Why is my project red? What are the steps required to manage a project on a monthly basis in EPM 2010?

Size: px
Start display at page:

Download "Why is my project red? What are the steps required to manage a project on a monthly basis in EPM 2010?"

Transcription

1 Why is my project red? What are the steps required to manage a project on a monthly basis in EPM 2010?

2 Project Status Indicators in EPM 2010 Status determined by PM Auto Calculated These project indicators display in the Project Web App (PWA) Project Center or in the USIT Project Tracking View in MS Project Professional and they indicate quickly at-a glance what the status of the project is:

3 Project Status Indicators in EPM 2010 Red = Project requires management intervention Red = Scope is undefined and deviates from plan Red = Duration (schedule) variation greater than 20% Red = Work variation (cost) variation greater than 20% Determined by PM Determined by PM Auto Calculated Auto Calculated

4 Monthly Project Update Steps Step 1: Approve & publish timesheet updates Step 2: Review & update remaining work and reschedule incomplete work that is scheduled in the past Step 3: Respond to Project Variance Step 4: Update project indicators Overall Health, Scope & SDLC Phase) Step 5: Take corrective action (e.g. change request, rebaseline, etc.) if necessary. Step 6: Complete required SDLC Phase Documents Step 7: Create and Upload Monthly Status Report

5 Step 1: Approve & Publish Project Time Project time must be entered by each team member for the previous month by the 3 rd business day of the following month. Time entry report is sent by the PMO on the 4 th business day. Time should be accepted and status reports completed by the Project Manager by the 5 th business day. Project status reports cannot be done accurately without time being accepted.

6 Step 2: Review & Update Remaining Work Make any updates to remaining work for uncompleted tasks. Reducing remaining work on unfinished tasks could result in a positive change in the schedule or cost-work indicator (e.g., moving from yellow to green, or red to green).

7 Step 3: Respond to Project Variance Schedule The variance between the planned project finish date (baseline duration) to the current projected finish date (duration). Cost-Work The variance between the planned work effort (baseline cost) and the current forecasted cost for the project (cost).

8 Project Schedule Variance Duration /Baseline Duration (Planned) = Variance Variance greater than 20% Variance between 10 & 20% Variance within 10% No Baseline Schedule variance compares the scheduled or actual finish dates with the baseline start and finish dates.

9 Project Schedule Variance Project Schedule Variance Action Steps: Add more effort (units) to an unfinished task so that it can get done sooner. Add additional resources to an unfinished task so it can get done sooner. Reduce the amount of remaining work on any unfinished tasks. Close out any completed tasks by changing remaining work to 0. Submit a change request describing the change and the impact to the project plan and re-baseline (after change request has been approved).

10 Project Cost-Work Variance Cost /Baseline Cost (Planned) = Variance Variance greater than 20% Variance between 10 & 20% Variance within 10% No Baseline The Cost-Work status indicator will change if there is a variance greater than 10% between the planned cost (baseline cost) and the current forecasted cost for the project. Cost will increase if internal labor or consulting hours entered on the project are significantly more than what was planned for or if material costs (e.g., hardware, software, etc.) being tracked and they are more than planned.

11 Project Cost-Work Variance Project Cost-Work Variance Action Steps: Reduce the amount of remaining work on any unfinished tasks. Close out any completed tasks by changing remaining work to 0. Submit a change request describing the change and the impact to the project plan and re-baseline (after change request has been approved). Typically, more work (hours) need to be added to the project and the budget adjusted to reflect the additional hours).

12 Step 4: Update Project Indicators (Overall Health, Scope & SDLC Phase) Project overall health, scope and SDLC phase indicators are determined by the Project Manager and should be updated when there is a change. These indicators are part of the overall project information and can be updated in either Project Web App (PWA) or in MS Project Professional.

13 Step 5: Take Corrective Action (if needed) A Change Request should be submitted by the Project Manager to the Project Sponsor if there is significant change to the project such as change in scope, cost or schedule. In most cases, a project will need to be re-baselined after a change request has been approved by the Project Sponsor.

14 Step 6: Complete Required SDLC Phase Documents At each Solution Development Life Cycle (SDLC) phase there are required documents that must be completed for all Fast Track and Enterprise Projects in University Services and uploaded to the project SharePoint site. The Project Proposal for each project in EPM 2010 has a form that must be updated when the required phase documents are complete.

15 Step 7: Create & Upload Monthly Status Report SDLC Phase: Must match the information that displays in the USIT Monthly Status Report View. Executive Summary: Must match the information that displays in the US IT Monthly Status Report View. Work and Baseline Work should be the same and are entered as budgeted hours. Status indicators: Must match the indicators that display in the US IT Monthly Status Report View in EPM 2010 Project Web App (PWA). An Action Plan or an explanation should be listed for any indicator that is red or yellow Overall Health: Must match the overall health as determined by the PM. Indicate here if the project has moved to another SDLC phase since the last monthly report. This section is completed by the Project Manager and is used to inform Sponsors, Stakeholders and Team Members about the status of the project.

Managing Tasks with Microsoft Project Server, Project Online and Project Lite

Managing Tasks with Microsoft Project Server, Project Online and Project Lite Managing Tasks with Microsoft Project Server, Project Online and Project Lite for Microsoft Project Server 2013 (4 Hours) Course Overview After attending this course you will be able to Use the Project

More information

Commonwealth of Massachusetts CommonWay Schedule Management Guidelines. Common Values - Common Goals Common Way. Schedule Management.

Commonwealth of Massachusetts CommonWay Schedule Management Guidelines. Common Values - Common Goals Common Way. Schedule Management. Schedule Management Values - Goals Schedule Management Schedule Management v1.0 1 of 6 10/27/2010 Schedule Management Values - Goals Table of Contents 1 Schedule Management Guideline... 3 1.1 Determine

More information

Module 5 Cost Management PMP Exam Questions

Module 5 Cost Management PMP Exam Questions Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional

More information

PMO Metrics Recommendations

PMO Metrics Recommendations Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project

More information

PROJMGT 7840. Project Management Capstone Course. Project Progress Reporting

PROJMGT 7840. Project Management Capstone Course. Project Progress Reporting PROJMGT 7840 Project Management Capstone Course Project Progress Reporting Table of Contents Introduction...3 Weekly Progress Reports...4 Scheduled Reporting...4 Report Format...4 Final Project Report...5

More information

55034-Project Server 2013 Inside Out

55034-Project Server 2013 Inside Out Course Outline 55034-Project Server 2013 Inside Out Duration: 5 days (30 hours) Target Audience: This course is intended for anyone that will need to manage and use Project Server 2013. This includes the

More information

PHASE 8: IMPLEMENTATION PHASE

PHASE 8: IMPLEMENTATION PHASE PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the

More information

IMS Online Max. Clocking settings & warnings. Administrator Guide

IMS Online Max. Clocking settings & warnings. Administrator Guide IMS Online Max Clocking settings & warnings Administrator Guide Table of Contents Introduction... 3 Settings... 4 Snap & rounding rules... 4 Early start / Late finish warnings... 6 Managing clock data

More information

Implementing Gartner s PPM Reporting recommendations in Project Online and Project Server

Implementing Gartner s PPM Reporting recommendations in Project Online and Project Server Implementing Gartner s PPM Reporting recommendations in Project Online and Project Server Kenneth Steiness, CEO & Managing Partner Sensei Project Solutions SERVICES SOLUTIONS TRAINING APPS Microsoft PPM

More information

Note: This App is under development and available for testing on request. Note: This App is under development and available for testing on request. Note: This App is under development and available for

More information

2012 National BDPA Technology Conference. Defining Project and PMO Metrics

2012 National BDPA Technology Conference. Defining Project and PMO Metrics 2012 National BDPA Technology Conference Defining Project and PMO Metrics Betty Hutchins, MBA, PMP August 1 4, 2012 Baltimore, MD Presentation Objectives Project Performance Determine the Process Defining

More information

~Project Management Institute, Inc.

~Project Management Institute, Inc. Project The most crucial success factor in project management is effective communications to all stakeholders a critical core competency to all organizations. In a complex and competitive business climate,

More information

Microsoft Project Dissected

Microsoft Project Dissected Microsoft Project Dissected by Ron Winter, PSP Schedule Analyzer Software Copyright 2012 Third Annual Construction CPM Conference Introduction Although Oracle/Primavera P6 is dominant Many contracts specify/allow

More information

Implementing Project Server 2010

Implementing Project Server 2010 Implementing Project Server 2010 Course ISI-1327 4 Days Instructor-led, Hands-on Course Description This instructor-led course will provide you with the knowledge and skills to effectively install and

More information

Request for Project Approval

Request for Project Approval Date Issued: 04/13/2016 Page #: 1 of 5 1.0 POLICY OVERVIEW 1.1. This policy establishes uniform practices and procedures to be followed for authorizing ITD software projects. 1.2. LAUSD s Information Technology

More information

PHASE 6: DEVELOPMENT PHASE

PHASE 6: DEVELOPMENT PHASE PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product

More information

Tracking Project Progress

Tracking Project Progress L E S S O N 2 Tracking Project Progress Suggested lesson time 45-55 minutes Lesson objectives To begin tracking an active project, you will: a b c Modify the environment for tracking. You will use the

More information

Course 55034A: Microsoft Project Server 2013 Inside Out

Course 55034A: Microsoft Project Server 2013 Inside Out Course 55034A: Microsoft Project Server 2013 Inside Out Five days, instructor-led About this Course This 5-day Instructor Lead course how to work with Microsoft Project Server 2013. You will also create

More information

MINNESOTA STATE POLICY

MINNESOTA STATE POLICY Version: 2.00 Approved Date: 02/24/2012 Approval: Signature on file MINNESOTA STATE POLICY From the Office of Carolyn Parnell Chief Information Officer, State of Minnesota IT Project Portfolio Data Management

More information

Improve Project Team Collaboration Using Microsoft Project Online

Improve Project Team Collaboration Using Microsoft Project Online Improve Project Team Collaboration Using Microsoft Project Online Presented by Steven Vowles, PMP, CISA, MCTS Senior Program Director, Infor Consulting Services Global PMO April 29, 2016 1 Discipline!

More information

Project Execution, Monitoring and Control (IS PM 8. Lecture; 2012 Spring)

Project Execution, Monitoring and Control (IS PM 8. Lecture; 2012 Spring) Project Execution, Monitoring and Control Topics of the lecture as follows: PDCA cycle Project execution processes by PMBOK Project monitoring and controlling processes by PMBOK Project monitoring and

More information

Create Stoplight charts using Milestones Professional

Create Stoplight charts using Milestones Professional Stoplight Charts: Ideal for At-a-Glance Project Reporting Create Stoplight charts using Milestones Professional In a report which has extensive data, how can action items be quickly highlighted and addressed?

More information

Project Cost Management

Project Cost Management Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please

More information

National IT Project Management Methodology

National IT Project Management Methodology NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA National IT Project Management Methodology Project Reporting Support Guide Version 0.5 Project Reporting Support Guide version 0.5 Page 1 Document Version

More information

Microsoft Project 70-178 Exam Study Guide

Microsoft Project 70-178 Exam Study Guide Microsoft Project 70-178 Exam Study Guide Prepared by The Versatile Company for MPUG. www.versatilecompany.com The Versatile Company, 2012. About this Study Guide This guide was developed based upon the

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

PROJECT MANAGEMENT PLAN <PROJECT NAME>

PROJECT MANAGEMENT PLAN <PROJECT NAME> PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals

More information

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days 3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: rwhitney@discoveritt.com Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

Project Server 2013 Inside Out Course 55034; 5 Days, Instructor-led

Project Server 2013 Inside Out Course 55034; 5 Days, Instructor-led Project Server 2013 Inside Out Course 55034; 5 Days, Instructor-led Course Description This course will teach you how to work with Microsoft Project Server 2013. You will also create and manage projects

More information

Six sigma project management

Six sigma project management Six sigma project management Bizagi Suite Six sigma project management 1 Table of Contents Six Sigma Project Management... 3 Process Elements... 9 Project Charter... 9 Define... 11 Measure...12 Analyze...12

More information

Performance Testing: Migrating Large Lotus Notes Databases to Office 365

Performance Testing: Migrating Large Lotus Notes Databases to Office 365 Performance Testing: Migrating Large Lotus Notes Databases to Office 365 Using Notes Migrator for SharePoint Randy Rempel Senior Product Manager Published December, 2014 Table of Contents Introduction...

More information

A Framework for Project Metrics

A Framework for Project Metrics A Framework for Project Metrics Deciding what to measure and how to measure it August 13, 2007 Dr. Gary J. Evans, PMP CVR/IT Consulting LLC www.cvr-it.com Welcome! Focus of this workshop: Project Metrics

More information

1. INTRODUCTION...2 2. PRODUCT...2. 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2. 3. workbench features...2

1. INTRODUCTION...2 2. PRODUCT...2. 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2. 3. workbench features...2 Table of Contents 1. INTRODUCTION...2 2. PRODUCT...2 2.1. Installation... 2 2.2. Documentation... 2 2.3. Website... 2 3. workbench features...2 3.1. Project Planning... 2 3.2. Project Tracking... 3 4.

More information

Attachment 1. PGW IS expects to use the Demand Management and Project Prioritization tools and methodologies to:

Attachment 1. PGW IS expects to use the Demand Management and Project Prioritization tools and methodologies to: Attachment 1 1. Introduction 1.1 Overview Philadelphia Gas Works (PGW) has used Microsoft Project and Project Server to manage Information Services (IS) Projects since 2006. In 2014, PGW upgraded its Project

More information

Microsoft Project Server 2010 Project Manager s Guide for Project Web App

Microsoft Project Server 2010 Project Manager s Guide for Project Web App Microsoft Project Server 2010 Project Manager s Guide for Project Web App Copyright This document is provided as-is. Information and views expressed in this document, including URL and other Internet Web

More information

INTRODUCTION. Page 1 of 16

INTRODUCTION. Page 1 of 16 INTRODUCTION CALIFORNIA STATE TEACHERS RETIREMENT SYSTEM REQUEST FOR QUOTE JAMA LICENSING AND SERVICES RFQ NUMBER 201204 Offer Due Date: July 23, 2013, 2:00 p.m. Pacific Time (PT) The California State

More information

CA PA for CA Clarity PPM 14.2: Project and Investment Management 200

CA PA for CA Clarity PPM 14.2: Project and Investment Management 200 CA PRODUCTIVITY ACCELERATOR CONTENT DESCRIPTION CA PA for CA Clarity PPM 14.2: Project and Investment Management Content Overview PRODUCT RELEASE CA Clarity PPM 14.2 DURATION & COURSE CODE Three (3) Hours

More information

Creating Dashboards for Microsoft Project Server 2010

Creating Dashboards for Microsoft Project Server 2010 Creating Dashboards for Microsoft Project Server 2010 Authors: Blaise Novakovic, Jean-Francois LeSaux, Steven Haden, Microsoft Consulting Services Information in the document, including URL and other Internet

More information

ESKITP7145.01 Manage IT service delivery performance metrics

ESKITP7145.01 Manage IT service delivery performance metrics Overview This sub-discipline covers the competencies required to manage the monitoring, analysis and communication of IT service delivery performance metrics. Monitoring service level performance is a

More information

Pilot CSI Project Setup Guide

Pilot CSI Project Setup Guide Pilot CSI Project Setup Guide Table of Contents 1. Introduction... 3 2. Setting up Project Information... 4 3. MS Project Basics... 7 Versions, Licensing & Installation... 7 Configure MS Project to Connect

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

July 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services

July 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services John Keel, CPA State Auditor The ReHabWorks System at the Department of Assistive and Rehabilitative Services Report No. 12-045 The ReHabWorks System at the Department of Assistive and Rehabilitative Services

More information

Guidelines: Project Schedule Project Management Office (PMO)

Guidelines: Project Schedule Project Management Office (PMO) Guidelines: Project Schedule Project Management Office (PMO) Process The project Schedule outlines the tasks and activities of the project; the duration; start and end dates for each individual task and

More information

PMAP. Project Management At Penn PMAP

PMAP. Project Management At Penn PMAP Project Management At Penn 1 Fundamentals Course Objective To provide you with an overview of Topics Project Management at Penn () Project Governance Phases & Project Management Activities Project Management

More information

MS-55115: Planning, Deploying and Managing Microsoft Project Server 2013

MS-55115: Planning, Deploying and Managing Microsoft Project Server 2013 MS-55115: Planning, Deploying and Managing Microsoft Project Server 2013 Description The goal of this three-day instructor-led course is to provide students with the knowledge and skills necessary to effectively

More information

COMPANY LOGO. Project Charter Project Charter

COMPANY LOGO. Project Charter Project Charter Project Name Project Number The is created in the Initiating Process Group. Typically, a Project Manager, external to the project, writes the as an objective assessment. It formally authorizes the project

More information

PHASE 6: DEVELOPMENT PHASE

PHASE 6: DEVELOPMENT PHASE PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution

More information

CDC UNIFIED PROCESS JOB AID

CDC UNIFIED PROCESS JOB AID Purpose The purpose of this document is to provide guidance on the practice of using Microsoft Project and to describe the practice overview, requirements, best practices, activities, and key terms related

More information

Managing Projects with SharePoint

Managing Projects with SharePoint Managing Projects with SharePoint Building a Collaborative Project Management System with SharePoint 2013 PRESENTED BY: Brittany Kwait, PMP October 2014 Protiviti @BritKwait brittany.kwait@protiviti.com

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

Project Management. Gregory Zelfond PMI SOC GTIS Branch April 18, 2013

Project Management. Gregory Zelfond PMI SOC GTIS Branch April 18, 2013 Utilizing SharePoint for Project Management Gregory Zelfond PMI SOC GTIS Branch April 18, 2013 My Experience with SharePoint My experience with SharePoint Project Sites www.gregoryzelfond.com 2 Agenda

More information

Project Online: User Management

Project Online: User Management Project Online: User Management 1 P age Contents Project Online Licensing...3 How to check Project Online Licenses...3 Permission mode...5 How to change the Permission Mode...6 How to add users in SharePoint

More information

IBM Software Testing and Development Control - How to Measure Risk

IBM Software Testing and Development Control - How to Measure Risk IBM Software Group Practical Approaches to Development Governance 2007 IBM Corporation Program parameters (cost, schedule, effort, quality, ) are random variables Area under curve describes probability

More information

Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources

Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources Project Management for Small Business Moderator: Maria Mancha Frontline Systems, Inc. Objectives Project Management Overview Successful Project Fundamentals Additional Training Resources Project Management

More information

Swisscom Mobile Device Services Quick Start Guide: Set-up Remote Management basic. Mobile Device Services Februar 2014

Swisscom Mobile Device Services Quick Start Guide: Set-up Remote Management basic. Mobile Device Services Februar 2014 Swisscom Mobile Device Services Quick Start Guide: Set-up Remote Management basic Mobile Device Services Februar 2014 Contents 2 Login «Welcome to Swisscom MDS» First steps Step 1: Installing the MDM certificate

More information

When Project Management meets Agile

When Project Management meets Agile When Project Management meets Agile By Adam Ryall 19 May 2014 Overview This whitepaper provides a summary of the points discussed in the Core Consulting Group Breakfast Event held in April 2014 Author

More information

Using Financial Planning to Assist in Successful Dairy Farm Development

Using Financial Planning to Assist in Successful Dairy Farm Development Using Financial Planning to Assist in Successful Dairy Farm Development Kevin Connolly Financial Management Specialist Teagasc Farm Management and Rural Development Knowledge Transfer Planning at farm

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

Request for Resume (RFR) for Project Manager (Senior) CATS+ Master Contract All Master Contract Provisions Apply. Section 1 General Information

Request for Resume (RFR) for Project Manager (Senior) CATS+ Master Contract All Master Contract Provisions Apply. Section 1 General Information Request for Resume (RFR) for Project (Senior) Section General Information RFR Number: (Reference BPO Number) Functional Area (Enter One Only) Q00R00 BPO # 060B900 in ADPICS Functional Area 0 IT Management

More information

Using Financial Planning to Assist in Successful Dairy Farm Development

Using Financial Planning to Assist in Successful Dairy Farm Development Using Financial Planning to Assist in Successful Dairy Farm Development Kevin Connolly Financial Management Specialist Teagasc Farm Management and Rural Development Knowledge Transfer Planning at farm

More information

MICROSOFT PROJECT 2010 - II

MICROSOFT PROJECT 2010 - II MICROSOFT PROJECT 2010 - II Course Material This 2-day course is for intermediate and advanced users of the MS Project scheduling application who want to increase their capabilities managing projects in

More information

Richmond SharePoint User Group. Project Management Tools in SharePoint Bob Ramos and Greg Brown

Richmond SharePoint User Group. Project Management Tools in SharePoint Bob Ramos and Greg Brown Richmond SharePoint User Group January 2011 Project Management Tools in SharePoint Bob Ramos and Greg Brown Project Management Tools 1. Who has the excel checklist? 2. Where are latest weekly report updates?

More information

Managing Projects and Portfolios in the Enterprise with Oracle Primavera. Key prerequisites for a successful approach.

Managing Projects and Portfolios in the Enterprise with Oracle Primavera. Key prerequisites for a successful approach. An ASG Group White Paper April 2012 Managing Projects and Portfolios in the Enterprise with Oracle Primavera. Key prerequisites for a successful approach. EXECUTIVE OVERVIEW The management of projects

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT 7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major

More information

Cash flow is the life line of a business. Many start-up

Cash flow is the life line of a business. Many start-up PM.02 ABC of Cash Flow Projections Mark T. Chen, PE CCE Cash flow is the life line of a business. Many start-up companies fail because of insufficient cash flow. From the perspectives of both owner and

More information

OVERVIEW. Microsoft Project terms and definitions

OVERVIEW. Microsoft Project terms and definitions PROJECT 2003 DISCLAIMER: This reference guide is meant for experienced Microsoft Project users. It provides a list of quick tips and shortcuts for familiar features. This guide does NOT replace training

More information

CA Clarity PPM pro Business PMO a IT PMO. Petr Běhávka CA Technologies, Principal Consultant

CA Clarity PPM pro Business PMO a IT PMO. Petr Běhávka CA Technologies, Principal Consultant CA Clarity PPM pro Business PMO a IT PMO Petr Běhávka CA Technologies, Principal Consultant What is the Goal for PPM? Grow Revenues & Profits Higher Revenues & Profits Visibility Control Reduce Costs Agility

More information

Project Management through

Project Management through Project Management through Unified Project and Portfolio Fluent User Interface Management Built on SharePoint Server 2010 Time Reporting Enhancements Project Initiation & Business Case Exchange Server

More information

The date the initiative has been given approval to proceed. This excludes any initiatives in start-up or concept stage.

The date the initiative has been given approval to proceed. This excludes any initiatives in start-up or concept stage. Data glossary This glossary provides definitions of the terms related to data collection for this site. It has been provided so that interested parties can quickly and easily check the terms as they encounter

More information

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the

More information

IESO Information & Technology Services Group Roles, Responsibilities, and Project Management. Doug Thomas: VP- I&TS and CIO May 28, 2015

IESO Information & Technology Services Group Roles, Responsibilities, and Project Management. Doug Thomas: VP- I&TS and CIO May 28, 2015 IESO Information & Technology Services Group Roles, Responsibilities, and Project Management Doug Thomas: VP- I&TS and CIO May 28, 2015 IESO I&TS: Presentation Agenda Group Overview Roles and responsibilities

More information

OmniPlan for Mac Reviewer s Guide

OmniPlan for Mac Reviewer s Guide OmniPlan for Mac Reviewer s Guide 2 Overview What is OmniPlan? OmniPlan is a professional-grade project management application that's designed with the Mac in mind. It can be used to manage projects of

More information

SELECTING PROJECT MANAGEMENT SOFTWARE

SELECTING PROJECT MANAGEMENT SOFTWARE SELECTING PROJECT MANAGEMENT SOFTWARE Information needs People at different levels within an organization have different information needs. Information should be made available to all as needed, in a standardized

More information

Status Report Guidelines

Status Report Guidelines Values - Goals.doc 1 of 8 10/27/2010 Values - Goals Table of Contents 1 Status Report Overview... 3 1.1 Status Report Type... 3 1.2 Instructions Monthly... 4 1.3 Instructions Weekly... 6.doc 2 of 8 10/27/2010

More information

Project Management Quick Reference Guide for MS Project 2010

Project Management Quick Reference Guide for MS Project 2010 Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

TimeNet (API) portal. 1. Type in user name and password: (note: user name and password is the same as your GHSU email user name and email password)

TimeNet (API) portal. 1. Type in user name and password: (note: user name and password is the same as your GHSU email user name and email password) TimeNet (API) portal 1. Type in user name and password: (note: user name and password is the same as your GHSU email user name and email password) By checking the Quick badge only, and then clicking on

More information

55115 - Planning, Deploying and Managing Microsoft Project Server 2013

55115 - Planning, Deploying and Managing Microsoft Project Server 2013 55115 - Planning, Deploying and Managing Microsoft Project Server 2013 Duration: 3 Days Course Price: $1,785 Software Assurance Eligible Course Description Course Overview The goal of this three-day instructor-led

More information

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP

www.pmworldjournal.net Featured Paper Satya Narayan Dash By Satya Narayan Dash, PMP, CSM, MCP PMBOK Guide 5 th Edition and MS Project 2010: A Practical Step-by-Step Approach 1. Abstract By Satya Narayan Dash, PMP, CSM, MCP Project Management Body of Knowledge (PMBOK) Guide, from PMI, comes with

More information

Project and Resource Management: A Do-it-Yourself guide

Project and Resource Management: A Do-it-Yourself guide Project and Resource Management: A Do-it-Yourself guide By Shyam Kapoor Prisio Technologies LLC Introduction As per Gartner about one third of the projects are never complete and more than half exceed

More information

RED-AMBER-GREEN STOPLIGHTS IN MICROSOFT PROJECT

RED-AMBER-GREEN STOPLIGHTS IN MICROSOFT PROJECT RED-AMBER-GREEN STOPLIGHTS IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP, PMI-SP, MVP For Additional Information about Earned Value Management Systems and reporting, please contact: CelerisSystems,

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

IT Project Management Methodology. Project Scope Management Support Guide

IT Project Management Methodology. Project Scope Management Support Guide NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...

More information

Manager Domain Experts. Delivery Team. C h ic a g o

Manager Domain Experts. Delivery Team. C h ic a g o Outsourc es erv ice Engagement Domain Experts Vendor Account er d i ov Pr Finance Executive Sponsor Bo sto n C h ic a g o Project Empowering Agile with PPM Digite, Inc. 21060 Homestead Rd, Suite 220, Cupertino,

More information

Sound Transit Internal Audit Report - No. 2014-3

Sound Transit Internal Audit Report - No. 2014-3 Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management

More information

PROJECT TRACKING and CONTROL

PROJECT TRACKING and CONTROL PROJECT TRACKING and CONTROL 1 Outline of Project Tracking & Control 2 Project Planning & Control Context 3 Realistic and Measurable Plans Create Measurable Plans! 4 Data Sources for Project Tracking 5

More information

ITS Project Management

ITS Project Management ITS Project Management Policy Contents I. POLICY STATEMENT II. REASON FOR POLICY III. SCOPE IV. AUDIENCE V. POLICY TEXT VI. PROCEDURES VII. RELATED INFORMATION VIII. DEFINITIONS IX. FREQUENTLY ASKED QUESTIONS

More information

Project Management Methodology

Project Management Methodology Project Management Methodology 1/6/2015 PAGE 1 OF 28 Version 2.0 Contents INTRODUCTION... 4 1. Overview... 4 PHASE 1 PROJECT INITIATION... 5 1. Governance Model... 6 2. Project Prioritization Process...

More information

Creating a project management office (PMO)

Creating a project management office (PMO) Executive summary The project management was initially developed to define and maintain standards for project management in the organisation. In many organisations, the PMO has developed a strategic role

More information

EPMLive Product Review by Eval Source

EPMLive Product Review by Eval Source Features: Project Management, Gantt chart, Document Management, Project Portfolio, Time Management, Collaboration, Mobility Industry: Non Specific Customers: Small, Medium and Large Business Geography:

More information

Project Management by Using MS PROJECT 2013

Project Management by Using MS PROJECT 2013 Project Management by Using MS PROJECT 2013 Program is offered by: 3D Educators Trainers & Consultants Table of Contents Detail Inauguration Structure Topics & Time Allocation Other Learning Activities

More information

Ver. 1.8. Remarks 26-4- 2013. Introduced (Copy resource from One Work package to another work package ) 07-06- 2013

Ver. 1.8. Remarks 26-4- 2013. Introduced (Copy resource from One Work package to another work package ) 07-06- 2013 Ver. 1.8 Date Version Created by Reviewed by Reviewed date 26-Apr-13 1.5 Charu Jain Manjanath Hegde/RKL/Ch andrasekhar Daglur 07-May-13 1.6 Bimal Shahi Manjanath Hegde 25-sept-13 1.7 Niranjan / Arun Kumar

More information

Scope Management Guideline August, 2015

Scope Management Guideline August, 2015 Scope Management Guideline August, 2015 Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Scope Management Overview... 1 Charter... 4 Scope Statement...

More information

Asset Management & Capital Project Management System Review

Asset Management & Capital Project Management System Review Asset Management & Capital Project Management System Review October 21, 2013 Citywide Capital Systems Review Introduction 2 Goals Share findings of Controller s Office survey of asset management and capital

More information

MS Project 2007 Certification

MS Project 2007 Certification MS Project 2007 Certification Consultant/Trainer What are the new Certifications? Desktop Technology Specialist. Demonstrates competency in the use of Microsoft Office Project Professional 2007 to plan

More information

CA Clarity PPM. Business Objects Universe Developer Guide. v13.0.00

CA Clarity PPM. Business Objects Universe Developer Guide. v13.0.00 CA Clarity PPM Business Objects Universe Developer Guide v13.0.00 This documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation

More information