effectively grounded. Only EXCEPTION is to use a guy insulator Fiberglass guy strain insulators Johnny Balls used in the past Eliminated EXCEPTION for triplex service conductors Guys on secondary poles must be grounded Big change for many utilities Per Bulletin 1724E-153 RUS considers it to be nonstandard construction when guy wires are not effectively grounded. 46

RUS Use of Insulator Links RUS calls for insulator links on 12 kv systems when there is less than 15 inches of wood separating guy attachment and phase associated hardware. RUS also calls for the lower portion of the guy to be grounded. Thus it meets the requirements of 215C2 Insulator link used for two reasons 1. Increase BIL on the structure 2. Provide for increased spacing between phase conductors and ground conductors as one means of providing safety to lineman. 47

Guy on secondary pole must be grounded Guy must be grounded or have guy strain insulator 48

Grounded Guy Grounded guy near to phase associated hardware Susceptible to flashover from lightning Solution 1. Lower guy RUS says 18 inches 2. Install guy insulator Still ground the lower part of the guy Guy Attachment 49

Guy Insulator Link Common mistake is to assume the guy insulator link must extend past lower conductors Not a NESC requirement To achieve BIL goals 18 inches is long enough To achieve working space Some use 36 inches 50

Span Guys Span guy is grounded at structure At stub pole Grounding jumper from span guy to down guy RUS requires grounding nut in anchor eye 51

52

Pole Guying Verify/Know your material/inventory. Be careful of short guy leads RUS - insulate and ground Questions? 53