The Life-Cycle of Commissioning for New Construction



Similar documents
Guide Specification SECTION COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

Sample Company SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Denver International Airport Data Center Commissioning Plan

Energy Design Resources Commissioning Plan Outline Template

The Building Commissioning Association

Cx for Enhanced Healthcare Project Delivery. Presentation Format. Project features and timeline

COMMISSIONING OF FIRE ALARM SYSTEMS

Building Commissioning

Commissioning of Fire Protection and Life Safety Systems. Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA

Commissioning of Mission Critical Facilities

Statement of Work. 3.0 Details of Service Pre Start-up Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary

Project Management Plan for

Module 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION"

New Construction Building Commissioning Best Practice

Post Occupancy Evaluation (POE) Technical Instructions

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

Project Close Out Summary

UNIVERSITY OF MISSOURI Heating Ventilating and Air-Conditioning (HVAC) March

Data Center Commissioning: What you need to know

Real Estate Management Services Capital Management Fair Oaks Blvd. Suite I. Fair Oaks, CA / Fax

Advanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings

HOURLY ANALYSIS PROGRAM QUICK REFERENCE GUIDE

UNIFIED FACILITIES GUIDE SPECIFICATIONS

GSA Public Buildings Service. the building commissioning guide

INFORMED MECHANICAL DESIGN THROUGH TESTED AIR LEAKAGE RATES. Jeff Speert, AIA MAIBC LEED AP

Measurement & Verification Plan

Commissioning Design/Build Projects

CAN/ULC S Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

Question/Answer Addendum to Request for Proposals for HVAC/Maintenance Services

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM

COMMISSIONING SUMMARY TEMPLATE

The Future in Fire Protection and Life Safety Cx. David J. LeBlanc, PE, FSFPE

Mechanical Contractor Pre-Qualification Packet. SPSC N180 Computer Data Room Phase II. Project No. CP Notice No. Notice

Sample - Existing Building Commissioning Plan

Design Guidelines for Facilities Construction:

Establishing Commissioning Costs

Mechanical Systems Proposal revised

Metrics That Matter: Pam Greenley MIT EHS Associate Director Steve Lanou MIT Deputy Director, Sustainability

Basic Construction Management

Sika Sarnafil World Class Roofing and Waterproofing

CONTRACTOR CERTIFICATION

Summary of Modifications/Changes in this Update

LEED for Homes Rating System

ACG COMMISSIONING GUIDELINE. For Building Owners, Design Professionals and Commissioning Service Providers

Career Path Project Engineer to Project Manager 1

<name of project> Software Project Management Plan

RFI Response RFP: HSCG88-16-R-PQQ015 Replace HVAC Bldg A & C San Diego, CA.

NFPA 3 and 4 Commissioning and Integrated Testing of Fire Protection and Life Safety Systems. Matt Klaus Senior Fire Protection Engineer NFPA

Developing a Proper Scope of Work, Request for Proposal & Commissioning Specification

Challenges and Failures in Green Building Design Using Under-Floor Air Distribution. Ken Urbanek, PE, HBDP, LEED AP Director of Engineering

Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia

LEED Specifications SECTION TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS SECTION SUSTAINABILITY REQUIREMENTS 11/14, OMAHA 1/15

Collaborative Laboratory Commissioning and Sustaining the Optimal Building. By E. Lon Brightbill, P.E Facility Dynamics

PACIFIC GAS AND ELECTRIC COMPANY ENERGY EFFICIENCY PORTFOLIO LOCAL PROGRAM IMPLEMENTATION PLAN INNOVATIVE DESIGNS FOR ENERGY EFFICIENCY

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows:

2009 Seattle Energy Code Impacts: See below for a recap of Changes in Envelope performance from 2006 to 2009

SPECIAL ISSUE: NATIONAL SCIENCE FOUNDATION WORKSHOP

ABSTRACT DCMCCT PROJECT OVERVIEW

4.4 Commissioning, Handover and Warranty

ADDENDUM No. 2. RFP No /27, Oakland Maintenance Center Facility Management Services

EFFECTIVE PREPLANNING AND PROJECT SCHEDULING COURSE CONTENTS

Rhode Island State Fire Marshal Fire Protection Systems Narrative Reports. What is a Narrative Report?

Planned, Limited Notice and Emergency Outage Guidelines

Managing Open Source Code Best Practices

Spec. Standard: 11/27/ Revision: 11/27/06

Module 6: QUALITY MANAGEMENT FOR CONSTRUCTION PROJECTS. Submodule 1: Introduction. Objectives: After completing this submodule, you will be able to:

SMA Custodial Schedules:

Volume II- Project Development Processes

2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT

REQUEST FOR PROPOSAL GUARANTEED ENERGY SAVINGS CONTRACT. Dallas School District 2000 Conyngham Avenue Dallas, PA Addendum 2

Total Building Commissioning: Case Study of the U.S. District Courthouse in Salt Lake City, Utah, USA

SECTION a - CONSTRUCTION PROGRESS DOCUMENTATION

MISSION CRITICAL SERVICES

Topics for Today. Order of Magnitude Mechanical Estimating. Order of Magnitude Estimate Goal. Project Delivery Methods. Questions for Client

Michael W. Ruth, LEED AP 34 Atherton Road Lutherville, Maryland (443)

FIRE ALARM SYSTEMS PERMIT APPLICATION, PLAN SUBMITTAL, DESIGN, INSTALLATION AND INSPECTION REQUIREMENTS Effective Date: January, 2011

SECTION CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS

BECx& Building Airtightness. Presented by: Eric Amhaus Principal

Assured Joint Integrity

IR F-1 EMERGENCY VOICE/ALARM COMMUNICATION SYSTEMS

National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, MD ph: fax:

Passive Building Systems vs Active Building Systems and the Return On Investment

Section 100 Contractor Quality Control Program

Real property solutions for Federal agencies*

MONTHLY MONITORING REPORT. World Trade Center Port Authority Trans-Hudson Terminal PORT AUTHORITY OF NEW YORK AND NEW JERSEY New York, New York

Los Angeles Community College District

UNDER FLOOR AIR DISTRIBUTION (UFAD) SOLUTIONS

SECTION PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

California Department of Corrections and Rehabilitation

CIS Asset Identification and Labelling Standard

Transcription:

The Life-Cycle of Commissioning for New Construction A Case Study at NGA Campus East Owner/Facility Manager: Dan Kailey and Matt Burkholder National Geospatial-Intelligence Agency (NGA) Commissioning Service Provider: Mike Luffred Eaton Energy Solutions, Inc. (Eaton) Design Professional: Charlie Rowland RTKL/KlingStubbins, Joint Venture (JV) Construction Manager: Mike Lloyd Clark Balfour Beatty Construction - NCE, A Joint Venture (CBB)

Agenda NCE Project Scope NCE Commissioning Scope Commissioning Process Perspectives from Owner Facility Manager Design Professional General Contractor Commissioning Provider

NGA Campus East (NCE) Project Scope New headquarters facility for the National Geospatial-Intelligence Agency Fort Belvoir North Area Located in Springfield, Virginia Largest BRAC 2005 building project 2.4 million ft 2 - $1.7 billion Largest U.S. Government LEED 2.2 Gold project Eaton was Commissioning Authority (CxA) for all phases Design through warranty LEED 2.2 Enhanced Cx Also provided third party QA

NGA Campus East (NCE) Project Scope Main Office Building (MOB) Visitor Control Center (VCC) Central Utility Plant (CUP) Parking Garage Tech Center (TECH) Remote Inspection Facility (RIF))

NCE Commissioning Scope Commissioning Scope of work Commissioning Authority (CxA) for Campus Main Office Building Central Utility Plant Technology Center Parking Garage Visitor Control Center Remote Inspection Facility Water Feature Pump House

NCE Commissioning Scope Cx Scope of work (continued) Implemented ASHRAE Guideline 0-2005 Commissioning In pursuit of LEED 2.2 Credits EA 3.1 (Enhanced Cx) Services Covered Mechanical, Electrical and Plumbing Building Automation & Power Management Systems Building Envelope Systems Life Safety Systems Elevators / Escalators Data / Voice Systems Acoustical

How well have we done? Commissioning Definitions LEED Requirements How the Cx Project Leadership Team (PLT) worked within the project s governance Phases of Commissioning Use of Metrics and Macro Schedule tools to manage expectations of senior leaders not familiar with the black box of the Cx process Successes and Challenges

Definition of Commissioning The Commissioning Process is a qualityoriented process for achieving, verifying, and documenting that the performance of facilities, systems, and assemblies meets defined objectives and criteria. - ASHRAE Guideline 0-2005 The process is performed specifically to ensure that the finished facility operates in accordance with the Owner s Project Requirements (OPR) and the construction documents. To be successful the commissioning process must be integrated into all phases and major elements of the project

LEED for New Construction v 2.2 LEED Enhanced (before construction) LEED Fundamental (during construction) LEED Enhanced (after construction) Prerequisite Fundamental Cx required for LEED Review owner s requirements, develop plan, create final report Verify performance and incorporate Cx into construction documents Counts for Energy and Atmosphere Prerequisite 1 Point Credit Enhanced Cx Before Construction: Conduct design review, review submittals After Construction: Verify training of O&M staff, review operations after turnover Counts for Energy and Atmosphere Credit 3

Project governance Program Board Stakeholders Represented at each level: USACE, NGA, DPW, Designer, Builder, IT, Security, Deployment, Facility Ops Executive Leadership Team Project Leadership Team: Site Project Leadership Team: CUP/Tech Project Leadership Team: Main Bldg Project Leadership Team: Commissioning Project Leadership Team: Infrastructure Project Leadership Team: Ops/Deployment Project Leadership Team: Turnover The Commissioning project leadership team (PLT) was comprised of a cross section of members from several other PLT s and successfully integrated the Cx process into all major project facilities and elements through the resources provided by the independent third Party Commissioning Authority.

Commissioning PLT

Commissioning Process Flow

Commissioning Phases

Levels of Inspection & Testing Pre Functional Inspections & Tests CONSTRUCTION TESTING Participants Level 1 Factory Witness Tests - Where called for in Specifications JV, QC, QA, CxA, NGA Level 2a On-Site Equipment Delivery Inspections QC, QA Level 2b Installed Equipment Inspections (PFC) JV, CxA, QA, QC Acronyms: AE Design Professional CxA Eaton QA U.S. Army Corps of Engineers Quality Assurance QC CBB Quality Control and Commissioning Coordinator Level 2c Prior to Energy or Fluid Connection Inspections CxA, QA, QC Level 2d Manufacturers Factory Start-up and Inspections CxA, QA, QC Level 2e As required for mechanical systems complete TAB and TAB Verification JV, CxA, QA, QC Functional Participants ACCEPTANCE TESTING Performance Tests Level 3 Functional Performance Tests - With Loads CxA, QA, QC, NGA Level 3 Functional Performance Tests - Controls and External Monitoring Inspections CxA, QA, QC, NGA Integrated Systems Testing INTEGRATED SYSTEM TESTING Participants Level 4 Identify reliability constraints that result from normal and adverse operation All Parties tests. Level 4 Prove the Engineer's design for capacity and failover. All Parties Level 4a Enhanced testing to verify monitoring and control system accuracy All Parties

Main Office Building Sequence Constructed, Commissioned & turned over by Segment C North Bar J K L South Bar F

Revised 4/14/2011 Mechanical H G F E D * C * Ellipse * B* A * Projected U&P Dates Complete 4/22/2011 4/29/2011 5/6/2011 Segment TAB Work Completed Complete 4/21/2011 4/22/2011 Segment TAB Report Completed by CBB/Pierce Complete 4/26/2011 5/3/2011 Segment TAB Report Submitted to USACE 3/9/2010 4/9/2010 10/25/2010 10/27/2010 1/14/2011 3/2/2011 4/4/2011 4/27/2011 5/4/2011 RTU PFCs Completed by CBB/Pierce Complete 4/13/2011 4/8/2011 4/22/2011 4/22/2011 U&P RTU PFCs Submitted to USACE 7/15/2010 7/23/2010 9/3/2010 10/1/2010 3/25/2011 4/15/2011 4/10/2011 4/24/2011 4/24/2011 RTU PFCs Approved Complete 4/1/2011 4/22/2011 4/17/2011 5/1/2011 5/1/2011 BAS Pre PVT Completed by CBB/Pierce/Siemens Complete 4/12/2011 4/15/2011 4/8/2011 4/20/2011 4/20/2011 BAS Pre PVT Submitted 7/8/2010 7/23/2010 2/1/2011 2/1/2011 4/14/2011 4/17/2011 4/10/2011 4/22/2011 4/22/2011 BAS Pre PVT Approved Complete 4/21/2011 4/24/2011 4/17/2011 4/29/2011 4/29/2011 FPT Start 5/15/2010 7/13/2010 10/5/2010 10/8/2010 11/15/2010 11/23/2010 2/21/2011 2/11/2011 4/11/2011 FPT RTU Start Date Complete 4/4/2011 4/25/2011 4/19/2011 4/29/2011 5/2/2011 Sub. Comp. FPT Floor Level Completion (VAVs) 9/3/2010 9/3/2010 9/3/2010 9/3/2010 2/18/2011 2/27/2011 4/8/2011 4/15/2011 4/22/2011 FPT Completion RTU 4/29/2011 4/29/2011 4/29/2011 4/29/2011 4/29/2011 5/20/2011 5/14/2011 5/24/2011 5/27/2011 BAS PVT Completion 2/23/2011 2/23/2011 4/29/2011 4/29/2011 5/6/2011 5/27/2011 5/21/2011 5/31/2011 6/3/2011 **Deferred Start Date Deferred Water TAB & Verification Complete 44 0 system 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 3/28/20011 Deferred Deferred Water TAB & Verification Complete Hot Water system 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/12/2011 Deferred Water TAB & Verfi cation Complete 52 0 system 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 5/2/2011 Deferred Air TAB Verification Complete 5/16/2011 5/23/2011 5/30/2011 6/6/2011 6/13/2011 6/20/2011 5/27/2011 6/3/2011 6/10/2011 5/9/2011 Electrical U&P PFCs Approved 10/1/2010 9/14/2010 10/1/2010 10/1/2010 9/23/2010 9/23/2010 9/23/2010 10/7/2010 9/23/2010 FPT Completion (less lighting) 10/5/2010 10/5/2010 10/11/2010 11/12/2010 11/12/2010 12/10/2010 11/12/2010 12/6/2010 11/12/2010 Sub. Comp. PMS PVT Complete 1/12/2010 1/13/2010 7/23/2010 8/6/2010 12/23/2010 12/23/2010 12/23/2010 12/23/2010 12/23/2010 S. Bar Cx Completion vs. APT E Float: 105 APT E 1/14/2011 S. Bar Cx Complete 4/29/2011 Completion N. Bar Cx Completion vs. APT F Float: 63 APT F 4/1/2011 N. Bar Cx Complete 6/3/2011 Deferred Cx Completion vs. APT F Float: 98 Deferred Cx Complete 7/8/2011 General Notes 1. Deferred water TAB is expected to be completed by 4/29/2011 in the CUP and 7/8/2011 in the MOB (~100 work days) 2. Deferred Wa ter TAB Verifi cati on will be completed immediately following Deferred TAB of each individual system. 3. **Start Date for Deferred air TAB Validation and Rooftop Unit FPTs is based upon the removal of ALL partitions in the MOB on approximately 5/9/2011 after fire alarm testing is completed. 4. Deferred air TAB consists of rooftop AHUs, toilet exhaust, stairwell pressurization fans, miscellaneous exhaust; 5 work days per segment. 5. Deferred FPT Requirements (rooftop AHUs, toilet exhaust, miscellaneous exhaust) will most likely occur during off hours; 5 work days per segment. 6. RTU FPTs are projected to take about 5 weeks to complete per segment minus deferred items. 7. First floor of the North Bar along with the ellipse may not be completed and turned over until 4/25/2011; this will impact completion of first floor TAB, Mechanical FPTs and Mechanical PVTs. 8. PFCs will be tra cked as completed once they are signed off by both EMC and USACE. 9. *The dates shown above for the north bar compl eti on do NOT include the work associated with the amenities areas on the 1st floor. LEGEND WORKING ITEM U&P Deferred COMPLETE Sub. Comp. Metrics and Macro Schedule Tools Helped manage senior leader expectations of progress for functional (acceptance) testing Used during Construction Phase of Cx Tracking Mechanisms Evolved Macro schedule included both electrical and mechanical functional testing activities Metrics included deferred testing Cx PLT wrote two simple Cx fact sheets targeted to senior leadership providing updates of the NCE Commissioning Program MOB Commissioning Schedule Segment Deferred Air FPT Requirements Complete 5/23/2011 5/30/2011 6/6/2011 6/13/2011 6/20/2011 6/27/2011 6/3/2011 6/10/2011 6/17/2011 5/16/2011

Successes & Challenges Successes Complied with LEED v2.2 Cx Credits Independent 3 rd Party CxA: Helped lead a fully integrated project team to ensured the Cx process was integrated into all major project facilities and elements Enforced compliance of acceptance testing Developed clear metrics for functional and integrated system testing which helped managed expectations of owner Captured lessons learned Was contracted to provide post construction Cx services during warranty period Challenges Phased construction presented several challenges Operations contractor not fully mobilized during first major project turnover Major facilities were not functionally tested under load and permanent power before turnover Final TAB report not yet complete CxA was not selected until middesign phase Final Report not yet completed

Owner Perspective Design & Construction Successes Provided valuable experience and lessons learned for application in future construction projects Thorough testing of missioncritical power and cooling systems provided a very high level of confidence in their reliability (subsequently proved by unexpected utility power losses June 2012 Derecho) Provided a treasure trove of information for ongoing O&M of the Facility Challenges Had to overcome USACE s concern of managing a third party CxA not their typical approach Speed and complexity of the project created inevitable schedule crunch commissioning wasn t on the construction contractor s schedule in enough detail The last 5% of a project takes 95% of the effort we re not quite finished yet

Owner Perspective Operations & Maintenance Successes Base operations support contractor attained invaluable training and experience through participation in Cx activities Provided opportunity to move into continuous CX Challenges How do we take the mountain of data provided from the Construction CX task and translate that into a Continuous CX process? The delay in completing CX makes the transition to continuous CX more challenging

Design Professional Perspective Successes Innovative Systems Chilled Beams Dual Temperature Chilled Water System Pond Standby Water Storage ETFE Roof System False Loading Modified boiler/chiller systems Challenges Phased Turnover Balancing Issues System Turndown Issues Late Changes to the Program

General Contractor Perspectives Requirements for Successful Commissioning Schedule Early development of construction schedule Must incorporate ALL Cx activities with realistic durations Need to know the scope of the Cx process Must have all the test scripts early Use the schedule to manage the commissioning process Review and update the schedule weekly

General Contractor Perspectives Requirements for Successful Commissioning Early Involvement of All Stakeholders Owner, Design Team, Construction Manager, General Contractor, Subcontractors, Commissioning Authority Clearly defined roles and responsibilities» Who documents the process» Who has authority to make changes» Who has authority to sign off on items Accountability between stakeholders Develop relationships with all stakeholders» Know each members goals and risks

General Contractor Perspectives Requirements for Successful Commissioning Subcontractor Management Demand a dedicated commissioning team from appropriate subcontractors Meet regularly with principals of the subcontractors Hold each sub accountable for their responsibilities Listen to their ideas and welcome their input

General Contractor Perspectives Requirements for Successful Commissioning Staffing Incorporate appropriate staffing into all budgets and cost proposals Evaluate the requirements for each staff position Select the Right person for each position Delicate balance between project management, field supervision, and engineering

General Contractor Perspectives Takeaways Commissioning begins prior to proposal submission Early collaboration of all stakeholders Develop a realistic construction schedule that incorporates all commissioning activities Manage the subcontractors and hold them accountable Drive the schedule

Commissioning Provider Perspective Successes Many Potential Show Stoppers Issues were Identified Early Warranty Issues Seem Minimal Results of Post Construction Occupancy Survey Favorable BRAC Mission was Accomplished Challenges Security Requirements Multiple Tracking Tools Used Scale of Project Overcoming Contractors Preconceived Notions of Cx

Wrapping Up Lessons Learned Cx is a defined process that needs to be followed. Clearly defined Cx expectations early to all. In particular the definition of DONE. Cx is only as effective as the commitment of the owner s representative. UFGS master specs need to be updated to reflect current Cx standards. Increase facility management engineering capabilities to address increase in complexity of facilities. Partnering works. Quality is a victim of schedule.

Questions

References ASHRAE Guideline 0-2005 The Commissioning Process USGBC LEED for New Construction & Major Renovations version 2.2 October 2005