1 2011 Office of Surface Mining, Reclamation, and Enforcement Abandoned Mine Land Reclamation Award Nomination Submitted April 19, 2011 Project Name: Project Location: Brookside/Spring Creek Park Reclamation Project Town of Brookside Fremont County, Colorado Submitted by: Colorado Division of Reclamation, Mining and Safety Inactive Mines Reclamation Program 1313 Sherman Street, Room 215 Denver, Colorado Bruce Stover, Program Director Julie Annear, Project Manager Project Details: Reclamation Construction Begun: June 23, 2009 Reclamation Construction Completed: April 6, 2011 Reclamation Construction Cost (OSMRE only): $76,734 Reclamation Construction Total Cost: $238,734 Parties Involved in Reclamation Process: Project Design, Bidding, Construction Management: Colorado Division of Reclamation, Mining and Safety - Inactive Mine Reclamation Program Project Partners: Office of Surface Mining, Reclamation, and Enforcement Town of Brookside McCollum Excavating Great Outdoors Colorado Colorado Division of Reclamation, Mining and Safety Colorado Correctional Industries Colorado Work Crew Cornell Youth Detention Center Cowboy Erosion Control Fremont Paving Mountain Masonry The Aggregate Source

2 Introduction The Spring Creek Park Project is located in the Town of Brookside south of Canon City, Colorado. The acre parcel was purchased by the Town of Brookside in 2006 with the intent of creating a park. The site was the previous location of the historic Brookside Mine and contained numerous coal waste piles as well as several abandoned mine openings. The park is a natural wildlife sanctuary as it is frequented by elk, deer, bear, fox, coyotes, and a variety of birds. The plant growth is predominately native species, well established, and suitable for wildlife observation. Spring Creek runs the length of the park, and is fed by springs from south of the area. The south park boundary lies high on the rocky bluffs, giving a panoramic view of the Sangre de Christo Mountain Range. The master plan for the park included preserving the native flora and the man-made remnants from the mining era, while constructing hiking paths that highlight its natural and historic attributes. The other goal of the project was to involve the community and create a space that would provide access to the natural environment for future generations. History The Town of Brookside, a small town located on the south side of Canon City, was founded in 1888 by the Canon City Coal Company as a community for the Italian miners and their families. Brookside became an incorporated town in 1913 and has persisted in keeping its own identity since then. Many of the descendents of the original mining families still live in the town today and can remember the mine when it was operating. The Brookside Mine was one of the largest mines in the town, and operated from the late 1800 s through Over 2,000,000 tons of coal was extracted from the site during its operation. Presently, the town is almost completely residential with a mix of small agricultural acreages containing orchards, vineyards, and small pastures. However, in the apex of the mining era, the town contained many bars, and perhaps a few brothels, since liquor was not allowed in nearby Canon City. The town was a favorite set for many silent movies and remained lively until it burned in the late 1800 s. The park still contains foundations of old mining buildings and coal waste piles that testify to its early coal-mining origins. After the coal mines were closed many sites still contained open mine features and barren land. The Brookside Mine contained numerous waste piles and abandoned mine features. Frequently, windblown dust emanating from the area created hazards to both people and livestock. Beer bottles and other debris indicate that the adits received frequent visitation. The unsightly barren areas also became a dumping ground for trash and other debris. In 2006 the Town of Brookside purchased the land containing the Brookside Mine with funds from a natural resource damage settlement. Prior to the purchase, the town approached the Colorado Division of Reclamation Mining and Safety (CDRMS), Inactive Mines Reclamation Program with a request to address the mining related problems on the site. Concurrently, the town solicited funds for the development of a park from the Department of Natural Resources, in the form of a Great Outdoors Colorado (GOCO) grant. Project Partnerships and Funding Due to the hazards related to legacy coal mining, the reclamation and cleanup of the Brookside/Spring Creek Park became a priority for the Colorado Division of Reclamation Mining and Safety (CDRMS), Inactive Mines Reclamation Program. In 2005, the project was funded by the annual Office of Surface Mining, Reclamation, and Enforcement (OSMRE) grant. 2

3 The town was also successful in procuring over $162,000 for park improvements from GOCO. The dual funding sources necessitated CDRMS and the Town of Brookside to develop an action plan for park development. CDRMS used OSMRE funds to reclaim the waste piles and safeguard open mine adits as well as provide help with project design, development, construction oversight, and postreclamation revegetation and monitoring. The Town of Brookside used GOCO funds to provide the park amenities and organized multiple volunteer groups to help with trail development and site cleanup. In addition, the Town of Brookside board members contributed countless volunteer hours to park development. The public ownership of the site and its proximity to local residents allowed CDRMS and the Town of Brookside to enlist the assistance, financial commitments, and cooperation of many partners to reclaim land that has become Brookside/Spring Creek Park. Partners included numerous local residents, Colorado Correctional Industries, multiple volunteer groups, college students and several local businesses. Reclamation Plan Using computer-aided design and topographic site surveys, a plan was developed to guide the park development. The plan s initial phase involved safeguarding abandoned mine adits. The next phase of the project involved site cleanup, regrading waste piles and application of topsoil. Finally, site improvements such as trails, a parking area, picnic shelter, toilet, picnic tables, and fencing were installed using a combination of GOCO and OSMRE funds. The trail routes were mapped by a Colorado State University engineering student planner after an on-site visit. The completed plan is attached. The three trails through the park provide slightly over a mile of walking. The three trail variations constructed are shown on the site map, and include the following: A level, easy, American Disability Act (ADA) accessible trail loop through the center of the park, six to eight feet wide; this loop of the trail also provides access for maintenance vehicles and fire trucks, if needed. A second trail of medium difficulty, four-foot wide, that climbs the hill on the west side of the park where preserved mining artifacts can be seen. A bench installed at the highest point of this trail, gives hikers a chance to stop and enjoy the view. A strenuous, three-foot wide trail will climb the bluffs at the south end of the park. Once constructed, it will feature a built-on-site bridge constructed primarily of wood. A revegetation plan was developed for the site by CDRMS environmental specialists. Following final grading of the cover soils, a custom seed mix was combined with Biosol to form a slurry which was sprayed over all disturbed areas. The site then received an application of hydro-mulch. 3

4 Easy trail ADA accessible Parking lot Medium trail Hard trail Construction Sequence Initial preparation of the site was completed by members of the Colorado Correctional Industries State Wildland Inmate Fire Team (SWIFT). In June of 2009 SWIFT inmates cleared the under story and brush in the lower (northern) section of the park and created fuel breaks on the southern boundary. SWIFT crew members are qualified sawyers and worked for six days at the park. The crew size consisted of up to twenty offenders and two staff. The next phase of the project began in June of 2010 with removal of trash and debris from the site. Over 1000 cubic yards of trash was loaded into dumpsters and removed to an authorized waste disposal facility. Following trash removal, clean material was trucked to the site and placed over various areas of the park containing coal waste. Prior to installing the trails and other site improvements, two waste piles were regraded to blend into the surrounding topography. Several abandoned mine adits related to the historic mine were safeguarded by backfilling with imported rip rap. Following the site cleanup, the next phase of the park development included construction of a parking lot and two ADA-accessible hiking trails. 4

5 Concurrently, the Town of Brookside installed a picnic shelter and tables, vault toilet, benches and a split-rail fence around the perimeter of the park. The town also constructed a medium difficulty trail using GOCO funds and the labor of numerous volunteer groups. The medium difficulty trail was specifically designed to highlight the remnants of numerous historic structures related to the Brookside Coal Mine. Finally, hydroseeding and hydromulching of all disturbed areas was completed in April of 2011 using funds from the OSMRE. Over five acres of disturbed land received an application of Biosol, seed and hydromulch in time to capture the benefits of early spring precipitation. A special seed mixture, along with native wildflower seed harvested from the park, was applied to the site. Before After 5

6 Sequence of reclamation construction: The understory of park was cleared of dead branches. Dead trees were felled and mulched. Fire breaks were installed around the southern perimeter of the park. Trash, glass and other debris was loaded into dumpsters and hauled to an authorized waste disposal facility. Coal waste and clinker was graded to blend with the surrounding topography. Clean fill material was imported to the site and to cover coal waste. The material was graded to blend in with the surrounding areas compacted to provide a base for the installation of site improvements. Two ADA-accessible trails and an ADA-approved parking area were created using a combination of gravel and crusher fines. One of the trails is eight feet wide to accommodate fire and emergency vehicles. The other trail meanders through the park to shady benches and picnic areas. This trail is underlain by erosion control fabric to provide stability for wheel chairs. An ADA accessible bridge was built over Spring Creek to link the ADA accessible trail to the parking area. A picnic shelter, vault toilet, split rail fence and picnic benches were installed. The medium difficulty trail was constructed. Biosol, seed and mulch were applied to the area. Future plans include installing signage and completion of the difficult trail. It is anticipated that some additional seeding and erosion control, on a relatively small scale, will continue over the next few years. Picnic Shelter and ADA-Accessible Bridge 6

7 Before After Reclamation Success Although the overall site work involved limited budgets, the Brookside/Spring Creek Park Project overcame all adversity. Success can be measured in various ways; partner involvement, vegetation establishment, or a subjective improvement of land quality based on the potential for beneficial use. By any measure, reclamation on the Brookside/Spring Creek Park Project was successful. This project s accomplishments are largely due to the dedication and commitment of the Town of 7

8 Brookside and the volunteers that donated countless hours. The success of inmates in inmate training programs, such as SWIFT, is also well documented. The inmates that participate in this program, and others like it, have a much lower recidivism rate than non-participants. This was also an incredibly beneficial use of human resources, as these inmates will soon be released with a much greater chance of job placement in fire-fighting jobs. As a CCI superintendent has so eloquently stated, they become men and learn responsibility. SWIFT Crew Colorado Correctional Industries The park project also provided assistance to individuals from the Colorado Work Center, who were currently unemployed, by providing them an opportunity to learn new skills and network with other people. The teens from the Cornell Youth Detention Center learned trail building skills, while at the same time meeting their community service obligations. The residents of the town have already benefitted greatly from the project. This is the only park in the town and, since the town is financially limited, a very important resource for the residents. Many of the town residents do not have cars and there is no public transportation. As a result of its location, residents are able to walk to the park and enjoy the amenities. This park provides the basic elements of an outdoor space with parking, hiking, and picnicking to the residents of the town and surrounding Fremont County. The trails three levels of difficulty from ADA-accessible to difficult allow people of all ages and abilities access to natural areas within their community. 8

Mine Plan of Operations Reclamation Bond Checklist

Mine Plan of Operations Reclamation Bond Checklist Mine Plan of Operations Reclamation Bond Checklist NOTE: This checklist is provided to assist the operator in calculating the engineering and environmental costs required to properly stabilize, reclaim,

More information

2012 Program Report. Agricultural Group Drainage Program

2012 Program Report. Agricultural Group Drainage Program 2012 Program Report Agricultural Group Drainage Program Accomplishments: It was a successful year for the drainage program. We were able to complete two new projects and seven maintenance projects throughout

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

1 INTRODUCTION. Kayenta Complex Page 9 December 2011 Cumulative Hydrologic Impact Assessment

1 INTRODUCTION. Kayenta Complex Page 9 December 2011 Cumulative Hydrologic Impact Assessment 1 INTRODUCTION The Office of Surface Mining Reclamation and Enforcement (OSMRE) is the regulatory authority for coal mining operations under the Surface Mining Reclamation and Control Act of 1977 that

More information

Helen Mercury Mine EE/CA OPINION OF PROBABLE COST

Helen Mercury Mine EE/CA OPINION OF PROBABLE COST G Cost Estimates Helen Mercury Mine EE/CA Alternative 2: Limited Action 3 Minor Road Improvements 4 Clear & Grub diversion channel areas 5 Surveying 6 Cleanup & Demobilization 7 Pull back of material 8

More information

Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices

Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices Purpose The purpose of this document is to provide guidance and recommendations for minimizing potential impacts to

More information

Angora Fire Restoration Activities June 24, 2007. Presented by: Judy Clot Forest Health Enhancement Program

Angora Fire Restoration Activities June 24, 2007. Presented by: Judy Clot Forest Health Enhancement Program Angora Fire Restoration Activities June 24, 2007 Presented by: Judy Clot Forest Health Enhancement Program California Tahoe Conservancy Independent California State Agency within the Resources Agency Governed

More information

File Code: 1950-1 Date: June 24, 2013 Subject: Mulberry River Watershed Improvement and Access Project

File Code: 1950-1 Date: June 24, 2013 Subject: Mulberry River Watershed Improvement and Access Project United States Department of Agriculture Forest Service Boston Mountain Ranger District TTY 479-667-1931 1803 N. 18 th Street Ozark, AR 72949 Phone 479-667-2191 FAX 479-667-5807 File Code: 1950-1 Date:

More information

Using Aerial Photography to Measure Habitat Changes. Method

Using Aerial Photography to Measure Habitat Changes. Method Then and Now Using Aerial Photography to Measure Habitat Changes Method Subject Areas: environmental education, science, social studies Conceptual Framework Topic References: HIIIB, HIIIB1, HIIIB2, HIIIB3,

More information

How To Plan A Buffer Zone

How To Plan A Buffer Zone Backyard Buffers Protecting Habitat and Water Quality What is a buffer? A buffer (also called a riparian buffer area or zone) is the strip of natural vegetation along the bank of a stream, lake or other

More information

LAND USE APPLICATION SUMMARY SHEET. Planner: C. Gathman Hearing Date: October 6, 2015

LAND USE APPLICATION SUMMARY SHEET. Planner: C. Gathman Hearing Date: October 6, 2015 LAND USE APPLICATION SUMMARY SHEET Planner: C. Gathman Hearing Date: October 6, 2015 Case Number: Applicant: USR15-0038 Wells Trucking, LLC Address: 32010 County Road 63, Gill, CO 80624 Representative:

More information

SANTA BARBARA COUNTY COMPREHENSIVE PLAN LOMPOC AREA

SANTA BARBARA COUNTY COMPREHENSIVE PLAN LOMPOC AREA SANTA BARBARA COUNTY COMPREHENSIVE PLAN LOMPOC AREA A. LAND USE ELEMENT INTERPRETIVE GUIDELINES B. COMMUNITY BENEFITS C. COUNTY ACTION ITEMS Adopted by the Board of Supervisors November 9, 1999 A. Santa

More information

King Fire Restoration Project, Eldorado National Forest, Placer and El Dorado Counties, Notice of intent to prepare an environmental impact statement.

King Fire Restoration Project, Eldorado National Forest, Placer and El Dorado Counties, Notice of intent to prepare an environmental impact statement. This document is scheduled to be published in the Federal Register on 12/24/2014 and available online at http://federalregister.gov/a/2014-30158, and on FDsys.gov [3410-11- P] DEPARTMENT OF AGRICULTURE

More information

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PIPELINE ROUTING PERMIT For A NATURAL GAS PIPELINE IN DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PUC DOCKET No. G002/GP-05-1706 In accordance with the requirements

More information

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL This manual applies to all development projects within Pitkin County. A Construction Management Plan (CMP) shall be submitted for all projects in Pitkin

More information

PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions

PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY Introduction and Assumptions 1. The existing section 27 Mineral Extraction of the Zoning Ordinance would remain and continue

More information

APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES

APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan Transportation Authority (Metro) 2009 Transportation Improvement Program Call for Projects APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan

More information

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting

More information

Woodlands Management Plan. (Draft June 2011) A. Definition of Woodlands Areas vs. Landscaped Areas of Parkfairfax

Woodlands Management Plan. (Draft June 2011) A. Definition of Woodlands Areas vs. Landscaped Areas of Parkfairfax Woodlands Management Plan (Draft June 2011) I. Background A. Definition of Woodlands Areas vs. Landscaped Areas of Parkfairfax The woodlands are defined as those wooded areas of Parkfairfax which are left

More information

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local

More information

Proposal to the Trinity Adaptive Management Working Group (TAMWG)

Proposal to the Trinity Adaptive Management Working Group (TAMWG) Proposal to the Trinity Adaptive Management Working Group (TAMWG) Request that the TAMWG recommend that the Trinity River Restoration Program fund BLM to purchase the Weigel parcel at Gold Bar (river mile

More information

Health Consultation MID-AMERICA TANNING COMPANY SERGEANT BLUFF, WOODBURY COUNTY, IOWA EPA FACILITY ID: IAD085824688 FEBRUARY 17, 2005

Health Consultation MID-AMERICA TANNING COMPANY SERGEANT BLUFF, WOODBURY COUNTY, IOWA EPA FACILITY ID: IAD085824688 FEBRUARY 17, 2005 Health Consultation MID-AMERICA TANNING COMPANY SERGEANT BLUFF, WOODBURY COUNTY, IOWA EPA FACILITY ID: IAD085824688 FEBRUARY 17, 2005 U.S. DEPARTMENT OF HEALTH AND HUMAN SERVICES Public Health Service

More information

Contaminants of Concern Exposure Pathways

Contaminants of Concern Exposure Pathways Table of Contents Purpose... 1 Background... 1 Contaminants of Concern... 2 Exposure Pathways... 2 Community Health Concerns... 3 Recommendations... 3 Pubic Health Action Plan... 3 Figure 1 : Site Map...

More information

Colorado Coal Mines Activity Status

Colorado Coal Mines Activity Status Colorado Coal Mines Activity Status Bowie No. 2 Mine (Producing) C-1996-083 Delta County Company Name: Bowie Resources, LLC Bowie No. 2 2011 Production: 2,235,055 tons No. Miners 319 8,300.5 (3,998.0 BLM

More information

Broadmoor Public Golf Course TREE MANAGEMENT GUIDE

Broadmoor Public Golf Course TREE MANAGEMENT GUIDE Broadmoor Public Golf Course TREE MANAGEMENT GUIDE Conservation of the trees at the Broadmoor Public Golf Course is a priority for environmental, economic and human health reasons. Trees make a difference

More information

Appendix C. Municipal Planning and Site Restoration Considerations

Appendix C. Municipal Planning and Site Restoration Considerations Appendix C Municipal Planning and Site Restoration Considerations 67 68 Appendix C - Municipal Planning and Site Restoration Considerations This appendix contains best practice standards for site planning

More information

Preventing Storm Water Pollution: What We Can Do

Preventing Storm Water Pollution: What We Can Do Preventing Storm Water Pollution: What We Can Do ~Employee Training Series~ Streets and Drainage Maintenance PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S. ENVIRONMENTAL

More information

EXHIBIT A LOCATION MAP AND LAND USE INFORMATION

EXHIBIT A LOCATION MAP AND LAND USE INFORMATION EXHIBIT A LOCATION MAP AND LAND USE INFORMATION In accordance with Arizona Corporation Commission Rules of Practice and Procedure R14-3-219, Applicant provides the following location maps and land use

More information

Wausau and Marathon County Parks, Recreation, and Forestry Department Forestry Division 2015 Work Plan

Wausau and Marathon County Parks, Recreation, and Forestry Department Forestry Division 2015 Work Plan Wausau and Marathon County Parks, Recreation, and Forestry Department Forestry Division 2015 Work Plan Personnel: Forest Administrator 1.00 FTE County Forester 0.80 FTE Director 0.06 FTE Department Clerical

More information

Final Report. Dixie Creek Restoration Project. Funded by Plumas Watershed Forum

Final Report. Dixie Creek Restoration Project. Funded by Plumas Watershed Forum Final Report Dixie Creek Restoration Project Funded by Plumas Watershed Forum Plumas Corporation January 2009 1 Background FR-CRM staff presented this project to the Dixie Valley Landowners Association

More information

Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS

Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS Chapter 3 3.01 General Provisions 3.01.1 Introduction 3.01.2 Application and Interpretation of Chapter 3.01.3 Unbuildable Lots 3.01.4 Other Permits 3.01.5 Prohibited Activities 3.02 Service Provider Letter

More information

Frequently Asked Transmission Pipeline Questions

Frequently Asked Transmission Pipeline Questions Frequently Asked Transmission Pipeline Questions Who is PennEast, LLC? PennEast was formed by the partnership of AGL Resources, NJR Pipeline Company, South Jersey Industries and UGI Energy Services (UGIES).

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and

More information

SWANA 2013 Award of Excellence Application

SWANA 2013 Award of Excellence Application 1 SWANA 2013 Award of Excellence Application Category: Landfill Reuse Submitted by the City of Raleigh Solid Waste Services Department Executive Summary The city of Raleigh s Wilders Grove Solid Waste

More information

APPENDIX G. California Coastal Commission & Conservancy Accessibility Standards

APPENDIX G. California Coastal Commission & Conservancy Accessibility Standards APPENDIX G California Coastal Commission & Conservancy Accessibility Standards STANDARDS AND RECOMMENDATIONS FOR ACCESSWAY LOCATION AND DEVELOPMENT These standards provide guidelines for the location,

More information

PART I DEPARTMENT OF HUMAN RESOURCES DEVELOPMENT 9.097 STATE OF HAWAII 9.099... 9.101 9.103 Class Specifications 9.105 for the

PART I DEPARTMENT OF HUMAN RESOURCES DEVELOPMENT 9.097 STATE OF HAWAII 9.099... 9.101 9.103 Class Specifications 9.105 for the PART I DEPARTMENT OF HUMAN RESOURCES DEVELOPMENT 9.097 STATE OF HAWAII 9.099............................. 9.101 9.103 Class Specifications 9.105 for the FORESTRY AND WILDLIFE WORKER SERIES This series

More information

APPENDIX C Noxious Weed Management Plan

APPENDIX C Noxious Weed Management Plan APPENDIX C Noxious Weed Management Plan Prospector Pipeline Company North Elko Pipeline TABLE OF CONTENTS 1 INTRODUCTION... 89 1.1 Project Description... 89 1.2 Plan Purpose... 89 1.3 Goals and Objectives...

More information

Wildlife Habitat Conservation and Management Plan

Wildlife Habitat Conservation and Management Plan Wildlife Habitat Conservation and Management Plan For [Applicant Name] [Insert photo of property] Developed in Cooperation with Jane Doe Habitat Conservation Biologist Oregon Department of Fish and Wildlife

More information

Storm Water Management Requirements for Construction Projects Less than One Acre

Storm Water Management Requirements for Construction Projects Less than One Acre Storm Water Management Requirements for Construction Projects Less than One Acre Purpose: UC Irvine s Phase II Small MS4 Storm Water Permit requires construction projects less than one acre in size to

More information

OFFICE OF SURFACE MINING RECLAMATION AND ENFORCEMENT FY 2016 AML ECONOMIC REVITALIZATION PROPOSAL: A COMPONENT OF THE PRESIDENT S POWER+ PLAN

OFFICE OF SURFACE MINING RECLAMATION AND ENFORCEMENT FY 2016 AML ECONOMIC REVITALIZATION PROPOSAL: A COMPONENT OF THE PRESIDENT S POWER+ PLAN OFFICE OF SURFACE MINING RECLAMATION AND ENFORCEMENT FY 2016 AML ECONOMIC REVITALIZATION PROPOSAL: A COMPONENT OF THE PRESIDENT S POWER+ PLAN 1 Un-reclaimed coal mine lands create life threatening hazards,

More information

Ruffner Mountain Nature Preserve

Ruffner Mountain Nature Preserve Ruffner Mountain Nature Preserve Membership Has Its Privileges Nature In the City About Ruffner Mountain Nature Preserve p.2 Programs and Special Events p.4 Join Us or Renew Your Membership p.8 Published

More information

4.6 GEOLOGIC AND SEISMIC HAZARDS

4.6 GEOLOGIC AND SEISMIC HAZARDS 4.6 GEOLOGIC AND SEISMIC HAZARDS This Section describes the current conditions relating to the geologic and seismic characteristics of the City of Cypress. This Section concludes with an analysis of geologic

More information

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities.

More information

OSU Extension FACT SHEET

OSU Extension FACT SHEET OHIO STATE UNIVERSITY EXTENSION! OSU Extension FACT SHEET Ohio State University Extension, 2120 Fyffe Road, Columbus, OH 43210 Shale Oil and Gas Development Fact Sheet Series A Landowner s Guide to Understanding

More information

STANDARDS FOR RANGELAND HEALTH ASSESSMENT FOR SAGEHEN ALLOTMENT #0208

STANDARDS FOR RANGELAND HEALTH ASSESSMENT FOR SAGEHEN ALLOTMENT #0208 STANDARDS FOR RANGELAND HEALTH ASSESSMENT FOR SAGEHEN ALLOTMENT #0208 RANGELAND HEALTH STANDARDS - ASSESSMENT SAGEHEN ALLOTMENT #0208 STANDARD 1 - UPLAND WATERSHED This standard is being met on the allotment.

More information

Activity Yes No N/A Notes

Activity Yes No N/A Notes CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3

More information

PLANNING & REGULATION COMMITTEE 16 JANUARY 2012

PLANNING & REGULATION COMMITTEE 16 JANUARY 2012 Division(s): Sutton Courtenay & Harwell Contact Officer: John Duncalfe (john.duncalfe@oxfordshire.gov.uk) Tel: 01865 815356 PLANNING & REGULATION COMMITTEE 16 JANUARY 2012 TO CRUSH, SCREEN, BLEND AND STOCK

More information

Draft Construction Work Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut

Draft Construction Work Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut Draft Construction Work Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut Revision 0 Prepared for: Olin Corporation Cleveland, Tennessee February 2009 TABLE OF CONTENTS INTRODUCTION...

More information

Prattsville Berm Removal Project. 1.0 Project Location

Prattsville Berm Removal Project. 1.0 Project Location Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed

More information

Colorado Natural Heritage Program

Colorado Natural Heritage Program CNHP s mission is to preserve the natural diversity of life by contributing the essential scientific foundation that leads to lasting conservation of Colorado's biological wealth. Colorado Natural Heritage

More information

RE: Exploration Plan - 43 CFR Sec.305.45. The MNES 54217 Prospecting Permits covers the following area:

RE: Exploration Plan - 43 CFR Sec.305.45. The MNES 54217 Prospecting Permits covers the following area: Iron River Field Office PO Box 286 Iron River, MI 49935 April 21, 20010 Bureau of Land Management-Eastern States ATTN-Deputy State Director for Resources 7450 Boston Boulevard Springfield, Virginia 22153

More information

, ~ The ResourcesAgency. Dave McNamara

, ~ The ResourcesAgency. Dave McNamara ,a! California State of California Department of Forestry, ~ The ResourcesAgency - ~A' ~;::~Af;// ~/ ~~/1Y~~,\~'(.~~~~~ ~,~ F1rl WES7:RY ~~~~_.~~- note 1416 Ninth Street Sacramento, CA 95814 Phone 916-445-5571

More information

First Annual Centennial Strategy for. Yucca House National Monument

First Annual Centennial Strategy for. Yucca House National Monument First Annual Centennial Strategy for Yucca House National Monument August 2007 Year: 2007 Vision Statement Yucca House National Monument was set aside in 1919 to preserve an unexcavated Ancestral Puebloan

More information

What Is Rehabilitation?

What Is Rehabilitation? Location of Aggregate Operations Ready Mix Plant Locations Aggregate Locations Cement Terminal Locations What Is Rehabilitation? Rehabilitation is the treatment of land from which aggregate has been excavated

More information

Daybreak s Environmental History

Daybreak s Environmental History Daybreak s Environmental History Introduction Kennecott Utah Copper s Daybreak Community Development Team is dedicated to building an enduring community in the Salt Lake Valley. We manage our land holdings

More information

Introduction. So, What Is a Btu?

Introduction. So, What Is a Btu? Introduction The way of life that we Americans take for granted every day depends upon a stable and abundant supply of affordable energy. Energy shortages can quickly affect our everyday lives and harm

More information

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the

More information

This Chapter was compiled by GCS (2014) as part of the EMP Consolidation for MP 30/5/1/2/2/133MR and remains pertinent.

This Chapter was compiled by GCS (2014) as part of the EMP Consolidation for MP 30/5/1/2/2/133MR and remains pertinent. 11 ENVIRONMENTAL REHABILITATION PLAN The overall land use vision for the MR133 area is to ensure that the operations are safe, stable and non-polluting over the long-term in order to be integrated into

More information

Proposed Action and Alternatives

Proposed Action and Alternatives Chapter 2 Description of Proposed Action and Alternatives 2.1 Introduction As described in Chapter 1, Lone Star Northwest wishes to increase its maximum production rate at Maury Island from roughly 10,000

More information

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES Run-off Analysis Methods This document sets forth the minimum design, technical criteria and specifications for the

More information

Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan

Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Throughout the Plan 1. There is a fundamental need for the revised plan to address how

More information

SUP07-6: Shenandoah Waste Services, LLC Special Use Permit Application for A Materials Recovery Center in a M1 (Industrial) Zoning District

SUP07-6: Shenandoah Waste Services, LLC Special Use Permit Application for A Materials Recovery Center in a M1 (Industrial) Zoning District SUP07-6: Special Use Permit Application for A Materials Recovery Center in a M1 (Industrial) Zoning District Location and Proposed Use The subject 33.76 acre parcel (Tax Map # 42A5 (A) 79) is located on

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE PROPOSED TERMS OF REFERENCE ABOUT THE PROJECT: Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at Khasra

More information

Carlton Fields Memorandum

Carlton Fields Memorandum Carlton Fields Memorandum TO: FROM: RE: DAN WEEDE FRED RUSHING RIPARIAN BUFFER DATE: JULY 26, 2013 BACKGROUND Both the state of Georgia and the city of Atlanta 1 have certain guidelines that must be followed

More information

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE 1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

SURFACE REMEDIATION AND MANAGEMENT OVERVIEW

SURFACE REMEDIATION AND MANAGEMENT OVERVIEW SURFACE REMEDIATION AND MANAGEMENT OVERVIEW Giant Mine Remediation Project Environmental Assessment Public Hearings September 10-14, 2012 Adrian Paradis (AANDC) Mike Nahir (AANDC) Bruce Halbert (Technical

More information

Interpretive Elements

Interpretive Elements Interpretive Elements The Rachel Carson Greenway will be an interpretive trail its entire length. The major interpretive themes relate to the natural world and the cultural and industrial history of the

More information

REPORT TO REGIONAL WATER SUPPLY COMMISSION MEETING OF WEDNESDAY, SEPTEMBER 4, 2013 LEECH WATER SUPPLY AREA RESTORATION UPDATE

REPORT TO REGIONAL WATER SUPPLY COMMISSION MEETING OF WEDNESDAY, SEPTEMBER 4, 2013 LEECH WATER SUPPLY AREA RESTORATION UPDATE Making a difference... together Agenda Item #9 REPORT #RWSC 2013-17 REPORT TO REGIONAL WATER SUPPLY COMMISSION MEETING OF WEDNESDAY, SEPTEMBER 4, 2013 SUBJECT LEECH WATER SUPPLY AREA RESTORATION UPDATE

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)

More information

Welcome to the future of Terwillegar Park a Unique Natural Park

Welcome to the future of Terwillegar Park a Unique Natural Park Welcome to the future of Terwillegar Park a Unique Natural Park 1 Introduction The Terwillegar Park Concept Plan study will develop an overall concept plan, management objectives and development guidelines

More information

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY 1. Applicant's Name Address (Street or Rural Route) (City & State) (Zip) Person to contact Title Phone Fax

More information

Appendix D CONSTRUCTION MANAGEMENT PLAN

Appendix D CONSTRUCTION MANAGEMENT PLAN Appendix D CONSTRUCTION MANAGEMENT PLAN Contents Introduction... 2 Construction Work in Environmental Zones... 3 Construction Schedule... 6 Construction Work Hours... 7 Site Management... 7 Pre-construction

More information

Description Quantity Cost Total Cost

Description Quantity Cost Total Cost APPENDIX: ITEMIZED CONSTRUCTION COST ESTIMATE Description Quantity Cost Total Cost 1 CASCADE FALLS 1a Existing Cascade Falls Upgrades Structural Repairs - Steps, Railing, Walls, Pool Lump Sum $500,000

More information

Wildfire & Flash Flood Recovery Emergency Watershed Protection (EWP) Flood Mitigation Efforts April 2014. Fall 2013

Wildfire & Flash Flood Recovery Emergency Watershed Protection (EWP) Flood Mitigation Efforts April 2014. Fall 2013 Wildfire & Flash Flood Recovery Emergency Watershed Protection (EWP) Flood Mitigation Efforts April 2014 Fall 2013 Recovery Specific to Incident Recovery Efforts Depend on: Population Impacted Topography

More information

The BoRit Asbestos Piles, Ambler, Pennsylvania Lenny Siegel February, 2007

The BoRit Asbestos Piles, Ambler, Pennsylvania Lenny Siegel February, 2007 The BoRit Asbestos Piles, Ambler, Pennsylvania Lenny Siegel February, 2007 At CPEO s Brownfields 101 workshops, I normally explain my understanding of the benefits of Brownfields redevelopment. At blighted

More information

A SEISMIC OIL AND GAS PRIMER by Kevin B. Hill

A SEISMIC OIL AND GAS PRIMER by Kevin B. Hill A SEISMIC OIL AND GAS PRIMER by Kevin B. Hill Hill Geophysical Consulting 415 Texas Street, Suite 200 Shreveport, LA 71101 318.221 3329 hillgeop@gte.net 1) What is seismic data? Outline 2) How is seismic

More information

APPENDIX B: TRAIL DEVELOPMENT AND MANAGEMENT STANDARDS

APPENDIX B: TRAIL DEVELOPMENT AND MANAGEMENT STANDARDS APPENDIX B: TRAIL DEVELOPMENT AND MANAGEMENT STANDARDS This section provides guidance on a variety of trail issues for planners and developers of the Ice Age NST across the state. It also provides introductory

More information

Lower Crooked Creek Watershed Conservation Plan EXECUTIVE SUMMARY

Lower Crooked Creek Watershed Conservation Plan EXECUTIVE SUMMARY EXECUTIVE SUMMARY Project Background Located in southwestern Pennsylvania, Crooked Creek is a major tributary of the Allegheny River, entering near Ford City in Armstrong County. It is rich in natural

More information

Legacy Trail Extension Feasibility Study. Preliminary Cost Estimate

Legacy Trail Extension Feasibility Study. Preliminary Cost Estimate Preliminary Cost Estimate February 2015 Category item Unit Unit Cost Quantity Cost Notes Trail Corridor (Combined Trail length ~ 25,800' + Separated Trail length ~ 13,700' = Total Length ~ 39,500' or 7.5

More information

Appendix C. Project Opportunities. Middle Twisp River (RM 7.8 18.12)

Appendix C. Project Opportunities. Middle Twisp River (RM 7.8 18.12) Appendix C Project Opportunities Middle Twisp River (RM 7.8 18.12) This table describes project opportunities by project area. Locator maps of the project opportunities are included below the table. Reach

More information

Memorandum. GGNRA Dog Management Work Group. Draft Progress Report from Work Group Meetings

Memorandum. GGNRA Dog Management Work Group. Draft Progress Report from Work Group Meetings Memorandum To: From: Subject: GGNRA Dog Management Work Group Facilitation Team Draft Progress Report from Work Group Meetings Date: October 25, 2007 Based on discussions during three Work Group meetings,

More information

Town of Montezuma, New York Community Survey 2015

Town of Montezuma, New York Community Survey 2015 Town of Montezuma, New York Community Survey 2015 The Montezuma Comprehensive Planning Committee and the Central New York Regional Planning & Development Board MONTEZUMA, NEW YORK COMMUNITY SURVEY PLEASE

More information

DIVISION 200 - EARTHWORK SECTION 201 - CLEARING RIGHT-OF-WAY

DIVISION 200 - EARTHWORK SECTION 201 - CLEARING RIGHT-OF-WAY DIVISION 200 - EARTHWORK SECTION 201 - CLEARING RIGHT-OF-WAY 201.01 Description This work shall consist of clear cutting, selective clearing and thinning, tree trimming, removing single trees, including

More information

The National Wildfire Mitigation Programs Database: State, County, and Local Efforts to Reduce Wildfire Risk 1

The National Wildfire Mitigation Programs Database: State, County, and Local Efforts to Reduce Wildfire Risk 1 Proceedings of the Second International Symposium on Fire Economics, Planning, and Policy: A Global View The National Wildfire Mitigation Programs Database: State, County, and Local Efforts to Reduce Wildfire

More information

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can

Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can Construction Site Inspection Checklist for OHC000004 By making use of some simple Best Management Practices (BMPs) a construction site operator can do his or her share to protect Ohio's water resources

More information

APPLICATION PROCESS FOR LAND DISTURBING PERMIT

APPLICATION PROCESS FOR LAND DISTURBING PERMIT PREFACE: APPLICATION PROCESS FOR LAND DISTURBING PERMIT The property owner, developer and designated planners and engineers shall review the general development plans and detailed plans of the Local Issuing

More information

Big Black Mesa Wildlife Water Development Plan

Big Black Mesa Wildlife Water Development Plan Big Black Mesa Wildlife Water Development Plan The goal of the plan is establishing reliable sources of permanent water for wildlife on the Prescott National Forest lands on Big Black Mesa. This 100 square-mile

More information

STATEMENT OF SHARON BUCCINO SENIOR ATTORNEY NATURAL RESOURCES DEFENSE COUNCIL WASHINGTON, DC

STATEMENT OF SHARON BUCCINO SENIOR ATTORNEY NATURAL RESOURCES DEFENSE COUNCIL WASHINGTON, DC STATEMENT OF SHARON BUCCINO SENIOR ATTORNEY NATURAL RESOURCES DEFENSE COUNCIL WASHINGTON, DC Good morning. My name is Sharon Buccino. I am an attorney with the Natural Resources Defense Council (NRDC).

More information

Table Mesa Recreation Area

Table Mesa Recreation Area TV-3 9990 9992 387000.000000 388000.000000 389000.000000 390000.000000 391000.000000 392000.000000 393000.000000 394000.000000 395000.000000 396000.000000 397000.000000 3768000.000000 Table Mesa Recreation

More information

STATEMENT OF JOSEPH G. PIZARCHIK, DIRECTOR OFFICE OF SURFACE MINING RECLAMATION AND ENFORCEMENT U.S. DEPARTMENT OF THE INTERIOR BEFORE THE

STATEMENT OF JOSEPH G. PIZARCHIK, DIRECTOR OFFICE OF SURFACE MINING RECLAMATION AND ENFORCEMENT U.S. DEPARTMENT OF THE INTERIOR BEFORE THE STATEMENT OF JOSEPH G. PIZARCHIK, DIRECTOR OFFICE OF SURFACE MINING RECLAMATION AND ENFORCEMENT U.S. DEPARTMENT OF THE INTERIOR BEFORE THE COMMITTEE ON ENVIRONMENT AND PUBLIC WORKS U.S. SENATE ON THE IMPLICATIONS

More information

Demo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts

Demo Existing Curb Demo Existing Asphalt Roadway Demo Asphalt Saw Cutting Protection Fence - 4 Snow Fence with T posts SECTION 00300 BID FORM S For additions and deletions to the Contract, the following unit prices shall be applicable for the specific items listed. Unit Prices shall be complete, in place including required

More information

Wildfire & Flash Flood Recovery NACo Justice & Public Safety Symposium January 2014

Wildfire & Flash Flood Recovery NACo Justice & Public Safety Symposium January 2014 Wildfire & Flash Flood Recovery NACo Justice & Public Safety Symposium January 2014 Fall 2013 Jim Reid Executive Director Public Service El Paso County, Colorado Recovery Specific to Incident Recovery

More information

FAIRFAX WATER OCCOQUAN RESERVOIR SHORELINE EASEMENT POLICY. February 17, 2011

FAIRFAX WATER OCCOQUAN RESERVOIR SHORELINE EASEMENT POLICY. February 17, 2011 FAIRFAX WATER OCCOQUAN RESERVOIR SHORELINE EASEMENT POLICY February 17, 2011 I. Purpose The Occoquan Reservoir (the "Reservoir"), located in Fairfax and Prince William Counties, Virginia, was constructed

More information

Coldwater Heritage Partnership Implementation Grant Final Report Morrison Run Watershed Restoration Project Western Pennsylvania Conservancy Project Summary The goal of the Morrison Run Watershed Restoration

More information

(1) Discuss the determination of the need for public visitation. Visitor center density within 100 miles.

(1) Discuss the determination of the need for public visitation. Visitor center density within 100 miles. Chapter 4 Specifications Designs 3. Visitors Centers 3. Visitors Centers. The Introduction (Chapter 1) for these design data collection guidelines contains additional information concerning: preparing

More information

STATEMENT OF PURPOSE

STATEMENT OF PURPOSE STATEMENT OF PURPOSE Community Properties, Inc. ( CPI ) is applying to Chatham County for approval of a major subdivision, Meadowview PUD (the Project ), with access to NC 87 and Old Graham Road, just

More information

SPACE ALLOCATION AND ENCLOSURE DESIGN GUIDELINES FOR TRASH AND RECYCLING

SPACE ALLOCATION AND ENCLOSURE DESIGN GUIDELINES FOR TRASH AND RECYCLING SPACE ALLOCATION AND ENCLOSURE DESIGN GUIDELINES FOR TRASH AND RECYCLING For Residential and New Commercial Construction and Remodel Dated July 1, 2010 If you have any questions regarding the Design Guidelines

More information

Chapter 19.45 O-R-D OFFICE RESEARCH PARK AND DEVELOPMENT ZONE. 19.45.010 Purpose of provisions. Title 19 ZONING. 19.45.010 Purpose of provisions.

Chapter 19.45 O-R-D OFFICE RESEARCH PARK AND DEVELOPMENT ZONE. 19.45.010 Purpose of provisions. Title 19 ZONING. 19.45.010 Purpose of provisions. Title 19 ZONING Chapter 19.45 O-R-D OFFICE RESEARCH PARK AND DEVELOPMENT ZONE 19.45.010 Purpose of provisions. 19.45.020 Design and site plan approval. 19.45.030 Permitted uses. 19.45.040 Conditional uses.

More information