1 Outcome Realisation Plan Version 1.A (14 August 2008) Copy: Uncontrolled Corporate Support Department of Treasury and Finance
2 DOCUMENT ACCEPTANCE and RELEASE NOTICE This is version 1.A of the Outcome Realisation Plan. The Outcome Realisation Plan is a managed document. For identification of amendments each page contains a release number and a page number. Changes will only be issued as complete replacement. Recipients should remove superseded versions from circulation. This document is authorised for release once all signatures have been obtained. PREPARED: DATE: / / (for acceptance), CIS APPROVED: DATE: / / (for acceptance) Assistant Director, CIS ACCEPTED: DATE: / / (for release) Director, Corporate Support Project Sponsor Outcome Realisation Plan Version 1.A Page ii
3 1. BUILD STATUS: The most recent amendment first. Version Date Author Reason Sections 1.A 13 May 2008 Initial Release All 2. AMENDMENTS IN THIS RELEASE: Section Title Section Number Amendment Summary This is the first release of this document. 3. DISTRIBUTION: 1 2 Copy No Version Issue Date Issued To Outcome Realisation Plan Version 1.A Page iii
4 Table of Contents Introduction... 1 Document Purpose... 1 Intended Audience... 1 Assumptions and Constraints... 1 Outcome Realisation... 2 Project Objective... 2 Outcome(s)/Benefits... 2 Output Ownership... 3 Output Utilisation... 4 Target Outcomes and Performance Measures... 5 Monitoring and Reporting Outcome Realisation... 7 Project Closure and Review... 7 Post Project Tasks... 8 Output Management and Transition Plan... 9 Output Delivery and Acceptance Outcome Realisation Plan Version 1.A Page iv
5 Introduction Document Purpose The purpose of the Electronic Document Management (EDMS) Project Outcome Realisation Plan is to ensure: the final stages of the project are managed in a satisfactory manner; the utilisation of the project s outputs are linked to the planned project outcomes; the long term output management responsibilities are understood and accepted by the Business Owner(s); that the success of the project s outputs are assessed and corrective action performed if required; and the planned project outcomes are achieved to a significant extent prior to formal project closure. This document is the responsibility of the,,, and Assistant Director, Corporate Support and may be revised and amended to meet changing conditions for a period after the project closes to monitor outcome realisation. Intended Audience This document is intended to manage and monitor the progress of the project in delivering the project outcomes and be used by the: Sponsor; and Communications Steering Committee (); Steering Committee; ; Team;, ; and Records. Assumptions and Constraints Assumptions Business Owner(s) have been identified for all project outputs, and accept the role; The EDMS Steering Committee will not continue after project closure. Monitoring of the outcomes will be undertaken by the ; and Branch (ISB) will be responsible for ongoing hardware and software maintenance costs. Outcome Realisation Plan Version 1.A Page 1
6 Outcome Realisation Project Objective The objective is to replace the Department s Records Management system (RecFind), due to the lack of system support available, with a new Electronic Document Management System that will also address the capture of , Word and Excel documents. This system will show staff not only the paper files that are available at Records, but also all of the s, Word and Excel documents on a topic. It will enable: 1. Improved planning, reporting, business decisions and performance through removal of duplication, and gaining timely and comprehensive access to relevant Treasury information; 2. Enhancement of the existing information management culture within the Department; and 3. Removal of costly inefficiencies in identification and retrieval of information by enabling staff to gain access to information directly. Outcome(s)/Benefits The agreed outcomes/benefits the seeks to achieve from the utilisation of the project outputs are: Table 1: Outcome ownership Outcomes/Benefits Accountable Business Owner(s) A. A system that is well supported CIS ISB B. Agency-wide implementation of the EDMS EDMS Steering Committee C. Agency-wide use of the EDMS EDMS Steering Committee D. Improved information management and compliance Corporate Support E. Better document discovery abilities, access control, sharing and reuse of information Team EDMS Steering Committee Outcome Realisation Plan Version 1.A Page 2
7 Output Ownership Table 2 Output ownership Output Business Owner 1 Scope for the EDMS implementation i.e. capture of only and/or inclusion of MS Office documents 2 Business Needs Analysis EDMS Reference Group 3 Tender and product selection processes EDMS Steering Committee EDMS Tender Selection Panel 4 Policy and procedure development EDMS Reference Group 5 Software purchase 6 System design, configuration and acceptance testing EDMS Reference Group 7 Configuration of a new EDMS based on the selected product, RecFind data, and endorsed policies and procedures 8 Development of change management, communication and training plans to assist in the product implementation and improving the Department s Management culture EDMS Reference Group EDMS Steering Committee 9 ICT deployment of the EDMS ISB 10 Migration and decommissioning of production use of RecFind databases (GPOC/OTTER, Treasury and Treasurer s Office) to new EDMS Director, GPOC/OTTER Office, Treasurer s Office 11 Train Records staff and RecQuery users 12 Branch Implementations Confirm implementation schedule BCS and Management training BCS review Shared drive clean-up Process analysis and development TRIM Training Shared drive data migration Support Survey and feedback Branch Head Unit s Outcome Realisation Plan Version 1.A Page 3
8 Output Business Owner 13 Develop and implement outcome realisation plan 14 Project review Director, CSD 15 Project Closure EDMS Steering Committee Director, CSD 16 Post implementation review Director, CSD Output Utilisation The will deliver the following outputs for use by the project customers: Table 3: Output utilisers Outcome Name of Output Stakeholders Utiliser A well supported EDMS A framework that meets our useability and recordkeeping requirements An operational records management system Scope for the EDMS implementation i.e. capture of only and/or inclusion of MS Office documents Business Needs Analysis Tender and product selection processes Software purchase Policy and procedure development System design, configuration and acceptance testing Configuration of a new EDMS based on the selected product, RecFind data, and endorsed policies and procedures Development of change management, communication and training plans to assist in the product implementation and improving the Department s Management culture ICT deployment of the EDMS Migration and decommissioning of production use of RecFind databases (GPOC/OTTER, Treasury and Treasurer s Office) to new EDMS Train Records staff and RecQuery users EDMS Steering Committee EDMS Steering Committee Director, ISB Director, GPOC/OTTER Office, Treasurer s Office Team Records staff in Treasury, GPOC/OTTER and Treasurer s Office TRIMQuery users Outcome Realisation Plan Version 1.A Page 4
9 Outcome Name of Output Stakeholders Utiliser Operational Branch Implementations Branch Head Branch staff EDMS Records staff Removal of duplication Improved access to information Improved information management Unit s Branch staff culture Completed project with outputs accepted by business owners Planning, reporting, business decisions making is improved Confirm implementation schedule BCS and Management training BCS review Shared drive clean-up Process analysis and development TRIM Training Shared drive data migration TRIM administration Help desk support Quality Assurance Implement records processes BCS maintenance Survey and feedback Develop and implement outcome realisation plan Project review Project closure Post-implementation review Team Records staff Director, CSD Target Outcomes and Performance Measures Table 4 Outcome Performance Measures Target Outcome 1 Performance Indicator Measure Baseline Target Level Completion Date Accountability A well supported EDMS Vendor support available when needed Local support available Support provided interstate Support provided locally Complete (9 October 2006) EDMS Steering Committee A framework that meets our useability and recordkeeping requirements Enabling staff to meet our business and legislative requirements Electronic documents stored in Recordkeeping system. Paper records only stored in Recordkeeping system. Electronic documents stored in unmanaged environment ( and shared drives). Paper records managed and supported in new system. Electronic documents stored in new system. Complete (30 June 2008) EDMS Steering Committee An operational records management system Successful migration from RecFind. Data migrated from RecFind. Existing data in RecFind. Successful migration of data from RecFind. Complete (9 October 2006) Configuration of New system Best practice Maintain Complete Director, ISB Director, GPOC/OTTER Office, Outcome Realisation Plan Version 1.A Page 5
10 Target Outcome 1 Performance Indicator a new EDMS based on the selected product, RecFind data, and endorsed policies and procedures. Measure Baseline Target Level and procedures implemented. records management practices. existing practices. Completion Date Accountability (9 October 2006) Treasurer s Office Team Branch implementations: Operational EDMS Removal of documents stored in multiple locations (shared drives) All staff using EDMS. Documents stored in a single location (EDMS). Staff trained and using EDMS. Staff accessing single document (EDMS). No EDMS in use. Documents stored in multiple locations (shared drives). All staff trained and using EDMS. Documents stored in single location (EDMS). Complete (30 June 2008) Branch Head Unit s Branch staff Team Improved access to information EDMS used to access information across the Department. Branches sharing information. Access to shared drives limited to individual branches. Access to all relevant information. Single search tool. Lack of searchability on server drives. s shared in EDMS. s only available to other staff if printed and filed. Improved information management culture Staff having the knowledge and understanding of our information management principles, policies and procedures. Staff use the system in line with our policies and procedures. Hardcopy information management in accordance with policies and procedures. Hardcopy and electronic information management in accordance with policies and procedures. Completed project with outputs accepted by business owners Adoption by business owners. Department-wide implementation. 30 June 2008 Director, CSD Planning, reporting and decision making is improved through improved access to information. Staff are able to access all relevant information in a timely manner. Staff have improved access to the business records they need for their planning, reporting and decision making. 30 June 2009 Outcome Realisation Plan Version 1.A Page 6
11 Monitoring and Reporting Outcome Realisation The will monitor the performance of each outcome and will report on the progress to the EDMS Steering Committee, and. Project Closure and Review The project will be closed on acceptance of the project outputs, including acceptance of ongoing management requirements and any residual matters, by the business owner, and approval of the EDMS Steering Committee of the Outcome Realisation Plan and the recommendation to close the project. Monitoring of the realisation of project outcomes and benefits will continue, with the providing oversight. On project closure, the following reviews will be undertaken: Process review this will be a project procedure review to assess how the project ran, including quality of governance, documentation, consultation, budget management, adherence to project management guidelines and so on. It will commence subsequent to project closure; and Outcomes and Benefits Review this will be a review of the projects outcomes in line with the performance measures detailed in Table 4 above. It will be conducted by the Project Sponsor 12 months after completion of the project to establish if the targeted project outcomes and benefits have been secured. Outcome Realisation Plan Version 1.A Page 7
12 Post Project Tasks The following tasks have been identified as required to be undertaken following project closure: Output Task Responsible Business Owner 1 Business Review BCS review To review the BCS after the TRIM implementation across the Department and where necessary refine it to enhance useability. Project brief approved at Special 25 June Data clean-up Review and clean-up the data migrated to TRIM files for verification of security, consistency and appropriateness. Project brief approved at Special 25 June 2008 Library epublications Import P: Shared drive publications to TRIM Migrate epublications to TRIM Project Librarian TRIM BUSA 2 Resources Review Resource arrangements in CIS post project completion Approved at Special 25 June Technical Review Software upgrade to take advantage of new features (LDAP integration) and bug fixes (TRIM hanging) * Submit paper to August 2008 Director, ISB Workgroup server implementation at Treasurer s Office, GPOC/OTTER and Henty House *. Submit paper to September 2008 Director, ISB * Access to scanned documents at Henty House may be dependant on the upgrade and workgroup server implementation currently being investigated. Future Tasks The following tasks have been identified as future tasks that originated from the EDMS Project. Output Task Responsible Business Owner Lotus Notes Database Review Submit paper to Replace existing Lotus Notes Databases by TRIM where appropriate Project Outcome Realisation Plan Version 1.A Page 8
13 Review of workflow capabilities Assess business benefits. Point forward scanning Submit paper to Develop policy Review results of scanning consultancy. * Back-scanning Review results of scanning consultancy. * Include in LAGB System Review Director, LAGB Director ISB AD CIS Director, LAGB Output Management and Transition Plan In moving from project mode to operational mode the following outputs have been identified as ongoing and need to be transitioned from the Project Team to Records. Resource requirement for this work were approved at Special June Attachment A provides a breakdown of the outputs detailed below. TRIM administration Output Task Responsible Start Scheduled Review tasks to be undertaken and statement of duties. Release BUSA from EDMS Project Team to Records., TRIM BUSA Scheduled Finish 1/11/07 Complete Help desk support Review tasks to be undertaken and statement of duties., Management Supervisor TRIM BUSA 1/11/07 Complete Help desk training for Records staff. TRIM BUSA 1/5/08 31/7/08 Outcome Realisation Plan Version 1.A Page 9
14 Transition help desk to Records. TRIM BUSA 1/6/08 31/7/08 Quality Assurance Review tasks to be undertaken and statement of duties., Management Supervisor TRIM BUSA 1/11/07 Complete Produce work instructions Team 1/5/08 Complete Training for Records staff Team 1/5/08 Complete Transition to Records. Team 1/5/08 Complete BCS maintenance Review tasks to be undertaken and statement of duties., Management Supervisor TRIM BUSA 1/11/07 Complete Produce work instructions, 1/7/08 30/6/09 Training for Records staff, 1/7/08 30/6/09 Transition to Records., 1/7/08 30/6/09 Outcome Realisation Plan Version 1.A Page 10
15 IT System Support Transition to ISB, Infrastructure Support, Application Support 1/5/08 Complete Output Delivery and Acceptance Output delivery and acceptance has been conducted with Branch Heads throughout the implementation. Regular reporting to the EDMS Steering Committee, and was conducted throughout the implementation, including: Status; Resources; Timelines; Risk and Issues management; Implementation issues; Change management and communications plans; and Budget. Outcome Realisation Plan Version 1.A Page 11
16 Attachment A Output TRIM administration Help desk support Quality Assurance Tasks Manage TRIM Help Desk Development and delivery of TRIM training including basics, advanced, refresher and follow up training Provide training and support to staff in new functionality as a result of system upgrades Develop and maintain system operating procedures, instruction manuals, and other necessary documentation. Develop specifications for the design and maintenance of TRIM reports including correspondence management. Identify, plan and manage system upgrades including evaluation and testing in consultation with ISB. Monitoring and maintenance of the TRIM Event, through the TRIM Enterprise Management tool. Management of TRIM system parameters and change control documentation such as record types, numbering patterns, BCS and AKA integration, record imports, metadata forms. Security management in TRIM Identification and management of TRIM related hardware and integrated software Provide consulting advice in relation to integration with other technical and operational business systems Create/amend Locations for new starters, file movements and terminations Create and deactivate ispace, Flex and PMI files for new staff, terminations and movements. Manage the deletion of records flagged for deletion by staff Maintain TRIM website Provide TRIM help desk support including recording, resolution, allocation and escalation of requests to appropriate staff Liaise with the TRIM System Administrator and Branch staff to resolve complex issues and identify training requirements Development and updating of procedures and work instructions. Develop and maintain help desk resources and reports Provide basic TRIM, BCS and Management training for Treasury staff Work with the TRIM System Administrator to tailor and deliver training packages Create and amend internal and external locations in TRIM for new staff, terminations and movements Undertake the quality assurance of records including titles, field completion, finalisation, record types, security, retention, and duplication. Monitor branch holding files and documents are not left checked-out of TRIM. Follow-up on issues with the relevant staff. Process new file requests and the creation of physical files as required. Monitor titling of documents saved in TRIM for titling consistency Monitor sub-folders to ensure file titles are included in Notes Outcome Realisation Plan Version 1.A Page 12
17 Monitor locations to identify and remove ghosts Identify finalised records and lock down access controls to prevent the updating of metadata. BCS maintenance IT System Support Monitor and update BCS terms and approved acronyms as required Maintain the BCS in the software packages AKA and TRIM Liaise with ISB regarding TRIM technical problems staff updates regarding system outages Provide advice to ISB regarding TRIM server setup Provide advice to ISB regarding TRIM PC setup (integration with Office applications, Lotus Notes) Testing of TRIM installation processes Provide advice to ISB regarding TRIM upgrades Outcome Realisation Plan Version 1.A Page 13
EDMS Project Stage 1 Business Plan
EDMS Stage 1 Business Plan Corporate Information Support Branch DEPARTMENT OF TREASURY AND FINANCE Version 0.F (16 May 2005) TRIM Reference Number: 08/21227 (PM 001 Version 2.0 September 2002) Acknowledgements
Implementing an Electronic Document and Records Management System. Key Considerations
Implementing an Electronic Document and Records Management System Key Considerations Commonwealth of Australia 2011 This work is copyright. Apart from any use as permitted under the Copyright Act 1968,
Digital Archives Migration Methodology. A structured approach to the migration of digital records
Digital Archives Migration Methodology A structured approach to the migration of digital records Published July 2014 1 Table of contents Executive summary... 3 What is the Digital Archives Migration Methodology?...
Digital Archiving Survey
Digital Archiving Survey Background information Under the Public Records Act 2002 (the Act), public authorities have a responsibility to ensure that digital records under their control remain accessible
Implementing an Electronic Document and Records Management System. Checklist for Australian Government Agencies
Implementing an Electronic Document and Records Management System Checklist for Australian Government Agencies Acknowledgments The checklist for implementing an electronic document and records management
Project Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
Records Management - Department of Health
Policy Directive Records Management - Department of Health Document Number PD2009_057 Publication date 24-Sep-2009 Functional Sub group Corporate Administration - Records Ministry of Health, NSW 73 Miller
EDRMS Procurement and Pre- Implementation
GPO Box 2343 Adelaide SA 5001 Tel (08) 8204 8773 Fax (08) 8204 8777 DX:467 [email protected] www.archives.sa. gov.au EDRMS Procurement and Pre- Implementation August 2009 Version 3.1 Table
NFSA Project Management Guidelines
NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
To provide a procedure and associated guidelines to facilitate the management of project dependencies.
Management DEPENDENCY MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project dependencies. Overview Dependencies in this Phase are defined as actions,
How To Manage A Project
Realising Project Benefits Staff Management Plan Version 1.0 (2/10/07) Inter Agency Policy and Projects Unit Department of Premier and Cabinet Acknowledgements The contribution of the following individuals
Maruleng Local Municipality ICT CHANGE MANAGEMENT POLICY
Maruleng Local Municipality ICT CHANGE MANAGEMENT POLICY Contents ICT CHANGE MANAGEMENT...1 POLICY...1 1. Preamble...3 2. Terms and definitions...3 3. Purpose...4 4. Objective of this Policy...4 5. References
JOB DESCRIPTION CONTRACTUAL POSITION
Ref #: IT/P /01 JOB DESCRIPTION CONTRACTUAL POSITION JOB TITLE: INFORMATION AND COMMUNICATIONS TECHNOLOGY (ICT) SECURITY SPECIALIST JOB SUMMARY: The incumbent is required to provide specialized technical
Technical Project Manager JOB DESCRIPTION
JOB TITLE: BUSINESS UNIT: REPORTS TO: Technical Project Manager ICT Manager, ICT EA GRADE: Non-EA Position DATE APPROVED: 17/12/2015 JOB SPECIFICATION SUMMARY OF THE BROAD PURPOSE OF THE JOB The Technical
Customer Hosted Service Description and Service Level
Customer Hosted Service Description and Service Level Customer Hosted service description and service level Copyright Egton Medical Information Systems Limited 2014 Controlled Document Version 8: 1 November
UoD IT Job Description
UoD IT Job Description Role: Projects Portfolio Manager HERA Grade: 8 Responsible to: Director of IT Accountable for: Day to day leadership of team members and assigned workload Key Relationships: Management
Outcome Realisation and Organisational Change Management. the Tasmanian Government Approach
Slide 1 Outcome Realisation and Organisational Change Management the Tasmanian Government Approach Carol Bond, Senior Project Officer Inter Agency Policy and Projects Unit Slide 2 The Tasmanian Government
Capacity Plan. Template. Version X.x October 11, 2012
Template Version X.x October 11, 2012 This is an integral part of infrastructure and deployment planning. It supports the goal of optimum provisioning of resources and services by aligning them to business
K-Series Guide: Guide to digitising your document and business processing. February 2014 LATEST EDITION
K-Series Guide: Guide to digitising your document and business processing February 2014 LATEST EDITION Kefron are the Document Kefron & simplifies the document and Information information management world
Digital Continuity Plan
Digital Continuity Plan Ensuring that your business information remains accessible and usable for as long as it is needed Accessible and usable information Digital continuity Digital continuity is an approach
The Danwood Group Professional Services Offering DANWOOD
The Danwood Group Professional Services Offering DANWOOD Our Professional Services Our Professional Services department can provide you with a variety of services from Audit and Assessment to Technical
Mapping the Technical Dependencies of Information Assets
Mapping the Technical Dependencies of Information Assets This guidance relates to: Stage 1: Plan for action Stage 2: Define your digital continuity requirements Stage 3: Assess and manage risks to digital
<Project Name> ACCEPTANCE TEST PLAN <SCOPE OF TEST E.G. SYSTEM TESTING> <BUSINESS UNIT/DIVISION> DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES
DEPARTMENT of INFRASTRUCTURE, ENERGY and RESOURCES ACCEPTANCE TEST PLAN Version - DOCUMENT ACCEPTANCE and RELEASE
HSE P0801 HSE Document Control and Records Management Procedure
HSE P0801 HSE Document Control and Records 1. DOCUMENT CONTROL... 2 2. PURPOSE... 4 3. SCOPE... 4 4. DEFINITIONS... 4 5. ROLES AND RESPONSIBILITIES... 5 6. PROCESS DETAILS... 7 6.1 Document Control...
ANU Electronic Records Management System (ERMS) Manual
ANU Electronic Records Management System (ERMS) Manual May 2015 ERMS Manual May 2015 1 Contents The ERMS Manual 1. Introduction... 3 2. Policy Principles... 3 3. The Electronic Records Management System...
University of Waikato Change Management Process
1. Overview Information Technology Services and the Faculty and Division ICT staff have adopted the Information Technology Infrastructure Library (ITIL) systems management framework as its model for best
RECORDKEEPING MATURITY MODEL
Introduction Maturity Rating Definitions 1 Level 1 Inadequate/Sub-standard Practice is not formalised or documented. Processes and practices are fragmented or non-existent. Where processes and practices
Employability Skills Summary
s Summary Monday, 22 November 2010 10:55 AM Version 1.2 s Summary Page 2 Table of Contents BSB10107 Certificate I in Business... 3 BSB20107 Certificate II in Business... 4 BSB30107 Certificate III in Business...
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
ELECTRONIC DOCUMENT & RECORDS MANAGEMENT
ELECTRONIC DOCUMENT & RECORDS MANAGEMENT Administration Policy Shared Services 2012 Outline Background What is? Implementation Strategies Implementation Approach Change Management Approach Expected infrastructure
Domain 1 The Process of Auditing Information Systems
Certified Information Systems Auditor (CISA ) Certification Course Description Our 5-day ISACA Certified Information Systems Auditor (CISA) training course equips information professionals with the knowledge
TERRITORY RECORDS OFFICE BUSINESS SYSTEMS AND DIGITAL RECORDKEEPING FUNCTIONALITY ASSESSMENT TOOL
TERRITORY RECORDS OFFICE BUSINESS SYSTEMS AND DIGITAL RECORDKEEPING FUNCTIONALITY ASSESSMENT TOOL INTRODUCTION WHAT IS A RECORD? AS ISO 15489-2002 Records Management defines a record as information created,
Image Gateway for Apeos 2.0
IGA2.0 Image Gateway for Apeos 2.0 Business Process Solutions Business Process Optimisation Versatility of the multi-function device (MFD) is an often-touted benefit by all the major office equipment manufacturers,
How To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
Functional Area 3. Skill Level 301: Applications Systems Analysis and Programming Supervisor (Mercer 1998 Job 011)
Functional Area 3 Skill Level 301: Applications Systems Analysis and Programming Supervisor (Mercer 1998 Job 011) Description: Supervises activities of all applications systems analysis and programming
Queensland recordkeeping metadata standard and guideline
Queensland recordkeeping metadata standard and guideline June 2012 Version 1.1 Queensland State Archives Department of Science, Information Technology, Innovation and the Arts Document details Security
State Records Guideline No 25. Managing Information Risk
State Records Guideline No 25 Managing Information Risk Table of Contents 1 Introduction... 4 1.1 Purpose... 4 1.2 Authority... 4 2 Risk Management and Information... 5 2.1 Overview... 5 2.2 Risk management...
Second Clinical Safety Review of the Personally Controlled Electronic Health Record (PCEHR) June 2013
Second Clinical Safety Review of the Personally Controlled Electronic Health Record (PCEHR) June 2013 Undertaken by KPMG on behalf of Australian Commission on Safety and Quality in Health Care Contents
Software Configuration Management Plan
For Database Applications Document ID: Version: 2.0c Planning Installation & Acceptance Integration & Test Requirements Definition Design Development 1 / 22 Copyright 2000-2005 Digital Publications LLC.
Project Charter and Scope Statement
Prepared by: Mike Schmidt Version: 1.0 Last Revision Date: April 14, 2010 Create Date: May 6, 2010 EXECUTIVE SUMMARY... 3 1 INTRODUCTION... 4 2 PROJECT OBJECTIVES... 4 2.1 MISSION... 4 2.2 OBJECTIVES...
Department of Finance and Deregulation 2011/004 Portfolio Panels for IT Services ATTACHMENT A
2011/004 Portfolio Panels for IT Services Definition of IT Services The definition for IT Services supports the Portfolio Panel Policy and reflects the Victorian eservices model. Key Service Category Management
An ITIL Perspective for Storage Resource Management
An ITIL Perspective for Storage Resource Management BJ Klingenberg, IBM Greg Van Hise, IBM Abstract Providing an ITIL perspective to storage resource management supports the consistent integration of storage
Retained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
Information Management Policy
Title Information Management Policy Document ID Director Mark Reynolds Status FINAL Owner Neil McCrirrick Version 1.0 Author Deborah Raven Version Date 26 January 2011 Information Management Policy Crown
HealthConnect Tasmania Program Plan 2006-07
HealthConnect Tasmania Program Plan 2006-07 Department of Health and Ageing Department of Health and Human Services Version 1.a (September 2006) Acknowledgements The HealthConnect Program Management methodology
9. GOVERNANCE. Policy 9.8 RECORDS MANAGEMENT POLICY. Version 4
9. GOVERNANCE Policy 9.8 RECORDS MANAGEMENT POLICY Version 4 9. GOVERNANCE 9.8 RECORDS MANAGEMENT POLICY OBJECTIVES: To establish the framework for, and accountabilities of, Lithgow City Council s Records
Brown County Information Technology Aberdeen, SD. Request for Proposals For Document Management Solution. Proposals Deadline: Submit proposals to:
Brown County Information Technology Aberdeen, SD Request for Proposals For Document Management Solution Proposals Deadline: 9:10am, January 12, 2016 Submit proposals to: Brown County Auditor 25 Market
Project Management Fact Sheet:
Project Management Fact Sheet: Document Control Version: 1.3, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It follows that this
PHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
Transition Guidelines: Managing legacy data and information. November 2013 v.1.0
Transition Guidelines: Managing legacy data and information November 2013 v.1.0 Document Control Document history Date Version No. Description Author October 2013 November 2013 0.1 Draft Department of
Bring Your Own Device (BYOD) Policy
Bring Your Own Device (BYOD) Policy Version: 1.0 Last Amendment: N/A Approved by: Executive Committee Policy owner/sponsor: Director, Digital Library Services and CIO Policy Contact Officer: Manager, ICT
Information Management Advice 18 - Managing records in business systems: Overview
Information Management Advice 18 - Managing records in business systems: Overview Introduction The purpose of this Advice is to assist agencies to identify and manage State records in business systems,
Request for Proposal. Supporting Document 3 of 4. Contract and Relationship Management for the Education Service Payroll
Request for Proposal Supporting Document 3 of 4 Contract and Relationship December 2007 Table of Contents 1 Introduction 3 2 Governance 4 2.1 Education Governance Board 4 2.2 Education Capability Board
Role Description Curator - Digital Assets
Role Description Curator - Digital Assets Cluster Agency Division/Branch/Unit Location Department of Planning & Environment Sydney Living Museums Collections & Access The Mint Classification/Grade/Band
ICT (INFORMATION AND COMMUNICATION TECHNOLOGY) HELP DESK SUPPORT OFFICER
ICT (INFORMATION AND COMMUNICATION TECHNOLOGY) HELP DESK SUPPORT OFFICER The ICT Help Desk Support Officer is the first point of contact for all ICT Support and utilises their knowledge, training and skills
Digital Continuity in ICT Services Procurement and Contract Management
Digital Continuity in ICT Services Procurement and Contract Management This guidance relates to: Stage 1: Plan for action Stage 2: Define your digital continuity requirements Stage 3: Assess and manage
PROJECT DELIVERY METHODOLOGY (PDM) Florida Department of Transportation Office of Information Systems. Business Systems Support Office
2013 Florida Department of Transportation Office of Information Systems Business Systems Support Office Version 1.6 : 5/17/2013 PROJECT DELIVERY METHODOLOGY (PDM) Index May 17, 2013 1 CHAPTER 1 INTRODUCTION
PHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
Information Management Advice 20 Managing Change in EDRMS implementation projects
Information Management Advice 20 Managing Change in EDRMS implementation projects Introduction Archival authorities around the country have commenced the introduction of deadlines on the acceptance of
REVIEWED ICT CHANGE MANAGEMENT POLICY
LI_M_POPO PROVINCIAL GOVERNMENT ~EP.j8L-C OF SO;_;-H.'\FR1C.... DEPARTMENT OF CO-OPERATIVE GOVERNANCE. HUMAN SETTLEMENTS & TRADITIONAL AFFAIRS REVIEWED ICT CHANGE MANAGEMENT POLICY Version: 2 Table of
Contract Management Guideline
www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract
PHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
Software Asset Management (SAM) and ITIL Service Management - together driving efficiency
Software Asset Management (SAM) and ITIL Service Management - together driving efficiency Ian Preskett MIET C.Eng. MBCS CITP Software Asset Management Consultant [email protected] Agenda
Resource Management. Determining and managing the people resources on projects can be complex as:
Baseline Resource Management RESOURCE MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project people resources. Overview This Phase is used to establish
Records Management Policy
Records Management Policy Responsible Officer Chief Operating Officer Approved by Vice-Chancellor Approved and commenced April, 2014 Review by April, 2017 Relevant Legislation, Ordinance, Rule and/or Governance
Project Charter Updated
Enterprise IT Service Management Pilot Proof of Concept Project Charter Updated Prepared By: M. Riley & J. Foster Date of Publication: March 13, 2006 Date Last Revised: April 25, 2007 PMO CH1, 8/01 Document
Project Assessment Framework Establish service capability
Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.
ITIL 2011 Lifecycle Roles and Responsibilities UXC Consulting
ITIL 2011 Lifecycle Roles and Responsibilities UXC Consulting Date November 2011 Company UXC Consulting Version Version 1.5 Contact [email protected] http://www.uxcconsulting.com.au This summary
White Paper November 2006. BMC Best Practice Process Flows for Asset Management and ITIL Configuration Management
White Paper November 2006 BMC Best Practice Process Flows for Asset and ITIL Configuration Copyright 2006 BMC Software, Inc. All rights reserved. BMC, the BMC logo, all other BMC product or service names,
Records Management Policy
Records Management Policy Document Number SOP2006-073 File No. 07/7 Date issued 1 September 2006 Author Branch Records and Mail Services Unit Branch contact 9320.7722 Division Finance & Data Services Summary
Company A Project Plan
Company A Project Plan Project Name: Close Optimization Project Example Prepared By: David Done - Project Manager Title: John Doe -Project Manager Date: March 17, 2011 Project Plan Approval Signatures
Network Rail Infrastructure Projects Joint Relationship Management Plan
Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf
Statement of Work. Systems Center Configuration Manager. Prepared for School Board of Sarasota County Thursday, 12 June 2008 Version 1.3.
Statement of Work Systems Center Configuration Manager Prepared for School Board of Sarasota County Thursday, 12 June 2008 Version 1.3.1 Released Prepared by Dom Vila Program Manager [email protected]
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
How To Write An Slcm Project Plan
SLCM 2003.1 Artifacts in a Nutshell ( as of 01/21/2005) Project Development Phases Pension Benefit Guaranty Corporation s (PBGC) System Life Cycle Methodology (SLCM) is comprised of five project development
NSW Data & Information Custodianship Policy. June 2013 v1.0
NSW Data & Information Custodianship Policy June 2013 v1.0 CONTENTS 1. PURPOSE... 4 2. INTRODUCTION... 4 2.1 Information Management Framework... 4 2.2 Data and information custodianship... 4 2.3 Terms...
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Procedure. Work Health and Safety Contractor Management. Document number: PRO-00808. Rev no. Description Process Owner Approved for issue
Procedure Work Health and Safety Contractor Management Document number: PRO-00808 This document is the property of Seqwater. It must not be copied or reproduced in any way whatsoever without the authority
Validating Enterprise Systems: A Practical Guide
Table of Contents Validating Enterprise Systems: A Practical Guide Foreword 1 Introduction The Need for Guidance on Compliant Enterprise Systems What is an Enterprise System The Need to Validate Enterprise
information Records Management Checklist business people security preservation accountability Foreword Introduction Purpose of the checklist
Records Management Checklist Foreword We fi rst developed the Records Management Checklist in 2008 to complement our performance audit Records Management in the Victorian Public Sector. At that time the
ICTSUS4183A Install and test renewable energy system for ICT networks
ICTSUS4183A Install and test renewable energy system for ICT networks Release: 1 ICTSUS4183A Install and test renewable energy system for ICT networks Modification History Not Applicable Unit Descriptor
Records Management Checklist. preservation. accountability. information. security. peoplep. A tool to improve records management
Records Management Checklist preservation accountability information security busine ess peoplep A tool to improve records management preservation people security business Foreword accountability information
The position reports directly to the Diversification Program Manager and indirectly to the Program Management Office (PMO)
Position Description Employee: Position title: Location: Grade: Organisation: Project Manager Diversification Head Office Management The position reports directly to the Diversification Program Manager
Islamic Relief Worldwide ICT Desktop Support Technician
Islamic Relief Worldwide ICT Desktop Support Technician BASE LOCATION: REPORTING TO: LINE MANAGEMENT RESPONSIBILITIES: Waterloo, London ICT Service Delivery None PURPOSE OF DIVISION: ICT is part of the
Records management in SharePoint 2010
Records management in SharePoint 2010 Implications and issues Crown copyright 2011 You may re-use this information (excluding logos) free of charge in any format or medium, under the terms of the Open
Enterprise File Service
` Service Definition Enterprise File Service Draft Version 1.6 Signoff: Name Role Signature & Date Mark Fortini Director, IT infrastructure Services Page 1 of 22 16/03/2011 Document Control Information
Recordkeeping for Good Governance Toolkit. GUIDELINE 14: Digital Recordkeeping Choosing the Best Strategy
Recordkeeping for Good Governance Toolkit GUIDELINE 14: Digital Recordkeeping Choosing the Best Strategy i The original version of this guideline was prepared by the Pacific Regional Branch of the International