Sample Micro Hydro Initial Report



Similar documents
Micro-hydro Power. Introduction. What is hydropower? System types. Power the entire farm Generate power to sell back to the national grid

1. Purpose and scope. 2. SEPA's role in hydropower and planning

What are the Benefits?

micro hydro in the UK a case for special consideration

Hydro Power Projections Report. Jennifer Palmer

1 Introduction. 1.1 Key objective. 1.2 Why the South Esk

Frequently Asked Questions (FAQs) on Hydropower

A Green Sector Overview

MICRO-HYDROPOWER NEED FOR ENERGY FOR RURAL DEVELOPMENT. By: Payman Hassan Rashed

Clean Development Mechanism Project Opportunities in Indonesia

Howsham fish passage Consultation document

MICRO HYDRO FOR THE FARM AND HOME

An Introduction to. Micro- Hydropower. Systems. Natural Resources Canada. Ressources naturelles Canada

NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand

Essex County Council Flood Investigation Report

USAID ENERGY POLICY PROGRAM SITE VISIT REPORT STATUS OF 4 RUN OF RIVER HYDROPOWER PROJECTS. October 2013

A GUIDE TO UK MINI-HYDRO DEVELOPMENTS

London Borough of Merton Local Flood Risk Management Strategy

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a

A LAYMAN S GUIDE TO SMALL HYDRO SCHEMES IN SCOTLAND

Harlaw Hydro-Electric Scheme. Business Plan for. Balerno Village Trust

Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details

NEW CABLE? - Understanding the cost to connect renewable generation in Orkney

Micro Hydro Feasibility Study

FACT SHEET 6: HYDRO ELECTRICITY

Community and Renewable Energy Scheme Project Development Toolkit

WILLOCHRA BASIN GROUNDWATER STATUS REPORT

MICRO-GRIDS FOR RURAL ELECTRIFICATION Case Study from Zambia on the Zengamina Micro-Hydro Power Grid

How To Build A Road Into A Lake In The North Of The Korean Island Of Hongkoon

DISTRIBUTION CONNECTION

Is a community based micro-hydro ELEctrification SCHEME. suitable for your village?

approval of matters specified in conditions; and The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013

Action plans for hotspot locations - Ash Study

Outlet stabilization structure

HIGHWAYS. Drainage design on M25 motorway widening project (J16 - J23) Brijesh Vats

17. Appendix C Summary of Biennial Flood Reports

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document

Development proposals will require to demonstrate, according to scale, type and location, that they:-

London Borough of Croydon Local Flood Risk Management Strategy

Engineering in the water environment: good practice guide. River crossings

SEPTIC TANKS AND SOAKAWAYS TO HOUSES AND THE BUILDING REGULATIONS

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

Technology Fact Sheet for Mitigation B. Small Hydropower Technology i 1. Introduction 1.1. Historical - All over the World, hydropower sector is

Designed and produced by geo-graphicsdesign.com DP 300 3/02

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

SUSTAINABLE URBAN DRAINAGE SYSTEMS

Hydropower on Hebden Water, Dog Bottom

Micro-Hydro. Module Introduction. Tokyo Electric Power Co. (TEPCO)

Pico Power: A Boon for Rural Electrification

The economic scale of community and locally owned renewable energy in Scotland and projections to 2020

Emergency Spillways (Sediment basins)

Ardessie Hydro Electric Project

Financial and Economic Study of Alternatives for the proposed N2 Wild Coast Toll Highway for the section of the road from Mthatha to Port Shepstone

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Assessment. Ian Uglow Technical Director, SLR Consulting 7 th October 2010

Newbiggin House Farm,

INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies

WaReg The Flow Regulator

EPR Exempt Flood Risk Activities: descriptions and conditions

Getting Connected. A guide to how to apply for a New Connection to the Network

Assessment of hydropower resources

FEED-IN OF EXCESS ENERGY AND SELF CONSUMPTION: NEW REGULATIONS IN GHANA S ENERGY SECTOR JULIUS NKANSAH-NYARKO ENERGY COMMISSION

Sustainable Schools Renewable Energy Technologies. Andrew Lyle RD Energy Solutions

11.2 The proposals to deal with the leachate within the closed Lodmoor North Landfill site are assessed in Chapter 10 Geology and Soils.

XAYABURI HYDRO POWER PLANT, LAO PDR

environment briefing02

Report Relating to Incidents of Flooding within the Dollar Catchment

Vital Earth Composting Facility Flood Risk and Drainage Statement

Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers

Accounting A7/15 A7/A8 Activity Costing Analysis

City of Shelbyville Site Inspection Checklist

The correct answers are given below. Some talking points have been added for the teachers use.

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013.

Waterway Technote Drains

Fundamentals Level Skills Module, Paper F7 (INT) 1 (a) Viagem: Consolidated goodwill on acquisition of Greca as at 1 January 2012

Agricultural & Farm Development - The Planning Issues

4 Water supply description

Newsletter #5: Groundwater In The National Water Balance

Consultation on integrating flood defence consents into the Environmental Permitting regime in England and Wales

GEOENGINE MSc in Geomatics Engineering (Master Thesis) Anamelechi, Falasy Ebere

Type of Sewer Systems. Solomon Seyoum

Watershed Works Manual

PB POWER ISLAND OF IRELAND CAVAN-TYRONE AND MEATH-CAVAN 400KV PROJECTS PRELIMINARY BRIEFING NOTE OVERHEAD AND UNDERGROUND ENERGY TRANSMISSION OPTIONS

Feed in Tariffs for Microgeneration. Jos Mister Energy Saving Trust

WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED

Renewable Electricity and Liberalised Markets REALM. JOULE-III Project JOR3-CT GREECE ACTION PLAN. By ICCS / NTUA K. Delkis

The Flow Regulator. Flow regulation

Wind Power and District Heating

Commercial solar. Harnessing the earth s natural energy. Cold Store 250 kwp. Warehouse 186 kwp

Handbook for Developing MICRO HYDRO In British Columbia

Water Resource Plan 2015 (Summary Report) Ensuring customers have clear, fresh, safe drinking water to 2040 and beyond

Queensland Dam Safety Management Guidelines. February 2002

Final Report August 26th 2008

06 - NATIONAL PLUVIAL FLOOD MAPPING FOR ALL IRELAND THE MODELLING APPROACH

Eddleston Water Project: Natural flood management & river restoration in a catchment context

Improving the physical condition of Scotland s water environment. A supplementary plan for the river basin management plans

Micro-hydro applications in rural areas

Transcription:

Sample Micro Hydro Initial Report

Sample Micro Hydro Initial Report Introduction The Hydro Burn at Glen Water was visited by Richard Haworth of Glen Hydro to assess its suitability for a micro hydro installation. It is the aim of this report to help the owner decide whether to invest in a full feasibility study. The Hydro Burn has an unusual catchment area, as it extends over three kilometres in a narrow valley. This is not a particularly large catchment area but the west coast of Scotland does benefit from high rainfall levels. From the catchment valley, the burn runs north westward steeply down the hillside to Loch Seaside. Access is provided by a track which crosses the burn by a wooden bridge at grid reference NR 7369 5223. A few metres downstream the burn is also crossed by an 11kV distribution power line. Approximately 100m further downstream, the burn crosses the march onto a neighbouring estate. The power produced by any hydroelectric scheme is a product of both the flow and the height loss (head) between the intake and turbine. On the Hydro Burn, the head relevant to this potential scheme is developed over a relatively short distance as the burn descends the steep hillside. This is significant, as a short penstock length reduces the capital costs and increases the viability of the scheme. A steeper section of burn also has favourable influence on the application for an abstraction licence from SEPA (see below). There are lengths of the banks of the burn which are not in the ownership of the Estate (see Appendix 1, showing the estate boundaries). This should be addressed prior to any application for licences/planning. Page 1 of 10

Catchment area and flow levels The catchment area of the proposed scheme measures 1.08 km2 and is shown in the map extract below. Hydro Burn catchment area As would be expected, average rainfall levels in the area at 1300-1700 mm/year are reasonable, being in line with the Scottish average (1436mm) and significantly above UK average (1079mm). Predictions of the flows in the burn have been made using LowFlows, a software package widely used throughout the industry, including by SEPA. LowFlows calculates predicted flow levels based on historic rainfall levels and data on the local geology/geography which influences the amount of rainfall that runs off into watercourses. LowFlows analysis gives the following data for the catchment area outlined above: Basin area Annual average runoff (mm) Base flow index Mean annual flow (l/s) Qn90 flow (l/s) Qn95 flow (l/s) Page 2 of 10 1.08 1509 0.16 52 5 3

The runoff figure is the annual amount of rainfall flowing out of the catchment as surface water and is a factor of rainfall levels and the effect the local terrain & geology has on water retention/dispersal. It is useful as a relative measure of flow for different sized catchment areas. The predictions in excess of 1500mm are significantly above both the Scottish (1049mm) and UK (645mm) averages. The base flow indexes are an indication of how quickly the rainfall would flow in to the burns and is based on the local geology. Potential values range from 0.1 to 1.0 with lower values representing catchments that are flashy, i.e. rainfall will run off very quickly. The low base flow index indicates that water levels will fluctuate very quickly. Whilst this will give rise to some very high spate flows of water, it is not beneficial to a hydro scheme as the system will need to be sized on the longer term flow of water and will not be able to make additional utilisation of very high flow levels. LowFlows also predicts the flow levels across the year and these are expressed as exceedence percentiles. The Qn90 figure shown above is the flow level that is exceeded 90% of the year, i.e. for 90% of the year the flow is above 5 l/s. Qn95 is the flow exceeded 95% of the year. These figures are important as they are commonly used by SEPA to set the level of compensation flow. This is the flow which must be left in the river at all times (subject to sufficient natural flow) and cannot be abstracted for generation purposes. In the case of Hydro Burn it is expected that SEPA would require the higher Qn90 figure as the compensation flow since the catchment area is under 10 km 2. The performance of hydro schemes is impossible to predict with certainty due to variations in rainfall levels and therefore watercourse flows. These figures are based on a widely utilised method of predicting flow levels but are given as guidance only and should not be considered as a guarantee. Further flow analysis to validate these figures would be undertaken during the ensuing stages of the project. Scheme design overview Over much of its length the burn has eroded a deep gorge in which it now runs. These gorges prevent the use of large sections of the burn for the construction of both the intake structure and the outfall from a turbine house. The cost effectiveness of any hydro scheme has a close correlation to the steepness on the section of watercourse involved. Therefore the steeper section of the burn upstream from the access track bridge is favoured for the proposed scheme. It would be normal to site the turbine house as low as possible on the burn, while within the boundary of the property. However, below this section, the burn below the bridge quickly enters a narrow gorge, Page 3 of 10

around 10 metres deep, which would make the construction of a turbine house on this stretch very difficult and costly. Glen Water proposed scheme, location of turbine house and intake Above the bridge, the hillside soon starts to rise steeply towards the wooded section above. Once the steeper gradient is reached, the burn again runs in the bottom of a deep gorge. This section of the watercourse is currently on land belonging to a neighbouring estate. Approximately 500m upstream of the bridge, there is a large waterfall (marked on the 1:25000 OS map). 60m upstream of this waterfall, the burn re-joins the client s march, with its northern bank being part of the Glen Water Estate (point A on the map above). Above this point the gradient of the burn becomes markedly reduced, meaning that it would not be cost effective to take the site of the intake much farther upstream. The geological features of this small area of land mean that there are two possible sites for an intake structure. The lower of these is just above the large waterfall and downstream of point A. From here the penstock would run down through the conifer forest requiring a significant amount of deforestation. The second, higher, option for an intake would be around 40 meters upstream of point A. An intake located here would enable the penstock to be run down the northern side of the forest. With either intake, Page 4 of 10

elements of the scheme would involve land owned by the neighbouring estate and a suitable agreement should be reached with them prior to any development. The intake design would consist of a concrete weir constructed in the burn bed and include a screen to filter out debris in the water (which can damage some types of turbine if not removed). This screen would be a Coanda type which achieves a high degree of filtration and minimises maintenance. The intake structure would also include a large settling tank, which would allow any air introduced by the Coanda screen to be removed from the water prior to it being introduced to the penstock. The proposed pipeline route is on the north bank of the burn. The penstock pipe would need to be buried beneath ground to comply with planning requirements and to provide support and protection for the pipe. Site access would be gained from a temporary track formed close to the march fence on the north side of the burn. The total penstock length would be around 500 meters. The proposed turbine house would be sited close to the burn in the area immediately up or downstream from the wooden bridge. The exact location would need to be determined taking into consideration the maximum flood level of the burn. Connection to the 11kV line would be relatively straightforward. The gross head (height difference between intake and turbine) of the scheme is 60m if the lower of the two possible intake sites is used, or 64m for the upper intake. There are many varying types of turbine capable of generating hydro power and the type of turbine selected depends on both the head and flow of the system. This site would suit a Pelton wheel turbine, which is ideally suited to sites of low flow and high head. Electricity generated by the system can either be connected direct to the grid for export or via a property where it may be utilised to offset current electricity purchased (with any excess being exported). The latter has financial benefits in that the cost of the electricity saved is far in excess of that paid for exported electricity. However, to run a cable to the Glen Water buildings would require a cable over a kilometre long. This would result in a considerable voltage drop, which in turn would necessitate a large cross sectional area of copper in the cable to minimise the drop. Therefore this solution would be prohibitively expensive and far outweigh any benefits from offsetting current electricity cost. Therefore direct connection to the grid is proposed. Page 5 of 10

Scheme power generation Gross head (m) 60 Estimated net head (m) 52 Turbine rated flow (l/s) 46 Turbine capacity (kw) 15 Capacity factor 49.97% Annual power generation (MWh) 65.7 The net head available for generation is lower that the gross head (or actual height difference in water levels) due to the falls required in the system design to allow flow of water and pressure losses in the pipe. The capacity factor is the actual generated power expressed as a percentage of the power that would be generated if the turbine were running at full power throughout the year. Obviously there are times when the water flow levels are not sufficient to run the turbine at full power and indeed some periods when generation will stop completely. Should the higher intake be utilised, the head will be marginally greater. It is likely that the turbine would still be rated at 15 kw as this is a step in the level of FITs payments (see below). However the rated flow would decrease slightly and the capacity factor improve leading to a slight overall increase in the power generated. This would in turn improve the income and return figures later in this report. We have opted to present the (slightly) more pessimistic option subject to further detailed design. Environmental and planning considerations Any hydro scheme requires an abstraction licence from SEPA. In general SEPA are less favourable to schemes under 100 kw and have issued guidance outlining the factors to be considered. Key within these is the steepness or slope of the watercourse and the length affected. Steeper watercourses are more favoured with a gradient of 1 in 10 or 10% being a critical threshold with the guidance. The average slope of the section of the Hydro Burn under consideration is very close to 10% (taking the height loss over the length of the course of the burn). This will need to be validated by detailed survey, but it is hoped that the Hydro Burn is unlikely to be considered by SEPA as a significant fish Page 6 of 10

habitat and a scheme could be considered favourably for an abstraction licence. The end decision is a result of consultation with the local SEPA officials and our experience is that their approach can vary significantly between different SEPA offices. Were the client to choose to proceed with the scheme, we would recommend early consultation with SEPA. Planning permission is likely to be required, particularly for the turbine house or shelter and this will probably require a design that is sympathetic with the surrounding environment. Revenue generation The new government feed in tariffs (FITs) guarantee a revenue for each kwh of electricity generated regardless of whether it is used locally or exported to the grid. The feed in tariff is guaranteed for twenty years from the start date and will increase at the rate of inflation (RPI). The tariff rate declines with higher levels of generation as detailed in the table below. This is reflective of the reduced capital costs per kw of larger schemes. Generation capacity Revenue p/kw h 15 kw 20.9 >15-100kW 18.7 >100kW - 2MW 11.5 >2MW - 5MW 4.7 Tariff levels April 2011 March 2012 It will be noted that the scheme (utilising either intake) would be sized at 15 kw to maximise the FITS rate per kw h. Though not applicable in the proposed scheme, where the generated electricity is used to replace power previously purchased there is a saving of approximately 12p per kwh. Electricity exported to the grid is guaranteed a revenue at a minimum of 3p per kwh and may be higher if market conditions dictate. The revenue generation figures below presume that the system would be connected to the grid at the turbine house and that there would be no savings on current electricity bills. Should the higher intake be used, revenues would be approximately 2.5% higher. Page 7 of 10

Annual power generation (MWh) 65.7 Feed in tariff 13,724 Saving on current electricity bills n/a Exported electricity 1,970 Gross revenue 15,694 Capital costs The terrain on which the penstock would be installed is rugged and contains an unknown amount of rock. Some form of access track would have to be constructed over this terrain to allow the necessary machinery access for the construction of the intake and burying of the penstock pipe. These aspects of the scheme are harder to estimate without visiting the site with a contractor or a construction consultant, which would be done at the feasibility study stage of the project development. It is nevertheless estimated that the scheme would cost in the region of 154,000. This cost is based on the construction of a scheme designed and built to current industry best practices. Such a scheme, well maintained, should have a life expectancy well in excess of 25 years. It should be understood that this is very much an initial estimate based on our experience with other schemes. A significant amount of detailed site analysis, engineering calculations and obtaining of quotes would need to be done during the next feasibility stage to generate more accurate budget figures. At this stage we would also get more accurate figures for the cost of grid connection to the 11kV lines, which would be done be SSE, the Distribution Network Operator (DNO). These costs do not take in to account any payments, either one off or ongoing to the landowner of the adjoining estate. Page 8 of 10

Scheme returns The FITs payments which make up the majority of the income are guaranteed by the government for 20 years. However, the expected lifespan of a hydro scheme should be in the region of 25 years and the scheme could go on for double this if properly maintained. An allowance should be made for running costs and some capital replacement in the longer term. This is expected to average 1,000 over the 20 year period, although expenditure in the early years would be expected to be much lower. This could be reduced if elements of the routine maintenance could be undertaken in house. Based on the figures above the predicted returns for the schemes would be as below. Gross revenue 15,694 Annual costs 1,000 Net revenue 14,694 Capital cost 154,000 Rate of return* 9.54% Payback period (years)* 10.48 *Undiscounted for future years as FITs increases by RPI. Conclusion and the way forward Hydro Burn has good potential for hydro power generation. The access problems for the construction of the intake structure and the penstock mean that the construction costs are relatively high, despite the short penstock length. The return on the capital invested, at 9.54%, is good and above the government target of 8% targeted in setting the feed in tariffs. Should you wish to advance, we would recommend that before any further work is done on the development of the schemes, discussions are held with the neighbouring landowner in relation to the location of the scheme. Should those prove positive we would then recommend commissioning a full feasibility study to develop the project in detail. Page 9 of 10

The feasibility study which would include the following steps: Detailed design & method statement Contractor and equipment estimates/quotes Detailed capital cost breakdown Consultation with the SEPA to initiate the approvals process, identify areas of concern and potential solutions Seasonal flow/power/revenue model In river flow spot monitoring Grid connection costing and consultation with the DNO Completion of the feasibility report would allow you to decide whether to proceed to apply for an abstraction licence and planning permission. Our charge for the full feasibility study is xxxx (inclusive of all expenses) ex VAT. Charges for later stages of the project (as detailed at the end of this report) would be identified during the feasibility stage. We trust this report is helpful. Please do not hesitate to contact me if you have any queries or would like to discuss this report further. Richard Haworth Glen Hydro Email: richard@glenhydro.co.uk Office: 01250881732 Mobile: 07971577320 Page 10 of 10