Session: Tue 1110 to 1225. How to Cost Load a schedule. OR Understanding the SDEF



Similar documents
UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

EXHIBIT 2-2-C PROGRESS SCHEDULES

SECTION PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

CRITICAL PATH METHOD (CPM) SCHEDULES

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

MODEL SCHEDULING SPECIFICATION

Module 8: QUALITY CONTROL SYSTEM (QCS) and RESIDENT MANAGEMENT SYSTEM (RMS) Submodule 1: Introduction and Overview

Pricing of Construction Contract Change Order Documentation

Distribution Restriction Statement Approved for public release; distribution is unlimited.

AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, :30 PM INTRODUCTION TO GOVERNMENT CONTRACTING

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

UNIFIED FACILITIES GUIDE SPECIFICATIONS

PN /16/ CRITICAL PATH METHOD PROGRESS SCHEDULE

Scheduling Glossary Activity. A component of work performed during the course of a project.

SECTION COST LOADED CRITICAL PATH SCHEDULE

RFQ NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 REF. LOCATION DESCRIPTION OF CHANGE. Revised Scope of Work. Work tasks have been revised.

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Designer & Builder Symposium Construction Scheduling. Glenn Saito NAVFAC Pacific Construction Division December 1, 2010

Planning and Managing Projects with Microsoft Project Professional 2013

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised )

Alexandria National Cemetery SECTION NETWORK ANALYSIS SCHEDULE

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

Oracle Primavera. P6 Resource Leveling Demo Script

CONSTRUCTION CONTRACT TERMINOLOGY

ALLOCATE RESOURCES STEP 6 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)

CHAPTER 53 COST ACCOUNTING STANDARDS

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I

Florida Department of Transportation 605 Suwannee Street Tallahassee, FL

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule

Spec. Standard: 11/27/ Revision: 11/27/06

REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office

Module 9: NAVFAC s Web-based Construction Management System (WebCM) Objectives: After completing this module, you will be able to:

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS. Presented by ALEXANDER F. FERRINI, III

Presented by: Laura Davis, President Strategic Consulting Solutions, Inc. PDS Consulting Solutions, LLC November 12, 2015

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

ITEM DOCUMENT CONTROL MANAGEMENT DESCRIPTION:

UFGS (February 2011) UNIFIED FACILITIES GUIDE SPECIFICATIONS

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Developing Critical Path Method Scheduling (CPM)

1. Interpretation of this Schedule

Manual on Training Preparation

NextGEN Project Managers

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT Approval Date:

UFGS (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS

Contract Administration

Introduction to Project Management

IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)

Document Comparison. AIA Documents A and A131CMc 2003

A Comparative Analysis of US Departments of Transportation Scheduling Specifications and Industry Recommended Scheduling Practices.

Microsoft Project Activity

Module 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION"

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT S. Marion Avenue, Mail Station 2015 Lake City, Florida

Appendix B: Work Breakdown Structure (WBS)

TECHNIQUES FOR MANAGING COMPLEX PROJECTS WITH PLANNING AND SCHEDULING SOFTWARE PAUL E HARRIS EASTWOOD HARRIS

Project Time Management

NJEMs Bill ID: This is a unique identification number created by the billing software to identify this particular invoice with the responsible party.

DEPARTMENT OF THE ARMY U.S. Army Corps of Engineers Washington, DC Construction CONTRACTOR SUBMITTAL PROCEDURES TABLE-OF CONTENTS

Norsouth Construction Company of Georgia, Inc. Bid Information and Requirements To Whom it May Concern:

Are You Looking to Sell Your Products & Services to the US Government? Overview

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

INTRODUCTION TO PROJECT MANAGEMENT AND MS PROJECT

J.R. Huston Enterprises, Inc.

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

UNIFIED FACILITIES GUIDE SPECIFICATIONS

TECHNICAL INFORMATION MEMORANDUM 93-5 AUGUST 19, 1993

Project Time Management

Project Execution - PM Elements

CHAPTER 6 PROJECT CASH FLOW

Project Management Using Earned Value

Cracking the ICE: Ensuring a Compliant Incurred Cost Submission. Carlos Alvarado, VP, FP&A

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-CE Washington, DC

SAFETY IN NAVFAC-SE ACQUISITIONS. Presented by Tina Dancy 29 June 2012

THE DCAA AUDIT BECOMING DCAA COMPLIANT

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG

Guidelines: Project Schedule Project Management Office (PMO)

Design Consultant Project Management Requirements

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS

The Implementation Advance Planning Document (IAPD)

USACE NAVFAC Sample QA/QC Plan 20 selected pages (out of )

Contract Compliance and the Federal Acquisition Regulation (FAR)

Transcription:

Session: Tue 1110 to 1225 How to Cost Load a schedule for USACE s QCS/RMS OR Understanding the SDEF

(understanding the SDEF) Introduction David Long Sr. Project Controls Specialist With 20+ years of Scheduling and Cost Analysis experience on USACE funded/managed projects. Including Environmental, Bid/Construct, and Design/Build. Cost reimbursable, Time and Material, and Firm Fixed Price Contracts. It is important to understand the USACE intent and usage of a cost loaded schedule and QCS/RMS as part of the Progress Payment process. That is, your cost loaded schedule is your SOV. Therefore, it is understanding the Process and the Standard Data Exchange File (SDEF) that becomes the key to understanding how to Cost Load the Schedule.

(understanding the SDEF) Introduction Today s presentation is built around Primavera s P6 Version 6.2 but the principles and techniques are applicable to MS Project and other Scheduling Applications It is also based on Firm Fixed Price Contracts, however, applicable for Cost Reimbursable and T&M contracts.. Based on Actual Cost not Earned Value Firm Fixed Price vs. Cost Reimbursable Affects the source of Actual Cost not the Field used.

Relative Standards / Documents

ER 1-1-11

ER 1-1-11 This regulation states the policy on the use of any of the various scheduling management methods. various systems (bar charts, network analysis etc.) as well as administration of contract provisions. This regulation is applicable to all USACE commands. FAR 52.236 15 DOD FAR Supplement 236.273

Primavera P6 SDEF Conversion

Primavera P6 SDEF Conversion

Unified Facilities Guide Specifications (UFGS) ************************************************************************** USACE / NAVFAC / AFCEC / NASA UFGS 01 32 01.00 10 (August 2008) Change 1 08/13 Preparing Activity: USACE Superseding UFGS 01 32 01.00 10 (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS References are in agreement with UMRL dated October 2013 ************************************************************************** SECTION 01 32 01.00 10 PROJECT SCHEDULE ************************************************************************** NOTE: This guide specification covers the requirements for the preparation and maintenance of the project schedule for construction projects or design build construction projects.

Basic Reason for Cost Loading the Schedule USFG Section 01 32 01.00 10 Paragraph 3.2 BASIS FOR PAYMENT AND COST LOADING To Get Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. That is, the cost loaded schedule is your schedule of value for progress payments. Therefore

Cost Loading the Schedule It is reasonable. Acceptable to the Contracting Officer. The activity scope is measurable and represents a deliverable value to the Government. All activities for a specified CLIN sums up to the CLIN value USFG Section 01 32 01.00 10 Paragraph 3.2 BASIS FOR PAYMENT AND COST LOADING Activity cost loading shall be reasonable, as determined by the Contracting Officer. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule. The schedule is your schedule of value for progress payments.

Cost Loading the Schedule The Earnings Report Budgeted Total Cost at the activity level must roll up and equal to the Contract CLINs (SubCLINS) Actual Cost is the actual cost to date for Cost Reimbursement Contract or is equal to the Earned Value for FFP Contracts (SOV Value)

Cost Loading the Schedule Only Resource Assignment Budget and Actual Cost are exported to QCS/RMS. That is: User Defined Cost Fields or P6 Expenses are not included in the SDEF Multiple Resource Assignments are allowed, however, it is only the Resource Assignment s total Budget and Actual Cost that are exported to QCS/RMS. Resource units, Activity Earned Value, Activity % Complete are not exported to QCS/RMS. That is: % Complete is calculated in QCS/RMS by dividing the Actual Cost by the Budget, that is, % Spent.

Cost Loading the Schedule Role ID SUB/MTL Resource ID $$$$.Fully Burdened Cost Resource Type Nonlabor [NOTE: can use Labor or Material Resource Type] Rate Type Used with Resource or Role Rate Source Rate Source Override (allows for manual entry of Price/Unit) [NOTE: Resource or Role Rate Source can be used] Price/Unit Used if Calculate Cost form Units is Checked Budgeted Cost Budget (Price/Unit * Budget Units) Actual Units Actual Units to date (Entered value unless using Auto Compute ) Actual Cost Actual Cost to date (Entered value unless using Cal cost from units) SDEF PROG Record PROG C1040 31AUG12 3 12000.00 4800.00.00 06SEP12 17SEP12 + 7

Cost Loading the Schedule The Earnings Report Review

Cost Loading the Schedule

Cost Loading the Schedule? SDEF ACTV Record ACTV C1040 Install Storm Water System 3 5 0 CVIL DRNG 000000 0002 CN W Stabilization Methods

Cost Loading the Schedule Direct Cost (Direct Labor include Fringe and Overhead) Any Contingency and prorated General Conditions and PMO Costs G&A and any other indirect costs excluding Bond and Insurance costs Fee / Profit (unless allowed as a separate billing line item typically Cost Re) Cost must be loaded on deliverable activities with measurable scope having value to the Government.

Cost Loading the Schedule Prep/Submit Concept Design Design Management/Support Staff (GC) Gov't Review Concept Design Prep/Submit 100% Civil Design Design Conf. Concept Design Gov't Review 100% Civil Design Construction Management/Support Staff (GC) Prep/Submit SWS Submittal Design Conf. 100% Design Prep/Submit IFC Civil Design Gov't Review/Acceptance IFC Civil Design Issue IFC Civil Design Civil and SWS Preparatory Remove Fencing Fill/Compact Sinkhole Del. Fencing Materials Install Storm Water System $ 2,600.00 $ 0.00 $ 0.00 $ 5,200.00 $ 0.00 $ 0.00 $ 0.00 $ 1,000.00 $ 0.00 $ 1,300.00 $ 0.00 $ 1,300.00 $ 0.00 $ 560.00 $ 6,400.00 $ 2,000.00 $12,000.00

The Process Schedule Review and Reports Network Diagram Earnings Report Activity Report Logic Report Total Float Report Generate the SDEF Load SDEF into QCS [CLINs must balance with RMS] Submit to RMS Draft Prompt Payment and Application for Payment Progress Cost Loaded Schedule Payment Received Internal Approval, Compliance, and Billing Process [Signed Prompt Payment and Pay Application]

Understanding SDEF Requirements Cost Loaded That is: Cost to the Government. Activity Coded That is: 10 specifically defined activity codes in ER 1 1 11 USFG Section 01 32 01.00 10 Paragraph 3.1.1 Approved Project Schedule Use the approved Project Schedule to measure the progress of the work Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments.

Understanding the SDEF Requirements Standard Activity Codes USFG Section 01 32 01.00 10 Paragraph 3.4.5 Standard Activity Coding Dictionary Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1 1 11, Appendix A. This exact structure is mandatory, even if some fields are not used. The SDEF format is as follows: Activity Code Field Code Length Description 1 WRKP 3 Workers per Day 2 RESP 4 Responsible Party (e.g. GC, subcontractor, USACE) 3 AREA 4 Area of Work 4 MODF 6 Modification or REA number 5 BIDI 6 Bid Item (CLIN or SubCLIN) 6 PHAS 2 Phase of Work 7 CATW 1 Category of Work 8 FOW1 10 Feature of Work (used up to 10 characters in length) 9 FOW2 10 Feature of Work (used up to 20 characters in length) 10 FOW3 10 Feature of Work (used up to 30 characters in length)

Understanding the SDEF Requirements Standard Activity Codes USFG Section 01 32 01.00 10 Paragraph 3.4.5 Standard Activity Coding Dictionary These activity codes were originally defined for P3 which was a flat and finite length register. Therefore, all codes had to be Use the activity coding structure defined in the Standard Data Exchange Format defined (SDEF) in the in ER order 1 1 11, shown Appendix and A. with This code exact length structure as is specified. mandatory, even if some fields are not used. The SDEF format is as follows: Several Tips and Tricks for P6: The order Activity is no Code longer important, in fact you do not even need to define all Fieldof them. Code Length Description 1 The Max WRKP length of 3 the Code Workers ID per is still Dayimportant, except: 2 FOW RESP 1, 2, & 43 needs Responsible to be replaced Party (e.g. with GC, just subcontractor, FOW with a USACE) code value of 3 AREA 4 Area of Work 1 to 20 characters it is not the code value that gets converted to the 4 MODF 6 Modification or REA number SDEF, it will load up to 30 characters of the Code Value Description. 5 BIDI 6 Bid Item (CLIN or SubCLIN) 6 You can PHAS use the Hierarchical 2 Phase Activity of Work Code feature in P6 What gets 7 converted CATW to the 1 SDEF is Category simple of the Work code assigned at whatever level you 8 assign FOW1 it. 10 Feature of Work (used up to 10 characters in length) 9 FOW2 10 Feature of Work (used up to 20 characters in length) 10 FOW3 10 Feature of Work (used up to 30 characters in length)

Title Sub-Title

Understanding the SDEF Requirements Calendars First work day = NTP +1d 7 day no holiday calendar for activities contractually assigned calendar days. Use an appropriate work week calendar for each activity as you plan to work it. Identify Weather Sensitive Installation with a weather day calendar. Plan the work then work the plan. If you do not show non work periods you cannot claim as non work days in a time impact analysis. USFG Section 01 32 01.00 10 Paragraph 3.3.3 Scheduled Project Completion and Activity Calendars The first scheduled work period shall be the day after NTP is received by the Contractor. Activities may be assigned to a 7 day calendar when the contract assigns calendar day durations for the activity If the Contractor intends to perform physical work less than seven days per week, schedule the associated activities on a calendar with non work periods identified including weekends and holidays. Assign the Category of Work Code [CATW] Weather Sensitive Installation to those activities that are weather sensitive. Original durations must account for anticipated normal adverse weather. The Government will interpret all work periods not identified as non work periods on each calendar as meaning the Contractor intends to perform work during those periods.

Understanding the SDEF Requirements The SDEF Records ER 1 1 11 Part 2 SDEF SPECIFICATION, Section 6. SDEF Organization: The SDEF shall consist of the following records provided in the exact sequence shown Below: Volume Record Mandatory First Line of File Project Record Mandatory Second Line of File Calendar Record(s) Mandatory One Record Min. (one record for each calendar) Holiday Record(s) Mandatory if Holidays Used (one record for each calendar) Activity Record(s) Mandatory Records (one for every activity) Precedence Record(s) Mandatory for Precedence (one record for each pred.) Unit Cost Record(s) Mandatory for Unit Costs (scheduling application specific) Progress Record(s) Mandatory Records (one for every activity) File End Record Mandatory Last Line of Disk/File SDEF Example

UFGS Project Schedule Requirements [Section 01 32 01.00 10] WED 0115 0230 UFGS Project Schedule Reporting Requirements [Section 01 32 01.00 10] WED 0245 0400

Thank you Q & A