REHABILITATION AND EXTENSION PROJECT FOR PORT OF LOBITO



Similar documents
Logistics and Infrastructure

TANZANIA HARBOURS AUTHORITY PO Box 9184 DAR-ES-SALAAM TANZANIA

MLD: Domestic Maritime Transport Project

Container design and types

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA

Tariff General Cargo. Tariff DB Port Szczecin Sp. z o.o. Bytomska14_Str Szczecin, Poland. This Tariff includes: rates for services,

Congo (D. R.) Ports description

SINGAPORE. A PREMIER GLOBAL HUB PORT THE WORLD S BUSIEST PORT

THE LIVORNO PLATFORM

KRISHNAPATNAM PORT COMPANY LIMITED

Southern California International Gateway Project Description

A SOLUTION FOR THE NEW YORK HARBOR TODAY. A LEADER FOR THE SHIPPING WORLD TOMORROW.

Self-Discharging Cement Carrier

Mexico s ports. Hub Ports. Altamira. Veracruz. Manzanillo Lazaro Cardenas

Operations Systems of Container Terminals: A Compendious Overview

TOGETHER! Let s sea more

Inland intermodal terminals and freight logistics hubs

WATERWAYS in Finland

Vessel Traffic Monitoring and Information System (VTMIS) Enhancing throughput, efficiency, safety and security in Brazilian Ports

Presentation ThyssenKrupp Bulk Materials Handling Dr. Markus Oles

GOVERNMENT OF PAKISTAN MINISTRY OF PORTS AND SHIPPING

Crane and Harbor Services Keeping your business moving

Fourth Generation Modular Construction

World Vessel Traffic Services Guide - Australia - Melbourne

TRANSPORT MODES AND THE CONSOLIDATION OF TRANSPORT LOTS

Port of Narvik. The Gateway to the Arctic PORT LOGISTICS: RAIL-ROAD-SEA-AIR. No draft restrictions. Sheltered waters. Ice-free all year round

Professor Dimitrios Tsamboulas National Technical University of Athens, Greece Expert

Failing Coastal Wood Infrastructure on the Great Lakes

Ship Fleet Management System Market Outlook FMS Adoption in Ships Likely to Accelerate by 2018 with New-generation Ships Creating Opportunities

Container Terminal Operation and Cargo Handling

Table 5 Core Port and Transport Logistic Measures: Definitions, priorities, and sources of data

RAILWAY INFRASTRUCTURE AND SERVICES. April 2nd, 2015

We provide international road haulage services all throughout Europe. Our dispatchers have many years of experience and are ready to meet the

Capital Improvement Project Status Report October 2015 (Actuals through August 2015) Percent Design Complete. Design Finish. Construction Finish

APP - Portuguese Ports Association Vítor Caldeirinha Lisbon,

Impact of Larger Vessel Size on Port Infrastructure Costs

BULGARIAN RIVER SHIPPING JSC RUSE, BULGARIA. PROJECT : LOGMOS 29 February 2012 Brussels

APRIL 2014 PORT OF ITAQUI

Hay Point Coal Terminal Queensland, Australia

Passenger Terminal Amsterdam

Why infrastructure is so important

Marine industry careers

Automated Material Handling and Storage Systems

The Changing Nature of Port Infrastructure and Port Management. Way K.W.

NAPCS Product List for NAICS 5324: Rental and Leasing of Commercial and Industrial Machinery and Equipment

Port of the Americas Rafael Cordero Santiago

IBAU HAMBURG Marine Cement Terminals

SULTANATE OF OMAN SPECIAL ECONOMIC ZONE AUTHORITY AT DUQM

Guardian Telecom Systems. Telephone.

Hurricane Hotwash. Presented by: David W. Mock, P.E. Director S.E. Region, Ports and Maritime Group CH2M HILL. AAPA Cruise Committee

OFFSHORE FIELD DEVELOPMENT

Automated Container Handling in Port Terminals

TECHNICAL INFORMATION

Department of Homeland Security Control Systems Security Program

MARITIME OFFICE IN SŁUPSK PRESENTATION OF MID COAST PORTS OF POLAND

Report of Investigation into the fatal accident happened on board m.v. Najran at Kwai Chung Container Terminal on 15 May 2008

Marine Guide for Ship Masters Contents

Regional Maritime Law Enforcement Training Center

CONTAINER TERMINAL SIMULATION. A CASE STUDY: PORT OF VALENCIA.

Atlas. Automatic Storage & Retrieval Systems

Chapter 2 Container-Terminal Logistics

Software Stability Model for Dump Truck Scheduling

Welcome to Odessa region

Port of Farsund. The exotic choice. Your first and foremost port in Norway

TARIFF September 2010

2011 REPORT ON CARGO HANDLING IN KLAIPöDA STATE SEAPORT

PORTS OF. sh i p to no r way

CUXPORT - IN POLE POSITION

Crowley LNG. Puget Sound Harbor Safety Committee June 3 rd, Matthew Sievert Director Business Development LNG

Trade Statistics for Queensland Ports

21. oktober Arctic-Hub. Mineral terminal largest in the Barents region

London Array. Operations and Maintenance

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER

Pollution Response RESPONDING TO AN OIL SPILL

The Nationwide Automatic Identification System Newsletter Issue #1 3 rd Quarter FY 2007

Hellesylt. PORT Contact on arrival (detail name): VHF channel: 13/16 PFSO on duty Telephone: Notice required:

INVESTIGATION OF THE GROUNDING OF MV FULL CITY IMO No AT SASTEIN JULY 31st 2009

PRICING TARIFF Effective 01 July 2014 to 30 June 2015

ING FORWARDING & SHIP'S AGEI

Los Angeles Port Police Maritime Law Enforcement Training Center

Mersin, TURKEY. Port extension project

Member Nation Report 2010 from Denmark.

Curriculum for the Degree of. Bachelor of Science. Nautical Science

India s Infrastructure - Trends, Projections, Requirements

MARINE LIABILITY PRODUCTS

ENGINEERING FOR WATER TRANSPORTATION

Biofiltra on: West Hylebos Log Yard

I BAU HAMBURG. Information. Shipunloaders, Road- or Port-Mobile

Safe & Sound Bridge Terminology

How To Prevent Accidents At Work

Transcription:

REHABILITATION AND EXTENSION PROJECT FOR PORT OF LOBITO

Advantages of Port Lobito (1) Predominant geological locations Facing the Atlantic, Port Lobito locates around 30km north to Beguela City, and it is the main seaport in the middle of Angola.

(2) Favorable onshore transportation system LOBITO LUANDA LOBITO NAMIBE

(3) Excellent natural conditions Well sheltered by a natural sand bar; Excellent water depth inside the bay; Well municipal supporting nearby; Fantastic beach for tourism. -20m

Development Target (1) A hinge of land/water transportation for middle south of Angola, even for the inland neighbors; (2) A big port with advanced infrastructure and modern handling equipments; (3) A center port of luxury cruise for middle south of Angola; (4) Port Lobito should be able to import the general cargo and containers, export the minerals, also transport the incoming crude oil and outgoing refined oil for the proposed refinery.

Plan of time implementation It is suggested that Port Lobito should be improved to a preliminary modern port in 3.5 years, which is arranged in three steps including rehabilitation works, extension works (phase I) and updating works. 1 st stage: to rehab the existing quays in one year; 2 nd stage: to make the overall plan of Lobito Port and fulfill the Extension Work (phase I) in 2 years; 3 rd stage: to update the existing quay area in one year. After 3 rd stage, other projects such as container terminal, mineral terminal, fishery harbor and industry terminal (oil, product oil and cement, etc.) in master plan will be carried out step by step.

No. Project 1 2 3 The Rehabilitation Work of Existing Berths The Phase I Extension Work The Updating Work of Existing Berths First Year Second Year Third Year Fourth Year Duration Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 12 months 24 months 12 months

1 st Stage: Rehab the existing quay

Items of Rehabilitation (1) Install/replace the rubber fenders and bollards to improve the safety of docking and mooring;

(2) Rehab the damaged part of maritime structure crashed by ship recently, and repair/replace the deteriorated components of structure.

(3) Re-pave the apron and stacking yard;

2 nd Stage: Extension Work (phase I) for Port of Lobito

Master Plan for Port of Lobito

Situation of usage on shoreline resources of Lobito Bay 1700 3100 3100 964 964 2000 There are about 11.7km natural shoreline inside the Lobito Bay, in which 7.8km long is suitable for building port.

Situation of usage on shoreline resources of Lobito Bay Oil terminal of refinary Sonangol Cement factory Sonamet

Situation of usage on shoreline resources of Lobito Bay Shoreline can be used: 2.3km in green And divided into four parts 570 570 1130 1130 1200 1200 400 400 800 800 700 700 552 552 414 414 1000 1000

Maximum Vessel Type 100,000 DWT Basing on the investigation data, the surface of rock layer is very v shallow at the entrance of Lobito Bay.. The geological conditions has been an obstacle to develop large berths more than 100,000 DWT.

Maximum Vessel Type 100,000 DWT For all kinds of terminals, 100,000 DWT berths can satisfy the requirement. Container terminal: 100,000 DWT Berths (the fifth generation) can meet the requirement of transportation of container. Mineral terminal: There is no ire ore minerals, 100,000 DWT berths can meet the requirement of exporting minerals. Oil terminal: Since the oil farm isn t t far away from Port of Lobito, 100,000 DWT oil terminal can meet the requirement of importing crude oil.

Vessel Type Selected Vessel Type Load Capacity (DWT) Short-Term Long-Term General Cargo Vessel 20,000~30,000 20,000~30,000 Bulk Cargo Vessel 50,000 100,000 Container Vessel 30,000 (The third generation) 70,000 (The fifth generation)

Throughput Forecast for Lobito Port Throughput forecast of container Unit: TEUs Year 2010 Growth Rate 2015 Growth Rate 2020 Container 130,000 15% 260,000 15% 520,000

Throughput Forecast for Lobito Port Throughput Forecast of Minerals Unit: tons Year 2010 Growth Rate 2015 Growth Rate 2020 Copper 500,000 15% 1,000,000 15% 2,000,000 Others 1,500,000 12% 2,600,000 12% 4,600,000 Total 2,000,000-3,600,000-6,600,000

Throughput Forecast for Lobito Throughput Forecast of General Cargo Unit: tons Year 2010 Growth Rate 2015 Growth Rate 2020 General Cargo 400,000 10% 600,000 10% 1,000,000

Throughput Forecast for Lobito Port Throughput forecast Year 2010 General Cargo (tons) Growth Rate 2015 Growth Rate 2020 400,000 10% 600,000 10% 1,000,000 Containers (TEUs) 130,000 15% 260,000 15% 520,000 Mineral except iron ore (tons) 2,000,000 15% for copper 12% for others 3,600,000 15% for copper 12% for others 6,600,000

Mineral Tourism Oil Cement Fishery Road Master Plan of Port Lobito Master Plan of Port Lobito Tourism Container Railway

Throughput Capacity of the Proposed Port The throughput capacity of Port Lobito for short-term and long-term is calculated as below: Description Short-term Long-term General Cargo (tons) Containers (TEUs) project Rehabilitation on the existing quays (In 2009) 414m long special container terminal (In 2010) Throughput capacity 400,000 200,000 project Rebuilding on the existing quays (In 2013) 360m long special container terminal (In 2020) Throughput capacity 1,000,000 700,000 Mineral except iron ore (tons) 310m long mineral terminal (In 2010) 3,650,000 Another mineral terminal (In 2020) 11,650,000 (Except iron ore)

Development of Container Terminal in the Port of Lobito Year 2010 2015 2020 Throughput Forecast 130,000 TEUs 260,000 TEUs 520,000 TEUs Construction Items A 414m long Container Terminal A 414m long Container Terminal Another 360m long Container Terminal Marine Structure For 70,000 DWT For 70,000 DWT For 70,000 DWT Water Depth For 30,000 DWT (-12.7m) Handling Equipment See Table 4-4 and 4-5 in Preliminary Design Report Design Throughput Capacity of the Port of Lobito Cost Estimate For 70,000 DWT (-14.7m) See Table 4-4 and 4-5 in Preliminary Design Report For 70,000 DWT 200,000 TEUs 300,000 TEUs About 700,000 TEUs 660.36 million USD 94.42 million USD

Development of Mineral Terminal in the Port of Lobito Year 2010 2015 2020 Throughput Forecast 2,000,000 tons 3,600,000 tons 6,600,000 tons Construction Items A 310m long Mineral Terminal A 310m long Mineral Terminal Another planned Mineral Terminal Marine Structure For 100,000 DWT For 100,000 DWT For 100,000 DWT Water Depth For 50,000 DWT For 100,000 DWT For 100,000 DWT (-14.1m) (-15.5m) Handling Equipment See Table 8-4 in Preliminary Design Report See Table 8-4 in Preliminary Design Report Design Throughput Capacity of the Port of Lobito 2,850,000 tons 3,650,000 tons About 11,650,000 tons Cost Estimate 483.9 million USD 71.75 million USD

Extension Work (phase I) for Port of Lobito

Extension Work (phase I) for the Port of Lobito It is proposed to build a 414m long container terminal and a 310 long mineral terminal for the extension works (phase I). Terminal Design Item Design Vessel Type Container Water area 30,000 DWT Container Vessel Marine structure 70,000 DWT Container Vessel Mineral Water area 50,000 DWT Bulk Cargo Vessel Marine structure 70,000DWT Bulk Cargo Vessel

Container Terminal

Work Scope Container Terminal (including a 414m container quay and a dry port about 3km away from the harbor) Special Railway Line connecting the container quay and dry port Bridge Communication and Vessel Traffic Service System

General Layout of Container Terminal Container Quay Bridge Special Railway Line Dry Port

Container Quay

Layout of Container Quay B A C B A C

Handling Technology

Annual Throughput: 200,000 TEUs in short-term term and 250,000 TEUs in long-term. Load and Unload Ship Load and Unload Train Load and Unload Cargos in Stacking Yard

Marine Structure (to be continued) classical suspended quay deck combination structure of suspended quay deck with front steel tubular sheet pile

Marine Structure (continued) combination structure of suspended quay deck with front steel tubular sheet pile classical suspended quay deck

classical suspended quay deck

Combination structure of suspended quay deck with front steel tubular sheet pile

Dry Port

Layout of Dry Port E D E D

Handling Technology

Handling Equipment at Container Quay NO. Name Unit Quantity In short-term (In 2010) In long-term (In 2015) 1 Multi-purpose Portal Crane set 2-2 Container bridge crane set 1 +2 3 Rubber-tyred Gantry Cranes set 4 +4 4 Container reach stacker set 1 +1 5 Empty container handler set 2 +1 6 Container Tractor set 10 +5 7 Container Trailer set 12 +6 8 Rail-mounted Gantry Cranes set 2 +2 9 Weighbridge set 2 +2

Handling Equipment at Dry Port NO. Name Unit Quantity 1 Rubber-tyred Gantry Cranes set 2 2 Container reach stacker set 1 3 Empty container handler set 4 4 Container Tractor set 10 5 Container Trailer set 12 6 Rail-mounted Gantry Cranes set 2 7 Weighbridge set 2 8 Maintenance Equipment item 1 9 Other tools item 1

Schedule of Container Terminal (page 1/2)

Schedule of Container Terminal (page 2/2)

Special Railway Line

Special Railway Line Container Quay 5.5km long Dry Port

Bridge

Arrangement Plan of Bridge A Bridge Vertical B A B Bridge Plan Bridge Substructure Plan

Arrangement Plan of Bridge Section A-A Section B-B

Communication and Vessel Traffic Service System

Communication There are 6 systems for communication, namely: Digital Telephone Switch System; Inter-communication system Radio Telephone System Ship to Shore Communication System Marine VHF Telephone System IMMARSAT Satellite Communication

Communication The Diagram layout of digital telephone system

Communication General layout of radio telephone system

Communication General layout of ship to shore communication

Vessel Traffic Service System The VTS is very important for the modern port to improve the maritime safety and efficiency of navigation, safety of life at sea and the protection of the marine environment and/or the adjacent shore area. It is a practical solution for modern port traffic management. ent. The VTS system of the Port of Lobito should cover the harbor area and her nearby. One remote radar station, one local radar station, one VTS center and accessorial facilities need to be set up.

Vessel Traffic Service System REMOTE RADAR STATION LOCAL RADAR STATION VTS CENTER Location of VTS radar station

Vessel Traffic Service System Local Radar Station Remote Radar Station VTS Control Center General system layout of vessel traffic system

Mineral Terminal

General Layout of Mineral Terminal 650 m 1110 m Isobath of about -8m

Plan of Mineral Terminal B A B A C C

Handling Technology

Handling Technology

Annual Throughput: 3,650,000 tons Bagged Mineral Load Ship Bulk Mineral Unload Train for Bulk Cargo Bagged Mineral Storage Yard and warehouse Bulk Mineral Storage Yard Load and Unload Cargos on Storage Yard

Handling Equipment NO. Name Unit Quantity 1 Portal crane set 2 2 Ship loader set 1 3 Rubber-tyred mobile Crane set 2 4 Tractor set 4 5 Trailer set 10 6 Fork lift set 2 7 Fork lift set 4 8 Bulldozer set 2 9 Bucket Loader set 1 10 Rail-mounted Stacker and Reclaimer set 1 11 Belt Conveyer m 870 12 Belt Conveyer m 810 13 Screw Wagon Unloader set 3 14 Wagon Weighbridge set 1 15 Maintenance Equipment item 1 16 Other tools item 1

Marine Structure Plan of Mineral Cargo Quay Elevation of Mineral Cargo Quay

Marine Structure Plan of Mineral Cargo Quay Elevation of Mineral Cargo Quay

Cross Section of Mineral Terminal

Plan of Unit

Typical Section of Revetment (1)

Typical Section of Revetment (2)

Schedule of Mineral Terminal

3 rd : Updating of the Existing Quay

It is proposed to reconstruct the existing north and south quay based on the Master Plan after extension work is finished North quay and South quay will be rebuilt as multipurpose terminal of about 50,000 DWT. It is proposed that Parts of north quay be used for luxury cruises.