EDMS Project Stage 1 Business Plan



Similar documents
EDMS Project Outcome Realisation Plan

Implementation Plan: Development of an asset and financial planning management. Australian Capital Territory

PROJECT AGREEMENT FOR THE PLANNING AND DESIGN OF THE COMMON REGISTRY SOLUTIONS

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

Council, 6 February IT Report. Executive summary and recommendations. Introduction

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

Project title (in Chinese) 項 目

Case 2:08-cv ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8

JISC data.bris project & EPSRC Platform project: progress against workplan (October 2012)

SUMMARY PROFESSIONAL EXPERIENCE. IBM Canada, Senior Business Transformation Consultant

Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017

Basic Project Management & Planning

Executive Branch IT Reorganization Project Plan

STRATEGY AND RESOURCES COMMITTEE ITEM MARCH 2012 FACILITIES MANAGEMENT: FUTURE CONTRACTUAL ARRANGEMENTS

Project Management Fact Sheet:

Information Commissioner's Office

In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including:

Project Management Fact Sheet:

Gilead Clinical Operations Risk Management Program

<Project Name> ACCEPTANCE TEST PLAN <SCOPE OF TEST E.G. SYSTEM TESTING> <BUSINESS UNIT/DIVISION> DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES

Architectural Services Data Summary March 2011

Central Hosting. Case Study

The proposed Project Phase work II is expected to be completed in July of 2008

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

GIO Workers Compensation Training Calendar. Tasmania July 2010 to June 2011

Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report

Tasmanian Cloud & Government use of public cloud services

Supplier Forum. Contingent Hub NSW Government. Monday 16 th Feb 2015

HRIS v20 Project: updating software and infrastructure to bring business benefits. Personnel Services June 2015

Business Idea Development Product production Services. Development Project. Software project management

Project Management System Services

SCHEDULE 3. Milestones and Deliverables. Redacted Version

Project Management Planning

Analysis One Code Desc. Transaction Amount. Fiscal Period

QCA Pricing Practices Recommendations SunWater Implementation Plan

UNSOLICITED PROPOSALS

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Roles: Scrum Master & Project Manager

Department of Technology & Information. Standards

Tasmanian Government Electronic Procurement Pilot Project. Project Review & Closure Report

PROJECT MANAGEMENT PLAN <PROJECT NAME>

State Records Guideline No 25. Managing Information Risk

Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre

ACTIVE MICROSOFT CERTIFICATIONS:

REPORT OF: DIRECTOR OF DEMOCRATIC AND LEGAL SERVICES 13/358 WARDS AFFECTED: ALL

PROJECT AGREEMENT FOR INDEPENDENT PUBLIC SCHOOLS INITIATIVE

Manchester City Council Report for Information. Managing Attendance (Real Time Absence Reporting)

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY

Oakland County Department of Information Technology Project Scope and Approach

City of Minneapolis RCA Provision of IT Services. Committee of the Whole February 11, 2015

Financial Operating Procedure: Budget Monitoring

Stephen Doune HRIS Project Manager Plan International

Government Projects (as Prime Contractor)

Thanks to an extension of the scope of

To provide a procedure and associated guidelines to facilitate the management of project dependencies.

DIPLOMA OF PROJECT MANAGEMENT BSB (Classroom Delivery)

CHANGE MANAGEMENT PLAN WORKBOOK AND TEMPLATE

Network Security Innovation Platform

MONTHLY PROJECT PROGRESS REPORT

Ashley Institute of Training Schedule of VET Tuition Fees 2015

Presentation Standing Committee on Appropriations (SCOA)

Bad Honnef September Reiner Schmitt. schmitt consulting. your license. our business

SCHEDULE 8 Generalist Project Services Framework 2015

Project Management Information and Resources Project

PROJECT MANAGEMENT FRAMEWORK

Project Assessment Framework Establish service capability

PROJECT: Online Shop STATUS REPORT September 2015

Implementation Plan for Local Government Capacity Building Project - Northern Territory

2012 CBECS: Preliminary Results and Timeline for Data Release

Engine Workscope Optimization. Jim Henry VP Technology Development Standard Aero

Resource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager

Consumer ID Theft Total Costs

Standards for Developing and Implementing Administrative Systems at UC Davis

1. Introduction. 2. User Instructions. 2.1 Set-up

Implementing Capacity Management within SIAM (Service Integration & Management) Amrit Bhattacharya

Place Scrutiny Briefing AGENDA ITEM 13

Guide to Business Planning

2016 Examina on dates

Project Management Fact Sheet:

STATEMENT OF WORK (SOW) for Web Content Management System Professional Services

City & County of San Francisco Permit & Project Tracking System

Walton Centre. Document History Date Version Author Changes 01/10/ A Cobain L Wyatt. Monitoring & Audit

Employers Liability Registers

Storm Clouds Ahead? An Introduction to Cloud Computing

Deep Security Intrusion Detection & Prevention (IDS/IPS) Coverage Statistics and Comparison

Sustaining Progress Fourth Progress Report

VICTORIAN CARDIAC OUTCOMES REGISTRY. Data Management Policy

Long Term Data Center Facilities Program

Staff Survey A Summary of Service

Project Management Development Scheduling Plan: Data Mart. By Turell Makins

2015 Examination dates

Castellon, of January Copyright Grupo Europeo de Consultoría LocalEurope. Reservados todos los derechos.

BRENT COUNCIL IT STRATEGY

Purchased Services Areas of Opportunity:

Implementing Carbon Reduction Without Impacting Working Capital. Presented by Dylan Crompton

Human Resources Management System Pay Entry Calendar

"Your career as a project manager begins here!"

Governance of Evaluation, Proof of Concept and Pilot Projects

EXECUTIVE COMMITTEE OF THE HIGH COMMISSIONER S PROGRAMME UPDATE ON THE CHANGE MANAGEMENT PROCESS

Transcription:

EDMS Stage 1 Business Plan Corporate Information Support Branch DEPARTMENT OF TREASURY AND FINANCE Version 0.F (16 May 2005) TRIM Reference Number: 08/21227 (PM 001 Version 2.0 September 2002)

Acknowledgements The contribution of the following individuals in preparing this document is gratefully acknowledged: Julie Jones, Lynne Valentine, Robert Cockerell, Marita Holding This document has been derived from a template prepared by the Department of Premier and Cabinet and the Department of Treasury and Finance, Tasmania. The structure is based on a number of methodologies as described in the Tasmanian Government Management Guidelines. For further details, refer to http://www.projectmanagement.tas.gov.au. BUILD STATUS: Version Date Author Reason Sections 0.F 16/5/05 Amendments ICSC 1.7, 1.8, 2.1, 5.1, 6 0.E 26/4/05 Amendments 4.1, 5.1, 6 0.D 17/2/05 Amendments IMC 1.3, 1.4, 1.7, 1.8, 2.3, 4.2 0.C 31/1/05 Amendments RC 2.3, 4.2, 6 0.B 20/1/2005 Amendments - LV All 0.A 4/1/05 Preliminary draft All EDMS Business Plan Stage 1 16 May 2005 Page 2 of 11

Corporate Information Support Branch 1. OVERVIEW, OBJECTIVES AND SCOPE 1.1 Title: Electronic Document Management System (EDMS) 1.2 Objective: The aim of the project is to implement an EDMS within the Department of Treasury and Finance. The EDMS will replace the existing Records Management System (RecFind) and provide an effective tool for the management of emails and other unstructured information (for example, Word and Excel documents) across the Agency. 1.3 Scope: The project covers the replacement of the RecFind Records Management System and the electronic capture and management of email. Stage 1 will determine the capture of other forms of unstructured data i.e. MS Office Word documents and Excel spreadsheets. Stage 1 of the project is limited to the Business Needs Analysis, Policy Development, Product Selection, Prototyping and Testing. Stage 1 will be followed by two further stages: Stage 2: Migration of RecFind into the new system and EDMS software pilot; and Stage 3: Complete Agency-wide EDMS rollout. It is important to note that Stages 2 and 3 are totally dependent on the outcomes of Stage 1. With particular reference to the: process of product selection; and business decision on how other MS Office documents will be captured and at what stage of the project this will be implemented. EDMS Business Plan Stage 1 16 May 2005 Page 3 of 11

1.4 Reason: As outlined in the Information Management Strategic Plan (July 2004) a review of the Department s information management issues nominated the management of unstructured information as a high priority area. Unstructured information includes hard copy records, information in our email system (Lotus Notes) and information stored on our servers, for example; word documents on our shared drives. The EDMS project will see the implementation of a new [single] system to replace RecFind (the Department s current tool for managing hard copy information) and manage unstructured data. 1.5 Priority: Critical The replacement of RecFind at Treasury is seen as a mandatory and urgent part of the EDMS project as: Systems support for the Department s Record Management System (RecFind) has declined to an unacceptable level due to the vendor s loss of market share in Tasmania. Both DPIWE and DoE have experienced similar problems with exceptionally poor systems support. RecFind is a critical infrastructure system, potential system failure places the Department in a high level of risk. 1.6 size: Large 1.7 Outputs EDMS Product Selection Agency wide implementation of a new EDMS software application. Replacement of RecFind. Completion and implementation of a new corporate Business Classification Scheme. Change management, communication and education/training plans to assist in the product implementation and improving the Department s Information Management culture. EDMS Business Plan Stage 1 16 May 2005 Page 4 of 11

Stage 1 Outputs: Scope for the EDMS implementation i.e. capture of email only and/or inclusion of MS Office documents Business Needs Analysis complete Tender and product selection processes complete Policy Development complete Initial Software Purchase Completion of system design, configuration and acceptance testing Note: the scoping of the EDMS implementation, the results of the tender process and the policy stage will have a direct bearing on the scope of Stages 2 and 3. 1.8 How will the success of the project be measured: The success of Stage 1 of the project will be measured by: 1. The creation of both a business and a functional requirements document. 2. Completion of the product selection and product prototyping phases. 3. Initial Policy Development 4. Approval of the Steering Committee to continue to Stages 2 and 3. The success of the full project will be measured by: 1. Ease of use of the selected product, 2. Agency-wide implementation of the EDMS, and 3. Agency-wide use of the EDMS. 2. GOVERNANCE 2.1 Corporate Management Group (CMG) and Executive The CMG & Executive are responsible for policy and resourcing decisions. 2.2 Steering Committee: Information and Communications Steering Committee EDMS Business Plan Stage 1 16 May 2005 Page 5 of 11

2.3 Sponsor: 2.4 Reference Group: Director, Corporate Support Division The Sponsor has ultimate accountability and responsibility for the project. Director, Corporate Support Division Director, Information Systems Branch Assistant Director, Corporate Information Support Branch Senior Information Officer, Corporate Information Support Branch Information Management Supervisor, Corporate Information Support Branch Stage 1 Business Needs Analysis Reference Group: 2.5 Manager: Comprised of at least one staff member from each branch within Treasury. Manager, Corporate Information Support Branch. The Manager is contracted by the Steering Committee to deliver the defined project outputs. 3. STAKEHOLDERS AND RELATED PROJECTS 3.1 Key Stakeholders: Information and Communications Steering Committee Corporate Management Group Information Systems Branch Corporate Information Support Branch Treasury staff 3.2 Related s: 4. RISK MANAGEMENT Information Security, including a risk assessment of all Treasury information assets and the development of an Information Security Plan and Information Security Risk Register. Rollout of the new version of Microsoft Windows. Additional projects will be identified as a result of the EDMS. 4.1 Major Risks: The major risks to the success of the project are as follows: 1. As this is a long term staged project, maintaining ongoing commitment and support by internal and external stakeholders. EDMS Business Plan Stage 1 16 May 2005 Page 6 of 11

2. The product could be seen as an imposition and keeping user focus and support might be difficult. 3. Failure to conduct an effective change management and training program. 4. Not achieving an improved information management culture. 5. Insufficient or loss of funding. 6. size need to involve entire Agency. 7. team staffing inability to provide skilled resources. 8. The ability of EDMS products to work within the Treasury IT environment, particularly with regards to Novell & Lotus Notes 4.2 Minimising the Risks: Steps to be undertaken to minimise these major risks to the success of the project: 1. Development of a full risk register. 2. Regular reporting of progress to the Steering Committee (ICSC) and the Corporate Management Group (CMG). 3. Appropriate and comprehensive communication strategies to ensure that all stakeholders are fully informed and engaged early (in relation to the benefits of information management) and ongoing throughout the implementation (to manage expectations and maintain interest levels). 4. The establishment of user/reference groups with representatives from various branches that can provide input/advice during evaluation and development of the project. Helping to provide confirmation of the product fit in line with the Department s business needs. 5. The conduct of an effective change management and training program with regular briefings and training etc. 6. The provision of skilled resources to drive and support the project. 7. The willingness of senior management to commit time and be visibly supportive of the project. EDMS Business Plan Stage 1 16 May 2005 Page 7 of 11

8. Robust product selection processes, including comprehensive product testing within Treasury s IT environment. 9. Scope and develop the IT infrastructure specifications so that the selected product will operate seamlessly in our environment and effectively for the end-users. 10. Comprehensive product prototyping, including; supplier competency, supplier ability to provide comprehensive support, and the use of tried and proven core products. 11. Establishment of a close working relationship between the project team, CIS and ISB to ensure comprehensive information sharing, gathering and advice. 12. Staged implementation avoidance of the big bang approach, helping to gain user confidence, prove the application and overcome teething problems. EDMS Business Plan Stage 1 16 May 2005 Page 8 of 11

5. BUDGET 5.1 Estimated Expenditure Stage 1: * Note: all costs to be confirmed (particularly software costs) at the end of the tender process. CSO 2: Change Management and Training Officer: Training Tender Costs Consulting Software: Hardware: Annual Maintenance: Stage 2 CSO2: Change Management and Training Officer: Consulting: Stage 3 Software Annual Maintenance Consulting EDMS Business Plan Stage 1 16 May 2005 Page 9 of 11

6. PROJECT ACTIVITIES AND MILESTONES FOR STAGE 1: Id Description Who Scheduled Start 1. Formal commencement of project: submission of draft Business Plan to ICSC Manager Scheduled Finish Predecessor 1 Feb 05 April 2005-2. Research local, interstate and international Information Management products and implementation strategies and processes. 3. Reference Group Workshops (Business Needs Analysis) Manager Manager & Reference Group Nov 04 Jun 05 - Feb 05 Mar 05 4. Tender Development and Release Manager, Tender Review Committee, ICSC May 05 Jul 05 3 5. Product selection and associated report to the ICSC & Tender Review Committee Manager, Tender Review Committee, ICSC Aug 05 Aug 05 4 6. CSO 2 Recruitment Manager, AD-CIS May 05 Jun 05 7. Senior Change Management and Training Officer Recruitment Manager, AD-CIS May 05 Jun 05 8. Test environment creation Team 9. Policy Development Manager & Reference Group Sep 05 Sep 05 5 Sep 05 Nov 05 5 1 The activities appearing in the predecessor column must be completed before the activity described can begin. EDMS Business Plan Stage 1 16 May 2005 Page 10 of 11

Id Description Who Scheduled Start 10. Review Policy Manager, Reference Group, ICSC and CMG Scheduled Finish Predecessor 1 Dec 05 Feb 06 9 11. System Configuration and Acceptance Testing (in line with the Department s Policy/Business Requirements). Team Dec 05 Feb 06 5 & 9 STAGE 2 Replacement of RecFind and pilot in two branches. STAGE 3 Agency-wide EDMS Rollout. 7. RECOMMENDATION It is recommended that the Information and Communications Steering Committee provide the authority to complete the activities as per this Plan. 8. ENDORSEMENT Prepared: ---------------------------------------------------- ----------------------------------------------------- Responsible Officer: Manager Assistant Director Date: / / Date: / / Accepted: ---------------------------------------------------- Sponsor: Director, Corporate Support Division On behalf of the Information and Communications Steering Committee Date: / / EDMS Business Plan Stage 1 16 May 2005 Page 11 of 11