The ABWR Project at Shimane-3, Japan



Similar documents
Hitachi s Involvement in Nuclear Power Plant Construction in Japan

TOSHIBA s Nuclear Energy Activities

Prospect of Hitachi Nuclear Business (Boiling Water Reactor)

Introduction of the education and training courses to support emerging countries

Advanced Construction Methods for New Nuclear Power Plants

Decommissioning situation of Nuclear Power Plant in Japan

Development of Next-generation Boiling Water Reactor for Era of Large-scale Plant Construction

NEWS RELEASE. Apr 08, Rating and Investment Information, Inc. (R&I) has announced the following:

Global Nuclear Power Developments Asia Leads The Way

CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS

KERNREACTOREN EEN OVERZICHT VAN GENERATIE III+ KERNREACTOREN

Reduction of Capital Costs

Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build

JCR's Rating Review of Electric Power Companies

Nuclear Safety Regulation Reform in Japan

Power Systems Company, Hitachi, Ltd. Babcock-Hitachi K.K. Hitachi-GE Nuclear Energy, Ltd.

Overview of Worldwide Nuclear Decommissioning

Step 2 Assessment of the Conventional Fire Safety of Hitachi-GE Nuclear Energy Ltd. s UK Advanced Boiling Water Reactor (UK ABWR)

NEW NUCLEAR POWER PLANTS FOR ONTARIO - THE CONTENDERS October

An overview of available reactor designs 2012 Jim Thomson

Boiling Water Reactor Power Plant

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

COMPARISON OF ELECTRICITY GENERATION COST OF NPP WITH ALTERNATES IN PAKISTAN

Japan s current Nuclear Energy Policy

Hitachi-GE UK ABWR Concept Design

NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012

Damage of Fukushima Nuclear Accident and a new compensation scheme

Report. November 2013

Financing New Nuclear Generation. John E. Parsons, MIT July 9, 2009 EPRG / CEEPR / GDF Suez European Electricity Workshop

The World Nuclear Supply

Update on Japan s Nuclear Energy Development and Spent Fuel Management Plans and Options

Lessons Learned from past NPP Construction Technology/Management

The Next Generation of Nuclear Reactor Designs. Prof. Sama Bilbao y León

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

Olkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011

Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants

Activities of Nuclear Damage Compensation & Decommissioning Facilitation Corporation (NDF) Yasuharu Igarashi

Solutions for Nuclear & Renewable Power Generation

2013 TEPCO ILLUSTRATED

Three Mile Island Unit 2 Overview and Management Issues

Financial Summary 3rd quarter of FY2012. January 29, 2013 Tohoku Electric Power Co., Inc.

MHI Air-Blown IGCC Technology & Application to Chinese Project

Alternatives of Financing for New Nuclear Reactors in Mexico

The Risks of Building New Nuclear Power Plants

A short history of reactors

Nuclear Power and Emergency Management

Life-cycle cost analysis for nuclear power plants with seismic isolated system

Westinghouse and the AP1000 Offering Great Opportunity for the Czech Republic

New Comprehensive Special Business Plan. Tokyo Electric Power Company [January 15, 2014]

Future of Solution Business for Electric Power and Energy Sectors

/All APPLICANTS SHOULD NOTE THAT THE TOUR LENGTH OF A RESIDENT INSPECTOR AT A SINGLE SITE IS LIMITED TO SEVEN (7) YEARS BY COMMISSION POLICY.

Japanese Requirements for Wind Turbine TÜV Rheinland Japan

RENCEE SAFETY MARIES

U.S. Commercial Power and Fuel Supply Outlook

Japan s Electricity Market Reform and Beyond

The Price-Anderson Act and the Three Mile Island Accident

Electricity Market Integration in Japan

Olkiluoto 3 Experience

Advanced Boiling Water Reactor

Japan s Largest Photovoltaic Power Plant

Outlook for RWE s nuclear operations. Prof. Dr. Gerd Jäger London, 16 January 2012

Plant Maintenance Services and Application of ICT

Fundamentals of Nuclear Power

Case 2:08-cv ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

CENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY Small Commercial Service (SCS-1) GSR

NRC INSURANCE AND LIABILITY REQUIREMENTS

COFRENTES NPP. March 14, Iberdrola Generación, SA Producción Nuclear Iberdrola Generación, SA Producción Nuclear 1

Reality Check: Energy Mix 2030 and Japan's Collapse in Nuclear Power Generation

The Status of Nuclear Power in the World Before and After Fukushima

Nuclear Design Practices and the Case of Loviisa 3

AREVA Advanced nuclear power plants

Analysis One Code Desc. Transaction Amount. Fiscal Period

Engineers Australia Nuclear Engineering Panel. The Economics of Nuclear Power

EDUCATION AND TRAINING OF OPERATORS AND MAINTENANCE STAFF AT COMMERCIAL NUCLEAR POWER STATIONS IN JAPAN

A Reviewof AkkuyuNPP Project in Turkey After Fukushima Daiichi Accident

SOURCE TERMS FOR POTENTIAL NPPS AT THE LUBIATOWO SITE, POLAND

Development Study of Nuclear Power Plants for the 21st Century

A PROCESS-INHERENT, ULTIMATE-SAFETY (PIUS), BOILING-WATER REACTOR

Building New Generation Nuclear Plants Worldwide : AREVA's Experience

SCDAP/RELAP5-3D : A State-of-the-Art Tool for Severe Accident Analyses

February 19, Senior Fellow, Nuclear Energy Systems & Services Division Power Systems Company

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Business Risks and Opportunities Related to Climate Change. Helen A. Howes Vice President, EH&S Exelon Corporation

Fukushima Fukushima Daiichi accident. Nuclear fission. Distribution of energy. Fission product distribution. Nuclear fuel

U.S. Operators Perspective on Nuclear Liability

SETSCO. Year 2016 Course Programme. 03 Mar 02 Jun 01 Sep 01 Dec. 21 Dec Mar 20 Jun 26 Sep. 01 Feb 02 May 01 Aug 31 Oct.

Reality Check: Energy Mix 2030 and Japan's Collapse in Nuclear Power Generation

WNA Report. Nuclear Power Economics and Project Structuring

International Safeguards Infrastructure Development

Heterogeneous world model and collaborative scenarios of transition to globally sustainable nuclear energy systems

July 30, 2012 Nuclear Emergency Response Headquarters Government-TEPCO Med-and-long Term Response Council

Status on Spanish Regulations and Industry. actions related to Filtered Containment. Venting Systems (FCVS)

UAE Nuclear Power Programme : Status and Update

POLICY FEEDING RENEWABLE. How the Energy Bill might affect green electricity suppliers and also renewable generators

STRATEGY AND RESOURCES COMMITTEE ITEM MARCH 2012 FACILITIES MANAGEMENT: FUTURE CONTRACTUAL ARRANGEMENTS

INTERNATIONAL NUCLEAR LAW ASSOCIATION NUCLEAR INTER JURA 2012 MANCHESTER, 8-11 OCTOBER 2012

Chameliya Hydroelectric Power Project

The integrity evaluation of the reactor building at unit4 in the Fukushima Daiichi nuclear power station

IMPLEMENTING THE REGULATORY AUTHORITY INFORMATION SYSTEM (RAIS)

Transcription:

CASE STUDIES ON PROJECT AND LOGISTICS MANAGEMENT IN NUCLEAR NEW BUILT The ABWR Project at Shimane-3, Japan Sang-Baik Kim, Jan-Horst Keppler OECD Nuclear Energy Agency, Nuclear Development Division OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 1

Contents Shimane Nuclear Power Plants Status of BWR Nuclear Power Plants in Japan ABWR Development and Licensing Practice in Construction of NPPs in Japan Project Management of Shimane-3 ABWR Advanced Technologies in ABWR Construction Workforce in ABWR Construction Summary OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 2

Shimane Nuclear Power Plants (I) In Japan, before the Fukushima accident, nuclear energy accounted for almost 30 % of the total electricity from 47.5 GWe of capacity (30 BWRs and 24 PWRs). The Shimane nuclear power station is located in Kashima-chou, Shimane Prefecture, and owned by the Chugoku Electric Power Company (The Chugoku EPCO) The Chugoku EPCO has two Boiling Water Reactors. The ratio of nuclear power generation capacity is less than 10 %. - Unit No. 1 of Shimane (460 MW): Operation in 1974 - Unit No. 2 of Shimane (820 MW): Operation in 1989 This unit No. 1 is the first all-japanese plant, whose design, manufacture and construction were conducted by The Chugoku EPCO and Hitachi LTD. OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 3

Shimane Nuclear Power Plants (II) Unit No. 3 of Shimane (Shimane-3) is under construction. - One of the largest and the 5 th ABWR (1373 MWe) in Japan - After issuance of construction license, the excavation of main building started in Oct. 2006. - Originally planned to enter commercial operation in Dec. 2011 - After the Fukushima accident, the construction was suspended (construction progress 94 %) - In Sep. 2012, METI approved the restart of construction in Shimane-3 and Ohma-1 plants. The final schedule is not known. The Chugoku EPCO planned to build two Kaminoseki ABWR nuclear Power units on Nasgashima Island and confirmed its intention to proceed in 2012. OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 4

ABWR NPPs in Japan Since 1970, 32 BWRs (including 4 ABWRs) have been brought into operation. The first ABWRs were TEPCO s Kashiwazaki-Kariwa 6&7, build by a consortium of General Electric (USA), Toshiba and Hitachi. (Source : Hitachi-GE Nuclear Energy, Ltd.) OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 5

All ABWR NPPs in Japan Plant Construction Start* Commercial Operation Kashiwazaki- Kariwa 6 Kashiwazaki- Kariwa 7 Nov. 1992 Nov. 1996 July 1993 July 1997 Hamaoka 5 July 2000 Jan. 2005 Shika 2 Aug. 2001 Mar. 2006 Shimane 3 Sep. 2007 defered, TBD Ohma 1 May 2010 TBD Hagashidori defered - (* : Construction Start is based on the first concrete of the reactor building base mat ) OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 6

ABWR Development and Licensing The development of the ABWR started in 1978 as an internationalcooperation between five BWR vendors. - The ABWR was included in the third standardization programme of Japan from 1981, carried out by Toshiba, Hitachi and GE with six Japanese utility and Japanese government. - From 1987 GE, Hitachi and Toshiba started project engineering and preparation of licensing for Kashiwazaki-Kariwa 6&7. - In Sep. 1987, GE applied for certification of the US ABWR standard design. USNRC adopted as final design certification rule for the US ABWR design in May 1997. Both Toshiba and GE-Hitachi have applied separately to NRC for design certification renewal. In 2011, the NRC certified for GE- Hitachi an evolved version. Hitachi was also developing 600, 900 and 1700 MWe versions of the ABWR. OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 7

ABWR Development and Licensing GE Hitachi s ESBWR is in advanced stages of licensing review with the US NRC. Japan launched the Next- Generation LWR development program in 2008, for one PWR & one BWR design. OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 8 (Source : Hitachi- GE Nuclear Energy, Ltd.)

Japanese Practice in Construction of NPPs (Source : IAEA N. E. series No. NP-T-2.7).) Japanese legislation define that the sole licensee must be the electric power company, which is responsible for the safety of the plant and must submit for the approval of the safety analysis report and the construction permit. All Japanese electric companies are large and have the tradition to do the engineering of their power plant themselves. The owner/utilities in Japan carry the burden of major portions of the engineering, procurement and construction (EPC) of their NPPs. Consequently, the Japanese electric companies have built NPPs by awarding split-package contracts (the so-called island approach) as well as smaller component contracts. Given the large number of utilities in Japan, each company built relatively few NPPs and this has made it difficult to maintain a highly qualified workforce. All utilities in Japan have developed and maintained good relationship with each other and willingly share their human resources. Salaries and expenditures continued to be paid by the original employers. OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 9

Project Management of Shimane-3 (I) For Shimane-3, the Chugoku EPCO coordinates all contractors in civil, building and mechanical fields, and control work progress among each contractor. - Civil work (land forming, intake and discharge structure): Civil Joint Venture - Building work (main building): Building Joint Venture - Mechanical work (piping/equipment/commissioning): Hitachi-GE The project management is responsible for the cost, schedule and technical performance of the project and is in control of design, engineering, procurement, manufacture, construction and commissioning. There are many activities in project management, for project planning and scheduling, design schedule, construction schedule, control of project progress, management of information and method to subcontract materials and construction works. The quality assurance (QA) programme is an interdisciplinary management tool that provide a mean that all work is adequately planned, correctly performed and assessed. OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 10

Project Management of Shimane-3 (II) The most significant point in ABWR is standardization, which consists of design standardization, document standardization and quality management standardization. Fig. Project Organization for TEPCO s Kashiwazaki-Kariwa 6&7 Project OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 11

Advanced Tech. in ABWR Construction(I) Comparison of construction periods of Kashiwazaki-Kariwa Power Station (Source : IAEA-SM-353/36) The normal definition of the construction period refers to from pouring of first structural concrete to start commercial operation. In case of K-6, the time from I/F (July 1992) to C/O was 51.5 months. From the first concrete (Nov. 1992) to the first criticality (Dec. 1995), it took 37 months. The 40-month schedule is a aggressive target in comparison with the past U.S. construction experience(before the TMI it was 60-70 months; after that, extended significantly) OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 12

Advanced Tech. in ABWR Construction(II) Advantages of ABWR in construction of Kashiwazaki-Kariwa 6&7 as FOAK (first of a kind Engineering) - Design features of ABWR for better plat constructability - Prudent design change control with a principle of test before use - Advanced construction technology - Detailed engineering at early stage of the project - Good construction management Main features in reduction of construction time in Kashiwazaki-Kariwa 6&7 - Increased composite modularization - Increased pre-fabrication - Application of steel-concrete structure - Inspections rationalization - Better communication through IT OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 13

Advanced Tech. in ABWR Construction(III) Applied Construction Technologies in Shika-2 - Broader application of large module/block construction methods - Open-top and parallel construction method - Application of floor packing construction methods - Full application of information technology to qualify plant engineering and construction achievements. Further Improvement of Construction Technology in Shimane-3 - Parallel construction - Floor packaging construction - Modularization : about 190 modules including the HCU (hydraulic control unit) room module - Development of integrated on-site construction system - Advanced construction management using RFID (radio-frequency identification) OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 14

Advanced Tech. in ABWR Construction(IV) Modularization Method (Source : Hitachi-GE Nuclear Energy, Ltd.) OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 15

Workforce in ABWR Construction Owner s Project Management Team in case of Kashiwazaki-Kariwa 6&7 (Source IAEA-TECDOC-1390.) Other resources utilized in Kashiwazaki-Kariwa 6&7 - Manpower- construction [ man-hours] : U6 14,400,000; U7: 10,800,000 - Materials : Piping [tons]: U6: 11,000.; U7 : 6,000. Concrete [m3]: U6: 200,000. ; U7: 167,000. OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 16

Summary The ABWR is the evolutionary design of the conventional BWR and the first design, among Generation III LWR designs, with construction and operating experiences. The first ABWR, Kashiwazaki-Kariwa 6, was constructed on a 37 months schedule from the first reactor building structure concrete pour to fuel load. The advanced management and construction technologies have been developed and demonstrated through continuous experiences of ABWR construction in Japan. The Shimane-3 was constructed for On-budget and On-schedule with application of more advanced design and construction methodology, just before the Fukushima accident. It was 94 % complete and construction was suspended in March 2011. OECD NEA Workshop on Project and Logistics Management, Paris, 11 th March 2014 17