MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5

Similar documents
Seattle Public Schools Building Excellence IV Projects Under Construction

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

KIEWIT CM/GC Enabling/Utilities

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

Case 2:08-cv ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

Analysis One Code Desc. Transaction Amount. Fiscal Period

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule

SECTION TABLE OF CONTENTS. H Proposed Material, Product or Equipment Substitution Request

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Request for Proposal for Construction Management Services

TD AMERITRADE Park Omaha

Construction Technologies Career Field Pathways and Course Structure

OPTIMUS WORK CLASSIFICATION LIST ENTER ALL THAT APPLY

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

ST. MONICA FOOD PANTRY HOUSTON, TEXAS

Building, Plumbing, Electrical and Residential Water and Sewer Inspection Requirements

NOTICE TO CONTRACTORS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

BUILDING PERMIT SPECIFICATIONS

Inspecting to a higher standard.

OPEN ITEMS LIST - CONSTRUCTION Project Name: East Central Middle School - Jackson County CLA#: 11003

Estimating Database Checklist

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

MRI RF SHIELDING DESIGN

ADDENDUM NO. 1. DATE: February 10, 2015 INVITATION FOR BID: IFB K Commerce Road Renovations Project DATED: February 9, 2015

Name of course: Residential Construction Site Management (RCSM) Level 1

Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Schematic Design: Quality Management Phase Checklist Project Phase Checklist Series

A Homeowner s Guide to Building Permits

Lincoln Public Schools. 15 Attachments (separately bound) Schematic Design Schematic Design Project Manual

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

Buildings Construction Procurement Strategy

HEANEY General Contracting, Inc.

BUILDING/PLUMBING PERMIT APPLICATION REQUIREMENTS

Design Development Quality Management Phase Checklist Project Phase Checklist Series

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

Excerpts from the Canadian National Building Code (NBC)

2012 BIM Guidelines and Standards (Rev. 00) University at Albany

Ashley Institute of Training Schedule of VET Tuition Fees 2015

Building Energy Codes 101 October 23, Matthew Giudice Building Policy Associate Midwest Energy Efficiency Alliance

Newtown and Holland Middle Schools Construction Project Bid Review

Gramercy Place Condo Association, Inc.

INCORPORATION BY REFERENCE OF INTERNATIONAL. (1) The Department of Labor and Industry adopts and incorporates by

Does Wall Township require an inspection by the building department on resale of a home?

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

CITY OF BERKELEY BUILDING PERMIT DETAILED CHECKLIST

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Exterior Elevated Elements Inspection Guidelines

VOLUME I PROCUREMENT AND CONTRACTING DOCUMENTS GROUP

Basement Moisture Problems

SECTION 3 ONM & J STRUCTURAL ANALYSIS

Village of Airmont APPLICATION FOR BUILDING PERMIT INSTRUCTIONS

The work has continued on final Phase 4 and is nearing completion.

LITITZ MUTUAL INSURANCE COMPANY 2 North Broad Street Lititz, Pennsylvania - MAIN OFFICE -

HomeSpec REPORT SUMMARY

The Lambton County Homeowner's BUILDING PERMIT INFORMATION GUIDE

Frequently Asked Questions

Veterans Memorial Coliseum Options Study Appendix A - Deconstruction Scope of Work and Cost Estimate August 31, 2015

Preparation for 2015 Residential Code Changes Discussion with Local Builders and Designers

Estimated Cost of Repair

C I T Y O F P E A R S A L L

Every Student I Every Day I Every Possibility

CHARLOTTE COUNTY Community Development Department

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, Underground branch circuit feeding a detached garage:

Building Construction and Development in Norristown: A User s Guide to the Land Development and Building Permit Process 1/25/11

Building Code Inspections and Fees

Presented by: Ray Crawford ASQ Design and Construction Division

BUILDING SAFETY UNIT

CENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY Small Commercial Service (SCS-1) GSR

School Construction Authority Architecture & Engineering

Occupancy: Assembly (A-3) and Business -Includes offices, seminar rooms, classrooms, and café facility. Duke University Medical School

PROPOSAL. Prepared for: Craig Mottram & Family, 118 Rangoon Rd. Prepared by: Carlos Andrade, Owner & Operator. Brandon Andrade, Project Coordinator

EL LAGO BUILDING DEPARTMENT PERMIT ISSUANCE PROCEDURES As of February 20, 2013

2014 British Columbia Building Code Changes

PROPERTY INSPECTION OR ASSESSMENT OF DAMAGES

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

2009 IECC Update. Scope. Content. International Energy Conservation Code

COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS

Schedule B to By-law

MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3

PROPERTY INSPECTION OR ASSESSMENT OF DAMAGES

Structure Survey Findings:

Transcription:

Rendering Provided by McKissick Associates MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Additions and Alterations to Williamsport Area Middle School Williamsport Area School District 17 July 2012

Geo-Thermal Well Field Geo-Thermal Well Field PROJECT SUMMARY Work Completed June/July 2012 SITE WORK: Maintain Erosion & Sediment(E&S) controls Site grading Completed temporary HS site parking. Geo-thermal contractor mobilized, performed conductivity test. Completed installation of underground storm retention system Continued Storm piping. Began site electrical distribution. Tie-in of sanitary and storm lines on 4 th St. Continued concrete repairs in crawl space. Continued exterior bldg conc. Restoration Continued footer excavation at rear of building. Continued masonry foundation at rear of building. Continued foundations Mechanical Room. Began Insulation Concrete Form(ICF) work. Continued metal stud framing-1 st and 2 nd floors. Began installation of drywall Continued Mechanical/Electrical/Plumbing(MEP) rough-ins. 1 st and 2 nd floors of existing bldg. Continued underslab MEP rough-ins in Began concrete slab on grade. Begin roofing replacement Work Anticipated July/August 2012 SITEWORK: Continue Storm piping Continue Geo-thermal well field. Continue Electrical underground rough ins Area D Mechanical Room Foundation Walls Continued metal stud wall installation. Continue Mechanical/Electrical/Plumbing (MEP) layout & rough ins. 1

Work Anticipated(Cont ) July/August 2012 Insulation Concrete Forms(ICF) - Foundations Continue exterior concrete restoration Continue roofing replacement. Continue foundations rear of building Continue foundations Mechanical Room. Continue Insulation Concrete Form(ICF) work. Continue concrete slab on grade. Begin above grade masonry. Begin window replacement. Receive steel delivery. Continue drywall installation. PROJECT COST SUMMARY Billing Information: Original Contract Amount: $32,520,490.00 Changes to Contract: $ 138,710.06 Current Contract Amount: $32,659,200.06 Previous Billed Amount: $ 4,135,770.91 Previous Balance Remaining: $28,523,429.15 Current Payment Due: $ 1,829,135.45 Remaining Balance: $26,694,293.70 Concrete Slab On Grade Preparation Concrete Slab Pour and Prep. Billing percentage this month: 5.60% Total Billing Percentage to date: 18.26% Potential/Upcoming Change Orders: Remove existing underground concrete area way from rear of building $5,500.00 Add platforms in existing mechanical chase with 2 access doors. GC $3,687.65 Acoustical Drywall Cont. $1,445.36 Remove and replace existing drywall and associated fixtures and material due to water damage on existing drywall in kitchen area. TBD Change select water fountains to bottle fillers. TBD. Provide Exhaust fans to crawl space. TBD Electrical requirements to install security sys. TBD. 2

Change Orders For Approval: LOBAR GC-008 - Credit associated with bulletin #2 to delete operable partitions ($54,937.02) GC-009(Revised) - Cost associated with bulletin #4 to reconfigure Technology and FCS CR s $22,435.37 GC-010 - Cost associated with removing existing metal studs framing and replace with masonry walls at west wall of serving room. $2,977.97 Cafetorium and Stage Area backfill MID STATE ROOFING ROOF -001 - Cost associated with bulletin #4 to reconfigure Technology and FCS classrooms(eliminate 2 EF penetrations) and bulletin #15 which revised coping detail around roof perimeter, eliminated one layer of dens deck sheathing and increased roof membrane thickness to achieve a 30 year roof warranty in lieu of the original 20 year warranty. No Cost $0.00. EASY DOES IT DRYWALL AC-001 - Credit associated with bulletin #2 to delete operable partitions. ($3,560.14) AC-002 - Cost associated with bulletin #4 to reconfigure Technology and FCS CR s $6,250.00 Metal Stud Wall Framing -2 nd Floor NITTANY BUILDING SPECIALTIES FL-001 - Cost associated with bulletin #2 to delete operable partitions. $392.47 FL-002 - Credit associated with bulletin #4 to reconfigure Technology and FCS CRs. ($7,064.43) WOOD MODE INDUSTRIES CASE - 001 - Cost associated with bulletin #2 to delete operable partitions & add casework. $2,960.00 CASE -002 - Credit associated with bulletin #4 to reconfigure Technology and FCS CRs ($31,960.00) HVAC Duct Work Rough-ins JAY R. REYNOLDS PC-001 - Credit assoc. with bulletin #4 to reconfigure Technology and FCS classrooms. ($10,684.00) 3

Change Orders For Approval:(Cont ) THE FARFIELD COMPANY HVAC-001 - Credit associated with bulletin #4 to reconfigure Technology and FCS classrooms. ($6,487.00) HVAC-002 - Credit associated with bulletin #2 to delete operable partitions. ($7,996.00) LEER ELECTRIC EC-001 - Credit assoc. with bulletin #4 to reconfigure Tech. and FCS CRs ($6,229.56) EC-002 - Credit associated with bulletin #2 to delete operable partitions. ($882.10) EC-003 - Cost associated with bulletin #9 to relocate existing conduit that was concealed in wall and feed equipment in DSC. $3,249.19 TOTAL CHANGE ORDERS FOR APPROVAL FOR JULY: ($91,535.25) Original Contingency $1,129,541.00 Change Orders Approved to date: $ 212,515.31 Remaining Contingency $ 908,025.69 SUBMITTALS/RFI s Contractors have continued to provide submittals to Architect for review and approval. Requests for Information: o 134submitted o 129answered o 5 open 60 50 40 30 20 10 0 Jan-12 Feb-12 PROJECT MANPOWER Mar-12 Apr-12 May-12 Williamsport Area Middle School Average Daily Workforce Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Manpower for the month of June 2012 averaged just over 48 workers on site per day. Contactors on Site in March included: o Lobar Inc. & sub-contractors o Easy Does It Drywall o Jay R. Reynolds o The Farfield Company o Triangle Fire Protection o Leer Electric o Jackson Geothermal PROJECT ISSUES The thermal conductivity test that was performed on the geo-thermal well field yielded different results from the test well completed prior to the project. An additional test will be performed to further evaluate the situation. 4