Alcatel-Lucent Modular Cooling Solution

Size: px
Start display at page:

Download "Alcatel-Lucent Modular Cooling Solution"

Transcription

1 T E C H N O L O G Y W H I T E P A P E R Alcatel-Lucent Modular Cooling Solution Redundancy test results for pumped, two-phase modular cooling system Current heat exchange methods for cooling data centers are inherently inefficient in meeting the requirements imposed by today s dense, high-speed computing equipment, and they can contribute considerable costs to operating expenditures. The Alcatel-Lucent Modular Cooling Solution (MCS) can reduce energy consumption (with respect to transport of waste heat to the location s heat sink) while offering a coefficient of performance (COP) much greater than current approaches. Using a building s chilled water secondary loop the MCS can operate with as little as 10 percent of the electrical power used by a comparable Computer Room Air Conditioner (CRAC). This paper presents the results of tests performed on the Alcatel-Lucent MCS to determine the effects of pump unit power loss on the system and data center equipment.

2 Table of contents 1 The Challenges of Data Center Cooling 1 Alcatel-Lucent Modular Cooling Solution 2 Testing MCUs in the Alcatel-Lucent MCS 3 Pump unit configuration 4 Test conditions 5 Test results 10 Conclusion 10 Acronyms 11 About the Author

3 The Challenges of Data Center Cooling Data center cooling continues to be a major challenge for data center operators. The densely-spaced, high-speed hardware that provides the computing power to enable a variety of data center operations places significant demands on data center cooling and power systems. In fact, recent reports estimate that as much as half the energy used by a data center is dedicated to powering cooling systems 1. In an effort to operate more cost-effectively and efficiently, data center operators continue to search for new ways to reduce energy consumption and address environmental and green computing initiatives. But traditional air cooling approaches prevent data center operators from optimizing data center real estate, since they do not deliver adequate cooling unless equipment is spaced far apart. At the same time, air cooling systems add operational costs because they require installation of expensive raised floors to be used as cool air channels. As more computing equipment is installed, more cooling units are required, which places even more strain on space and power. And additional costs are incurred when operators have to reconfigure the data center for aisle containment (either hot or cold) or in-line heat removal, dedicated cabinets, and IT hardware upgrades. Compounding the issue is the fact that operators must also navigate through a variety of cooling solutions from multiple vendors, while keeping an eye on industry efforts around emerging standards designed to define the requirements for a green data center. Unfortunately, in this constantly changing environment, operators need a solution that can be applied today rather than tomorrow. And that solution must align with a range of business objectives, including cost-effective operation, optimization of energy efficiencies, reduced management complexity, as well as the need to meet green computing initiatives. The Alcatel-Lucent Modular Cooling Solution (MCS) offers data center operators with large data centers or high density electronic equipment an end-to-end system that can reduce total cooling costs by up to 50 percent, reduce data center energy consumption by up to 90 percent (with respect to transport of waste heat to the location s heat sink), and offer performance far exceeding traditional approaches to data center cooling. With the Alcatel-Lucent MCS, data center operators can: Decrease energy costs by virtually eliminating the need for supplemental air conditioning units Maximize space utilization by cooling more servers per cabinet and more cabinets per data center Eliminate the need for hot and cold aisles and isolated high power cabinets/racks Minimize the need for specially conditioned rooms Address eco-sustainability requirements/issues by reducing a data center s carbon footprint, energy consumption, and noise output Alcatel-Lucent Modular Cooling Solution The Alcatel-Lucent MCS uses phase change or two-phase modular cooling to enable cooling as close to the heat source as possible. Rather than dispersing waste heat through the data center, it transfers it into a liquid coolant and pipes it outside the data center (Figure 1). This is accomplished by: Placing an evaporator inside the cabinet, frame or rack close to the source of the heat Pumping refrigerant at low pressure through micro-channel heat exchangers as a liquid Converting the liquid to a gas within the evaporator (this is the phase change, at which point the heat is captured) Returning the gas to the pumping unit, where it is re-condensed to liquid Removing rejected heat via a chilled water system or outdoor condenser unit 1 Cooling the datacenter: hippie engineering meets modern IT, Amy Coombs, Ars Technica, April 2010, news/2010/04/hippie-engineering-meets-information-technology.ars Alcatel-Lucent Modular Cooling Solution Technology Paper 1

4 Figure 1. Cool uniform air distribution with Alcatel-Lucent s Modular Cooling Solution This approach offers a major improvement over traditional methods that rely on forcing ambient air through the data center to keep equipment cool. With cooling coils much closer to the heat source, phase change/two-phase modular cooling is far superior in transporting heat away from equipment 2 than other methods. As a result, data center operators benefit from: Lower energy requirements, operating expense, and risk Improved real estate utilization Improved ability to meet green computing/environmental initiatives To validate the benefits of phase change/two-phase modular cooling, Alcatel-Lucent deployed the Alcatel-Lucent MCS at its Naperville Modular Cooling Lab in Illinois and subjected it to a variety of tests. The first series of tests were designed to determine the effects pump unit power loss and variations in environmental humidity would have on the system and data center equipment 3. The test results summarized in this document describe the effects a loss of a series of Modular Cooling Units (MCUs), similar to what may occur in a partial outage of a redundant system, will have on the Alcatel-Lucent system and data center equipment. This experiment was performed on the Naperville prototype MCUs and the Alcatel-Lucent MCS as a whole. All testing was conducted while IT equipment within the frames/cabinets was under full power. It should be noted that the lab was designed to provide for a wide range of experimentation. Field site conditions and equipment configurations will vary greatly and may not reflect conditions at the Naperville lab. Testing MCUs in the Alcatel-Lucent MCS The Alcatel-Lucent Modular Cooling Lab in Naperville, Illinois, has 10 equipment frames fully loaded with IT computing hardware. The operating environment is 324 ft 2 (30 m 2 ) with a ceiling height of nine feet (2.74 m), and it is thermally isolated from any benefits that could be offered by the building cooling system. All perforations and venting in walls, floors and ceiling have been sealed. In addition, ceiling tiles are foil backed to provide an acceptable level of humidity control. As a result, this lab is, for the most part, a sealed and isolated environmental enclosure. This enables experimentation without interaction or assistance from any outside cooling source. 4 2 For more information about the Alcatel-Lucent MCS see the Alcatel-Lucent white paper Keeping Cool In The Data Center: A High-Efficiency Modular Solution. 3 For details of the environmental humidity tests, see the Alcatel-Lucent white paper Alcatel-Lucent Modular Cooling Solution: Pumped, two-phase modular cooling humidity variation test results 4 For more details about the Alcatel-Lucent Naperville Modular Cooling Lab, see the Alcatel-Lucent white paper Alcatel-Lucent Modular Cooling Solution: Pumped, two-phase modular cooling humidity variation test results 2 Alcatel-Lucent Modular Cooling Solution Technology White Paper

5 Equipment frames are configured with the standard hot aisle/cold aisle arrangement with typical cabinet spacing. The lab s small size and the very high heat load in the room are not typical of most data centers. Therefore, to prevent condensation, the cooling system regulates the refrigerant temperature to maintain a temperature above the dew point temperature. But it is still very difficult to accommodate changing temperatures by maintaining a steady relative humidity (RH) level. To ensure conditions for this experiment could be correlated with typical site conditions, the system was set to maintain a room humidity target of percent RH. Obviously, not having to add humidity will lower operating costs. But, more importantly, low humidity conditions are optimal for the Alcatel-Lucent MCS or any cooling solution because condensation issues are greatly minimized. The MCUs of the Alcatel-Lucent MCS are designed to be installed within cabinet enclosures, and they have been tested to and comply with NEBS Level 3 (including NEBS Zone 4 Earthquake) ETSI, UL, IC, CE and CSA standards. With this approach, the robust hardware can endure and continue to operate in typical telecom industry environments. Figure 2. Equipment frames in the Alcatel-Lucent Modular Cooling Lab There are 30 MCUs installed in the equipment frames in the Modular Cooling Lab. Figure 2 shows some of the equipment frames, as well as the pump unit, MCUs, overhead distribution manifold, and flexible refrigerant lines. Pump unit configuration The Alcatel-Lucent MCS in the Modular Cooling Lab is supported by only one chilled water pump unit. Note that this pump unit is equipped with two pumps. The second pump is a redundant pump that will kick in if the first pump fails. Some data center designs may require a high level of system redundancy. For these data centers, it may be prudent to supply the MCUs within an equipment frame, or alternating frames, with separate cooling loops, each with their own pump unit. In this way, if a catastrophic pump unit outage does occur, the remaining operational MCS systems will continue maintaining appropriate operating conditions and the macroscopic thermal impact will be limited. A redundant configuration requires appropriate sizing to ensure that cooling capacity lost by an out of service pump unit is recovered by the remaining operational MCS systems. To make this possible, the site should be designed to allow for enough of a cooling capacity margin to protect against pump unit outage. Therefore, a fully redundant system should split the heat load between multiple pump units. It is imperative that appropriate operational conditions exist to support proper unit operation (chilled water temperature, flow and site humidity control). A chilled water secondary cooling loop used in the site design may look similar to the one presented in Figure 3. Alcatel-Lucent Modular Cooling Solution Technology Paper 3

6 Figure 3. Redundant MCS site configuration Circulating refrigerant supplied to alternating cabinets. Modular Cooling Units Pump Unit Pump Unit Test conditions To simulate a pump unit outage on a one pump system, half (50 percent) of the MCUs in the Modular Cooling Lab were removed from operation. As a result, the single pump unit continued to receive the same, full thermal load as it had with all MCUs operational. This created a scenario similar to the macroscopic dynamics of a multi-mcs installation with multiple pump units. In a multi-unit environment, the heat exhausted from out of service MCUs will be rejected into the room, thereby causing the room temperature to rise slightly. Assuming the site uses an Alcatel-Lucent MCS as the primary cooling solution, the rise in ambient temperature will slightly increase the temperature of the intake air flowing through the operational MCUs. Therefore, the cooling capacity of those units will increase to the point at which captured heat is rejected from the non-operating MCUs and thermal stabilization occurs. Results will be the same whether a chilled water or compressorized secondary cooling loop system is deployed. Figure 4. Modular Cooling Lab configuration for pump unit failure experiments Naperville Modular Cooling Solution Lab RPP C-238 Pump Unit Building Chilled H 2 O Provisions for this experiment included monitoring ambient room conditions during experimentation. To simulate a loss of 50 percent capacity, the supply refrigerant lines to half of the cooling units were disconnected in a pattern shown in Figure Number of MCUs taken out of service 4 Alcatel-Lucent Modular Cooling Solution Technology White Paper

7 This alternating pattern represents a method of connection to a redundant system in the field with alternating MCUs within the frame supported by alternating pump units. The equipment frames were run under these test conditions for a period of 22 hours to allow sufficient time for the room temperature to stabilize. Temperature data was recorded throughout the experiment, along with sound pressure levels. At the end of the test interval, supply line refrigerant connections were re-established and conditions monitored for an additional period of 12 hours. Figure 5 shows the top of the cabinets in the Modular Cooling Lab, as well as the manifold and the supply lines that were disconnected. This is an experimental lab; aesthetics are greatly improved in a customer installation. Figure 5. Disconnected MCU supply lines for the Alcatel-Lucent MCS pump unit failure test Test results With half of the cooling units disconnected there was an obvious change in the cabinet temperature profile, exactly as expected. An additional heat load of 1.8 kw in the room was created by the steam generating humidifier that was operating constantly at full capacity. As the room temperature rose, the air had a greater capacity to retain moisture and the percentage of RH dropped. To adjust for the drop in percentage of RH, the humidifier generated more steam. This was an extremely dynamic condition until stabilization occurred. Testing took place in the Chicago area in February, at which time the average outdoor temperature was 22 F ( 5.6 C) and the outside air was very dry. Alcatel-Lucent no longer controls indoor humidity in the building in which the Modular Cooling Lab is located. As a result the humidity in the hall just outside of the lab was 18 percent RH. The walls, floors and ceiling within the lab quickly wicked the moisture away, so it was an uphill battle to keep the room humidity near 50 percent RH in these conditions. A psychometric chart can best relay the impact of maintaining a specific humidity level as temperature rose in the lab. With initial start conditions of 68 F (20 C) and 47 percent RH the corresponding humidity ratio was grams water/gram dry air. During the test, the average room temperature rose to 79 F (26 C) with a humidity of 42 percent RH after stabilization. This resulted in a humidity ratio of grams water/gram dry air. As a result, there was 50 percent more moisture suspended in the room during the test. By the conclusion of the test, the dehumidifier had to remove this moisture and, therefore, recovery time was lengthened as the system maintained the refrigerant temperature above dew point. Figure 6. Infrared image of the exhaust side of the hot air aisle in the Modular Cooling Lab during testing 40 C 39.1 C 35 C 30 C 25 C Figure 6 is an infrared image of the exhaust side of the hot air aisle in the lab. The temperature scale along the right side indicates the temperature 20 C 15 C 17.0 C Alcatel-Lucent Modular Cooling Solution Technology Paper 5

8 gradient, with blues on the cool end and yellow/white with increased temperature. The operational MCUs were exhausting air at 64.4 F (18 C), while the non-operational MCUs were exhausting unconditioned server exhaust air at up to 100 F (38 C). The MCU fans were operational. Note the pattern created by alternating MCU disconnection. Figure 7 is the corresponding digital image of the same angle shown in Figure 6. All cabinet doors remained closed during test. Data gathered during the experiment is presented in Table 1. The room sound pressure level increased as the fans within the servers sped up to compensate for the increased room temperature. When the experiment concluded, sound levels dropped to their initial state. The introduction of the Alcatel-Lucent MCS can lower acoustic emissions and server power consumption. This was proven at the Alcatel-Lucent Plano IPTV lab where sound levels dropped by 20 db (A) after the Alcatel-Lucent MCS was installed. (A-weighting attempts to match the response of the human ear.) Figure 7. Digital image of the exhaust side of the hot air aisle in the Modular Cooling Lab during testing Table 1. Summary of data collected during testing EXPERIMENTAL DATA Initial Sound Pressure Level Sound Pressure Level During Experimentation Final Sound Pressure Level Chilled Water Supply Pressure Chilled Water Return Pressure 73.1 dba 75.4 dba 73.1 dba 42 psig (2.9 bar) 27 psig (1.86 bar) Thermocouples were placed in the exhaust aisle approximately 3.5 feet (1 m) above the floor in the center of the aisle and carefully placed so that no MCU would exhaust air directly on them (Figure 8). This placement enabled a temperature measurement of mixed aisle air at approximately waist high. Figure 8. Temperature measurement was conducted with thermocouples in the exhaust aisle Cab 6 Cab 7 Cab 8 Cab 1 Cab 2 Cab 3 Cab 9 Cab 4 Intake Aisle 2 Cab 10 Exhaust Aisle Cab 5 Intake Aisle 1 6 Alcatel-Lucent Modular Cooling Solution Technology White Paper

9 The green line shown in Figure 9 is a measurement taken at the pump unit, which is located in the server intake aisle approximately 5.5 ( 1.7 m) above the floor. Figure 9. Temperature profile measurements taken at the pump unit in the server intake aisle during testing The Modular Cooling Lab is also equipped with temperature sensors in the ceiling above the intake and exhaust aisles (Figure 10). These ceiling mounted probes are connected to a monitoring system offered as an option with the Alcatel-Lucent MCS, along with a refrigerant leak detection system, which is also connected to the monitoring system. In the Modular Cooling Lab, the system is set up to monitor and trigger alarms for high room temperature, refrigerant leak, pump outage and status of a fan unit. If an alarm is triggered, the system is configured to send an and text message. Figure 10. Temperature sensors in the ceiling above the intake and exhaust aisles in the Modular Cooling Lab Temperature sensors above exhaust aisle Alcatel-Lucent Modular Cooling Solution Technology Paper 7

10 Data recorded for a two day interval from ceiling mounted sensors is presented in Figures 11, 12 and 13. Temperatures are presented in F. The figures show that stabilization occurred quickly as the system dynamically adapted to changing environmental conditions. The system can be configured to display English or SI units, and these figures display English units. Figure 11. Two day intake aisle temperature profile Figure 12. Two day exhaust aisle Sensor 2 temperature profile Figure 13. Two day exhaust aisle Sensor 1 temperature profile 8 Alcatel-Lucent Modular Cooling Solution Technology White Paper

11 Recovery time, when all system components are brought back into operation, is important in these types of scenarios. Had the room percent RH been dryer (i.e., moisture was not added) recovery would have occurred more quickly. The system was controlling moisture to prevent condensation from forming on components. As indicated in Figures 14, 15, 16 and 17 the room temperature fully recovered in approximately 50 minutes. Figure 14. Exhaust aisle Sensor 1 two hour recovery window Figure 15. Exhaust aisle Sensor 2 two hour recovery window Figure 16. Intake aisle 1 sensor two hour recovery window Alcatel-Lucent Modular Cooling Solution Technology Paper 9

12 Figure 17. Intake aisle 2 sensor two hour recovery window This recovery time may vary somewhat depending on how heavily each MCU is thermally loaded, the temperature of the chilled water with a chilled water pump unit, room humidity and level of loading for each pump. However, the recovery time is very quick compared to other cooling methodologies and the system provides a more consistent temperature throughout the data center. Conclusion The Alcatel-Lucent MCS is a highly dynamic solution that can continually adjust and adapt to its operating environment. And it is capable of handling data center cooling requirements under a variety of operating conditions. Testing of the system in the Alcatel-Lucent Modular Cooling Lab with 50 percent of MCUs removed from service revealed that the solution can maintain proper temperature control in the event of a partial system outage and minimize impact to the rack mounted equipment. The rack mounted equipment was never exposed to inlet air temperatures greater than 80 F (26.7 C), which is well below the maximum operating intake air temperature of 95 F (35 C) specified by many IT hardware manufacturers. For data centers that require a high degree of redundancy (beyond that provided by the redundant pump in the pump unit) a site should be designed to allow enough cooling capacity margin for protection against the complete failure of a pump unit. A fully redundant system would split heat load between multiple pumping units. It is imperative that appropriate operational conditions exist to support proper pump unit operation (chilled water temperature and flow). And when high availability is required, proper planning is necessary to ensure system capacity is not exceeded, as would be the case if a pump unit was removed from operation. For data center operators with large data centers or high density electronic equipment, the Alcatel- Lucent MCS is an end-to-end system that can address immediate cooling requirements. It can be relied upon to maintain cooling levels in even the most demanding data center conditions. In addition, it can reduce total cooling costs by up to 50 percent, reduce data center energy consumption by up to 90 percent (with respect to transport of waste heat to the location s heat sink), and offer a coefficient of performance (COP) far greater than traditional approaches to data center cooling. Acronyms COP MCU RH coefficient of performance Modular Cooling Unit relative humidity 10 Alcatel-Lucent Modular Cooling Solution Technology White Paper

13 About the Author Bill Scofield Bell Labs Thermal/Environmental R&D Alcatel-Lucent Bill Scofield is a Bell Laboratories innovator and inventor responsible for Thermal/Environmental Design, Analysis & Assessment. Bill is the principal Designer and Inventor of the Alcatel-Lucent Modular Cooling Solution. He is also developing several other leading edge cooling technologies from the component level through site level. He has a long history working directly with global customers on-site to improve their deployed hardware s thermal performance and reliability. This coupled with his background in hardware regulatory compliance requirements and standards for environmental conditions enable a clear understanding of customer needs. His efforts have enabled improvement in both reliability and performance of customer equipment thereby minimizing service outages. Bill s expertise and his background in hardware compliance requirements have guided the design of the Alcatel-Lucent Modular Cooling Units to conform to telecom s most stringent hardware requirements, including meeting NEBS Level 3. Bill has five issued patents, eight pending patents and refrigeration certification issued by the US Environmental Protection Agency. He earned both Masters and Bachelors of Science degrees in Mechanical and Aerospace Engineering from the Illinois Institute of Technology. Alcatel-Lucent Modular Cooling Solution Technology Paper 11

14 Alcatel, Lucent, Alcatel-Lucent and the Alcatel-Lucent logo are trademarks of Alcatel-Lucent. All other trademarks are the property of their respective owners. The information presented is subject to change without notice. Alcatel-Lucent assumes no responsibility for inaccuracies contained herein. Copyright 2010 Alcatel-Lucent. All rights reserved. SBG (05)

Element D Services Heating, Ventilating, and Air Conditioning

Element D Services Heating, Ventilating, and Air Conditioning PART 1 - GENERAL 1.01 OVERVIEW A. This section supplements Design Guideline Element D3041 on air handling distribution with specific criteria for projects involving design of a Data Center spaces B. Refer

More information

IT White Paper MANAGING EXTREME HEAT: COOLING STRATEGIES FOR HIGH-DENSITY SYSTEMS

IT White Paper MANAGING EXTREME HEAT: COOLING STRATEGIES FOR HIGH-DENSITY SYSTEMS IT White Paper MANAGING EXTREME HEAT: COOLING STRATEGIES FOR HIGH-DENSITY SYSTEMS SUMMARY As computer manufacturers pack more and more processing power into smaller packages, the challenge of data center

More information

Data Center Rack Level Cooling Utilizing Water-Cooled, Passive Rear Door Heat Exchangers (RDHx) as a Cost Effective Alternative to CRAH Air Cooling

Data Center Rack Level Cooling Utilizing Water-Cooled, Passive Rear Door Heat Exchangers (RDHx) as a Cost Effective Alternative to CRAH Air Cooling Data Center Rack Level Cooling Utilizing Water-Cooled, Passive Rear Door Heat Exchangers (RDHx) as a Cost Effective Alternative to CRAH Air Cooling Joshua Grimshaw Director of Engineering, Nova Corporation

More information

International Telecommunication Union SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES IN PUBLIC NETWORKS

International Telecommunication Union SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES IN PUBLIC NETWORKS International Telecommunication Union ITU-T TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU Technical Paper (13 December 2013) SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES

More information

Analysis of data centre cooling energy efficiency

Analysis of data centre cooling energy efficiency Analysis of data centre cooling energy efficiency An analysis of the distribution of energy overheads in the data centre and the relationship between economiser hours and chiller efficiency Liam Newcombe

More information

Benefits of Cold Aisle Containment During Cooling Failure

Benefits of Cold Aisle Containment During Cooling Failure Benefits of Cold Aisle Containment During Cooling Failure Introduction Data centers are mission-critical facilities that require constant operation because they are at the core of the customer-business

More information

Dealing with Thermal Issues in Data Center Universal Aisle Containment

Dealing with Thermal Issues in Data Center Universal Aisle Containment Dealing with Thermal Issues in Data Center Universal Aisle Containment Daniele Tordin BICSI RCDD Technical System Engineer - Panduit Europe Daniele.Tordin@Panduit.com AGENDA Business Drivers Challenges

More information

Combining Cold Aisle Containment with Intelligent Control to Optimize Data Center Cooling Efficiency

Combining Cold Aisle Containment with Intelligent Control to Optimize Data Center Cooling Efficiency A White Paper from the Experts in Business-Critical Continuity TM Combining Cold Aisle Containment with Intelligent Control to Optimize Data Center Cooling Efficiency Executive Summary Energy efficiency

More information

DataCenter 2020: first results for energy-optimization at existing data centers

DataCenter 2020: first results for energy-optimization at existing data centers DataCenter : first results for energy-optimization at existing data centers July Powered by WHITE PAPER: DataCenter DataCenter : first results for energy-optimization at existing data centers Introduction

More information

How To Improve Energy Efficiency Through Raising Inlet Temperatures

How To Improve Energy Efficiency Through Raising Inlet Temperatures Data Center Operating Cost Savings Realized by Air Flow Management and Increased Rack Inlet Temperatures William Seeber Stephen Seeber Mid Atlantic Infrared Services, Inc. 5309 Mohican Road Bethesda, MD

More information

How To Improve Energy Efficiency In A Data Center

How To Improve Energy Efficiency In A Data Center Google s Green Data Centers: Network POP Case Study Table of Contents Introduction... 2 Best practices: Measuring. performance, optimizing air flow,. and turning up the thermostat... 2...Best Practice

More information

Best Practices for Wire-free Environmental Monitoring in the Data Center

Best Practices for Wire-free Environmental Monitoring in the Data Center White Paper Best Practices for Wire-free Environmental Monitoring in the Data Center April 2012 Introduction Monitoring for environmental threats in the data center is not a new concept. Since the beginning

More information

Reducing Data Center Energy Consumption

Reducing Data Center Energy Consumption Reducing Data Center Energy Consumption By John Judge, Member ASHRAE; Jack Pouchet, Anand Ekbote, and Sachin Dixit Rising data center energy consumption and increasing energy costs have combined to elevate

More information

Environmental Data Center Management and Monitoring

Environmental Data Center Management and Monitoring 2013 Raritan Inc. Table of Contents Introduction Page 3 Sensor Design Considerations Page 3 Temperature and Humidity Sensors Page 4 Airflow Sensor Page 6 Differential Air Pressure Sensor Page 6 Water Sensor

More information

CURBING THE COST OF DATA CENTER COOLING. Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers

CURBING THE COST OF DATA CENTER COOLING. Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers CURBING THE COST OF DATA CENTER COOLING Charles B. Kensky, PE, LEED AP BD+C, CEA Executive Vice President Bala Consulting Engineers OVERVIEW Compare Cooling Strategies in Free- Standing and In-Building

More information

Energy Efficiency Opportunities in Federal High Performance Computing Data Centers

Energy Efficiency Opportunities in Federal High Performance Computing Data Centers Energy Efficiency Opportunities in Federal High Performance Computing Data Centers Prepared for the U.S. Department of Energy Federal Energy Management Program By Lawrence Berkeley National Laboratory

More information

Two-Phase Modular Cooling

Two-Phase Modular Cooling Two-Phase Modular Coolin for the Data Center Ensurin the reliability and efficiency of your data center operations requires a strateic partner that is qualified to minimize enery usae, reduce costs, and

More information

Improving Data Center Energy Efficiency Through Environmental Optimization

Improving Data Center Energy Efficiency Through Environmental Optimization Improving Data Center Energy Efficiency Through Environmental Optimization How Fine-Tuning Humidity, Airflows, and Temperature Dramatically Cuts Cooling Costs William Seeber Stephen Seeber Mid Atlantic

More information

Choosing Close-Coupled IT Cooling Solutions

Choosing Close-Coupled IT Cooling Solutions W H I T E P A P E R Choosing Close-Coupled IT Cooling Solutions Smart Strategies for Small to Mid-Size Data Centers Executive Summary As high-density IT equipment becomes the new normal, the amount of

More information

Unified Physical Infrastructure (UPI) Strategies for Thermal Management

Unified Physical Infrastructure (UPI) Strategies for Thermal Management Unified Physical Infrastructure (UPI) Strategies for Thermal Management The Importance of Air Sealing Grommets to Improving Smart www.panduit.com WP-04 August 2008 Introduction One of the core issues affecting

More information

I-STUTE Project - WP2.3 Data Centre Cooling. Project Review Meeting 8, Loughborough University, 29 th June 2015

I-STUTE Project - WP2.3 Data Centre Cooling. Project Review Meeting 8, Loughborough University, 29 th June 2015 I-STUTE Project - WP2.3 Data Centre Cooling Project Review Meeting 8, Loughborough University, 29 th June 2015 Topics to be considered 1. Progress on project tasks 2. Development of data centre test facility

More information

The Different Types of Air Conditioning Equipment for IT Environments

The Different Types of Air Conditioning Equipment for IT Environments The Different Types of Air Conditioning Equipment for IT Environments By Tony Evans White Paper #59 Executive Summary Cooling equipment for an IT environment can be implemented in 10 basic configurations.

More information

Increasing Energ y Efficiency In Data Centers

Increasing Energ y Efficiency In Data Centers The following article was published in ASHRAE Journal, December 2007. Copyright 2007 American Society of Heating, Refrigerating and Air- Conditioning Engineers, Inc. It is presented for educational purposes

More information

How To Run A Data Center Efficiently

How To Run A Data Center Efficiently A White Paper from the Experts in Business-Critical Continuity TM Data Center Cooling Assessments What They Can Do for You Executive Summary Managing data centers and IT facilities is becoming increasingly

More information

Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings

Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings WHITE PAPER Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings By Lars Strong, P.E., Upsite Technologies, Inc. Kenneth G. Brill, Upsite Technologies, Inc. 505.798.0200

More information

Liquid Cooling Solutions for DATA CENTERS - R.M.IYENGAR BLUESTAR LIMITED.

Liquid Cooling Solutions for DATA CENTERS - R.M.IYENGAR BLUESTAR LIMITED. Liquid Cooling Solutions for DATA CENTERS - R.M.IYENGAR BLUESTAR LIMITED. Presentation Goals & Outline Power Density Where we have been- where we are now - where we are going Limitations of Air Cooling

More information

- White Paper - Data Centre Cooling. Best Practice

- White Paper - Data Centre Cooling. Best Practice - White Paper - Data Centre Cooling Best Practice Release 2, April 2008 Contents INTRODUCTION... 3 1. AIR FLOW LEAKAGE... 3 2. PERFORATED TILES: NUMBER AND OPENING FACTOR... 4 3. PERFORATED TILES: WITH

More information

APC APPLICATION NOTE #112

APC APPLICATION NOTE #112 #112 Best Practices for Deploying the InfraStruXure InRow SC By David Roden Abstract The InfraStruXure InRow SC (ACSC100 and ACSC101) is a self-contained air conditioner for server rooms and wiring closets.

More information

Data Center Power Consumption

Data Center Power Consumption Data Center Power Consumption A new look at a growing problem Fact - Data center power density up 10x in the last 10 years 2.1 kw/rack (1992); 14 kw/rack (2007) Racks are not fully populated due to power/cooling

More information

Utilizing Temperature Monitoring to Increase Datacenter Cooling Efficiency

Utilizing Temperature Monitoring to Increase Datacenter Cooling Efficiency WHITE PAPER Utilizing Temperature Monitoring to Increase Datacenter Cooling Efficiency 20A Dunklee Road Bow, NH 03304 USA 2007. All rights reserved. Sensatronics is a registered trademark of. 1 Abstract

More information

Blade Server & Data Room Cooling Specialists

Blade Server & Data Room Cooling Specialists SURVEY I DESIGN I MANUFACTURE I INSTALL I COMMISSION I SERVICE SERVERCOOL An Eaton-Williams Group Brand Blade Server & Data Room Cooling Specialists Manufactured in the UK SERVERCOOL Cooling IT Cooling

More information

An Introduction to Cold Aisle Containment Systems in the Data Centre

An Introduction to Cold Aisle Containment Systems in the Data Centre An Introduction to Cold Aisle Containment Systems in the Data Centre White Paper October 2010 By Zac Potts MEng Mechanical Engineer Sudlows October 2010 An Introduction to Cold Aisle Containment Systems

More information

Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings

Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings WHITE PAPER Cooling Capacity Factor (CCF) Reveals Stranded Capacity and Data Center Cost Savings By Kenneth G. Brill, Upsite Technologies, Inc. Lars Strong, P.E., Upsite Technologies, Inc. 505.798.0200

More information

Benefits of. Air Flow Management. Data Center

Benefits of. Air Flow Management. Data Center Benefits of Passive Air Flow Management in the Data Center Learning Objectives At the end of this program, participants will be able to: Readily identify if opportunities i where networking equipment

More information

GREEN FIELD DATA CENTER DESIGN WATER COOLING FOR MAXIMUM EFFICIENCY. Shlomo Novotny, Vice President and Chief Technology Officer, Vette Corp.

GREEN FIELD DATA CENTER DESIGN WATER COOLING FOR MAXIMUM EFFICIENCY. Shlomo Novotny, Vice President and Chief Technology Officer, Vette Corp. GREEN FIELD DATA CENTER DESIGN WATER COOLING FOR MAXIMUM EFFICIENCY Shlomo Novotny, Vice President and Chief Technology Officer, Vette Corp. Overview Data centers are an ever growing part of our economy.

More information

Data Center Components Overview

Data Center Components Overview Data Center Components Overview Power Power Outside Transformer Takes grid power and transforms it from 113KV to 480V Utility (grid) power Supply of high voltage power to the Data Center Electrical Room

More information

Data Center 2020: Delivering high density in the Data Center; efficiently and reliably

Data Center 2020: Delivering high density in the Data Center; efficiently and reliably Data Center 2020: Delivering high density in the Data Center; efficiently and reliably March 2011 Powered by Data Center 2020: Delivering high density in the Data Center; efficiently and reliably Review:

More information

White Paper. Data Center Containment Cooling Strategies. Abstract WHITE PAPER EC9001. Geist Updated August 2010

White Paper. Data Center Containment Cooling Strategies. Abstract WHITE PAPER EC9001. Geist Updated August 2010 White Paper Data Center Containment Cooling Strategies WHITE PAPER EC9001 Geist Updated August 2010 Abstract Deployment of high density IT equipment into data center infrastructure is now a common occurrence

More information

Measure Server delta- T using AUDIT- BUDDY

Measure Server delta- T using AUDIT- BUDDY Measure Server delta- T using AUDIT- BUDDY The ideal tool to facilitate data driven airflow management Executive Summary : In many of today s data centers, a significant amount of cold air is wasted because

More information

Best Practices for Wire-free Environmental Monitoring in the Data Center

Best Practices for Wire-free Environmental Monitoring in the Data Center White Paper 11800 Ridge Parkway Broomfiled, CO 80021 1-800-638-2638 http://www.42u.com sales@42u.com Best Practices for Wire-free Environmental Monitoring in the Data Center Introduction Monitoring for

More information

Nordic Heat Pump Product Guide

Nordic Heat Pump Product Guide Nordic Heat Pump Product Guide About Maritime Geothermal Maritime Geothermal is a privately owned, Canadian based manufacturer of geothermal heat pumps. We began manufacturing the Nordic line of heat pumps

More information

Air, Fluid Flow, and Thermal Simulation of Data Centers with Autodesk Revit 2013 and Autodesk BIM 360

Air, Fluid Flow, and Thermal Simulation of Data Centers with Autodesk Revit 2013 and Autodesk BIM 360 Autodesk Revit 2013 Autodesk BIM 360 Air, Fluid Flow, and Thermal Simulation of Data Centers with Autodesk Revit 2013 and Autodesk BIM 360 Data centers consume approximately 200 terawatt hours of energy

More information

The New Data Center Cooling Paradigm The Tiered Approach

The New Data Center Cooling Paradigm The Tiered Approach Product Footprint - Heat Density Trends The New Data Center Cooling Paradigm The Tiered Approach Lennart Ståhl Amdahl, Cisco, Compaq, Cray, Dell, EMC, HP, IBM, Intel, Lucent, Motorola, Nokia, Nortel, Sun,

More information

Boosting the Energy efficiency of a Server Room: experimental + virtual approach.

Boosting the Energy efficiency of a Server Room: experimental + virtual approach. Boosting the Energy efficiency of a Server Room: experimental + virtual approach. Nowadays, the increase in computing power allows the successful applications of the CFD simulation methods in civil environments.

More information

Data Center Precision Cooling: The Need For A Higher Level Of Service Expertise. A White Paper from the Experts in Business-Critical Continuity

Data Center Precision Cooling: The Need For A Higher Level Of Service Expertise. A White Paper from the Experts in Business-Critical Continuity Data Center Precision Cooling: The Need For A Higher Level Of Service Expertise A White Paper from the Experts in Business-Critical Continuity Executive Summary Today s data centers are changing rapidly,

More information

Strategies for Deploying Blade Servers in Existing Data Centers

Strategies for Deploying Blade Servers in Existing Data Centers Strategies for Deploying Blade Servers in Existing Data Centers By Neil Rasmussen White Paper #125 Revision 1 Executive Summary When blade servers are densely packed, they can exceed the power and cooling

More information

Energy Efficient Server Room and Data Centre Cooling. Computer Room Evaporative Cooler. EcoCooling

Energy Efficient Server Room and Data Centre Cooling. Computer Room Evaporative Cooler. EcoCooling Energy Efficient Server Room and Data Centre Cooling Computer Room Evaporative Cooler EcoCooling EcoCooling CREC Computer Room Evaporative Cooler Reduce your cooling costs by over 90% Did you know? An

More information

Direct Fresh Air Free Cooling of Data Centres

Direct Fresh Air Free Cooling of Data Centres White Paper Introduction There have been many different cooling systems deployed in Data Centres in the past to maintain an acceptable environment for the equipment and for Data Centre operatives. The

More information

Data Center Design Guide featuring Water-Side Economizer Solutions. with Dynamic Economizer Cooling

Data Center Design Guide featuring Water-Side Economizer Solutions. with Dynamic Economizer Cooling Data Center Design Guide featuring Water-Side Economizer Solutions with Dynamic Economizer Cooling Presenter: Jason Koo, P.Eng Sr. Field Applications Engineer STULZ Air Technology Systems jkoo@stulz ats.com

More information

Introducing AUDIT- BUDDY

Introducing AUDIT- BUDDY Introducing AUDIT- BUDDY Monitoring Temperature and Humidity for Greater Data Center Efficiency 202 Worcester Street, Unit 5, North Grafton, MA 01536 www.purkaylabs.com info@purkaylabs.com 1.774.261.4444

More information

Blade Servers and Beyond: Adaptive Cooling for the Next Generation of IT Systems. A White Paper from the Experts in Business-Critical Continuity

Blade Servers and Beyond: Adaptive Cooling for the Next Generation of IT Systems. A White Paper from the Experts in Business-Critical Continuity Blade Servers and Beyond: Adaptive Cooling for the Next Generation of IT Systems A White Paper from the Experts in Business-Critical Continuity Executive Summary In enterprise data centers, designers face

More information

Adaptive Cooling in Data Centers. Silicon Valley Leadership Group Energy Efficient Data Center Demonstration Project October, 2009

Adaptive Cooling in Data Centers. Silicon Valley Leadership Group Energy Efficient Data Center Demonstration Project October, 2009 Adaptive Cooling in Data Centers Silicon Valley Leadership Group Energy Efficient Data Center Demonstration Project October, 2009 Maximizing Cooling Efficiency in a Concurrently Maintainable and Fault

More information

Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001

Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001 Verizon SMARTS Data Center Design Phase 1 Conceptual Study Report Ms. Leah Zabarenko Verizon Business 2606A Carsins Run Road Aberdeen, MD 21001 Presented by: Liberty Engineering, LLP 1609 Connecticut Avenue

More information

Cooling Small Server Rooms Can Be. - Jim Magallanes Computer Room Uptime: www.cruptime.com Uptime Racks: www.uptimeracks.com

Cooling Small Server Rooms Can Be. - Jim Magallanes Computer Room Uptime: www.cruptime.com Uptime Racks: www.uptimeracks.com Cooling Small Server Rooms Can Be Inexpensive, Efficient and Easy - Jim Magallanes Computer Room Uptime: www.cruptime.com Uptime Racks: www.uptimeracks.com Server Rooms Description & Heat Problem Trends

More information

Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia

Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Case Study: Innovative Energy Efficiency Approaches in NOAA s Environmental Security Computing Center in Fairmont, West Virginia Prepared for the U.S. Department of Energy s Federal Energy Management Program

More information

Managing Data Centre Heat Issues

Managing Data Centre Heat Issues Managing Data Centre Heat Issues Victor Banuelos Field Applications Engineer Chatsworth Products, Inc. 2010 Managing Data Centre Heat Issues Thermal trends in the data centre Hot Aisle / Cold Aisle design

More information

Managing Cooling Capacity & Redundancy In Data Centers Today

Managing Cooling Capacity & Redundancy In Data Centers Today Managing Cooling Capacity & Redundancy In Data Centers Today About AdaptivCOOL 15+ Years Thermal & Airflow Expertise Global Presence U.S., India, Japan, China Standards & Compliances: ISO 9001:2008 RoHS

More information

Lesson 36 Selection Of Air Conditioning Systems

Lesson 36 Selection Of Air Conditioning Systems Lesson 36 Selection Of Air Conditioning Systems Version 1 ME, IIT Kharagpur 1 The specific objectives of this chapter are to: 1. Introduction to thermal distribution systems and their functions (Section

More information

High Density Data Centers Fraught with Peril. Richard A. Greco, Principal EYP Mission Critical Facilities, Inc.

High Density Data Centers Fraught with Peril. Richard A. Greco, Principal EYP Mission Critical Facilities, Inc. High Density Data Centers Fraught with Peril Richard A. Greco, Principal EYP Mission Critical Facilities, Inc. Microprocessors Trends Reprinted with the permission of The Uptime Institute from a white

More information

Rittal Liquid Cooling Series

Rittal Liquid Cooling Series Rittal Liquid Cooling Series by Herb Villa White Paper 04 Copyright 2006 All rights reserved. Rittal GmbH & Co. KG Auf dem Stützelberg D-35745 Herborn Phone +49(0)2772 / 505-0 Fax +49(0)2772/505-2319 www.rittal.de

More information

Challenges In Intelligent Management Of Power And Cooling Towards Sustainable Data Centre

Challenges In Intelligent Management Of Power And Cooling Towards Sustainable Data Centre Challenges In Intelligent Management Of Power And Cooling Towards Sustainable Data Centre S. Luong 1*, K. Liu 2, James Robey 3 1 Technologies for Sustainable Built Environments, University of Reading,

More information

Best Practices. for the EU Code of Conduct on Data Centres. Version 1.0.0 First Release Release Public

Best Practices. for the EU Code of Conduct on Data Centres. Version 1.0.0 First Release Release Public Best Practices for the EU Code of Conduct on Data Centres Version 1.0.0 First Release Release Public 1 Introduction This document is a companion to the EU Code of Conduct on Data Centres v0.9. This document

More information

Power and Cooling for Ultra-High Density Racks and Blade Servers

Power and Cooling for Ultra-High Density Racks and Blade Servers Power and Cooling for Ultra-High Density Racks and Blade Servers White Paper #46 Introduction The Problem Average rack in a typical data center is under 2 kw Dense deployment of blade servers (10-20 kw

More information

Glossary of Heating, Ventilation and Air Conditioning Terms

Glossary of Heating, Ventilation and Air Conditioning Terms Glossary of Heating, Ventilation and Air Conditioning Terms Air Change: Unlike re-circulated air, this is the total air required to completely replace the air in a room or building. Air Conditioner: Equipment

More information

Raised Floor Data Centers Prepared for the Future

Raised Floor Data Centers Prepared for the Future Raised Floor Data Centers Prepared for the Future Raised Floors Protect My Investment by Providing a Foundation for Current and Future Technologies. Creating the Future Proof Data Center Environment The

More information

DataCenter 2020: hot aisle and cold aisle containment efficiencies reveal no significant differences

DataCenter 2020: hot aisle and cold aisle containment efficiencies reveal no significant differences DataCenter 2020: hot aisle and cold aisle containment efficiencies reveal no significant differences November 2011 Powered by DataCenter 2020: hot aisle and cold aisle containment efficiencies reveal no

More information

Data Center Energy Profiler Questions Checklist

Data Center Energy Profiler Questions Checklist Data Center Energy Profiler Questions Checklist Step 1 Case Name Date Center Company State/Region County Floor Area Data Center Space Floor Area Non Data Center Space Floor Area Data Center Support Space

More information

AisleLok Modular Containment vs. Legacy Containment: A Comparative CFD Study of IT Inlet Temperatures and Fan Energy Savings

AisleLok Modular Containment vs. Legacy Containment: A Comparative CFD Study of IT Inlet Temperatures and Fan Energy Savings WH I TE PAPE R AisleLok Modular Containment vs. : A Comparative CFD Study of IT Inlet Temperatures and Fan Energy Savings By Bruce Long, Upsite Technologies, Inc. Lars Strong, P.E., Upsite Technologies,

More information

Data Centre Testing and Commissioning

Data Centre Testing and Commissioning Data Centre Testing and Commissioning What is Testing and Commissioning? Commissioning provides a systematic and rigorous set of tests tailored to suit the specific design. It is a process designed to

More information

How High Temperature Data Centers & Intel Technologies save Energy, Money, Water and Greenhouse Gas Emissions

How High Temperature Data Centers & Intel Technologies save Energy, Money, Water and Greenhouse Gas Emissions Intel Intelligent Power Management Intel How High Temperature Data Centers & Intel Technologies save Energy, Money, Water and Greenhouse Gas Emissions Power and cooling savings through the use of Intel

More information

Green Data Centers development Best Practices

Green Data Centers development Best Practices Draft Recommendation ITU-T L.DC Green Data Centers development Best Practices Summary This recommendation is a contribution for the reduction of negative climate impact of Data Centers.

More information

Office of the Government Chief Information Officer. Green Data Centre Practices

Office of the Government Chief Information Officer. Green Data Centre Practices Office of the Government Chief Information Officer Green Data Centre Practices Version : 2.0 April 2013 The Government of the Hong Kong Special Administrative Region The contents of this document remain

More information

abstract about the GREEn GRiD

abstract about the GREEn GRiD Guidelines for Energy-Efficient Datacenters february 16, 2007 white paper 1 Abstract In this paper, The Green Grid provides a framework for improving the energy efficiency of both new and existing datacenters.

More information

Defining Quality. Building Comfort. Precision. Air Conditioning

Defining Quality. Building Comfort. Precision. Air Conditioning Defining Quality. Building Comfort. Precision Air Conditioning Today s technology rooms require precise, stable environments in order for sensitive electronics to operate optimally. Standard comfort air

More information

Improving Data Center Efficiency with Rack or Row Cooling Devices:

Improving Data Center Efficiency with Rack or Row Cooling Devices: Improving Data Center Efficiency with Rack or Row Cooling Devices: Results of Chill-Off 2 Comparative Testing Introduction In new data center designs, capacity provisioning for ever-higher power densities

More information

Data Center Technology: Physical Infrastructure

Data Center Technology: Physical Infrastructure Data Center Technology: Physical Infrastructure IT Trends Affecting New Technologies and Energy Efficiency Imperatives in the Data Center Hisham Elzahhar Regional Enterprise & System Manager, Schneider

More information

IMPROVING DATA CENTER EFFICIENCY AND CAPACITY WITH AISLE CONTAINMENT

IMPROVING DATA CENTER EFFICIENCY AND CAPACITY WITH AISLE CONTAINMENT DATA CENTER RESOURCES WHITE PAPER IMPROVING DATA CENTER EFFICIENCY AND CAPACITY WITH AISLE CONTAINMENT BY: STEVE HAMBRUCH EXECUTIVE SUMMARY Data centers have experienced explosive growth in the last decade.

More information

Doc Ref: 2015.06.01.002. 602.783.1112 baselayer.com 2015 BASELAYER TECHNOLOGY, LLC

Doc Ref: 2015.06.01.002. 602.783.1112 baselayer.com 2015 BASELAYER TECHNOLOGY, LLC TM 602.783.1112 baselayer.com 2015 BASELAYER TECHNOLOGY, LLC TM D400E Data Module (60Hz) The EDGE D400E is designed to meet high power density requirements for both the HPC and Web Scale environments while

More information

Energy Efficient Data Centre at Imperial College. M. Okan Kibaroglu IT Production Services Manager Imperial College London.

Energy Efficient Data Centre at Imperial College. M. Okan Kibaroglu IT Production Services Manager Imperial College London. Energy Efficient Data Centre at Imperial College M. Okan Kibaroglu IT Production Services Manager Imperial College London 3 March 2009 Contents Recognising the Wider Issue Role of IT / Actions at Imperial

More information

AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries

AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries Hot tips and cool ideas to save energy and money! Air conditioning units or systems are often used by foundries

More information

Tech Byte 27: Small Computer Room and IT Closet Cooling

Tech Byte 27: Small Computer Room and IT Closet Cooling Questions Answered in This Paper Sensible cooling capacity is the measuring stick for IT cooling capacity needs. What is the sensible cooling capacity of the comfort split system in comparison to the precision

More information

Cooling Audit for Identifying Potential Cooling Problems in Data Centers

Cooling Audit for Identifying Potential Cooling Problems in Data Centers Cooling Audit for Identifying Potential Cooling Problems in Data Centers By Kevin Dunlap White Paper #40 Revision 2 Executive Summary The compaction of information technology equipment and simultaneous

More information

Five Strategies for Cutting Data Center Energy Costs Through Enhanced Cooling Efficiency

Five Strategies for Cutting Data Center Energy Costs Through Enhanced Cooling Efficiency Five Strategies for Cutting Data Center Energy Costs Through Enhanced Cooling Efficiency A White Paper from the Experts in Business-Critical Continuity TM Executive Summary As electricity prices and IT

More information

Using Simulation to Improve Data Center Efficiency

Using Simulation to Improve Data Center Efficiency A WHITE PAPER FROM FUTURE FACILITIES INCORPORATED Using Simulation to Improve Data Center Efficiency Cooling Path Management for maximizing cooling system efficiency without sacrificing equipment resilience

More information

Using Simulation to Improve Data Center Efficiency

Using Simulation to Improve Data Center Efficiency A WHITE PAPER FROM FUTURE FACILITIES INCORPORATED Using Simulation to Improve Data Center Efficiency Cooling Path Management for maximizing cooling system efficiency without sacrificing equipment resilience

More information

Free Cooling in Data Centers. John Speck, RCDD, DCDC JFC Solutions

Free Cooling in Data Centers. John Speck, RCDD, DCDC JFC Solutions Free Cooling in Data Centers John Speck, RCDD, DCDC JFC Solutions Why this topic Many data center projects or retrofits do not have a comprehensive analyses of systems power consumption completed in the

More information

Carnegie Mellon University School of Architecture, Department of Mechanical Engineering Center for Building Performance and Diagnostics

Carnegie Mellon University School of Architecture, Department of Mechanical Engineering Center for Building Performance and Diagnostics Carnegie Mellon University School of Architecture, Department of Mechanical Engineering Center for Building Performance and Diagnostics A Presentation of Work in Progress 4 October 2006 in the Intelligent

More information

State of the Art Energy Efficient Data Centre Air Conditioning

State of the Art Energy Efficient Data Centre Air Conditioning - White Paper - State of the Art Energy Efficient Data Centre Air Conditioning - Dynamic Free Cooling - Release 2, April 2008 Contents ABSTRACT... 3 1. WHY DO I NEED AN ENERGY EFFICIENT COOLING SYSTEM...

More information

Improving Rack Cooling Performance Using Airflow Management Blanking Panels

Improving Rack Cooling Performance Using Airflow Management Blanking Panels Improving Rack Cooling Performance Using Airflow Management Blanking Panels By Neil Rasmussen White Paper #44 Revision 3 Executive Summary Unused vertical space in open frame racks and rack enclosures

More information

Liebert CRV Row-Based Cooling Intelligent Precision Cooling For Data Center Equipment. Precision Cooling For Business-Critical Continuity

Liebert CRV Row-Based Cooling Intelligent Precision Cooling For Data Center Equipment. Precision Cooling For Business-Critical Continuity Liebert Row-Based Cooling Intelligent Precision Cooling For Data Center Equipment Precision Cooling For Business-Critical Continuity The Intelligent Data Center Cooling Solution: Liebert Trust the industry

More information

Maximize energy savings Increase life of cooling equipment More reliable for extreme cold weather conditions There are disadvantages

Maximize energy savings Increase life of cooling equipment More reliable for extreme cold weather conditions There are disadvantages Objectives Increase awareness of the types of economizers currently used for data centers Provide designers/owners with an overview of the benefits and challenges associated with each type Outline some

More information

Optimizing Network Performance through PASSIVE AIR FLOW MANAGEMENT IN THE DATA CENTER

Optimizing Network Performance through PASSIVE AIR FLOW MANAGEMENT IN THE DATA CENTER Optimizing Network Performance through PASSIVE AIR FLOW MANAGEMENT IN THE DATA CENTER Lylette Macdonald, RCDD Legrand Ortronics BICSI Baltimore 2011 Agenda: Discuss passive thermal management at the Rack

More information

Hot Air Isolation Cools High-Density Data Centers By: Ian Seaton, Technology Marketing Manager, Chatsworth Products, Inc.

Hot Air Isolation Cools High-Density Data Centers By: Ian Seaton, Technology Marketing Manager, Chatsworth Products, Inc. Business Management Magazine Winter 2008 Hot Air Isolation Cools High-Density Data Centers By: Ian Seaton, Technology Marketing Manager, Chatsworth Products, Inc. Contrary to some beliefs, air is quite

More information

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01

UNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01 GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per

More information

2010 Best Practices. for the EU Code of Conduct on Data Centres. Version 2.0.0 Release Public Review Public

2010 Best Practices. for the EU Code of Conduct on Data Centres. Version 2.0.0 Release Public Review Public 2010 Best Practices for the EU Code of Conduct on Data Centres Version 2.0.0 Release Public Review Public 1 Document Information 1.1 Version History Version 1 Description Version Updates Date 2.0.0 2010

More information

The Benefits of Supply Air Temperature Control in the Data Centre

The Benefits of Supply Air Temperature Control in the Data Centre Executive Summary: Controlling the temperature in a data centre is critical to achieving maximum uptime and efficiency, but is it being controlled in the correct place? Whilst data centre layouts have

More information

AIR-SITE GROUP. White Paper. Green Equipment Room Practices

AIR-SITE GROUP. White Paper. Green Equipment Room Practices AIR-SITE GROUP White Paper Green Equipment Room Practices www.air-site.com Common practices to build a green equipment room 1 Introduction Air-Site (www.air-site.com) is a leading international provider

More information

Paul Oliver Sales Director. Paul Oliver, Airedale Tom Absalom, JCA

Paul Oliver Sales Director. Paul Oliver, Airedale Tom Absalom, JCA Paul Oliver Sales Director Paul Oliver, Airedale Tom Absalom, JCA Airedale an overview 25,000m 2 UK premier test centre 450 staff Global distribution A Modine company Modine centre of excellence Airedale

More information

Energy Recovery Systems for the Efficient Cooling of Data Centers using Absorption Chillers and Renewable Energy Resources

Energy Recovery Systems for the Efficient Cooling of Data Centers using Absorption Chillers and Renewable Energy Resources Energy Recovery Systems for the Efficient Cooling of Data Centers using Absorption Chillers and Renewable Energy Resources ALEXANDRU SERBAN, VICTOR CHIRIAC, FLOREA CHIRIAC, GABRIEL NASTASE Building Services

More information

White Paper Rack climate control in data centres

White Paper Rack climate control in data centres White Paper Rack climate control in data centres Contents Contents...2 List of illustrations... 3 Executive summary...4 Introduction...5 Objectives and requirements...6 Room climate control with the CRAC

More information