1 Long Term Data Center Facilities Program ISAC Briefing August 22, 2012
2 Overview: The Long Term Data Center Facilities Program is an initiative of the approved data center strategic plan to consolidate Citizens data center operations into a purposed and protected environment. Success of this Program will ensure the long term survivability and sustainability of Citizens Data Center environments. To achieve the needed improvements, this plan has identified objectives and roadmaps to facilitate optimization of Data Center processes and reduce risk to core operative qualities (Protected, Secure, Redundant, Connected, Purposed, and Managed) of Data Center operations, while also decoupling these facilities from Citizens General Office Space facilities. Status Significant progress has been made since last report. Additional phase and stage definition has been applied to the program activity. Phase 1 Program Management (Oversight, Procurements and Special Projects) The program team is preparing for the second 2012 Bi-Annual conformance review of the approved Data Center Strategy and Program in October. Program management team is currently revising resource projections for 2013 and updating program control documents (Financials, Schedule, Risk) for Q4 steering review. Phase 2 - Data Center Provisioning (New Collocation Data Center site and Existing Disaster Recovery site) The majority of IT hardware infrastructure approved at April BOG has been procured and received into storage. The implementation vendors are being scheduled to begin hardware assembly and configuration in September, once the new data center environment has been constructed. The new data center environment is on plan to be released to Citizens on October 1 st. Construction of Wide Area and Point to Point data network services into the data center environments is underway. Services are being procured and coordinated through the State Department of Management Services (DMS), My Florida Network (MFN). Phase 3 - Data Center Migration Migration project management team is in full swing compiling asset and application data into a master scope record, for use by planning teams in September. Master scoping database is being coordinated with IT and organizational projects, for intersections which may cause changes to migration strategy or scope. Migration PM team to have benchmarks completed by end of August. Migration PM team is working with CSX (Collocation data center vendor) to engage migration planning resources for stage 2 planning activities. Engagement proposal and BOG Action Item is being presented at the August ISAC. Phase 4 - Data Center Decommission No additional activity for this period at this time. Status Overview 2
3 Financial Overview LTDCF Financial Summary Current Budget Value Approved $ 6,000,000 Net Additions from Consent 0 Actual Spend from Consent $ 1,650,558 Pending Spend from Consent $ 1,024,262 Remaining Budget for Allocation $ 3,325,180 Program remains on target to complete within the original $6M budget allocation for consented migration management services. Program has been utilizing 100% State of Florida (and government) contracts for services procured. Percent Budget Allocated 45% Percent Budget Remaining 55% Distribution by Program Phase Distribution by Procurement Type 11% 4% Phase 1 - Program Management / 0% Admin 19% 24% Phase 2 - DC Build (Provisioning) Phase 3 - DC Migration 0% STC / GSA Staff Aug Phase 4 - DC Decommission Phase 5 - CMDB 26% 55% CPIC Contract DMS 61% 3
4 Program Overview 4
5 Program Overview Phase Activity Strategic Plan Ongoing Bi-Annual Review Program Management PH1 Program Planning Program Oversight Data Center Provisioning PH2 Collocation Data Center (Procurement) Collocation Infrastructure (Procurement) Collocation / DR Build-Test-Commission Data Center Migration PH3 Migration PM (Procurement) Migration Planning Migration Execution Transformation Data Center Decommission PH4 Site 1 (Tallahassee Monroe) Site 2 (Jacksonville CAT) Site 3 (Jacksonville Corp) Site 4 (Tallahassee CC). Timed with Dependency Projects and Property lease activity.. Timed with Dependency Projects. 5
6 Project Overview Phase Jun Jul Aug Sep Oct Nov Dec Activity Status Data Center Provisioning P2 Collocation Data Center (Procurement) Pre-Engagement Vendor Coordination Collocation Data Floor Build Collocation / DR Infrastructure Build IT Infrastructure Systems Build IT Infrastructure Circuitry Build IT Infrastructure Systems Test Data Center Migration P3, Stg2 Migration Resource Procurement Pre-Engagement Resource Coordination Discovery Assessment Sequencing & Risk ( ) Migration Options Review & Strategy (2013) 6
7 Strategic Objectives Strategy Overview Reduce facility risks by providing a Protected environment with the Redundancy required by Citizens. Reduce operation and logistical risk with Managed facility support for Citizens production Data Center operations. Provide a scalable Data Center to enable appropriate sizing of resources for core business system services. Improve Security by enhanced use of remote management tools and off-site administration. Improve flexibility for future changes in Connectivity and changing bandwidth requirements. Realign operational expenses for Data Centers to appropriate Purpose built facilities. Reduce annual expenditure on maintenance and operation of facilities. Reduce dependency on non-data Center staff needed to support Data Center operations. Reduce management risk required for decentralized site logistics. LTDCF Objectives 1. Consolidate the current production IT and SLDC environments into a single, protected data center. 2. Re-align the IT operative culture to support a remote managed Data Center business model. 3. migration activities in alignment with planned technology refreshments, architectural improvements, and required business drivers; without incurring unaccepted risk or service disruptions. 4. Decommission migrated Data Center spaces and services from the general office facilities. 7
8 Strategy Overview We are here. 8
Long Term Data Center Facilities Program
Long Term Data Center Facilities Program ISAC Briefing December 2012 Overview: The Long Term Data Center Facilities Program is an initiative of the approved data center strategic plan to consolidate Citizens
More informationHow To Manage A Data Center
Long Term Data Center Facilities Program ISAC Briefing Second Quarter 2014 (5/28/2014) Status Overview Overview: The Long Term Data Center Facilities Program is an initiative of the approved data center
More informationLong Term Data Center Facilities Program
Long Term Data Center Facilities Program ISAC Briefing February 8, 2012 Status Overview Overview: The Long Term Data Center Facilities Program is an initiative of the approved data center strategic plan
More informationProposal: Long Term Data Center Briefing Presentation. Information System Advisory Committee May 24, 2012
Proposal: Long Term Data Center Briefing Presentation Information System Advisory Committee May 24, 2012 Data Center Strategic Roadmap Goal Provide functional data center facilities for Citizens which
More informationIT Disaster Recovery Services Program
Summary Overview of 2016-2018 Program v.20160526 IT Disaster Recovery Strategy Implementation 2008 Data Center Strategic Plan Part 1 Part 2 Disaster Recovery Strategic Plan Part 1 Part 2 2016 2019 Implementation
More informationCommittee of the Whole. January 22, 2014
Committee of the Whole January 22, 2014 Drivers for 2003 IT Outsourcing Cost savings - privatization model ($2- $3MM/year) Cost avoidance Data center lease with County expiring ($3.5MM) Disaster recovery
More informationAT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationThe proposed Project Phase work II is expected to be completed in July of 2008
REPORT TO THE CITY COUNCIL AGENDA ITEM NO. August 22, 2007 COUNCIL MEETING APPROVED BY FROM: BRUCE A. RUDD, Assistant City Manager DEPARTMENT DIRECTOR CITY MANAGER SUBJECT: ISD Network Migration Project
More informationINFORMATION TECHNOLOGY: Opportunities Exist to Improve Services, Economies, and Contract Performance
INFORMATION TECHNOLOGY: Opportunities Exist to Improve Services, Economies, and Contract Performance Report No. OIG-A-2013-013 April 16, 2013 NATIONAL RAILROAD PASSENGER CORPORATION Memorandum To: From:
More informationERP Briefing. Cook County Government. Bureau of Finance Enterprise Resource Planning Center of Excellence. August 19, 2014
Cook County Government Bureau of Finance Enterprise Resource Planning Center of Excellence ERP Briefing August 19, 2014 DISCLAIMER: This presentation is thought to be accurate on the date it is posted,
More informationCase 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
More informationBest Practices for Consolidation Projects
Best Practices for Consolidation Projects Lynne Glickman Solution Architect Hewlett-Packard 2004 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without
More informationFrom Virtualized to ITaaS. Copyright 2011 EMC Corporation. All rights reserved.
From Virtualized to ITaaS 1 Priority Discussion Topics Laying the foundation for IT-as-a- with the right architecture Key process areas and capabilities that need to be rethought during the process (ie.
More informationDEPARTMENT OF FIRE AND POLICE PENSIONS 360 East Second Street, Suite 400 Los Angeles, CA 90012 (213) 978-4545
DEPARTMENT OF FIRE AND POLICE PENSIONS 360 East Second Street, Suite 400 Los Angeles, CA 90012 (213) 978-4545 REPORT TO THE BOARD OF FIRE AND POLICE PENSION COMMISSIONERS APRIL 4, 2013 ITEM: A.8 FROM:
More informationComputing & Telecommunications Services Monthly Report March 2015
March 215 Monthly Report Computing & Telecommunications Services Monthly Report March 215 CaTS Help Desk (937) 775-4827 1-888-775-4827 25 Library Annex helpdesk@wright.edu www.wright.edu/cats/ Last Modified
More informationEnhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
More informationSchools Interoperability Framework (SIF) Project Overview
Schools Interoperability Framework (SIF) Project Overview Agenda Introductions Quick review of past successes and challenges Overview of refined strategy Timeline Questions and answers 2 Review of Past
More informationWhich Way Now: Does your organisation have an Oracle ERP roadmap? Dave Baines, ERP Specialist, Version 1
Which Way Now: Does your organisation have an Oracle ERP roadmap? Dave Baines, ERP Specialist, Version 1 Oracle ERP Webinar Series 1 2 Digitally Transform Oracle ERP 24th February 12:30pm Download Slides
More informationDEPARTMENT AGENCY STATEMENT OF OBJECTIVES FOR CLOUD MIGRATION SERVICES: INVENTORY, APPLICATION MAPPING, AND MIGRATION PLANNING MONTH YYYY TEMPLATE
DEPARTMENT AGENCY STATEMENT OF OBJECTIVES FOR CLOUD MIGRATION SERVICES: INVENTORY, APPLICATION MAPPING, AND MIGRATION PLANNING MONTH YYYY TEMPLATE 1 Introduction and Instructions This sample Statement
More informationExam Name: Certified Information Security Manager
Vendor: Isaca Exam Code: CISM Exam Name: Certified Information Security Manager Version: DEMO QUESTION 1 Senior management commitment and support for information security will BEST be attained by an information
More informationServer Consolidation & Virtualization Category Improving State Operations
Server Consolidation & Virtualization Category Improving State Operations State of Illinois Central Management Services Bureau of Communication & Computer Services 120 W. Jefferson Springfield, IL 62702-5172
More informationInformation Technology Master Plan Update: IMTech February 28, 2011
Information Technology Master Plan Update: IMTech February 28, 2011 Information Technology Master Plan Update: Agenda Background City of Georgetown s Vision Technology Transformation Approach Assessment
More informationAgenda and Materials Dec 11, 2012. ITS Executive Steering Committee (ITESC)
Agenda and Materials Dec 11, 2012 ITS Executive Steering Committee (ITESC) 1 2 Agenda Academic Technology Committee Update C. Scheidenhelm, B. Montes Sakai Migration Plans C. Scheidenhelm, B. Montes Disaster
More informationCity of Minneapolis RCA Provision of IT Services. Committee of the Whole February 11, 2015
City of Minneapolis RCA Provision of IT Services Committee of the Whole February 11, 2015 Background IT Services contract with Unisys signed 12/2002 Unisys contract renegotiated in 2007 Reduced cost, added
More informationCouncil, 6 February 2014. IT Report. Executive summary and recommendations. Introduction
Council, 6 February 2014 IT Report Executive summary and recommendations Introduction The report sets out the main activities of the IT Department since the last meeting of Council. It includes statistical
More informationSolutions White Paper. Using Storage Virtualization. to Meet the Challenges of Rapid Data Growth
Solutions White Paper Using Storage Virtualization to Meet the Challenges of Rapid Data Growth C GTSI Solutions / White Paper / Storage Economics GTSI s Data Management Solution Powered by Hitachi Data
More informationAccenture Cyber Security Transformation. October 2015
Accenture Cyber Security Transformation October 2015 Today s Presenter Antti Ropponen, Nordic Cyber Defense Domain Lead Accenture Nordics Antti is a leading consultant in Accenture's security consulting
More informationExecutive Branch IT Reorganization Project Plan
Office of Information Resource Management Executive Branch Project Plan Work Program Funded by for IT Appropriations Reorganization 2007, 2009 and Five Small Projects Date: August 2009 Version: 1.3 Revision
More informationSUMMARY MINUTES OF THE INFORMATION SYSTEMS ADVISORY COMMITTEE MEETING Friday, September 12, 2014
CITIZENS PROPERTY INSURANCE CORPORATION SUMMARY MINUTES OF THE INFORMATION SYSTEMS ADVISORY COMMITTEE MEETING Friday, The Information Systems Advisory Committee (ISAC) of Citizens Property Insurance Corporation
More informationPreparing Your Business for Magento 2.0
Preparing Your Business for Magento 2.0 William Harvey Director of Business Operations Magento Commerce How is Magento 2.0 different than 1.x? How is Magento 2.0 different than 1.x? New architecture Out-of-the-box
More informationDatacenter Migration Think, Plan, Execute
Datacenter Migration Think, Plan, Execute Datacenter migration is often regarded as a purely technical, almost trivial side-project, to be delivered by existing IT staff alongside their day jobs. With
More informationDetailed guidance for employers
April 2015 3 Detailed guidance for employers Appendix A: Pay reference periods This document accompanies: Detailed guidance no. 3 Assessing the workforce Pay reference period calendars where the definition
More informationCloud Computing. What Are We Handing Over? Ganesh Shankar Advanced IT Core Pervasive Technology Institute
Cloud Computing What Are We Handing Over? Ganesh Shankar Advanced IT Core Pervasive Technology Institute Why is the Cloud Relevant to In the current research workflow. Medical Research? Data volumes are
More informationInsurance and Banking Subcommittee
Insurance and Banking Subcommittee Citizens Depopulation Update September 16, 2015 Christine Ashburn VP Communications, Legislative and External Affairs 2 3 Depopulation Customer Communications 1. 40 days
More informationFederal Data Center Consolidation Initiative (FDCCI)
Federal Data Center Consolidation Initiative (FDCCI) Final Data Center Consolidation Plan U. S. Office of Personnel Management Office of the Chief Information Officer Update 9/30/2011 1 Introduction...
More informationHow To Be Successful At Workday
VMware Global HR Application in the Cloud March 2012 VMware HR System Replacement: Key Drivers for Change HR systems footprint was not optimized or scalable to support VMware s growth. Original core HR
More informationEnterprise Projects Fiscal Year 2011/2012 Third Quarter Report
Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance
More informationOPERATIONS SERVICE UPDATE
OPERATIONS SERVICE UPDATE EXECUTIVE SUMMARY Policy Processing At the June 24 Citizens Board of Governors meeting, Staff committed to achieving year end policy processing service goals by September 1, 24.
More informationHHS Data Center Consolidation Plan
1 Introduction The Department of Health and Human Services () is comprised of 11 Operating Divisions (OPDIVs), each with distinct missions and each with Information Technology management organizations.
More informationFlorida s Private Rebuilt Vehicle Inspection Program. Pilot Program Report January 30, 2015. Terry L. Rhodes, Executive Director
Florida s Private Rebuilt Vehicle Inspection Program Pilot Program Report January 30, 2015 Terry L. Rhodes, Executive Director Florida s Private Rebuilt Vehicle Inspection Program Pilot Program Report
More informationCABINET 9 th February 2006. Report of the Director of Partnerships and Customer Services
CABINET 9 th February 2006 Report of the Director of Partnerships and Customer Services ITEM 11 CRM DEVELOPMENT Purpose of the Report To seek approval to the replacement for the Council s Customer Relationship
More informationInformation Technology Strategic Plan
Information Technology Strategic Plan IT Strategic Plan Benefits Establishes strategic IT goals, assures corporate alignment Benefits of executive/it engagement in plan development Sets an agreed vision
More informationImportant Dates Calendar 2014-2015 FALL
Important Dates Calendar 204-205 FALL Rev. 6-8-4 st 8 H st 0 2nd 0 st 5 2nd 5 3rd 5 LSC Advanced Registration Begins May 27 May 27 May 27 May 27 May 27 May 27 May 27 May 27 May 27 Returning Students Advanced
More informationUniversity of Wisconsin System Strategic Initiatives
University of Wisconsin System Strategic Initiatives April 27,2015 Sasi K. Pillay UWSA CIO 1 Principles Mission Enablement Reduction of Risk Cost-effective Operations 2 The Four Tenets A. Elevate the Professionalism
More informationApplication Performance Monitoring/Management (APM) Request for Information (RFI) 28198-CH
Application Performance Monitoring/Management (APM) Request for Information (RFI) 28198-CH Issued: March 30, 2015 Responses Due: May 12, 2015 This is not a bid or proposal. This Request for Information
More informationMicrosoft Active Directory Project
Microsoft Active Directory Project Simcoe County District School Board Project Kick-off Meeting Rami Wehbe (Solution Architect) January 18, 2012 Agenda Introductions Project objectives and drivers Approach
More informationBoard Update. Performance Management Activities
Board Update Performance Management Activities May 2007 Purpose of Today s Meeting Update Board Members Share Scope, Plans & Results» Benchmarking & Performance Improvement» Compliance Activities 1 Chugach
More informationInformation Technology Master Plan. Information Technology Master Plan
Passion for Improving Performance Information Technology Master Plan Update: GGAF Subcommittee February 8, 2010 Information Technology Master Plan Update: Agenda Background City s Vision Master Plan Assessment
More informationData Consolidation and Application Optimization (DCAO) Organization
Data Consolidation and Application Optimization (DCAO) Organization 11 February 2015 Presented to: DON CIO IT Conference San Diego Convention Center Mr. John Pope DCAO Director Space and Naval Warfare
More informationDisaster Recovery & Business Continuity Dell IT Executive Learning Series
Disaster Recovery & Business Continuity Dell IT Executive Learning Series Presented by Rich Armour, Debi Higdon & Mitchell McGovern THIS PRESENTATION SUMMARY IS FOR INFORMATIONAL PURPOSES ONLY AND MAY
More informationCase Study U.S. Health System
Case Study U.S. Health System As with any major enterprise project, the organization must prepare its desktop environment and enterprise infrastructure to support the new application requirements. Bob
More informationManaging Cloud Infrastructure
Managing Cloud Infrastructure The Key to deliver IT as a Service Eitan Segal Technology Consultant 1 Managing Cloud Infrastructure The Key to Deliver IT as a Service Eitan Segal Technology Consultant 2
More informationData Center Optimization: California s Blueprint for Success
2011 NASCIO RECOGNITION AWARD NOMINATION Nomination Category: Enterprise IT Management Initiatives Data Center Optimization: California s Blueprint for Success California Technology Agency Office of Technology
More informationHow Cisco IT Plans and Executes a Large-Scale Data Center Application Migration
Cisco IT Case Study Januar 2012 Planning a Large-Scale Application Migration How Cisco IT Plans and Executes a Large-Scale Data Center Application Migration Moving applications and services between data
More informationAshley Institute of Training Schedule of VET Tuition Fees 2015
Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-
More informationCounty of Orange ~ Information Technology Quarterly IT Project Status Detail Report Fiscal Year 2014-15, 1st Quarter
County of Orange ~ Information Technology Quarterly IT Project Detail Report Fiscal Year 2014-15, 1st Quarter Executive Summary The Quarterly IT Project Detail report provides an inventory of all County
More informationRelease of the Draft Cybersecurity Procurement Language for Energy Delivery Systems
Release of the Draft Cybersecurity Procurement Language for Energy Delivery Systems Energy Sector Control Systems Working Group Supporting the Electricity Sector Coordinating Council, Oil & Natural Gas
More informationBlackboard Collaborate Web Conferencing Hosted Environment Technical Infrastructure and Security
Overview Blackboard Collaborate Web Conferencing Hosted Environment Technical Infrastructure and Security Blackboard Collaborate web conferencing is available in a hosted environment and this document
More informationEDMS Project Stage 1 Business Plan
EDMS Stage 1 Business Plan Corporate Information Support Branch DEPARTMENT OF TREASURY AND FINANCE Version 0.F (16 May 2005) TRIM Reference Number: 08/21227 (PM 001 Version 2.0 September 2002) Acknowledgements
More information20462 - Administering Microsoft SQL Server Databases
20462 - Administering Microsoft SQL Server Databases Duration: 5 Days Course Price: $2,975 Software Assurance Eligible Course Description Note: This course is designed for customers who are interested
More informationData Center Build vs. Buy
2014 Data Center Build vs. Buy More information available on our website: /page/whitepapers Data Center Build vs. Buy 2014 When considering colocating your data center, first you must understand your technical
More informationGTA Board of Directors September 4, 2014
GTA Board of Directors September 4, 2014 Our Strategic Vision Our Mission A transparent, integrated enterprise where technology decisions are made with the citizen in mind To provide technology leadership
More informationHow To Save Money On A Data Center
Federal Data Center Consolidation Initiative Data Center Consolidation Plan for the U.S. Small Business Administration Maintained by: The Office of the Chief Information Officer Paul Christy, CIO Revised:
More informationRequest for Quote HIPAA Security Risk Analysis
Request for Quote Security Risk Analysis 4/26/13 Florida Department of Children and Families Purpose The Florida Department of Children and Families (DCF or the Department) is looking for a qualified information
More informationCOMMUNIQUE. Information Technology (IT) Governance Guidance
COMMUNIQUE 14-COM-002 July 14, 2014 Information Technology (IT) Governance Guidance The Credit Union Prudential Supervisors Association (CUPSA) has established an IT Risk Working Group to focus on IT governance
More informationDRAFT Disaster Recovery Policy Template
DRAFT Disaster Recovery Policy Template NOTE: This is a boiler plate template much information is needed from to finalizeconsider this document pre-draft FOREWARD... 3 Policy Overview...
More informationEMR UPDATE ON TIME AND ON BUDGET CLINICAL TRANSFORMATION IMPLEMENTATION PLAN
EMR UPDATE ON TIME AND ON BUDGET CLINICAL TRANSFORMATION IMPLEMENTATION PLAN Testing and Build Stability View Only Scanning Interfaces Training Innovative Technology EMR UPDATE COMMUNICATION PLAN Essential
More informationStorm Clouds Ahead? A risk analysis of Cloud Computing
Storm Clouds Ahead? A risk analysis of Cloud Computing Andy Bolton Chief Executive Officer, Capacitas Abstract Many organisations are now considering using 'Cloud Computing' offerings to meet their scalability
More information20415 - Implementing a Desktop Infrastructure
20415 - Implementing a Desktop Infrastructure Duration: 5 days Course Price: $2,975 Software Assurance Eligible Course Description Course Overview This 5-day instructor-led training course provides you
More informationPTC Creo 2.0 Hardware Support Dell
PTC Creo 2.0 Hardware Support Dell Last updated: February 2, 2016 The Desktop Virtualization Environment Support Dell table displays at the end of this document, after the standard Creo certification table.
More informationAgriLife Information Technology IT General Session January 2010
AgriLife Information Technology IT General Session January 2010 Agenda Topics Year in Review Enterprise IT Services Update FirstCall Overview and Next Steps Sophos Antivirus Initiative Update Information/
More informationMaster Data Management Enterprise Architecture IT Strategy and Governance
? Master Data Management Enterprise Architecture IT Strategy and Governance Intertwining three strategic fields of Information Technology, We help you Get the best out of IT Master Data Management MDM
More informationNorth Carolina's Information Technology Consolidation Audit
STATE OF NORTH CAROLINA PERFORMANCE AUDIT INFORMATION TECHNOLOGY CONSOLIDATION JANUARY 2013 OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA STATE AUDITOR PERFORMANCE AUDIT INFORMATION TECHNOLOGY CONSOLIDATION
More informationPublic Sector Chief Information Officer Council
Report to Public Sector Chief Information Officer Council White Paper on a Pan Canadian Opportunities for Collaboration Project Goal Two Report: Outline and Approach Draft v1.0 Submitted by: Stuart Culbertson
More informationOhio Supercomputer Center
Ohio Supercomputer Center IT Business Continuity Planning No: Effective: OSC-13 06/02/2009 Issued By: Kevin Wohlever Director of Supercomputer Operations Published By: Ohio Supercomputer Center Original
More informationpavcloud PaaS IaaS VaaS DCaaS For orders and information call 01273 834 000 or email: info@pav.co.uk FEATURES: BENEFITS: DCaaS VaaS IaaS PaaS
Factsheet : pavcloud For orders and information With increased focus on maximising the financial resources of your IT department along with improving service agility, flexibility and availability, many
More informationW H I T E P A P E R. Reducing Server Total Cost of Ownership with VMware Virtualization Software
W H I T E P A P E R Reducing Server Total Cost of Ownership with VMware Virtualization Software Table of Contents Executive Summary............................................................ 3 Why is
More informationDESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE
SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Executive Summary The project will document campus requirements for IAM functionality and select and procure one or more technology
More informationMigration and Building of Data Centers in IBM SoftLayer with the RackWare Management Module
Migration and Building of Data Centers in IBM SoftLayer with the RackWare Management Module June, 2015 WHITE PAPER Contents Advantages of IBM SoftLayer and RackWare Together... 4 Relationship between
More informationBusiness Idea Development Product production Services. Development Project. Software project management
Page 1, 1/20/2003 Ivica Crnkovic Mälardalen University Department of Computer Engineering ivica.crnkovic@mdh.se Development Project Product Lifecycle Business Idea Development Product production Services
More informationCommonwealth of Massachusetts. Weekly Infrastructure Planning Status Update. September 15, 2009 DRAFT FOR DISCUSSION PURPOSES ONLY
Commonwealth of Massachusetts Statewide Strategic IT Consolidation (ITC) Initiative Weekly Infrastructure Planning Status Update Deloitte Consulting LLP September 15, 2009 DRAFT FOR DISCUSSION PURPOSES
More informationServer Consolidation. Report to the Joint Legislative Oversight Committee on Information Technology
Server Consolidation Report to the Joint Legislative Oversight Committee on Information Technology Chris Estes State Chief Information Officer December 2013 This page left blank intentionally Contents
More informationData Center Consolidation: Lessons From The Field. John Tsiofas, Kraft Kennedy David Carlson, Kraft Kennedy
Data Center Consolidation: Lessons From The Field John Tsiofas, Kraft Kennedy David Carlson, Kraft Kennedy Agenda Factors to consider Technology strategy Building a project team How to use vendors wisely
More informationFrom: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer Date: September
More informationThe Business Case For Private Cloud Services
Velocity Technology Solutions / May 015 This Private Cloud Services guide will: Define a common vocabulary around Private Cloud Service Providers Describe how Private Cloud Services can reduce the total
More informationImplementing Hybrid Cloud at Microsoft
Implementing Hybrid Cloud at Microsoft Published September 2013 The following content may no longer reflect Microsoft s current position or infrastructure. This content should be viewed as reference documentation
More informationAsset Management for the Public Sector with Total Accountability
Asset Management for the Public Sector with Total Accountability An asset is a tangible or intangible item of positive economic value which can be owned and managed, or controlled. Asset management (AM)
More informationCDL Warrior Truck Driver Communication & Safety (TDCS) System. May 12, 2015
CDL Warrior Truck Driver Communication & Safety (TDCS) System May 12, 2015 Background Estimated that 4,000 to 9,000 trucks used over the life of a well. This volume, combined with the remote location,
More informationTechnology. Accenture Data Center Services
Technology Accenture Data Center Services 2 Accenture employs marketleading technologies and processes to help clients design, implement and manage data center solutions that align to business priorities,
More informationAN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION
AN APPLICATION-CENTRIC APPROACH TO DATA CENTER MIGRATION Five key success factors Whether the decision to relocate or consolidate a data center is driven by cost pressure or the need for greater IT efficiency,
More informationIntroduction to Business Continuity Planning
Interested in learning more about security? SANS Institute InfoSec Reading Room This paper is from the SANS Institute Reading Room site. Reposting is not permitted without express written permission. Introduction
More informationBasic Project Management & Planning
Basic Project Management & Planning Dr. David K. Potter Director & Don Pether Chair in Engineering and Management em4a03@mcmaster.ca 1 What is Project Management? A set of principles, methods, tools, and
More informationEnterprise Technology, Office of. Projects Summary ($ in Thousands) 2010 Agency Priority
Projects Summary ($ in Thousands) Project Title 2010 Agency Priority Agency Project Request for State Funds ($ by Session) Governor s Recommendations Governor s Planning Estimate Ranking 2010 2012 2014
More information2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc
July 2015 CM Period 1501075 July 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 August 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
More informationOn Demand Cloud Services Value First
On Demand Cloud Value First Hardware, Software, and Engineered to Work Together John Barker Oracle On Demand john.barker@oracle.com 804-967-7228 Safe Harbor Statement The following
More informationData Center Consolidation Disaster Recovery Cloud Computing
Data Center Consolidation Disaster Recovery Cloud Computing Discussion and Overview September 9, 2010 John R. Savageau President Discussion Topics Develop a national data center consolidation and disaster
More informationOregon-Montana Disaster Recovery Phase 1 & 2
Oregon-Montana Disaster Recovery Phase 1 & 2 Oregon Department of Administrative Services Enterprise Technology Services http://www.oregon.gov/das/ets/pages/index.aspx Category: Disaster Recovery/Security
More informationRequest for Expressions of Interest On a contract to perform: Renewal of Information Technology Strategic Plan 2013-2018
Request for Expressions of Interest On a contract to perform: Renewal of Information Technology Strategic Plan 2013-2018 for City of Pitt Meadows Table of Contents Table of Contents... 2 General Information...
More information