Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

Similar documents
Pepco Holdings Distributed Energy Resources - First of the DER Market

TERMS AND CONDITIONS

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Rule Fast Track Analysis for National Life Insurance Co.

Smart Meter Capabilities and Implications for Net Metering. MADRI Smart Meters and Distributed Resource Data Issues

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Photovoltaic Incentive Program

SOUTH CAROLINA. Standard for Interconnecting Small Generation 100 kw or Less with Electric Power Systems (EPS) (Interconnection Standard)

Key Concepts Of Distributed Generation

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems

STANDARD INTERCONNECTION AGREEMENT FOR CUSTOMER-OWNED TIER 2 RENEWABLE GENERATION SYSTEMS (Greater than 10 kw and Less than or Equal to 100 kw)

Application for Small Generator Facility Interconnection Tier 2, Tier 3 or Tier 4 Interconnection

Physical Address: City: State: Zip Code:

FIT TIER 2 Application

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS

Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014

TERMS AND CONDITIONS

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

Distributed Generation: Feeder Hosting Capacity. Dean E. Philips, P.E. FirstEnergy Service Corp Manager, Distribution Planning & Protection

Step Voltage Regulators

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns

APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution

Net Energy Metering Southern California Edison

Dakota Energy Cooperative, Inc. POLICY STATEMENT

Interconnection Service - Frequently Asked Questions

Future of Electric Distribution Dialogue

Corona Department of Water & Power (DWP) Solar Partnership Program Guidelines and Application

4.1.1 Generator Owner Transmission Owner that owns synchronous condenser(s)

Distributed Generation and the Impact on a Distribution System. Brian Lassiter Technical Sales Engineer

Net Energy Metering Solar PV Interconnection Handbook. Effective January 1, 2016

Inverter / Charger Installation General Operations and AC and DC Connections

HOLYOKE GAS & ELECTRIC DEPT S Distributed Generation Policy Effective: September 18, 2012

Conservation Voltage Reduction (CVR)

MicroFIT Connection Application Guidelines

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES

AUSTIN ENERGY INTERCONNECTION GUIDE FOR CUSTOMER-OWNED POWER PRODUCTION FOR FACILITIES UP TO 10MW A INTERCONNECTION CLASSIFICATIONS...

JEA Net Metering Policy Tiers 1-3

2016 Santee Cooper Solar Home & Solar Share Home Program Manual

SA Power Networks Planning for Solar PV? Customer information guide to network connected solar PV inverter systems

PMLP s Net Metering Procedure

To complete the process for a net metering interconnection, please follow the steps below:

PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM

Electric Rate Schedule

KERALA STATE ELECTRICITY REGULATORY COMMISSION

SPECIFICATION COG-2007

Understanding Power Factor and How it Affects Your Electric Bill. Presented by Scott Peele PE

SDG&E Electric Distribution System Interconnection Handbook. <Revised as of 10/21/2015>

Portland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. C-1 RULE C CONDITIONS GOVERNING CUSTOMER ATTACHMENT TO FACILITIES

Effective: September 10, 2006 Vermont Attachment 1 to Rule Public Service Board Page 1 of 6

Minimizing Impact of Electric Utility Outages with Backup Generation

AMI and DA Convergence: Enabling Energy Savings through Voltage Conservation

Reactive Power and Importance to Bulk Power System OAK RIDGE NATIONAL LABORATORY ENGINEERING SCIENCE & TECHNOLOGY DIVISION

CENTRAL ELECTRIC COOPERATIVE, INC. NET METERING AGREEMENT

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Session 10: General Overview of Interconnection Standards & Grid Codes for High Penetration PV October 21, 2015 Santiago, Chile

Washington DC Power Sector Overview

ATTACHMENT F. Electric Utility Contact Information Utility Name. For Office Use Only

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

Plumas Sierra Solar Rebate Program Guidebook 2015

Guideline for Energy Efficient Electrical systems for building. Presentation by TERI

Microgrids. EEI TDM Meeting Charleston, South Carolina October 7, Neal Bartek Smart Grid Projects Manager

Distributed Generation Interconnection Manual

Residential Renewable Energy Rebate Instructions

SCE Experience with PV Integration

NORTH CAROLINA INTERCONNECTION PROCEDURES, FORMS, AND AGREEMENTS. For State-Jurisdictional Generator Interconnections. Effective June 16, 2009

Schedule 6VP LARGE GENERAL SERVICE VARIABLE PRICING

Energy Systems Integration

SCADA Controlled Multi-Step Automatic Controlled Capacitor Banks & Filter Banks

Worship Facility Matching Grant Program 2010 Program Manual

Request for Proposals for Photovoltaic System Installation

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

GPS Interfacing of Banediya Feeder (M.P) Using MI Power Software

ATTACHMENT G. Network Operating Agreement

ARRA Grant Case Studies SMUD s Smart Grid Program

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V V V (at 50 Hz)

TAMARAC FIRE RESCUE INSTRUCTIONS FOR FIRE ALARM PRE-SUBMITTAL CHECKLIST

CLASS Voltage Regulation Scheme. 27 February 2014

Technical Requirements. For Generating Facilities Interconnecting. To The Distribution System. Salt River Project

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman.

Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme

Preparing for Distributed Energy Resources

Distributed Generation and Power Quality Case Study

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW

Interconnection Application For Residential and Commercial Power Systems 10 kw or Smaller

Interconnection of Generators to EDI s Distribution System

TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION. Micro Generation & Small Generation, 3-phase, less than 30 kw

Construction, Management and Engineering Practices that Lead to Low Losses

KERALA STATE ELECTRICITY REGULATORY COMMISSION

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

LIPA. Long Island Power Authority

HOW A DC UTILITY METER CAN TRANSFORM THE U.S. SOLAR INDUSTRY

Financial Analysis of Solar Photovoltaic Power plant in India

Application for Purchased Systems Oregon Department of Energy

NORTH LITTLE ROCK ELECTRIC DEPARTMENT NET METERING RULES

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

Advanced Protection of Distribution Networks with Distributed Generators

Transcription:

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date:

Welcome A Look at the Net Energy Metering Engineering Review Process Speeding Up the Application Fee Process What s Changed Net Energy Metering and Interconnection Application Process GPC Team Contacts We support renewable energy and partner with our customers to ensure safe and reliable interconnection of renewable energy into the electric grid 2

Net Energy Metering Engineering Review Process 3

Overview Criteria Limits Restricted Circuit Map Interconnection Requirements Levels of Review 4

Existing Distribution Circuit Capacity Limits Guidelines The aggregate limit of large (250 kw and over) generators running in parallel with a single, existing distribution circuit is: 4 kv 0.5 MWs 12 13.8 kv 3 MWs 23 25 kv 6 MWs 33.26 34.5 kv 10 MWs After these limits are reached, customers and developers can continue to request connection of systems less than 250 kw. The circuit will continue to accommodate distributed energy resource (DER) systems until voltage limits or other limits are reached 5

Express Circuit Capacity Limits Distributed generation installations which exceed the limit for an existing circuit require an express circuit. The maximum generator size for express circuits is: 4 kv 0.5 MWs 12 13.8 kv 10 MWs 23 25 kv 10 MWs 33.26 34.5 kv 15 MWs The maximum length of an express feeder shall be 5 miles and must have demand and energy losses less than 3% 6

Distribution Power Transformer Limit The aggregate limit of large (250 kw and over) generator injection to a single distribution transformer of 22.5 MVA nameplate or larger is 10 MWs. Transformers with nameplate ratings lower than 22.5 MVA may be given lower generation limits We will consider adding a new transformer if there is no availability on any of the existing transformers and space is available in an existing substation. Any proposed transformers would be PHI s standard distribution transformer (37 MVA nameplate rating) 7

Restricted Circuit Map www.delmarva.com/gpc Map Legend: Red No New DERs Yellow No DERs 250 kw or greater Orange No DERs 50 kw or greater 8

Network Criteria Spot and Area Networks to ensure a safe level of import, if Delmarva Power determines that the proposed system could export or cause the network protector to operate, the following control scheme will be required: Customer shall install a monitoring system on the service(s) to the facility and install inverters that can receive a control signal and curtail output to maintain the target level of import on each phase Customer system shall provide a web link and access to PHI to have read-only access to view the electrical parameters and operation of the system Customer shall provide an alert to PHI via email or text if the import goes below a set point Customer shall send a trip signal to the inverters if the import level falls to another set point 9

System Reliability Interconnection Requirements Reliability of the electric system requires criteria that can be used to assess the impact of DER on the grid Accurate single-line drawing of the proposed generator system submitted with each application UL 1741-certified inverters System passes electrical inspection Systems shall not overload line transformers or cause high voltage for themselves or adjacent customers (otherwise upgrades would be required) Single Phase Limit the largest capacity single phase generator or DER (battery) operating in parallel with the grid is 100 kw. Above that size, a balanced 3-phase system is required 10

Levels of Engineering Review Pre-screen Screen Advanced Study 11

Engineering Pre-screens Required for systems between 50-250 kw Option 1: Determine distance from substation, radial or lateral connection and voltage level Main radial connections typically have larger wires, allowing systems further away to interconnect without problems Higher tolerance for larger voltage levels (25 kv vs 12 kv) Option 2: Calculate impedance at point of interconnection (POI) Failed Pre-screen Distance from substation and size of system are not in the allowable range to pass the pre-screen or impedance is too high Screen is required Operating requirements must be signed by customer (not required if application passes pre-screen) 12

Engineering Screens Required for systems > 250 kw or failed the pre-screen High level power flow analysis required Screening Criteria Voltage fluctuation is not greater than 2% at the POI or half the deadband at any capacitor or regulator Reverse power-generation does not exceed 80% of the daytime minimum load at voltage regulators, feeder terminals and/or substation transformer without proper mitigation DER does not cause high voltage anywhere on the circuit 13

Engineering Screens Step 1: Ensure accurate model Power flow (MVA, MW, MVAR) at peak and minimum load (typically use SCADA at feeder terminal to verify load) Capacitor, voltage regulator and LTC settings Power factor at feeder terminal Large customer loads Nearby PV installations (systems within ~2,000 ft. of proposed system will act as one system during cloud passing) Additional Information Back-up feeders Distribution automation schemes 14

Engineering Screens Step 2: Peak Load Voltage Study Run power flow at peak load with generators on Lock capacitors and voltage regulators to prevent from operating Turn generation on/off and record voltage at POI and closest capacitor or voltage regulator Calculate difference to determine voltage fluctuation If fluctuation is greater than 2%, apply absorbing power factors from 0.99 to 0.95 until criterion is met If above method fails, reduce size of system until violation no longer occurs 15

Engineering Screens Step 3: Minimum Circuit Load Voltage Rise Study Run power flow at minimum load with generators on and capacitors and voltage regulators unlocked Record highest voltage on feeder If voltage exceeds upper limit, apply power factor from 0.99 to 0.95 absorbing power factor until criterion is met If power factor mitigation does not work, reduce size of system until high voltage no longer occurs Lock capacitors and voltage regulators to evaluate voltage fluctuation (similar to peak load study) 16

Engineering Screens Step 4: Reverse Power If the aggregate generation exceeds 80% of the daytime minimum load at a specified location, the following mitigation techniques are required: Feeder Terminal Relay package as determined by Delmarva Power System Protection Voltage Regulator Install Beckwith controller with co-generation mode Substation Transformer Transfer trip 17

Engineering Advanced Study Required if application does not pass high level screening process (at maximum output) Time series power flow analysis required AMI smart-meter data is used to ensure accurate loads (as opposed to feeder terminal SCADA data and connected KVA loads) Same criteria as screening procedure Different types of advanced studies include: Phase balancing Capacitor controls Lowering load tap changer (LTC) voltage 18

Engineering Review Points Power Flow results are reviewed to determine PV system impacts in the following areas: Over-voltage or voltage fluctuation on feeder and at premise Conductor or equipment overload Reverse power on feeder equipment (voltage regulators) Reverse power on substation transformer Feeder phase loading balance Equipment improper operation (such as network protectors, reclosers) Circuit and equipment protection and coordination VAR flow and potential impact to capacitor operation Other items as dictated by circuit and generator configurations (such as impact on Delmarva Power Distribution Automation schemes) that could restore with DERs being transferred to other circuits 19

Speeding Up The Application Fee Process 20

The New Application Fee Process Contractor or customer submits a NEM Application Part I with all required documents, however they are not required to include an application fee check at this stage After the application has been entered into the online portal, the system automatically determines if an application fee is required and calculates the required fee, based on jurisdiction, system size, and application level The system automatically generates an invoice and emails it to the contractor or customer 21

The New Application Fee Process (continued) 22

The New Application Fee Process (continued) Contractors can pay their invoice through Speedpay or by mailing a check in with the invoice Access Speedpay at delmarva.com/specialbilling 23

The New Application Fee Process (continued) Review and agree to Terms of Use 24

The New Application Fee Process (continued) The system will allow the final Authorization to Operate (ATO) to be issued only after the application fee is paid Collections for unpaid invoices will be handled by Delmarva Power s remittance and collections processes 25

Benefits of the New Application Fee Invoice Process NEM Applications will be processed more quickly, without requiring upfront application fee payment NEM Applications will no longer be returned to contractors or customers as incomplete due to an incorrect or missing application fee The new online application process will automatically generate an invoice and email it to the contractor or customer Contractors will have the option to pay invoices via Speedpay or by mailing a check attached to the invoice Green Power Connection staff will no longer spend time searching for lost or separated checks 26

Net Energy Metering and Small Generator Interconnection Application Process 27

Using GPC Website as a Resource www.delmarva.com/gpc Delaware Interconnection Application and Agreement Forms Links to Applicable Regulations, Rules, Tariffs, Guidelines, and Maps Renewable News and Useful Links Frequently Asked Questions ALL FORMS CAN BE DOWNLOADED 28

Restricted Circuit Maps Interactive Type in premise address Red interconnection not available Orange interconnection available for systems up to 50 kw Yellow interconnection available for systems up to 250 kw Interconnection may be accommodated with system upgrade at developer s or customer s expense www.delmarva.com/gpc 29

Acceptable Inverter List: www.delmarva.com/gpc In most cases, inverters that comply with IEEE 1547 and UL 1741 will be acceptable for interconnection January 21, 2016 30

Where do I Find the Interconnection Applications? www.delmarva.com/gpc 31

Delmarva Power Delaware Application Steps 20 business days 37 business days 20 business days = 77 business days App. Part I Customer App. Part II Research Select Apply Approval Install Inspect Meter Authorization Operate Steps Actions To Take Responsible Party Level 1 Applications Research Research the various types of renewable energy systems available and decide which system best fits your consumption needs. Renewable energygenerating systems can be sized to meet up to 110% of your energy needs Understand your electrical load and energy consumption history Customer 2. Select Interview and select a reputable installing contractor Customer Acknowledge App. Receipt (5 days) Engineering Review to Approval to Install (15 days) 3. Apply Understand the documentation needed with the interconnection agreement (e.g., rebate forms, permit applications, inspection forms) Apply and submit Part I of Delmarva Power s interconnection application and agreement along with the supporting documentation Applications without supporting documentation will be delayed. You can resubmit a corrected application and documentation Delmarva Power will send contractor or customer an invoice for any application fee 4. Approval Wait for Delmarva Power s Approval to Install before installing your renewable generator equipment Delmarva Power will provide you a written screening result or Approval to Install Customer Delmarva Power Customer Apply for Building Permit Delmarva Power Customer Installs and has Inspected (37 days) Application Part II Received, Meter Exchange, Authorization to Operate (20 days) 5. Install Begin constructing and installing your renewable generator facility Customer 6. Inspect After installation, submit Part II of our interconnection agreement, including a copy of the certificate of completion and the inspection certificate We will review your documentation to verify the interconnection application meets regulatory requirements and the application fee, if any, has been paid Customer Delmarva Power 7. Meter We will install your net-capable meter Delmarva Power 8. Authorization We will send you an Authorization to Operate letter Delmarva Power 9. Operate Receipt of the authorization letter means you can operate your renewable system Customer December 31, 2015 32

Top 7 Ways to Ensure a Complete Application the First Time 1. Use the current application form for the correct system capacity Go to delmarva.com/gpc and download the appropriate files The Interconnection Application & Agreement Select the Level 1, Level 2, Level 3, or Level 4 application that meets the criteria for your situation Use only application forms dated July 2015 or later 2. Indicate the correct Delmarva Power customer name and account number The Interconnection Agreement & Application must be in the name of the Delmarva Power customer of record. Use the information found on the current Delmarva Power bill 3. Include the customer signatures The Delaware Public Service Commission requires the agreement be signed by the customer of record before Delmarva Power can process it 33

Top 7 Ways to Ensure a Complete Application the First Time (cont d.) 4. Attach the required supporting documentation Delmarva Power requires a single-line diagram, system specifications, and the location of the system be submitted with the initial Interconnection Agreement Part I Part II requires the signed Certificate of Completion and a copy of the inspection certificate The equipment information described on the inspection certificate must match the system specifications approved by Delmarva Power for installation 5. Ensure the proposed generator capacity matches the manufacturer's equipment data provided on the application The AC inverter rating stated in Part I of the application must be consistent with the total inverter kw as stated on the inverter manufacturer's equipment data sheets 34

Top 7 Ways to Ensure a Complete Application the First Time (cont d.) 6. Ensure the system sizing meets your consumption needs For Delaware, take the average of the total energy use for the 2 previous 12-month periods, as shown on your Delmarva Power bills. Divide that average by 1,200. Multiply that total by 1.1. The result is the maximum inverter nameplate rating (kw) you can install [ (average of the 2 previous 12-month periods kwh usage) / 1,200 ] x 1.1 = maximum kw inverter rating Your inverter rating can be equal to or less than this kw. Have your contractor verify the information they used to size your system 7. Know that a net-capable meter cannot be installed if: Other customer-requested work, such as a heavy-up, is in progress Unsafe meter conditions are found, such as damage to or improper contractor installation of the meter 35

Unauthorized Small Generator Interconnections Include operating equipment that has not passed an electrical inspection or received approval from a local, county, or jurisdictional inspector Include operating equipment that does not comply with: applicable jurisdictional regulatory rules Institute of Electrical and Electronics Engineer (IEEE) Standards for Distributed Energy Resources Underwriters Laboratory (UL) Certification Include renewable energy systems that have been installed or are operating without written approval from utility Unauthorized interconnections increase project costs if the design fails to meet our jurisdictional and utility interconnection requirements Potential Hazards: Endanger utility workers, who will not have a record of the system Pose a safety risk to the customer, system components, facility, and general public Can cause voltage overload problems on the grid, preventing safe and reliable electric service Can lead to a cease-and-desist notification The Delaware Public Service Commission prohibits the interconnection of generation facilities to the electric grid without our written approval 36

How Can I Learn More? See the wealth of information on www.delmarva.com/gpc Read additional FAQs on the GPC website Tell friends and neighbors about these webcasts Also offered for Pepco and Atlantic City Electric Contact us Green Power Connection Team www.delmarva.com/gpc gpc-north@pepcoholdings.com (866) 634-5571 37

Questions? Email questions to NEMeducation@pepcoholdings.com 38