Love Field Modernization Program (LFMP) & Airport Electronic Systems Management (AESM) Status Update

Similar documents
Bozeman Yellowstone International Airport Media Guide

AIRPORT ROUNDTABLE. Moderator: Kiel Barnekov, Manager of Projects & Programs, Greater Orlando Aviation Authority

PHOENIX-MESA GATEWAY AIRPORT AUTHORITY 5835 S. Sossaman Road Mesa, Arizona TELEPHONIC BOARD MEETING AGENDA. Monday, August 27, :50 a.m.

PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015

Basic Airport Security Awareness

FRAConnect Incentive program

Materna Integrated Passenger Services (Materna ips)

PHOENIX SKY HARBOR AIRPORT ADVERTISING MEDIA KIT 2015

TSA Implementation - Airport Security Initiatives 2011

LUBBOCK PRESTON SMITH INTERNATIONAL AIRPORT EMERGENCY CONTINGENCY PLAN

Info NEWS MEDIA GUIDE

Measurement Standards for Structures

How To Operate An Airport Security System At Love Field

AIR PASSENGER RIGHTS EU COMPLAINT FORM

Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program

Customer Service Plan. (Issued in Compliance with 14 CFR Part 259)

ป งบประมาณ พ.ศ.๒๕๕๘ ( ๑ ต ลาคม ๒๕๕๗ ถ ง 30 ก นยายน ๒๕๕๘ ) สร ปผลปร มาณงานพ สด การจ ดซ อ/จ าง/เช า ในรอบเด อนพฤศจ กายน ๒๕๕๗ ส าน กงานท ด นจ งหว ดเช

Software Centre 4 th June 2015

Aerodrome Advisory Circular

END TO END AIRPORT. PASSENGER ANALYTICS November 9, 2015

REQUEST FOR PROPOSALS

AIRPORT SECURITY BADGING PROGRAM PRESCOTT MUNICIPAL AIRPORT

Airport IT Services for Airlines. Kiel Barnekov, Manager Programs & Projects Greater Orlando Aviation Authority

Airport Performance Measurement

Business Information Technology. Airport Roundtable. ACI-NA Annual Conference and Exhibition BIT Workshop Atlanta, GA September 7, 2014

Social Narrative AIRPORT INSTRUCTION & READINESS. miami-airport.com/miaair.asp

LONG-TERM INFRASTRUCTURE DEVELOPMENT PLAN

Checking in at an airport check-in machine. Checking in at an airport check-in machine

Reservation agents must be at least 18 years old. High school graduation is required and some college or work related experience is desired.

Emerging Challenges in the Master Planning Process Airport Master Plans: Standing the Test of Time. Doug Trezise Ricondo & Associates, Inc.

K+P. Munich Airport International Terminal 2. Architekten und Stadtplaner GmbH Koch Voigt Zschornack

Common Use Systems and PCI Compliance

RFID in an airport is an excellent business case. Jan Zacho, Sector Manager IT-infrastructure operations Copenhagen Airports

SAFETY, SECURITY, AND OPERATIONAL EXCELLENCE

Flying with a ventilator in the USA

Walt Disney World Walt Disney World Walt Disney World Walt Disney World Walt Disney World Walt Disney World Walt Disney World

Charlotte County Airport

Los Angeles World Airports Information Technology Strategic Plan Fiscal Year November 2013

Nate Smith Executive Vice President DFW International Airport DALLAS/FORT WORTH INTERNATIONAL AIRPORT

Academy teachers and Industry Partner staff jointly developed and facilitate the programme.

Lee County Port Authority. Southwest Florida International Airport Emergency Contingency Plan

Notification of Request for Authorization under the Degree-Granting Institutions Act Date posted: December 14, 2015

How To Improve Your Airport Experience

Operating a Concession Business at Seattle-Tacoma International Airport

This SAS Plan is adopted for all scheduled flights operated by SAS to and from the US.

AGENCY: Federal Aviation Administration (FAA), Department of Transportation.

MANAGING THE MANAGEMENT SYSTEMS Business Information Technology

Building Bridges for Airport Customer Service & Enhancing the Customer Experience

AIRPORT DESIGN AND CONSTRUCTION MANAGER

MASTER PLAN DRAFT RECOMMENDED PLAN

Two-Year Academic Course Schedule - Fall 2015 through Summer Program Director: Dusty Mosness-Brailsford Campus Phone :

Existing Facilities. Current and Forecast Demand

Emirates Airline. Cargo Security The EK Experience

Airline Disruption Management

7 th CAPSCA Asia Pacific Meeting. Mr Desmond Chong, Manager, Airport Operations Centre

Charter services. Choose to fly your own schedule. Pick your choice of airport. Perfect for VIP s, sports teams, corporate shuttles and pop tours

- PUBLIC REPORT - CITY OF SAN ANTONIO INTERNAL AUDIT DEPARTMENT

Addition of New Premium Cards to the Suite of ANA and Diners Club Co-branded Cards

Aviation Infrastructure Costs

SECURING YOUR AIRCRAFT

FROM LANDING TO TAKE-OFF: WE CARE! COMPANY PRESENTATION

RECURRENT FLIGHT SCHOOL SECURITY AWARENESS (FSSA) TRAINING

AIRLINE PRICING STRATEGIES IN EUROPEAN AIRLINE MARKET

Spare Part Supply Chain: The case of airlines. utdallas.edu/~metin

Martha s Vineyard Airport Master Plan. Workshop December 6, 2012

METROPOLITAN AIRPORTS COMMISSION Department of Human Resources th Avenue South Minneapolis, MN 55450

2003 Patricia Ensworth Page 1

Airline Schedule Development

Federal Aviation Administration Aviation Insurance Program

MASTER PLAN PREPARATION

Major Components of a Typical Startup-Airline Business Plan

General Terms and Conditions FRA Comfort Services and My Airport Guide Services Available from the Service Shop of Fraport AG

Transcription:

Love Field Modernization Program (LFMP) & Airport Electronic Systems Management (AESM) Status Update Transportation & Environment Committee February 27, 2012

Background LFMP will deliver a brand new airport With new terminal, changing to a Tenant Shared Services Concept of Operations Airport Electronic Systems Maintenance (AESM) Organization was created between CIS and AVI Improved coordination for system support Focused on support contracts Airport managed vs. tenant managed 2

LFMP Update Love Field Modernization Program includes a New 20 gate concourse, new ticketing wing and new baggage claim area. Also includes new Baggage and Passenger screening systems 3

New Gates April 2013 New Security Lobby November 2012 4

New Passenger Screening Lobby Phase 1 Open Jan 2012 Phase 2 March 2013 5

New Ticketing Wing November 2012 6

Budget Program budget $519 M running at an estimated $7M under budget Terminal building ahead of schedule Aircraft Apron currently on schedule 7

Major Milestones Fall 2012 - Open Ticketing Wing Spring 2013 - Open first 12 gates with ticketing wing, baggage screening system and security lobby active Fall 2014 - Open remaining 8 gates with new baggage claim hall 8

Change in Airport IT needs The new building will have all new technology and the City needs to be able to maintain those technology systems Airline, Security and Life safety systems all dependent on IT infrastructure, support and maintenance To meet those needs the Airport and CIS created Airport Electronic Systems Management (AESM) team 9

What is AESM Model? A single Shared Services Concept of Operations (in support of FAA, TSA, Airline, Concessions and Airport Operations) One-stop shop for systems and services Centralized communication center for flying public, tenants, and airport operations Need to be in-place November 2012 for opening of new Ticket Hall 10

Benefits Improved communication with flying public, tenants, and airport operations Improved support of airport operations to fulfill national flight requirements Supports demand for higher level services mandated by FAA, TSA, and other government agencies Improved control of Love Field assets 11

Background Focused coordination for service delivery Began planning for requirements of new shared services model Moving to single network backbone controlled by City Defined and managed service level agreements Set up AESM Staffing and Operations 12

Tenant Shared Services Concept Cost recovery model for shared tenant services provided by AESM Network services Communication services CCTV services Video surveillance services 13

Airport Operations Communication Center Single point of contact for tenants, flying public, and airport operations IVR Event management Scripted event response procedures Initiate or log work orders/service requests Monitor airport activities in support of federal, state and local flight operations Coordinate emergency event response Coordination of service delivery 14

Planning & Design AESM group working directly with Project Management Office on the Love Field Modernization As systems bid and procured, AESM began developing requirements for implementation and future maintenance Systems now being installed in new terminal 15

Planning & Design Develop operating rules and requirements Standard Operating Procedures Managed third-party support resources Improve management review process of service delivery Management of 30+ airport systems including systems directly used by TSA, FAA, and national airport security and operations Services for new concessions operations 16

Timeline Initial Phase Create Organizations / Contract Support (ongoing to December 2012) Create RFPs / RFQs for 3 rd Party M&O Create Support Organization (e.g., Service Menus, Price Lists, Service Level Agreements) Second Phase System Commissioning & Final System Transition (Summer 2012 March 2013) 17

Role of URS Currently engaged with LFMP activities. Provide Experienced Subject Matter Experts (SMEs) in Airport Electronic Systems Design, Installation & Testing and Support Provide Local Staff Augmentation Communications and IT SMEs for Temporary Support Tasks Provide Improved Construction Coordination & Management Support to the LFMP 18

Next Steps Award supplemental agreement to URS for support services Begin implementation of new systems for LFMP Forward service contracts for maintenance of systems 19