Differences Between CPM and Linear Schedules



Similar documents
Linear Planning in Pipeline Construction

Planning and Scheduling. Railway Maintenance Work. with TILOS

Linear Schedules for Tunnel Projects

Practical Aspects of Construction Scheduling

APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION

The work breakdown structure can be illustrated in a block diagram:

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised )

TILOS GETTING STARTED & EXERCISES

MS Project Tutorial for Senior Design Using Microsoft Project to manage projects

Final Software Tools and Services for Traders

LINEAR SCHEDULING OF PIPELINE CONSTRUCTION PROJECTS WITH VARYING PRODUCTION RATES GREGORY ARTHUR DUFFY

Microsoft Project 2010

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS

Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University

Tracking Project Progress

SYSTEMS ANALYSIS AND DESIGN DO NOT COPY

MODEL SCHEDULING SPECIFICATION

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses

PIPING DRAWINGS BASICS N.P.TODKAR

CDR.07. CPM Scheduling and How the Industry Views Its Use

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

Scheduling Best Practices

P6 Analytics Reference Manual

5. Creating a Gantt Chart

Scheduling Document Creation

Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM)

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

CRITICAL PATH METHOD (CPM) SCHEDULES

Charting Your Course: Charts and Graphs for IT Projects

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

OVERVIEW. Microsoft Project terms and definitions

Graphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts Prepared for groups in ECE480 1/6/02, D. Grover

PN /16/ CRITICAL PATH METHOD PROGRESS SCHEDULE

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction Why Do We Need Schedules?...

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)

Priori ty

Plots, Curve-Fitting, and Data Modeling in Microsoft Excel

Use project management tools

Spec. Standard: 11/27/ Revision: 11/27/06

Road Rehabilitation and Reconstruction Using AutoCAD Civil 3D

Earned Value User s Guide

Scheduling Glossary Activity. A component of work performed during the course of a project.

Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.

Project Time Management

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

1. INTRODUCTION PRODUCT Installation Documentation Website workbench features...2

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

Scheduling: Program Evaluation and Review Technique Networks and Linear Operations

WORK PROGRAM GUIDELINES

How To Create A View Frame In 3D

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Steven Wood Software, 2 Harksome Hill, West Hunsbury Northampton. NN4 9YF. United Kingdom

PERCEPTION PERT-PAC Using Microsoft Project 2000

Using Excel (Microsoft Office 2007 Version) for Graphical Analysis of Data

The management of the projects with MS Project

Project Creation and Gantt Chart Design Using Microsoft Project. R. Baker. The University of Tampa

Tutorial 3: Graphics and Exploratory Data Analysis in R Jason Pienaar and Tom Miller

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING

Work Type Definition and Submittal Requirements

Table 2-1: Elements of the Project Management Plan

New advances in planning a bore Software helps take out the guesswork

GUIDELINES FOR PREPARING POSTERS USING POWERPOINT PRESENTATION SOFTWARE

CHAPTER 20. GEOPAK Road > 3D Tools > 3D Modeling

Technique (LOBST) for a Real estate sector

ECDL. European Computer Driving Licence. Project Planning Project Management Software BCS ITQ Level 2. Syllabus Version 1.0

EXHIBIT 2-2-C PROGRESS SCHEDULES

Strategies for creating accurate updates of CPM construction schedules.

Data representation and analysis in Excel

Briefing document: How to create a Gantt chart using a spreadsheet

Intellect Platform - The Workflow Engine Basic HelpDesk Troubleticket System - A102

Industrial Robotics. Training Objective

SECTION a - CONSTRUCTION PROGRESS DOCUMENTATION

CHAPTER 8 PROJECT TIME-COST TRADE-OFF

Work Breakdown Structure (WBS)

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Graphing in EXCEL for the Classroom: A Step-by-Step Approach. David F. Cihak and Paul A. Alberto, Georgia State University

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

TABLE OF CONTENTS. INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE...

Review on Using Packages to Enhance the Teaching of Critical Path Networks

PROGRAMMING TECHNIQUES. Chapter 5(Part 2)

Data Visualization. Prepared by Francisco Olivera, Ph.D., Srikanth Koka Department of Civil Engineering Texas A&M University February 2004

NE-50413B Mastering Microsoft Project 2010

Math Content by Strand 1

Civil Engineering Design

Project Management Fact Sheet:

Atomic Force Microscope and Magnetic Force Microscope Background Information

Developing Critical Path Method Scheduling (CPM)

Tableau Data Visualization Cookbook

Making Visio Diagrams Come Alive with Data

2-1 Position, Displacement, and Distance

Microsoft Project 2013 Guide to Task and Resource Planning

Mastering Microsoft Project 2013

Transcription:

Utilizing Linear Planning and Scheduling for Project Control and Claims Avoidance Lorne Duncan, Partner, Integrated Project Services Joanna Alvord, PSP, PMP, Project Controls Manager, HDR Engineering, Inc. Introduction Linear projects involve the continuous movement of activities along the length of an alignment or Rightof-Way (ROW). Some examples would include highway, pipeline, railway and high voltage transmission line projects. Linear projects are characterized by the repetition of each activity along the length of the project. The rate of progress of each crew is critical and is evaluated to ensure that adequate spacing between activities is maintained. Typically, the sequence of activities is not a concern but rather optimizing the productivity rates to minimize the total time is the primary objective (Duffy, 2009). Traditional scheduling methods used for linear construction projects have been either simple bar chart as developed by Henry Gantt during World War I or a critical path method (CPM) schedules first developed by DuPont in 1957(Duffy, 2009). Gantt charts, while easily developed and understood; don t convey sufficient information to control a project. CPM scheduling methodology was originally developed for facilities type of jobs where the project is broken down into a complex series of chronological discrete activities (Duffy, 2009) that are logically connected in a sequence from project start to finish. While these tools are very powerful, they are better designed for the construction of facilities (i.e., power generating stations, refineries and chemical plants) and are not adequate for the constructability issues and demands of building linear project such as a pipeline, rail system or roadway. Repetitive projects suitable for linear schedules can be classified into two categories: point based and alignment based (Duffy, 2009). A point based project is based on the Line of Balance (LOB) method developed by the U.S. Navy in the 1950 s to optimize production of units in an assembly plant and has been adapted to schedule multi-unit housing projects (Duffy 2009, Johnson, 1981). Another point based tool introduced by O Brien (1975) is the Vertical Production Method (VPM) to schedule the repetitive nature of multi-story buildings as crews move up from floor to floor. Alignment based repetitive projects involve the movement of crews along a defined ROW. Examples include road, pipeline, rail, transmission line, bridge and tunnel projects. The focus of this paper is the application of TILOS (a linear scheduling software tool) to alignment based projects. The key component of linear scheduling software is the creation of a march charts (also known as Time- Distance charts) to display project in two dimensions: time and distance. March charts have been widely used in linear projects, particularly in Europe and the U.K. While this methodology is newer to the Americas, it is rapidly gaining widespread acceptance. March charts are often hand drawn, prepared in Microsoft Excel or in a drawing program such as AutoCAD. Linear planning and scheduling software that automates development of the plan and progressing is relatively recent (app. the last 15 years). Differences Between CPM and Linear Schedules CPM schedules are familiar to anyone that has planned and executed a project. The planner creates a series of discrete activities and then logically connects these activities (Finish-Start, Start-Start, Finish- Finish and Start-Finish). Resources can be added to each schedule activity and resource loading can be easily displayed. In order to maintain crew sequencing in a linear-type project, the planner ensures that

each activity is connected to its successor by a Start-Start and a Finish-Finish relationship. A typical Gantt chart for a pipeline job is shown in Exhibit 1. Exhibit 1 - Traditional Gantt Chart This Gantt charts clearly shows each activity with its start and end date and progress is shown on the Gantt chart as the percent completed for each task. In a linear project the typical CPM progress report that a crew is 45 % complete is quite meaningless because these traditional tools assume that progress is from start to finish and no connection exists between progress and the geography of the ROW. The ability to include crew moves, permitting delays, environmental restrictions and other construction issues is simply not easily achievable in CPM schedules. A march chart on the other hand displays the same crews as a series of lines moving along the ROW. As with the CPM method, each crew is logically connected to its successor with Start-Start and/or Finish- Finish relationships. Completed sections are easily identified with crew moves, crossings and environmental windows clearly visible on the march chart. Using the same example as before, a march chart will clearly display what 45% of the alignment has been completed by a crew and how any moves or ROW access issues have impacted the progress of the project. A typical march chart (Exhibit 2) in its most basic form shows each crew represented by a different line type, color or shape. Usually distance along the ROW is horizontal and increases from the left to the right. Time is typically represented vertically, increasing from bottom to top (although it can just as easily be shown increasing top to bottom). It should be noted that the orientation of the time and distance axes is a matter of personal preference and can easily be switched in the software. The advantage of a march chart for linear projects is immediately obvious as you can determine the location of each crew at any particular point in time. Any issues associated with crew productivity rates are also readily apparent. For example, the red arrow in Exhibit 2 indicates that based on the productivity of each crew, the lower-in crew will overtake the ditching crew between KP 25+000 and 30+000, which was not obvious in the Gantt chart view (Exhibit 1). Exhibit 2 - Simple March Chart (including Productivity Rates and Slope) 2010, Lorne Duncan and Joanna Alvord -2-

In a march chart the slope of the activity indicates the relative productivity rate for the crew. The steeper the slope, the slower the crew is moving (because more time is spent and less distance is completed). Non-work periods such as scheduled days off or work stoppages can appear as vertical segments on the crew line. A vertical line indicates that time is passing but the crew is not moving. The productivity rates that are displayed are calculated automatically by TILOS based on duration and length of each task. Typically, each crew is assigned to a different layer of the march chart so that the planner can display one or many crews simultaneously, by activating the layers. Constructability Issues With a basic understanding of these march chart elements, a march chart can be further enhanced to display any other critical element of your project. These can include the ROW profile, crossings, environmental restrictions and land acquisitions. Other elements such as vegetation type, soil type and rainfall data can also be included on the march chart. The amount and type of information shown on a march chart is determined by the project team. ROW Profile The ROW profile is important in developing the hydrotes plan and to determine productivity rate changes based on elevation (discussed later in the speed profiles section). Most profile data (LIDAR or survey) is available in a spreadsheet format and can be easily imported into a profile diagram using the import function of the TILOS to generate the ROW profile as seen below in Exhibit 3. Exhibit 3 - Elevation Profile and Restricted ROW Access (work plan corrected on the right) Restricted ROW Access Construction may be hampered by periods when certain parts of the ROW are not accessible. This would include environmental windows for wildlife and rare plants, irrigation seasons, permitting issues or ROW acquisition delays. Restricted access periods are easily represented graphically on march charts by rectangular shapes as shown in Exhibit 3 (above)error! Reference source not found.. Once the impact of a restriction has been evaluated, it may be necessary to modify the work plan to avoid working in restricted areas. This can be done by splitting the crews so that work which is impacted by restricted areas will be completed at a later date once the restriction period is over. Exhibit 3Error! Reference source not found. also 2010, Lorne Duncan and Joanna Alvord -3-

illustrates a move for both the grade and string crew to avoid a restricted area. In this example, both crews skip the restricted area (1 day lag to allow for move) and continue to the end of the ROW at 30+000. Once this work is finished, and the environmental restriction has expired, both crews move back to the restricted area and complete it in a reverse lay. The red dashed lines indicate the logical links between each crew segment. Crossings and Stockpile Locations Once the environmental or land restrictions have been established on your march chart, the next step is to identify crossings. Crossing types can include foreign utilities, roads, rail or water and are important features to display on your march chart. The method of crossing will be dependent upon the type of crossing. Water crossings usually require an open cut (if permissible under the environmental guidelines) or will utilize a HDD (Horizontal Directional Drill). Most roads and rail crossings utilize some type of bore method while foreign utilities are exposed using a hydrovac. Each type of crossing can be color coded on the march chart for quick and easy identification. Virtually any information that is considered important can be inserted into the march chart. Exhibit 4 (below) shows a highway (at KP 1+793) shown in grey and a blue river crossing (KP 29+690) on the march chart. Exhibit 4 Road, River Crossings and Stockpile Sites It is interesting to note that non-linear structured tasks (such as mainline block valves) can also be shown on a march chart. The two valves shown in Exhibit 4 are represented by a series of rectangular shapes indicating different stages of installation from civil to mechanical to instrumentation and telemetry. Other non-linear features that can be added to a march chart would include material deliveries and detailed HDD activities. In this regard, a march chart is able to represent both linear and non-linear components, providing an overview of the entire project. Weather Risk Risk related to weather events such as precipitation amounts or temperature, are easily evaluated by overlaying meteorological data on the march chart. In Exhibit 5, the different shades of blue represent average monthly rainfall amounts. The heaviest amounts of rain occur in the lower right of the march 2010, Lorne Duncan and Joanna Alvord -4-

chart, represented by a darker blue. In this example, the planner has avoided working in this area during high rainfall thus reducing the risk of heavy rain impacting construction. Exhibit 5 - March chart showing monthly average rainfall data. Spend Profiles and Resource Histograms Other Features Spend profiles and resource histograms are simple to create once costs are added to the labor, equipment and materials used in the march chart. Spend profiles are a function of time and are therefore displayed parallel to the time axis of the march chart. It is also possible to create a spend profile parallel to the distance axis showing the cost per section of the pipeline. Any changes to the march chart (such as crew moves) automatically create a change to the spend profile. Applying work and speed Profiles to crews Most estimates, schedules and march charts assume a consistent productivity (or work) rate for each crew along the ROW. This productivity factor is then applied for the entire length of the ROW to determine the duration of each crew. For example applying a constant productivity rate to a pipe crew doesn t account for changes in profile, soil, terrain (muskeg versus mineral soil conditions) or vegetation types. The following example shown in Error! Reference source not found. illustrates the difference when a vegetation classification system is used to define the productivity rates for logging and clearing crews in a Northern ROW. In this example the vegetation data and productivity rates for both crews in a particular location were imported directly into the march chart from an Excel data file supplied by a survey company. In Error! Reference source not found. (below), on the left we can see that both crews have very similar productivity rates with durations of 25 and 26 days respectively for the logging and clearing crews. The vegetation index in this example defines the amount of work (area) and work rate for each vegetation type along the ROW. Once this data is known and available in a spreadsheet format, it is easy to apply this index to each crew as shown in Exhibit 6 (right). The first noticeable change is that the crews are not consistently progressing along the ROW. 2010, Lorne Duncan and Joanna Alvord -5-

Exhibit 6 - Logging and Clearing Crews with constant productivity (left) and optimized by vegetation index (right) Each crew line now reflects a different productivity rate with each change in vegetation type. More importantly we can see that the duration for each crew has changed significantly. Logging has decreased from 25 days to 16 days while the duration for clearing has increased from 26 days to 40 days! Progressing March Charts Progressing crews on a march chart requires the start distance, end distance and the date range for each progress period (based on the inspector field reports). The exception to using linear meters for progress would be to count the number of welds, usually back end welds, or the number of UPI items, such as bag weights. Exhibit 7 - Progressing Crews in March Charts Error! Reference source not found. shows progress for both the grade and the haul & string crews. Progressing is as simple as selecting a crew by clicking on it, right click and select enter progress. Enter the start and end date for the progress period and the start and end distance. TILOS calculates the physical percent completed based on total installed quantities. 2010, Lorne Duncan and Joanna Alvord -6-

Application of Linear Schedules by the Owners As construction projects become larger and more complex, the delivery timeframes become tighter. This poses a significant challenge to both, construction managers to accurately plan, execute and control projects, and to the owners to oversee and partner with the contractor throughout the project. With various risks assignments between the owner and the contractor in any project delivery method, the owners have to manage their contractual commitments and how any deviations from the commitments may impact the contractor, and eventually time and cost. In order to effectively oversee project s cost or schedule from cradle to grave, proper schedule and cost control needs to be utilized from early stages and be ongoing on the project. Numerous challenges facing today s construction managers involve juggling between issues such as quality, scope, time, cost or safety. The time limitations can begin impacting quality and safety on the project. The earlier the issue is detected, the better the chance of deflecting it altogether or at least minimizing or eliminating its impacts to the project. And time is money. In construction this oftentimes translates to liquidated damages or incentive/disincentive payments. Therefore a well-prepared and approved comprehensive construction schedule is vital to the success of the overall project. And it is not only about preparing and closely monitoring it. If it is to be a useful tool, it has to be also about communicating the work plans to the parties involved. And this is where tools such as TILOS come in. As mentioned earlier, linear schedules have an advantage over a traditional CPM in the way the information is displayed and associated to the visual location of the work. As shown on Exhibit 9, a fortypage CPM schedule submittal from the contractor can correspond to a one-pager when using linear schedule to clearly outline construction sequencing and timing of work in various parts of the alignment. It communicates more information in an intuitive manner because the distance related data is assigned to each task and effectively displayed in the report. Those linear schedules can be used by both the contractor and the owner in meetings or negotiations. While a contractor can reap the benefits of using linear schedule in its planning and monitoring, the owner will find it beneficial in its monthly oversight, change order negotiations or claims analysis. Exhibit 9 A 40-page Primavera schedule represented on one page using linear schedule The degree of detail must be carefully evaluated based on the specific use of the displayed information. When too many activities are plotted on one page, a diagram is too crowded with slanted lines and 2010, Lorne Duncan and Joanna Alvord -7-

rectangles and it may be difficult to analyze the information. On another hand, if the information is plotted on several pages, it may be harder to spot the overall construction philosophy. An experienced scheduler can create different views of information sets to support the analysis and the task at hand. For example if an owner is responsible for acquiring and providing necessary ROW, a quick overlay of the potentially delayed ROW and the contractor s schedule will outline the planned activities and potential conflicts. Similarly, in a change order negotiation, an overlay of the baseline schedule and subsequent updates can reveal baseline conflicts that were not easily visible during the baseline review in the Primavera format. For example, in a contractor planned work in a linear fashion with base course following borrow operations (light blue and light grey in baseline and dark blue and black in revision). It can be easily spotted if the baseline had some flaws showing that base course would be completed ahead of borrow operations in certain segments. Similarly spacing between work crews in the baseline schedule and revision can also be spotted and used in negotiations. Practically, any Primavera schedule can be imported into TILOS. Some level of formatting of the information in Primavera is necessary. If an extensive use of TILOS is anticipated, the scheduling specification should outline the requirements. Typically the schedule will need additional fields to delineate start and end location of each of the construction activity in a separate column rather than in the activity description itself as it is typically done. Depending on how the activity coding structure is organized, additional activity codes may have to be introduced to facilitate intuitive display of information in the linear fashion. Conclusion The intent of this paper is to provide a comparison of traditional CPM scheduling tools to linear scheduling software (TILOS ) for alignment based projects. This overview described how to interpret march charts in the simplest form and then increased the complexity by adding constructability issues such as environmental restrictions and risk such as weather. The ability to represent non-linear activities on a march chart makes this a very powerful solution that enables one to view the entire project on one march chart. Also described was the ability to apply speed and work profiles to connect the productivity rates to soil, timber or any other factor that will have an impact. Progressing during project execution is dependent on the input of the crew inspector daily report. Typically the start and end KP for each crew is recorded daily for progressing the march chart. It should be apparent that linear scheduling software is very well suited for pipeline, road, rail and other similar projects. We have seen that march charts connect the schedule to the geography and risks of a project in a manner that is not simply possible using traditional CPM scheduling methods. References Duffy, G.A. (2009) Linear Scheduling of Pipeline Construction Projects with Varying Production Rates. PhD Thesis. Oklahoma State University 2010, Lorne Duncan and Joanna Alvord -8-