1 Engineers Australia Nuclear Engineering Panel The Economics of Nuclear Power Martin Thomas AM FTSE HonFIEAust HonFAIE 26 September 2012 Engineers Australia - Nuclear Engineering Panel - 26 Sep 12
2 The presentation 1 - Introduction 2 - Australia and the nuclear fuel cycle 3 - Nuclear power in the world 4 - Technologies reviewed 5 - Capital costs 6 - Operating costs 7 - Levelised Cost of Electricity (LCOE) - some comparisons 8 - Conclusion where next?
3 Why should Australia even think about nuclear power? Concerns rising as atmospheric CO2 concentrations approach 400ppm, highest level for thousands of years. Is this a worry? Weather patterns show some concerning changes. True or false?? Serious attention turning to low emission generation alternatives. Why then include solar and wind but exclude nuclear? Nuclear power, despite profitable uranium exports and commercially proven, is eschewed by Australian Government. Why is this so? Opponents claim nuclear too expensive; too long to build; too risky operationally and waste disposal too dangerous. Are these claims true? Australia may need to include nuclear power in low emissions portfolio by 2050 when 80% carbon emissions reduction targeted. Will it do so? Will international investors contribute to portfolios that exclude nuclear power? That is the question!
4 Infrastructure on the cliff edge Australia is facing a potential monumental infrastructure disaster as the politicians dither with long-term carbon questions and undertake speculative research on coal technologies. Unless someone starts actually making hard decisions now, fasten your safety belts for a very large rise in power prices in the eastern states, which will flow into inflation and interest rates. COMMENTARY ROBERT GOTTLIEBSEN 15 Jul 2009
5 Some facts, some thoughts and some questions Australia currently has around 50,000MW generation capacity By 2050 it will need around 100,000MW, much of it new build That will cost investors around $BN in generation assets alone in highly competitive capital and technology markets But doubled 2012 installed capacity by 2050 must deliver 80% less carbon emissions! How? Low emission technologies (LETs) comprise - in maturity order hydro, nuclear, wind, solar, geothermal, biofuels, tides, exotics Will Australia accept nuclear power as a LET? If not why not? Are 30 other nations wrong? What about France? If yes then why? When? At what cost? By whom? And who will be the investors - and why will they invest?
6 What are Australia s candidate generation technologies to 2050? Coal Oil and gas Nuclear Geothermal Hydro Solar Wind Other renewables Distributed energy and energy storage
7 Why would Australia want to consider nuclear power? Cost competitiveness of nuclear versus other low emission technologies Meeting 2050 carbon reduction targets Security of supply and independence from imported fuels Diversity of domestic electricity production Reduction in carbon pricing volatility Reduction in all power generation impacts climate change and otherwise The quest for sustainability!
8 The world nuclear power industry some facts In September 2012 there were: 433 reactors operating in countries generating about 13.5% of the world s electricity from GW installed (over 7 times Australia s 50GW) and reactors under construction (another 65GW) reactors planned (178 GW more) and reactors proposed (another 366 GW) Source: World Nuclear Association (WNA) website
9 Nuclear the bad news for Australia Technology still costly ~ 5,000-6,000$/kW Australian regulatory environment inadequate Shortage of suitably qualified Australian engineers and scientists Significant water demand for cooling (but can use dry cooling ie fan cooled radiators) Australian public still has concerns on: Safety of spent fuel disposal, Weapons proliferation, and NIMBY siting issues
10 Nuclear - the good news for Australia (1) Vast Australian uranium resources (~31% of world s low cost supplies) ANSTO Lucas Heights research reactor and nuclear medicine experience Technologies (mining, enrichment, reactors, spent fuel management and permanent disposal) internationally proven Australia a world leader in hard rock mining and minerals processing Australia geologically stable with vast regions of minimal population for safe waste disposal
11 Nuclear - the good news for Australia (2) Good base load generation - cap factors >90% LCOE ~ $/MWh - includes waste disposal and decommissioning costs Generation III and III+ reactors improved safe Generation IV reactors inherently safe - 60 times energy recovery from uranium fuel Worldwide RD&D program promises further gains Strong Australian engineering capability Small footprint Strong safety record compared with alternatives Longer term (30y) potential for thorium fuel
12 Evolution of nuclear power plant designs - current technologies Generation I 1950s to 60s - Early prototypes (eg UK Magnox) now nearly all decommissioned Generation II Mid 1960s Commercial power reactors (eg LWR, PWR (eg Fukushima), BWR, CANDU, RBMK (eg Chernobyl) many installed - designs now superseded Generation III Mid 1990s Advanced pressurised water reactors (PWRs) (eg ABWR, System 80+, AP-600 and AP- 1000, EPR) high safety - current generation of new reactors worldwide
13 Evolution of nuclear power plant designs - future technologies Generation III onwards Advanced pressurised water reactors (PWRs) (eg ABWR, System 80+, AP-600 and AP-1000, EPR) being installed now for generation this decade Generation IV 2020 at earliest Very advanced fast neutron technologies - highly economical (60 times energy from enriched uranium minimal waste (much is burnt ) inherently safe (shut down on fault) proliferation resistant - (the golf ball for life!) Fusion reactors say 2050+? Physics complex, deuterium fuel, theoretically possible, no radiation, no wastes Engineers Australia - Nuclear Engineering Panel - 26 Sep 12
14 Generation I Dungeness A Nuclear Power station - 2 X 219MW Magnox Reactors
15 Generation II - Cruas Meysse Nuclear Power Station, Montelimar, France 4 X 900MW PWRs
16 Generation II & III Olkiluoto Nuclear Power Station, Finland 2 X 880MW BWRs and 1 X 1600MW EPR
17 Generation III+ - Westinghouse AP-1000 PWR Engineers Australia - Nuclear Engineering Panel - 26 Sep 12
18 Generation IV Small Modular Reactors (SMRs) Hyperion Power Module (HPM) The HPM is a fast neutron LMR Gen IV reactor small enough to be transported by shipping container Power: Fuel: Weight: Fuel Cycle: Cost (est): 70MWt 25MWe/module 20% enriched uranium nitride pellets 50 tonnes 10 years USD$50M Size: 2.5m x 1.5m Steam: Coolant: Emissions: 520 o c Lead-bismuth Near zero
19 Fusion is this the nuclear future? ITER - Cadarache, France
20 Economics of nuclear power the big picture (1) Nuclear power between 20 and 50% more costly in Australia than coal and gas due very low coal and gas prices (UMPNER 2006) Gap closes if carbon priced in range $15 40/t CO 2 equivalent (around $15-40/MWh for black coal generation) Private investment in Australia s first nuclear reactors could require initial government support or directive In many countries nuclear now competitive with other baseload technologies
21 Economics of nuclear power the big picture (2) Nuclear characterised by high up front capital costs and very low fuel costs Later costs (eg waste storage and plant decommissioning) are internalised as minor additions to electricity cost Final plant cost dependent on capex discount rate and project duration Comparison with competing LETs depends on assumed construction time, capital financing, discount rate, economic treatment of externalities (eg carbon) and evaluation commercial, technological and social risks Key to cost reduction is engineering standardisation and uniform regulation (and a centrally planned economy!) Costs reduce dramatically (~40%) after FOAK plant
22 Capital costs ($kwe) what do we mean? Two most common indices are: Final capital cost all generation and ancillary plant, land purchase, licence costs and regulatory fees, capital raising including interest during construction (IDC), associated plant infrastructure (eg plant cooling, stores and offices and (sometimes) initial fuel load. Transmission to customers excluded. Overnight capital cost notional cost of project if no interest incurred during construction (IDC), ie as if project completed overnight. Alternatively: present value of lump sum paid up front to pay completely for project. Engineers Australia - Nuclear Engineering Panel - 26 Sep 12
23 Issues impacting nuclear plant construction costs Tables following (next two slides) gleaned from publicly available data from many reliable sources with consistent trends. Cost ranges attributed to essentially similar designs are hugely variable. Why is this so? USA prices have trended higher due to: industry move from state corporation ownership towards private (ie utility) financing with higher financing costs; lower risk appetite of private financiers arising from intrusive political and regulatory interference and well published massive time and cost overruns; undoubted impacts of Chernobyl and Fukushima on risk perceptions and insurance costs unexpected changes in plant licensing, inspection and certification arrangements, adding to delays and construction costs. (Note USA regulatory processes (eg siting, licensing and construction) now increasingly standardised) In contrast China prices falling due to: centrally planned and managed economy establishment of national PWR Major Program based on proven AP1000 design technological and plant standardisation to develop CAP1400 then CAP1700. strong commitment to independent indigenous nuclear power industry. more compliant labour force
24 Some typical specific capital costs ($/kwe) (1) Plant location and date of data Plant type Moody s Investor Services Various USA designs reviewed Moody s Investor Services Various USA cost June 2008 projections Florida Power & Light 2 AP1000 Turkey Point Feb MW PWRs Florida Progress Energy USA 2 AP1000 March MW PWRs South Carolina Virgil Summer 2 AP1000 USA May MW PWRs Duke Energy Carolinas 2 AP1000 USA Nov MW PWRs TVA Bellefonte 2 AP1000 USA Nov MW PWRs Georgia Power Vogtle 2 AP1000 USA Apr MW PWRs First two AP1000 units 2 AP1000 China MW PWRs Four AP1000 units 4 AP1000 China MW PWRs Darlington Point 4 CANDU totalling Canada ,512MWe Overnight Final approx Comments $/kwe $/kwe 2,950 5,000-6,000 Average of many plants 3,108 4,540 5,780 8,071 7,000+ Due to commodity price rises 5,144-3,376 If built 18 months apart 4,387 Unlikely to be built due cheap shale gas 4,924 2,516 4,649 6,266 2,372 1,791 5,187 Engineers Australia - Nuclear Engineering Panel - 26 Sep 12
25 Some typical specific capital costs ($/kwe) (2) Plant location and date of data Plant type Overnight $/kwe Final approx $/kwe Comments Olkiluoto Finland EPR MW PWR 4,000 Flamanville France EPR MW PWR 2,638 Taishan China EPR MW PWR 2,343 First CAP 1400 China CAP MW PWR ~1,500 CAP = China Advanced Passive First CAP 1400 China CAP MW PWR ~1,000 CAP = China Advanced Passive Generation IV Hyperion Power Module HPM 25MWe SMR ~5,000 Based on preliminary feasibility study New Generation III AP MW PWR ~5,500 ATSE Burgess Report Appendix A Fig A.1 New Generation III AP MW PWR ~4,500 ATSE Burgess Report Appendix A Fig A.2 New Generation III AP MW PWR ~4,000 ATSE Burgess Report Appendix A Fig A.3 Engineers Australia - Nuclear Engineering Panel - 26 Sep 12
26 Operating costs Uranium fuel Uranium costs very low compared with coal, oil and gas due abundance, ease of mining and processing and extraordinarily high specific energy, some 20,000 times higher per kg than high quality black coal. Fuel costs 1kg uranium oxide reactor fuel, enriched from around 9kg yellowcake (U 3 O 8 ), costs around $2,700-$2,800 and generates some 360MWh electricity, worth around $36,000 at an average power station sent out price of $100/MWh. Loaded fuel cost only $/MWh ( c/kWh). Fuel price sensitivity Fuel a very small portion of electricity cost; sensitivity to price escalation thus low. Reactor efficiencies - Spain reduced nuclear electricity costs 29% in late 1990 s boosting enrichment and burn-up to achieve 40% fuel cost reduction. Further efficiencies projected in Generation III+ designs. Generation IV promises 60 times higher efficiencies as more plentiful U238 used up and wastes burned. Uranium prices - can vary widely, especially on spot market, but most utility operators write long term contracts. With new mines opening worldwide uranium contract prices are likely to stabilise. Comparisons with fossil fuels OECD claims enriched, fabricated and treated fuel costs of Generation III+ plants are typically 30-35% of those for black coal and 20-25% of gas combined cycle. US Nuclear Energy Institute claims that 78% of coal fired sent out electricity cost is fuel alone; for gas combined cycle 89%. For Generation III+ plants equivalent fuel cost is 25-30%
27 Operating costs Operation and maintenance Operation and maintenance (O&M) costs are the annual recurrent costs associated with operation, maintenance, administration and support of a nuclear power plant including: Management and operational staff Operator training including simulators Maintenance staff, resources and consumable spares Contractor services, vehicles, etc Licensing and regulatory fees Consumable utilities The USA s Nuclear Energy Institute reports average 2011 O&M cost for nuclear power plants was 10.51$/MWh (say c/kWh)
28 Operating costs Spent fuel disposal and plant decommissioning Spent fuel disposal A 1,000MWe reactor produces around 12m³/a high level waste. Permanent safe disposal costs are a very long way into the future and can be dealt with economically by a modest levy or sinking fund of about 1.0$/MWh (say c/kWh) on electricity sold. Plant decommissioning - Plant decommissioning costs after a year life are estimated at 9-15% of plant capital cost but again lie very far in the future (60 years). Again a modest levy or sinking fund of around 1-2/$MWh ( c/kWh) on electricity sold will provide adequate funds. The nuclear industry is one of only few offering this holistic approach to meeting whole of life internal and external costs.
29 Operating costs (c/kwh) summary Cost item Typical minimum Typical maximum Uranium fuel (the true marginal cost of generation) Operation and maintenance Spent fuel disposal Plant decommissioning Totals
30 Levelised Cost of Electricity (LCOE) The Levelised Cost of Electricity (LCOE), usually expressed in $/MWh, is defined as that cost of electricity that enables the owner (generating company) to earn the lifetime cost of its capital and to cover its risk management and all operating costs including permanent waste disposal, plant decommissioning and site rehabilitation. It does not include profit on the equity investment.
31 Relative levelised cost ranges ($/MWh) (Source: EPRI for UMPNER 2006) Engineers Australia - Nuclear Engineering Panel - 26 Sep 12
32 LCOE ($/MWh) Levelised Cost of Electricity (LCOE) , 2030 and 2040 ($/MWh) $300 $250 $200 $150 $100 $ $0 ATSE Model with AEMO data; includes CO 2 costs and RECs; ranked in By kind permission of the Australian Academy of Technological Sciences and Engineering (ATSE) and author Dr John Burgess FTSE of Low-Carbon Energy Evaluation of New Energy Technology Choices for Electric Power Generation on Australia November 2010
33 LCOE ($/MWh) Levelised Cost of Electricity (LCOE) ($/MWh) AEMO Reference Group Data $200 Treasury Model Electricity Price $150 $100 $ $0 By kind permission of the Australian Academy of Technological Sciences and Engineering (ATSE) and author Dr John Burgess FTSE of Low-Carbon Energy Evaluation of New Energy Technology Choices for Electric Power Generation on Australia November 2010
34 My generation portfolio guesses for Australia? At 2010 (~50GW) By 2020 (60GW) By 2050 (100GW) Coal 76% Gas 16% Nuclear 0% Geothermal 0% Hydro 5% Wind 2% Solar <1% Coal 65% Gas 23% Nuclear 0% Geothermal 2% Hydro 4% Wind 4% Solar <2% Coal 30% Gas 25% Nuclear 20% Geothermal 10% Hydro 3% Wind 7% Solar 5%
35 What s yours? Thank-you for your kind attention!
Nuclear Power Plant & Systems David Downing / Kenneth Green. WSP Parsons Brinckerhoff / Sargent & Lundy TUESDAY, 6 OCTOBER 2015
Nuclear Power Plant & Systems David Downing / Kenneth Green WSP Parsons Brinckerhoff / Sargent & Lundy TUESDAY, 6 OCTOBER 2015 The Brief To develop whole-of-life cost estimates for the development of nuclear
WHEN AN EFFECTIVE EU ENERGY POLICY?
WHEN AN EFFECTIVE EU ENERGY POLICY? A. Clerici ABB Italy Honorary Chairman of WEC Italy Chairman of WEC WG The future role of nuclear in Europe 1 INDEX 1. General Comments 2. Vulnerability 3. Transmission
Generating Current Electricity: Complete the following summary table for each way that electrical energy is generated. Pros:
P a g e 1 Generating Current Electricity: Complete the following summary table for each way that electrical energy is generated. Generating Electrical Energy Using Moving Water: Hydro-Electric Generation
10 Nuclear Power Reactors Figure 10.1
10 Nuclear Power Reactors Figure 10.1 89 10.1 What is a Nuclear Power Station? The purpose of a power station is to generate electricity safely reliably and economically. Figure 10.1 is the schematic of
Reconciling Electricity Markets and New Nuclear Build. Platts 3rd Annual European Nuclear Power Conference
Reconciling Electricity Markets and New Nuclear Build Presentation at: Platts 3rd Annual European Nuclear Power Conference July 1, 2008 London Steve Thomas ([email protected]) PSIRU (www.psiru.org),
Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario
Canadian Energy Research Institute Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario Matt Ayres Senior Director, Research Electricity Morgan MacRae
Levelised Cost of Electricity for a Range of New Power Generating Technologies. Sciences and Engineering (ATSE)
New power cost comparisons Levelised Cost of Electricity for a Range of New Power Generating Technologies Report by the Australian Academy of Technological Sciences and Engineering (ATSE) MaRch 211 New
Re-assessing Costs in the European Power Sector. July 2013
Re-assessing Costs in the European Power Sector July 2013 The rise in non-conventional energy production in the United States along with the need to rebuild Europe s economy has led to a new focus and
Nuclear Power s Role in Enhancing Energy Security in a Dangerous World Al Shpyth, B.A., M.E.S. Director, Government Relations Cameco Corporation
Nuclear Power s Role in Enhancing Energy Security in a Dangerous World Al Shpyth, B.A., M.E.S. Director, Government Relations Cameco Corporation Introduction: Should we be concerned about energy security?
WNA Report. Nuclear Power Economics and Project Structuring
WNA Report Nuclear Power Economics and Project Structuring Title: Nuclear Power Economics and Project Structuring Produced by: World Nuclear Association Published: September 2012 Series: WNA Report Report
A Nuclear New Deal. Jacques Besnainou. President, AREVA Inc. AREVA
AREVA Building Energy Certainty: A Nuclear New Deal Jacques Besnainou President, AREVA Inc. AREVA EnergyBiz Leadership Forum, Session Two: Resource Review Washington, D.C. March 9, 2009 Three ways forward
Energy Productivity & Pricing
Energy Productivity & Pricing Markets for energy, renewable energy and carbon Dr Jenny Riesz February 2014 2 Average electricity retail prices Electricity price rises CSIRO Future Grid (2013) Change and
Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants
Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants Westinghouse Electric Company & The Nuclear Fuel Cycle Royal Commission - South Australia November 4, 2015 1 AP1000 is a trademark
Introduction to Nuclear Fuel Cycle and Advanced Nuclear Fuels
Introduction to Nuclear Fuel Cycle and Advanced Nuclear Fuels Jon Carmack Deputy National Technical Director Fuel Cycle Technology Advanced Fuels Program February 27, 2011 The Evolution of Nuclear Power
Energy Options in a Carbon Constrained World. Martin Sevior, School of Physics, University of Melbourne http://nuclearinfo.net
Energy Options in a Carbon Constrained World. Martin Sevior, School of Physics, University of Melbourne Energy underpins our Civilization Imagine one week without Electricity Imagine one week without Motorized
The economic competitiveness of nuclear energy
How competitive is nuclear energy? by J.H. Keppler* The economic competitiveness of nuclear energy will be crucial for determining its future share in world electricity production. In addition, the widespread
Global Nuclear Power Developments Asia Leads The Way
Global Nuclear Power Developments Asia Leads The Way Edward Kee Nuclear Energy Asia 2010 - Hong Kong (1400 1430) Global Nuclear Power Developments - Asia Leads The Way What is the competitive global position
Electricity Generation Costs
October 2012 Introduction Electricity generation costs are a fundamental part of energy market analysis, and a good understanding of these costs is important when analysing and designing policy. DECC regularly
Energy [R]evolution vs. IEA World Energy Outlook scenario
Energy [R]evolution vs. IEA World Energy Outlook scenario New set of scenarios takes climate crisis into account World Energy Outlook (WEO) 2008 for the first time takes the climate crisis really into
Projected Costs of Generating Electricity
Executive Summary Projected Costs of Generating Electricity 2015 Edition Projected Costs of Generating Electricity 2015 Edition INTERNATIONAL ENERGY AGENCY NUCLEAR ENERGY AGENCY ORGANISATION FOR ECONOMIC
TOSHIBA s Nuclear Energy Activities
December 12, 2010 IGARASHI, Yasuharu Toshiba Corporation, Executive Officer Corporate Senior Vice President President & CEO, Power Systems Company Export Control No. PSN-2010-1406 Document No. G3-1109
Nuclear Power: Benefits and Risks
Nuclear Power: Benefits and Risks H-Holger Rogner Head, Planning & Economic Studies Section (PESS) Department of Nuclear Energy International Atomic Energy Agency Technology options towards a sustainable
NEW NUCLEAR POWER PLANT UNIT IN FINLAND ACCEPTED BY THE FINNISH PARLIAMENT
International Conference Nuclear Energy for New Europe 2002 Kranjska Gora, Slovenia, September 9-12, 2002 www.drustvo-js.si/gora2002 NEW NUCLEAR POWER PLANT UNIT IN FINLAND ACCEPTED BY THE FINNISH PARLIAMENT
Nuclear Power Policy in Russia
Theocharis Grigoriadis FB Wirtschaftswissenschaft, Osteuropainstitut Nuclear Power Policy in Russia 19th REFORM Group Meeting Salzburg, 5th September 2014 Key Questions What is the role of nuclear power
The Real Cost of Electrical Energy. Outline of Presentation
2 Outline of Presentation Data Sources Electricity Demand and Supply Cost to Meet Demand Profile Electricity Pricing Cost Impact of Dispatching Generation (Load Following) Simplifying Assumptions Electricity
GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 2013
GLOBAL RENEWABLE ENERGY MARKET OUTLOOK 213 FACT PACK GUY TURNER HEAD OF ECONOMICS AND COMMODITIES APRIL 26, 213 GLOBAL RENEWABLE ENERGY MARKET OUTLOOK, 26 APRIL 213 1 INTRODUCTION This year s Global Renewable
THE NET BENEFITS OF LOW AND NO-CARBON ELECTRICITY TECHNOLOGIES
GLOBAL ECONOMY & DEVELOPMENT WORKING PAPER 73 MAY 2014 Global Economy and Development at BROOKINGS THE NET BENEFITS OF LOW AND NO-CARBON ELECTRICITY TECHNOLOGIES Charles R. Frank, Jr. Global Economy and
COMPARISON OF ELECTRICITY GENERATION COSTS
Tarjanne Risto, Kivistö Aija COMPARISON OF ELECTRICITY GENERATION COSTS LAPPEENRANNAN TEKNILLINEN YLIOPISTO LAPPEENRANTA UNIVERSITY OF TECHNOLOGY TEKNILLINEN TIEDEKUNTA ENERGIA- JA YMPÄRISTÖTEKNIIKAN OSASTO
URANIUM MINING, PROCESSING AND NUCLEAR ENERGY OPPORTUNITIES FOR AUSTRALIA?
URANIUM MINING, PROCESSING AND NUCLEAR ENERGY OPPORTUNITIES FOR AUSTRALIA? URANIUM MINING, PROCESSING AND NUCLEAR ENERGY OPPORTUNITIES FOR AUSTRALIA? URANIUM MINING, PROCESSING AND NUCLEAR ENERGY OPPORTUNITIES
THE CONSTRUCTION OF. Natural Gas 11% Coal 12% Industry 49% Nuclear 18%
THE CONSTRUCTION OF OLKILUOTO 3 IN FINLAND ND A CASE STUDY Summary The recent publication of the energy review and CoRWM s findings have ensured nuclear is currently top of the news agenda. With new build
SMR Financing and Economics. The Nuclear Option: Is Small Scale Nuclear Energy an Option for Alaska?
SMR Financing and Economics The Nuclear Option: Is Small Scale Nuclear Energy an Option for Alaska? Craig Welling Office of Nuclear Energy U.S. Department of Energy December 2010 Uncertainties in Nuclear
NUCLEAR FUEL CYCLE ROYAL COMMISSION. Advantages and disadvantages of different technologies and fuel sources; risks and opportunities
NUCLEAR FUEL CYCLE ROYAL COMMISSION Submission on Issues Paper 3: Advantages and disadvantages of different technologies and fuel sources; risks and opportunities 3.8 What issues should be considered in
Controlling Cost and Schedule for New Nuclear Construction
Controlling Cost and Schedule for New Nuclear Construction 672485v2 Scott A. Greer Financing New Nuclear Construction Roundtable Hosted by the Kansas Corporation Commission Topeka, Kansas, December 16,
Electric Utilities. Introduction to the module
Introduction to the module The electric utilities module is based on a reporting framework produced by the Institutional Investors Group on Climate Change (IIGCC), Ceres, and the Investor Group on Climate
Foratom event 29 April 2015
Foratom event 29 April 2015 New nuclear in the UK and Electricity Market Reform Colin Parker Head of European Liaison - EDF Energy 1 April 2015 EDF Energy plc. All rights reserved. EDF Energy A UK energy
Role of Natural Gas in a Sustainable Energy Future
Role of Natural Gas in a Sustainable Energy Future Alexander Medvedev, Deputy Chairman of Gazprom Management Committee, Director General of Gazprom Export 2 nd Ministerial Gas Forum Doha, 30 November 2010
310 Exam Questions. 1) Discuss the energy efficiency, and why increasing efficiency does not lower the amount of total energy consumed.
310 Exam Questions 1) Discuss the energy efficiency, and why increasing efficiency does not lower the amount of total energy consumed. 2) What are the three main aspects that make an energy source sustainable?
THE COSTS OF DECARBONISING ELECTRICITY GENERATION
THE COSTS OF DECARBONISING ELECTRICITY GENERATION This technical annex to Building a low-carbon economy presents further details on the analysis underlying the estimates of the costs of decarbonising the
The Economics of Nuclear Power: Is New Nuclear Competitive?
The Economics of Nuclear Power: Is New Nuclear Competitive? Craig A. Severance CPA Author, Business Risks and Costs of New Nuclear Power (2009) Co-Author, The Economics of Nuclear and Coal Power (1976)
Port Jackson Partners
Port Jackson Partners NOT JUST A CARBON HIT ON ELECTRICITY PRICES Many factors will drive a doubling of electricity prices in many states by 15. This will have a major impact on virtually all businesses.
Energy Megatrends 2020
Energy Megatrends 2020 Esa Vakkilainen 1 NOTE The data included in the following is mainly based on International Energy Agency's (IEA) World Energy Outlook 2007 IEA is considered the most reliable source
WORLD ENERGY INVESTMENT OUTLOOK 2014 FACTSHEET OVERVIEW
OVERVIEW More than $1.6 trillion was invested in 2013 in energy supply, a figure that has more than doubled in real terms since 2000, and a further $130 billion to improve energy efficiency. Renewables
SUSTAINABLE ENERGY BLUEPRINT
SUSTAINABLE ENERGY BLUEPRINT A PLAUSIBLE STRATEGY FOR ACHIEVING A NO-NUCLEAR, LOW- CARBON, HIGHLY-EFFICIENT AND SUSTAINABLE ENERGY FUTURE The following statement outlines an ambitious but doable strategy
THE FUTURE OF NUCLEAR POWER IN THE UNITED STAES. Richard A. Meserve Carnegie Institution 1530 P St., NW Washington, DC 20004 202-387-6404
THE FUTURE OF NUCLEAR POWER IN THE UNITED STAES Richard A. Meserve Carnegie Institution 1530 P St., NW Washington, DC 20004 202-387-6404 Outline Factors affecting domestic interest in nuclear power Challenges
Annual Electricity and Heat Questionnaire
Annual Electricity and Heat Questionnaire IEA Statistics Course Pierre Boileau International Energy Agency OVERVIEW Global trends in electricity production 1973-2009 IEA Annual Electricity and Heat Questionnaire
Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015
June 2015 Levelized Cost and Levelized Avoided Cost of New Generation Resources in the Annual Energy Outlook 2015 This paper presents average values of levelized costs for generating technologies that
MCQ - ENERGY and CLIMATE
1 MCQ - ENERGY and CLIMATE 1. The volume of a given mass of water at a temperature of T 1 is V 1. The volume increases to V 2 at temperature T 2. The coefficient of volume expansion of water may be calculated
World Energy Outlook 2009. Presentation to the Press London, 10 November 2009
World Energy Outlook 29 Presentation to the Press London, 1 November 29 The context The worst economic slump since the 2 nd World War & signs of recovery but how fast? An oil price collapse & then a rebound
Financing Nuclear Power Projects: Challenges and IAEA Assistance in Capacity Building
Financing Nuclear Power Projects: Challenges and Assistance in Capacity Building International Framework for Nuclear Energy Cooperation Finance Workshop London, 9-10 May 2012 Nadira Barkatullah International
Module 7 Forms of energy generation
INTRODUCTION In rich countries like Australia, our standard of living is dependent on easily available energy. Every time you catch a bus, turn on a light or watch television energy is being used up. Over
The Energy Transition in Germany Past, Present and Future
The Energy Transition in Germany Past, Present and Future smart energy Paraná, Conferência International 2014 9 May 2014 Dr. Carsten Tschamber A Brief History of the Energiewende 1973 - oil crisis, Federal
Chapter 1 The Development of Nuclear Energy in the World
Chapter 1 The Development of Nuclear Energy in the World Abstract In 2011 there were about 436 commercial nuclear power reactors operating in the world with a total capacity of 370 GW(e). Nuclear energy
Low Carbon Innovation Coordination Group. Technology Innovation Needs Assessment (TINA) Nuclear Fission Summary Report
Low Carbon Innovation Coordination Group Technology Innovation Needs Assessment (TINA) Nuclear Fission Summary Report April 2013 Background to Technology Innovation Needs Assessments The TINAs are a collaborative
DATA CENTRE DESIGN AND
SPUSC 2008 SOUTH PACIFIC USER SERVICES CONFERENCE DATA CENTRE DESIGN AND ENERGY INITIATIVES Presented by Jarrad Clift Electrical Engineer Greenstar Accredited Presentation Content Data Centres General
Prospect of Hitachi Nuclear Business (Boiling Water Reactor)
Prospect of Hitachi Nuclear Business (Boiling Water Reactor) 42 Prospect of Hitachi Nuclear Business (Boiling Water Reactor) Masahito Yoshimura Shoichiro Kinoshita Hiroshi Arima Nobuo Tada OVERVIEW: To
Environmental Science 101 Energy. Web-Based Course. Lecture Outline: Terms You Should Know: Learning Objectives: Reading Assignment:
Environmental Science 101 Energy 1 Web-Based Course Lecture Outline: 5. RENEWABLE ENERGY RESOURCES MODULE 5.1 Improving Energy Efficiency A. Improving Energy Efficiency MODULE 5.2 Geothermal, Hydro and
The Cost of Power Generation
ENERGY The Cost of Power Generation The current and future competitiveness of renewable and traditional technologies By Paul Breeze Paul Breeze Dr Paul Breeze has specialized in the electricity sector
Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems
Adapting Gas-Power Generation to New Role in Low-Carbon Energy Systems Sandra Scalari Enel Ingegneria e Ricerca SpA Copenhagen, May 27-28 th 2014 Enel Presentation Generation Shift & Market in Europe Enel
Nuclear Power Plant Construction Costs
Nuclear Power Plant Construction Costs July 2008 AUTHORS David Schlissel and Bruce Biewald Projected Nuclear Power Plant Construction Costs Are Soaring The construction cost estimates for new nuclear power
Cost estimates for nuclear power in the UK
Cost estimates for nuclear power in the UK ICEPT Working Paper August 2012 Ref: ICEPT/WP/2012/014 Grant Harris ([email protected]) Phil Heptonstall ([email protected]) Robert Gross
CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS
CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS Presented by W.J. (Chris) Zhang University of Saskatchewan Saskatoon, Canada Email: [email protected] Outline 1. Modularization in NPP 2. Comparison
PROS AND CONS OF NUCLEAR TECHNOLOGY FOR THE 21 st CENTURY
PROS AND CONS OF NUCLEAR TECHNOLOGY FOR THE 21 st CENTURY By Dr Clarence Hardy Secretary, Australian Nuclear Association Vice-President, Pacific Nuclear Council Presentation to Engineers Australia, Southern
AREVA. Solutions for Nuclear & Renewable Power Generation
AREVA Solutions for Nuclear & Renewable Power Generation 1 AREVA Group Arlit, Niger Melox, France La Hague, France Lynchburg, U.S.A. Alpha Ventus, Germany 2 AREVA Group 2011 Key Figures 8.872Bn in Annual
Nuclear Consultancy & Engineering Services
Insert a caption to go with the photograph in here ITER, France Wednesday, 14 December 2011 Nuclear Consultancy & Engineering Services T H E N U C L E A R A T K I N S A S S Y S T E M A L L I A N C E CONSTRUCTION
Nuclear Power Plants Tackling the Investment Dilemma. A EURELECTRIC contribution to the PINC (Nuclear Illustrative Programme)
Nuclear Power Plants Tackling the Investment Dilemma A EURELECTRIC contribution to the PINC (Nuclear Illustrative Programme) September 2015 EURELECTRIC is the voice of the electricity industry in Europe.
rising Electricity Costs:
rising Electricity Costs: A Challenge For Consumers, Regulators, And Utilities Electricity is the lifeblood of the U.S. economy. It powers our homes, offices, and industries; provides communications, entertainment,
Electricity Supply. Monthly Energy Output by Fuel Type (MWh)
Ontario Energy Report Q4 Electricity October December Electricity Supply Electricity production was lower in Q4 than in previous years, with milder than normal weather in October and December resulting
FIELD TRIP TO A POWER PLANT - A Reading Guide
TITLE: TOPIC: FIELD TRIP TO A POWER PLANT - A Reading Guide Energy and the sources of energy used in power plants GRADE LEVEL: Secondary CONTENT STANDARD: Earth and Space Science CONTENT OBJECTIVE: For
OBSTACLES TO GREEN ELECTRICITY GENERATION BUSINESS
OBSTACLES TO GREEN ELECTRICITY GENERATION BUSINESS Arta Denina¹, Janis Zvanitajs² Riga Technical University Faculty of Engineering and Management Meza str. 1/7, Riga, LV-1048, Latvia E-mail: ¹[email protected],
Fundamentals of Nuclear Power
Fundamentals of Nuclear Power Juan S. Giraldo Douglas J. Gotham David G. Nderitu Paul V. Preckel Darla J. Mize State Utility Forecasting Group December 2012 Table of Contents List of Figures... iii List
The Global Commission on the Economy and Climate. Major Economies Forum, Paris
The Global Commission on the Economy and Climate Major Economies Forum, Paris Jeremy Oppenheim, Programme Director 11 th July 2014 Purpose of the Global Commission Reframe the debate about economic growth
Construction Risk in New Nuclear Power Projects Eyes Wide Open
GLOBAL INFRASTRUCTURE Construction Risk in New Nuclear Power Projects Eyes Wide Open kpmg.com/infrastructure KPMG International Contents Foreword 1 Introduction 2 Why Construction Risk Matters 4 The Origins
COMPARISON OF ELECTRICITY GENERATION COST OF NPP WITH ALTERNATES IN PAKISTAN
COMPARISON OF ELECTRICITY GENERATION COST OF NPP WITH ALTERNATES IN PAKISTAN IAEA INPRO dialogue forum 8 toward nuclear energy system sustainability: economics, resource availability and institutional