Kinetic energy recovery on railway systems with feedback to the grid



Similar documents
Efficient recovery of braking energy through a reversible dc substation

Field experience and best practices in managing MW scale Li-ion energy storage systems coupled to large wind and solar plants

Analysis of fuel cell

Estimation of electrical losses in Network Rail Electrification Systems

DC Traction Power Supply. Powerful, efficient and safe. siemens.com/mobility

How To Make A Train Power Battery System For The Railways

Your Power. Traction energy

Hybrid shunter locomotive

UNINTERRUPTIBLE POWER SUPPLIES >9900AUPS UNINTERRUPTIBLE POWER SUPPLIES

2012 San Francisco Colloquium

A Design of DC/DC Converter of Photovoltaic Generation System for Streetcars

Energy Depot GmbH PRODUCT AND APPLICATION GUIDE. Total Monitoring Solution for PV. Delivering Solutions for Energy Management

Power Electronics Testings

Bussmann series Third rail fuse links application guide. Leadership in fusible circuit protection solutions

ENVILINE Reliable and efficient solutions for DC rail transportation

Variable Frequency Drives - a Comparison of VSI versus LCI Systems

Inverter / Charger Installation General Operations and AC and DC Connections

Power transformers. Special transformers Railway

Energy efficiency and fuel consumption of fuel cells powered test railway vehicle

Diode Applications. As we have already seen the diode can act as a switch Forward biased or reverse biased - On or Off.

Current and voltage measuring relays

Design Considerations for an LLC Resonant Converter

Business Area Power Supply

HYBRID POWER SYSTEMS for TELECOM applications

Transformerless UPS systems and the 9900 By: John Steele, EIT Engineering Manager

A MULTILEVEL INVERTER FOR SYNCHRONIZING THE GRID WITH RENEWABLE ENERGY SOURCES BY IMPLEMENTING BATTERY CUM DC-DC CONERTER

RISH EM 3490 DS Dual Source Energy Meter RISH EM 3490 DS. Application : Product Features:

POWER TRANSMISSION FROM OFFSHORE WIND FARMS

hybrid fuel cell bus

YSmart Technology Co.,Ltd

47000 SERIES - ELECTRONIC TRANSFORMERS

EssPro Energy Storage Grid Substation The power to control energy

Unit 96: Marine Propulsion Power Plant

What Is Regeneration?

Introduction. Harmonics and IEEE 519 Page 1 of 19

Minerals Day Chile 2015 Innovative Drives for Trucks and Shovels

WIND TURBINE TECHNOLOGY

Low Voltage Products

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

Understanding Delta Conversion Online "Power Regulation" - Part 2

Fronius IG Plus. The next generation grid-connected PV inverter

ABB PV + Storage REACT-3.6/4.6-TL 3.6 to 4.6 kw

Smart Grid and Renewable Energy Grid Integration. Jian Sun, Professor and Director Department of ECSE & Center for Future Energy Systems

LM1036 Dual DC Operated Tone/Volume/Balance Circuit

The design and performance of Static Var Compensators for particle accelerators

Storage Battery System Using Lithium ion Batteries

Half the cost Half the carbon

Power Electronics. Prof. K. Gopakumar. Centre for Electronics Design and Technology. Indian Institute of Science, Bangalore.

Federal Wage System Job Grading Standards for Electric Power Controlling, Table of Contents

The function of a power station is to deliver

vacon ac drives for mining & minerals

Maximum Demand Control

TERMS AND CONDITIONS

TRAMS TROLLEY-BUSES SUBWAY

Energy Management Energy Meter Type EM23 DIN

Battery Energy Storage

Knowing the FACTS. FACTS that enhance power quality in rail feeder systems

A Fuzzy Based Solution for Improving Power Quality in Electric Railway Networks

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply.

Photovoltaic Solar Energy Unit EESFB

525-MVA Generator-motor and Thyristor Starter Put into Service at the Tokyo Electric Power Co., Inc. s Kannagawa Hydroelectric Power Station

INTERFACES FOR RENEWABLE ENERGY SOURCES WITH ELECTRIC POWER SYSTEMS

KINETIC ENERGY RECOVERY SYSTEM BY MEANS OF FLYWHEEL ENERGY STORAGE

APPLICATION NOTE USING A MODEL 3060-MS SERIES AS A REGENERATIVE AC SOURCE FOR PV INVERTER TEST APPLICATIONS. Abstract.

Dynamic test environment for fuel cells From stack to vehicle energy system

CEMEP UPS. The high environmental performance solution for power supply to high-availability data centers

Appendix 7. Conceptual Design of Electrification System. December 2010

Server Technology, Inc.

How To Powertrain A Car With A Hybrid Powertrain

ABB central inverters PVS to 1000 kw

Switch. Building technology for the real world.

Operating Concept and System Design of a Transrapid Maglev Line and a High-Speed Railway in the pan-european Corridor IV

Modern electrical propulsion systems for rolling stock

UPS Applications and VRLA Battery Sizing

SOLAR MICRO INVERTER 260 COMMUNICATION GATEWAY. Apparent Power Control (APC) unique micro inverter with

A project to optimise quality and energy efficiency must include metering

Anti-blackout system for grid connected solar installations (Solsafe concept)

ABB central inverters PVI-55.0/ PVI-165.0/ PVI-275.0/ to 330 kw

EET272 Worksheet Week 9

Understanding Power Factor and How it Affects Your Electric Bill. Presented by Scott Peele PE

Design of an Auxiliary Power Distribution Network for an Electric Vehicle

IT S TIME TO EXPECT MORE FROM AN ENERGY STORAGE SOLUTION

3-PHASE LOW VOLTAGE NETWORK LOAD BALANCER : A COST EFFECTIVE SOLUTION TO LINE VOLTAGE VARIATIONS

AMTRAK UNVEILS ADVANCED TECHNOLOGY LOCOMOTIVES FOR NORTHEAST SERVICE Siemens-built equipment to improve reliability, efficiency and mobility

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer

CO-ORDINATION OF PARALLEL AC-DC SYSTEMS FOR OPTIMUM PERFORMANCE

A Stable DC Power Supply for Photovoltaic Systems

FREQUENCY CONTROLLED AC MOTOR DRIVE

Energy Storage System Performance Testing

SECTION 8 Heater Burnout Detection

PowerFlex Dynamic Braking Resistor Calculator

Thyristor-controlled power supplies and battery chargers

Energy Storage and Electrified Rail Systems (technologies, market and business cases) Richard Drake, P.E. R&D Program Manager NYSERDA

HSP GmbH Zum Handwerkerhof Wendelstein Tel / Fax: / Web: HSP@hsshsp.de NTG-3000.

3-phase, bidirectional energy meter

JSI Series Single Phase String Inverter. Features. Typical Efficiency Curve JSI-1500TL JSI-2000TL JSI-2500TL

/ The personal storage solution for 24H Sun. / Dynamic Peak Manager. / Smart Grid Ready THREE-PHASE

Transcription:

Kinetic energy recovery on railway systems with feedback to the grid Authors: J.M. ORTEGA, METRO DE BILBAO;S:A: H. IBAIONDO, A. ROMO. INGETEAM TRACTION,S.A. 1. Introduction The increasing concern with energy saving and efficiency has a clear application in the regenerative braking capacity common to most rolling-stock. This possibility crashes with the non-reversible characteristics of the substations of direct-current catenary-based rail systems. Different options for storage and subsequent reuse of energy have been studied for both onboard and substations. Storage options are more costly and bigger in size due to the power storage components used. Additionally, there are the limitations associated with the life time of the storage components. Direct return to the distribution grid has also been proposed as an alternative. This would be carried out by converters with capacity to transfer direct catenary power to the alternate three-phase grid. Previous proposals, required to use an independent transformer associated to the recovery system in order to be able to work with catenary's voltages close to the voltage imposed by the grid and by the substation rectifier. The solution presented in this paper deals with the design strategy and topology of a new converter developed for a 1500Vdc catenary subway traction system. The recovery system works connected to an already existing transformer in the substation, minimizing the investment needed. 2. RECOVERY SYSTEM DESIGN METHODOLOGY The study, design and construction of the first prototype have been carried out for the Metro Bilbao subway traction system in Spain. The main features of this underground system are the following: - Number of lines: 2. - Total kilometres: 39 Km. - Number of stations: 36. - Number of substations: 10. - Catenary rated voltage: 1650 Vdc. - Mobile material: 24 S500 units + 13 S550 units (148 cars). - Max. power of units: 4MW. - Transit frequencies: 5 min, 6 min, 10 min, 20 min, 30 min. NOTE: In the common segment of the two lines, the transit frequency is twice the specified frequencies.

- Total kilometres per year: > 4.300.000 km. - Total passengers per year: > 86.000.000 passenger. - Annual consumption for traction: 52.5 Million kwh. 2.1 MEASUREMENT OF AVAILABLE ENERGY The first step is to check the amount of energy that at present is being burnt during train braking processes. The prior study involved acquiring on-board real traction and braking-power profiles, as well as the speed datum of a relevant number of Electrical Multiple Units covering the roundtrip distance through all the existing lines and different operation frequencies. The following conclusions could be made from the analysis of the gathered data: The initial energy performance of the trains showed very high inter-train recovery data. This is due to the high transit frequency, particularly in the shared area of the two lines, and to the low impedance of the rigid catenary in line 2. Table 1 shows the percentages energy exchange between trains for the different segments of the route. ENERGY RETURNED BY SEGMENT Line 1 middle Common segment segment Line 1 final segment Line 2 47,04% 39,72% 30,24% 46,31% Table 1: Recovery between trains, by segment. Auxiliary 14,04% Total Losses 34,16% 7,19% InterTrain Recovery 44,61% Figure 1: Train energy balance in Metro Bilbao. Burned Total Regenerated 51,8% %Recovery %Burned %Fric+ D.Ch %Aux

The mean energy balance at the substations can be calculated from the train s behavior values above. Figure 2 shows the resulting percentages for the whole system consumption with an estimated catenary s loss of 7% of the total traction consumption. Catenary Losses 7,00% Losses 57,35% 23,57% Auxiliary 12,08% Burned %Aux %Burned %Frict + D.Ch %Cat Losses Figure 2: Energy balance of Metro Bilbao system. The study shows that the burned energy represents 12.08% of the total energy consumed for traction in the substations. This means: Annual saving potential = 6.34 million kwh 2.2 RECOVERY SYSTEM SPECIFICATION The next step was to determine the characteristics of the equipment to be installed at each of the substations, the required power capacity and the resulting work cycles for an optimum converter design. For dimensioning purposes, a simulation tool capable of calculating the interaction between the different substations and the different trains linked to the same catenary was developed. An electrical model of the static system was created, including substations, stations as well as catenary impedances. The main characteristic of the simulation tool is its capacity to use data obtained from the real measurements taken of each unit, calculating successively the evolution of the trains' position, the evolution of the impedances in the catenary s sections between the different components, and the resulting power flows for each instantaneous configuration. - Validation: The program and the model created were first validated by carrying out a simulation of the real installations and comparing the results obtained with real values.

- Simulations. Once the simulation tool was validated, the recovery systems were included in the mathematical model and new simulations were run in order to calculate the recoverable power profiles for each substation. The aim of these new simulations was to determine the optimal power capacity values for a given recovery system. The optimal values were calculated in terms of the following required characteristics: - Total energy recovered - Investment costs. - Amortization ratios. - Single converter design and modularity for an easy implementation on existing substations. - Existing substation characteristics. Nominal Power of the substation transformer to be used (2,25MW). The final conclusions after successive simulations were as follows: - Number of substations to equip: 5. o o o Line 1-2 shared segment: Ariz, Ripa, Line 1: Lutxana, Aiboa. Line 2: Urbinaga. - Max. power of the unit to be installed: 1500kW. - Total savings obtained: 8,26%. - kwh recovered annually: 4.6 million kwh. The following table summarises the estimates of energy recovered annually in each of the selected substations. ARIZ RIPA LUTXANA AIBOA URBINAGA TOTAL E Recovered 900 MWh 1030 MWh 650 MWh 1060 MWh 960 MWh 4600 MWh Table 2: Annual recovery by equipped substation. Data in megawatts hour. At first sight, the expected recovery percentage may seem to be low, this is due to the high level energy exchange between train that is already happening on the system. The data that really needs attention is the recovered energy absolute value, its enviromental impact and the resulting amortization time. In the case of Metro Bilbao, the expected average amortization period is 7 years for equipment with a useful life of 30 years.

3. NEW CONVERTER TOPOLOGY When recovering energy from the catenary, the converter has to inject into the distribution grid a high quality current with low harmonic components (THD<5%). In order to attain a good current regulation, and given that the power drops in outlet filters, the converter requires a minimum voltage level at the DC side. This means that the voltage at the DC side of the inverter always needs to be over the peak voltage at the AC side in order to achieve the required current quality. This fact can limit the capacity of the system to recover the power available to a great extent, especially when the voltage at the substation incoming feeder raises and gets close to the braking voltage of the trains. The solution presented in this paper proposes a cascade connection between an elevator chopper and an inverter. The chopper increases the existing voltage in the catenary by generating sufficient voltage for the inverter to return power to the distribution grid. This way, the catenary voltage margin with which the power recovery system is able to run is the maximum for any grid voltage situation, optimizing power recovery under all circumstances. Regarding the integration of the new recovery converter in the substation, the converter is directly connected in paralel to the existing rectifier. Due to the above described cascade topology with the DC voltage elevation stage, there is no need for an additional power transformer and the rectifier s pre-existing transformer is used for the connection of the converter to the distribution grid. Reliability of the whole system is an essential issue for any railway application. The converter is designed to enable its disconnection from both, the DC and AC sides. By this means, in case of any event happening, the converter is able to self-isolate from the substation without compromising its operation. The following figure shows the power diagram of the converter and its integration into the substation.

Figure 3: Power diagram. As mentioned above, the maximum power of the converter was determined to be 1500kW. The converter was designed to be able to stand this peak power but it was thermally designed according to the work cycle defined by the simulations. This design strategy gives as a result an optimum sizing of the converter since its working cycle will always be pulsative. 4. REAL APPLICATION RESULTS In order to validate the previous analysis, a prototype was designed and installed in one of the substations of the subway traction system. This particular substation was chosen because of its location in the catenary lane, since it is located in the middle of the section with highest train circulation - therefore the hardware and control requirements are expected to be more critical at this point. The simulations run for a single recovery substation deliver an expected recovery percentage range of 8% to 25%, based on system timetable and standard grid voltage variations (percentage values relate to the same substation consumption). The data outlined below shows the main characteristics of the substation and recovery equipment installed: No. of transformers 3 Nom. Power of transformer 2.25 MVA Nom. Power of substation 6,75 MW DC side Nom. Voltage 1600 V DC AC side Nom. Voltage (Tap -5%) 1177 V RMS Table 3: Main characteristics of the substation. Max. Instant Power 1500 kw DC Side Nominal Voltage 1500Vdc Max. DC side Voltage 1950Vdc Max. DC side Current 1000A AC side nominal Voltage [±7%] 1150Vrms AC side Max. Current 850Arms Grid current THD <3% Output Frequency 50 Hz System Cooling Forced Air Installation Area 7.5 m2 Table 4: Main characteristics of the recovery system converter..

Figure 4: Recovery system 3D drawing. The prototype has been successfully working since august 2009. The performance obtained after this time is shown below. Period Train Circulation Mean % Recovery Mean Recovery (% of Subs. (kwh) Consumption) Working Day (18 Hours) Mainly 6 min. 2640 kwh 8,22% Friday Night (2 Hours) 30 min 800 kwh 58% Saturday (18 Hours) 6min, 10 min 3130 kwh 14,2% Saturday Night (6 Hours) 30 min 1880 kwh 61,2% Sunday (18 Hours) Mainly 10 min 4050 kwh 24,6% Week 23080 kwh 11,32% - Mean monthly recovery: 100,000 kwh. - Annual recovery: 1,200,000 kwh. (>11% of substation consumption). Table 5: Performance summary. It is easy to see that the performance is quite better over the weekends due to the fewer train circulation. The energy exchange between trains is drastically reduced when there are fewer trains running and as a result, a bigger amount of recovery energy is available even though the total energy flowing through the system is much smaller.

The registered annual recovery is higher than the values calculated on the previous analisys for the whole system solution with five substation equiped. This is due to the fact that nowadays the prototype in Ripa is recovering part of the energy that in the future will be recovered by the nearby equiped substations. The variability on the performance as the influence of the existing voltage level on the grid has also been confirmed. The total energy recovery during a working day fluctuates between 1800 kwh and 4000 kwh, and raises up to 3000 kwh to 5000 kwh during weekends. Figure 5: Evolution of energy consumed, energy recovered and grid voltage. Y axe, percentage value according to the following minimum -maximum values: Grid Voltage: [1200VRMS - 1300VRMS Recovery Energy: [10000kWh - 14000kWh] Consumption Energy: [160000kWh- 210000kWh] Fig 5 shows the evolution of the grid voltage (blue), the total recovered energy (red), and the total energy consumption on the substation (green) during 24 hrs on a working day. Fig 5 illustrates the influence of the grid voltage on the ability for the energy recovery, as the local values of the de/dt fluctuate, depending on the grid voltage level. In the same way, it can be observed that high de/dt values are obtained at the beginning and at the end of the day. As explained before, this is because there is more available energy as a consequence of the fewer train circulation.

It is also interesting to point that not all the energy that the recovery system is injecting into the AC side is going back to the distribution grid. As it is common on railway systems, part of the total energy consumption is due to the infrastructure s auxiliary charges, mainly on stations and depots. In many cases, the transformers feeding these auxiliary charges are connected in parallel to the transformers feeding the catenary. We have measured that almost 60% of the total recovered energy is internally consumed on the infrastructure auxiliary charges due to this configuration and only 40% is sent back to the grid. In practice, this internal consumption becomes in a lower total consumption of energy from the grid. These percentage values belong to the particular configuration in Metro Bilbao. It could happen not to have any internal consumption of the recovered energy (if the transformers are not in connected in parallel) or just the opposite case, all recovered energy being consumed on internal infrastructure charges. 5. CONCLUSIONS. In this document we present a new technical solution for regenerative braking energy recovering in DC railway systems. The performance conclusions of the reversible substation prototype that has been successfully working for the last 18 months in Metro Bilbao are disclosed. We also have introduced the dimensioning methodology that Ingeteam Traction followed in order to find the optimal technical solution. All energy recovering potential predictions have been confirmed on the real application. The following step will be the installation of four new converters according to the optimal solution designed for the whole Metro Bilbao railway system. Figure5. Photo of the system installed on the substation.