/s/ Sidney Mannheim Davies Sidney Mannheim Davies Assistant General Counsel Counsel for the California Independent System Operator Corporation



Similar documents
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

San Diego Gas & Electric Company ) Docket No. ER MOTION TO INTERVENE AND PROTEST OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. California Independent System ) Docket No. ER Operator Corporation )

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

ALSTON&BIRD LLP. The Atlantic Building 950 F Street, N. W. Washington, DC Fax: July 11, 2007

December 30, Deseret Generation & Transmission Co-operative, Inc.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

ORDER ACCEPTING FOR FILING AND SUSPENDING PROPOSED RATES, AND ESTABLISHING HEARING PROCEDURES. (Issued March 12, 2003)

August 31, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Florida Gas Transmission Company, LLC Docket No. RP

Southern LNG Company, L.L.C. ( SLNG ) submits for filing the following section to its FERC Gas Tariff, First Revised Volume No.

Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC Compliance Filing Docket No.

Informational Report of the California Independent System Operator Corporation

March 25, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Rock Island Clean Line LLC ) Docket No. ER

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

154 FERC 61,020 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC January 19, 2016

Midcontinent Independent System Operator, Inc. FERC Docket No. ER Notice of Termination of Generator Interconnection Agreement

151 FERC 61,108 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING PROPOSED TARIFF REVISIONS. (Issued May 11, 2015)

May 27, Version

Mailing Address: P.O. Box 1642 Houston, TX July 27, 2015

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

hereby submits for filing a report of its Operational Purchases and Sales for the thirteen-month period ending December 31, 2011.

STATEMENT OF NATURE, REASONS AND BASIS

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

September 29, Docket No. ER Amendment to CAISO FERC Electric Tariff to Eliminate Annual External Operations Review

Midcontinent Independent System Operator, Inc. FERC Docket No. ER Notice of Termination of Multi-Party Facilities Construction Agreement

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southwest Power Pool, Inc. ) Docket No. ER )

104 FERC 61,128 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Washington Storage Service Update to Lists of Buyers Docket No. RP07-

Affidavit Of Charles A. Smart

Fourth Revised KCBPU Service Agreement

December 12, Certain Wireless Consumer Electronics Devices and Components Thereof Inv. No. 337-TA-853. James C. Otteson

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

How To Answer The Six Cities' Protest Against The Power Line Project

145 FERC 61,151 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Transcontinental Gas Pipe Line Company, LLC Rate Schedule S-2 Tracking Filing

MEMORANDUM. March 9, 2007

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C Amendment No. 3 to FORM S-3 VNR FINANCE CORP San Felipe, Suite 485

143 FERC 61,246 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA 151 FERC 62,146 FEDERAL ENERGY REGULATORY COMMISSION ORDER AUTHORIZING DISPOSITION OF JURISDICTIONAL FACILITIES

Flow Through of Texas Eastern Transmission, LP OFO Penalty Sharing

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) )

Case Doc 2193 Filed 03/07/14 Entered 03/07/14 11:33:32 Desc Main Document Page 1 of 5

Network Upgrades andSIAs Under California Tariff Clarifications

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) )

UNITED STATES OF AMERICA FEDERAL LABOR RELATIONS AUTHORITY Office of Administrative Law Judges WASHINGTON, D.C

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, LLC ) Docket No. ER

111 FERC 61,205 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

145 FERC 61,172 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

132 FERC 61,083 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING REHEARING AND INSTITUTING SECTION 206 PROCEEDING

'"l Davis Wright!! TremaineLLP

ISO/RTO Council Comments on National Institute of Standards and Technology Proposed Smart Grid Interoperability Standards

152 FERC 61,028 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL TRADE COMMISSION

153 FERC 61,374 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC December 30, 2015

December 13, WSPP Inc., Docket No. ER11- Incorporation of Rate Schedules into WSPP Agreement

Update to List of Non-Conforming Service Agreements Docket No. RP16-

July 1, Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C Magalie R. Salas, Secretary

RESTATED ARTICLES OF INCORPORTATION OF THE CALIFORNIA STATE UNIVERSITY FOUNDATION

151 FERC 61,274 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

California Independent System Operator Corporation - A Case Study

UNITED STATES OF AMERICA BEFORE THE FEDERAL TRADE COMMISSION ON

138 FERC 61,135 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER DENYING CONTINUATION OF STANDARDS OF CONDUCT WAIVER

Charging Party NOTICE OF TRANSMITTAL OF DECISION

Dear Mr. Lawrence, Thank you for your attention to this matter. Respectfully submitted,

QUALCOMM INC/DE FORM 8-K. (Current report filing) Filed 09/30/15 for the Period Ending 09/28/15

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION NOTICE. March 9, 2006

UNITED STATES OF AMERICA Before the SECURITIES AND EXCHANGE COMMISSION II.

Department of Public (D/B) Versus Precedent Agreements in Tennessee

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. PJM INTERCONNECTION, L.L.C. ) Docket Nos. ER ) ER

April 29, The ISO sent its proposed tariff amendment to the Commission via overnight delivery on December 23, 2009.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Greater Detroit Resource Recovery Project. ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) Southwest Power Pool, Inc. ) Docket No.

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Columbia Gas Transmission Corporation ) Docket No.

Trunkline Gas Company, LLC Docket No. RP

BEFORE THE STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION TWC DIGITAL PHONE LLC PETITION TO INTERVENE

103 FERC 61, 044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

FirstEnergy IRRC RECEVED. 20L5 APR 7 i 2: 59. April

Enbridge Gas Distribution Inc. Application re: Rate 332 Tariff STAR Board File No. EB

Enclosed for filing in the above-captioned proceeding is Counsel for the Public's Response to Motion to Adopt Procedural Schedule.

ARIZONA PUBLIC SERVICE COMPANY ORDER NO. EA-134

UNITED STATES OF AMERICA 100 FERC * FEDERAL ENERGY REGULATORY COMMISSION

San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions. Electric Grid Operations

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

How To Get A Refund From The Utilities Commission

Options Clearing Corporation ( OCC ) filed with the Securities and Exchange

San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions June 4, Electric Grid Operations

October 1, Exemption No A Regulatory Docket No. FAA

Version Part Section Description II Summary of Negotiated Rate Agreement

121 FERC 61,143 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

San Diego Gas & Electric Company FERC Order 717 Transmission Function Employee Job Descriptions August 10, Electric Grid Operations

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION

SANTANDER DRIVE AUTO RECEIVABLES LLC

THE GOLDMAN SACHS GROUP, INC. (Exact name of registrant as specified in its charter)

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

144 FERC 61,141 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Transcription:

California Independent System February 14, 2007 Via Electronic Filing The Honorable Magalie R. Salas Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: LSP South Bay, LLC Docket Nos. ER07-454-000 Dear Secretary Salas: Transmitted herewith for electronic filing in the above-referenced proceedings is the Motion to Intervene of the. Thank you for your attention to this matter. Yours truly, /s/ Assistant General Counsel Counsel for the California Independent System Enclosure cc: Service List

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Docket No. ER07-454-000 LSP South Bay, LLC ) ) MOTION TO INTERVENE OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION Pursuant to Rule 214 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission ( Commission ), 18 C.F.R. 385.214, and the Commission s January 29, 2007, Combined Notice of Filings, the ( CAISO ) submits this Motion to Intervene in the above captioned proceeding. In support thereof, the CAISO states as follows: I. DESCRIPTION OF THE PROCEEDING On January 24, 2007, LSP South Bay, LLC submitted certain conforming revisions to its Reliability Must-Run ( RMR ) Agreements between LSP South Bay, LLC and CAISO. By its Notice issued January 29, 2007, the Commission established February 14, 2007, as the comment date motions in the above-captioned proceeding. II. DESCRIPTION OF THE ISO AND COMMUNICATIONS The CAISO is a non-profit public benefit corporation organized under the laws of the State of California with its principal place of business at 151 Blue Ravine Road,. The CAISO is the Control Area operator responsible for the reliable operation of the electric grid comprising the

transmission systems of a number of utilities including San Diego Gas and Electric Company ( SDG&E ) as well as the coordination of the ancillary services and real-time electricity markets in California. The CAISO requests that all communications and notices concerning this motion and these proceedings be provided to: Assistant General Counsel Tel: (916) 608-7144 Fax: (916) 608-7222 E-mail: sdavies@caiso.com Robert C. Kott Manager of Model and Contract Implementation Tel: (916) 608-5804 Fax: (916) 351-2487 E-mail: rkott@caiso.com III. CAISO S INTEREST LSP South Bay s Units are located within SDG&E s transmission systems. These facilities are needed to maintain the reliability of the ISO Controlled Grid. As the Control Area operator and as the counter party to the RMR Agreements, the CAISO has a unique interest in any Commission proceeding that affects an RMR Agreement. Accordingly, the CAISO has a direct and substantial interest in this proceeding and requests that it be permitted to intervene. Because no other party can adequately represent the CAISO s interests in this proceeding, the CAISO s intervention is in the public interest and should be granted. 2

IV. CONCLUSION For the foregoing reasons, the CAISO respectfully requests that the Commission grant this Motion to Intervene and make the CAISO a party in the above-caption proceeding with full rights of participation. Dated: February 14, 2007 Respectfully submitted /s/ (916) 608-7144 (tel) (916) 608-7222 (fax) 3

CERTIFICATE OF SERVICE I hereby certify that I have, this 14 th day of February 2007, caused to be served a copy of the forgoing document upon all parties listed on the official service list compiled by the Secretary of the Federal Energy Regulatory Commission in this proceeding. /s/