National IT Project Management Methodology
|
|
|
- Crystal Parrish
- 9 years ago
- Views:
Transcription
1 NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA National IT Project Management Methodology Project Reporting Support Guide Version 0.5 Project Reporting Support Guide version 0.5 Page 1
2 Document Version Control Version Date Author Change Description Gerald Kisongoch, PMP. Draft Gerald Kisongoch,PMP, PMI-RMP Content Review Abdul Nsubuga, PMP Document general review and restructuring July 2013 Taskforce Incorporated Workshop comments Projects Reporting Support Guide version 0.5 Page 2
3 Table of Contents 1. INTRODUCTION Project Reporting Overview SCALABILITY MONITORING PROJECT PERFORMANCE REPORTING PROJECT PERFORMANCE REPORTING SCHEDULE Projects Off-Track and Exception Reporting Performance Reports Pipeline Report Project Status Report Project Finance Report Project Cost Tracker Dashboard Report PERFORMANCE REPORT DEFINITIONS Project / Programme Health Project Health (Traffic Light) Indicators Delivery Confidence Project Governance Business Change Management Benefits Realisation Project Dependency Project Resourcing Project Scope PROJECT STAGE GATES Project Stage Gate Definitions PROJECT SCHEDULE INDICATORS PROJECT BUDGET INDICATORS Projects Reporting Support Guide version 0.5 Page 3
4 1. Introduction 1.1 Project Reporting Overview This document provides guidance on the performance reporting used to monitor and control projects using the guidelines provided in the National IT Project Management Methodology. The guidelines in this document have been developed to ensure all IT projects in government apply similar control mechanisms and report in a consistent manner. It is designed to be used by stakeholders who are participating in the project and are required to provide project reports Project progress should be monitored and reported throughout the project life-cycle to be able to establish the follow among other aspects: 1) Measure objectives and outcomes presented in the Business case VS the actual deliverables 2) Monitor whether the business case is still justified 3) Assess that the project still meets Business / Institution needs 4) Measure what is actually achieved against the baseline (time, budget and quality) 5) Assess what remains to be achieved and the effort required to achieve it 6) Update plans and revise forecasts 7) Identify what control actions and corrective actions are required to keep the project on track 8) Establish how efficiently are we using resources 9) Forecast what the project is likely to cost and time required 10) Provide the basis for lessons learned 11) Obtain performance metrics to provide estimates for future projects Projects Reporting Support Guide version 0.5 Page 4
5 2. Project Reporting Scalability 2.1 The project reports will look similar for all projects regardless of their key characteristics of size, risk and complexity. The only difference between projects reporting will be the level of granularity applied to the monitoring and control activities. For example small projects, Project team may only monitor summary performance information at the overall project level, such as, the start and end dates and total spend against total budget, whilst a medium and large projects monitor at a much lower level of detail down to key milestone and key deliverables start and finish timelines, key dependencies, monthly spend by activity/cost element against budget, risks, issues, changes and forecasts among others. 2.2 It is the Project Managers responsibility to engage with the Steering Committee and other stakeholders to agree on the appropriate level of details for their project reports. 3. Monitoring Project Performance 3.1 Project performance should be monitored and controlled against the approved business case, project management plan and project baselines to ensure the project is delivered to the agreed timelines, cost and expected quality deliverables. Controlling the project baseline is absolutely essential to project success. Project quality will be monitored using the project health indicators and project quality assurance and controls, which must be agreed up in the early stages (initiation and planning) of the project. 3.2 Table 1 below provides guidelines for the performance reports expected throughout the lifecycle of a project: Projects Reporting Support Guide version 0.5 Page 5
6 Table 1: Guidelines on Performance Reports Project Status Definition Report Type Project Initiation Funnel Pipeline Project is proposed and awaiting approval and funding to proceed. Project is committed and is awaiting funding approval, and Project Manager to be assigned to enable it to start. Pipeline Report Active In Progress The project is in-progress in its project planning or execution or stages Close-out Project Manager is being de-assigned and the project accounts are still open until all project costs are accounted for or until the financial year has closed. In-active Deferred The project is on hold or deferred to be re-started at a later date. Project Status Report Project/Programme Summary Report Dashboard Report Finance Report Earned Value Report (optional) Exception Report (for projects off-track) Final Project Status Report Final Project/Programme Summary Report Final Dashboard Report Final Finance Report Procurement status report Dashboard Report Finance Report Cancelled Closed The project is cancelled, the project manager is deassigned and the project accounts are closing or closed. Project Manager has been de-assigned and the project and finances have been closed. Final Project Status Report Final Project/Programme Summary Report Final Dashboard Report Final Finance Report Post Implementation Review 4. Reporting Project Performance Projects Reporting Support Guide version 0.5 Page 6
7 4.1 The performance reporting process involves the collection of all project/programme data, and distribution of performance information to stakeholders. Project performance should be reported at a detailed level for each individual project, and a one-page overview produced to report performance of all projects in the MDA. 4.2 All projects In-progress, the Project Manager should report on project performance each month, as a minimum. At the end of the Project Close-out stage, and before the project manager is de-assigned and the project is formally Closed, a final project closure report should be produced. 4.3 The table below outlines the project performance areas that should be monitored and controlled to maximise the success of a project: Table 2: Project Performance Areas to be Monitored and Controlled Monitoring Performance: Project Schedule against the Baseline Project Spend against the Baseline Budget Project Health Reporting: The actual and estimated start and completion dates for the project, stages and milestones are reported to monitor any deviation from the agreed baseline start and completion dates. If the deviation from the agreed baseline is greater than the agreed threshold for performance corrective action will be required. A baselined Project Implementation Plan will be the source of information. The actual spend and forecast cost at completion is reported to monitor any deviation from the agreed baseline budget. If the deviation from the agreed baseline is greater than the agreed threshold for performance corrective action will be required. Approved Budget will be the baseline source of information Traffic Light indicators are reported to monitor the health of a project and identify whether corrective Projects Reporting Support Guide version 0.5 Page 7
8 Project Achievements Project Outlook Escalated Risks Escalated Issues action is required in the following areas: o Delivery Confidence o Project Governance o Business Change o Benefits Realisation o Project Dependency o Project Resourcing o Project Scope The definitions section of this document describes how to apply these indicators. The actual achievements of the project within a set time period should be reported to monitor the progress of the project. An achievement is generally the completion of a key milestone or key deliverable, and the set time period is usually aligned to the reporting schedule i.e. over the previous reporting month. The project outlook monitors the planned achievements of the project over a set time period, which is usually aligned to the reporting schedule i.e. over next reporting month. The combination of Achievements and Outlook provides another checking mechanism for project performance i.e. if the achievements that were planned within a set time period were not actually achieved with that time period, the project may be experiencing problems with delay. The escalated risks are those that are of high impact and probability and cannot be mitigated within the threshold of the project and have been escalated to the Steering Committee for higher level management prevention. These are taken from the project Risk Log and closely monitored as they could severely impact the successful delivery of the project. The escalated issues are those that are of high impact and cannot be resolved within the threshold of the project and have therefore been escalated to the Steering Committee for higher level management Projects Reporting Support Guide version 0.5 Page 8
9 intervention and corrective action. These are taken from the project Issue Log and closely monitored as they are severely impacting the successful delivery of the project. 5. Reporting Schedule Project managers should produce projects and/or programmes performance reports monthly. The following report schedule should be observed. 5.1 Projects Off-Track and Exception Reporting Despite an exceptionally well planned project, the actual performance of the project may not always achieve the agreed thresholds set out in the project management plan, due to unforeseen influencing factors, namely risks and issues. The Project Manager should always agree the performance thresholds for each project with the Sponsor and Steering Committee, as percentage margins of time, cost and quality. This should allow actual performance to fluctuate within these percentage margins and the project will still be considered under control. The Project Manager should produce an Exception Report to advise the Steering Committee that the plan has deviated or is predicted to deviate, significantly, outside of its agreed threshold margins. An exception report describes the forecast deviation, and provides analysis of both the exception and corrective action in terms of cost, time and quality. The recommended options to bring the project back on track should also highlight any impact on the benefits stated in the business case to ensure its continued viability. Template is available in the project reporting tool kit. 5.2 Performance Reports All projects should produce performance reports unless there are exceptional circumstances and the Steering Committee. Template is available in the project reporting tool kit. Projects Reporting Support Guide version 0.5 Page 9
10 5.3 Pipeline Report The Pipeline Report should be produced to provide a high level view of all proposed projects that are in either Funnel or Pipeline status, in the Project initiation stage. Each proposed initiative is reviewed and prioritised, on a regular basis, as part of the business as usual planning process to decide whether it is a viable proposition, and therefore should be allocated funding to proceed. Template is available in the project reporting tool kit. 5.4 Project Status Report The Project Status Report should be produced monthly to enable key stakeholders track project schedule and budget against the baseline plan, assess the project health, and monitor risks, issues and changes. The information supplied in this report should be used to produce Dashboard Reports as part of the monthly reporting cycle. Template is available in the project reporting tool kit. 5.5 Project Finance Report The Project Finance Report should be produced monthly to track actual spend and forecast costs against the baseline Budget. The report should include the summary KPI information that can be extracted from the Project Cost Tracker. The summary finance information should be used to produce Dashboard Reports. Template is available in the project reporting tool kit. 5.6 Project Cost Tracker The Project Cost Tracker should be maintained by the by the Project Manager to capture and track the detailed project costs and latest forecasts. It is recommended that the project manager updates the Project Cost Tracker on a weekly basis and extracts the summary KPI information to update the Project Finance Report. Template is available in the project reporting tool kit. Projects Reporting Support Guide version 0.5 Page 10
11 5.7 Dashboard Report The Dashboard Report should be produced monthly to provide key stakeholders with a summary of project performance. The report provides KPI information on project schedule and budget against the baseline plan and project health. Template is available in the project reporting tool kit. 6. Performance Report Definitions 6.1 Project / Programme Health A project health should be monitored in the following areas indicators: 1) Delivery Confidence 2) Project Governance 3) Business Change Management 4) Benefits Realisation Plan 5) Project Dependency 6) Project Resourcing 7) Scope Guidance on Programmes: When reporting status on programme health, determine the overall importance of each project that is included within the Programme. Based on the project s health in a given area and based on the Programme Manager s judgement of all the factors influencing the overall performance of the programme the overall health of the Programme can be determined. Note: this is an informed but subjective view of project/programme health. Table 3: Project Health Reporting Tool Project Name:... Implementing Agency:... Project Manager:... Reporting Period:... No. Project Health Indicator Projects Reporting Support Guide version 0.5 Page 11
12 (Dashboard Elements) 1 Delivery Confidence 2 Project Governance 3 Business Change Management 4 Benefits Realisation Plan 5 Project Dependency 6 Project Resourcing 7 Scope Overall Project Health Project Managers Signature and Date: Steering Committee Chairperson Signature and Date: Table 4: Programme Health Reporting Tool Programme Name:... Implementing Agency:... Project A:... Project B:... Project C:... Period of Reporting:... Project A Project B Project C No. Health Indicator (Dashboard Elements) 1 Delivery Confidence 2 Project Governance Projects Reporting Support Guide version 0.5 Page 12
13 3 Business Change Management 4 Benefits Realisation Plan 5 Project Dependency 6 Project Resourcing 7 Scope Overall Project Health Overall Programme Health Project Manager Name, Sign & Date Steering Committee Sign Off 6.2 Project Health (Traffic Light) Indicators Traffic light indicators should highlight the health status of the project/programme to the best of the Project Manager's knowledge and judgement. Amber and Red indicators should be used to highlight whether the project is experiencing issues that may impact its success if corrective action is not taken in time Although Amber and Red indicators signal the need for management attention, the Project Manager should also follow normal escalation channels via the Steering Committee to escalate risks and issues that need management intervention. Table 5: Overall Programme / Project Health Indicators Definitions Traffic Light Green Definition Programme/project is performing within the agreed thresholds for the specified health indicator, and although there may be issues, these are Projects Reporting Support Guide version 0.5 Page 13
14 Amber Red under control and are not expected to impact the ability to deliver the project with the agreed thresholds. There are risks and issues affecting the health of the project that may impact the ability to deliver the project within the agreed thresholds. A corrective action plan in place/being agreed with higher management and the project is being monitored as high risk. The return to green comments should specifically state the level to which the issues have been escalated and what corrective action is being taken. An Exception Report may be required if there are significant risks with a number of health indicators that will impact the ability to deliver the project within the agreed thresholds. There are serious issues affecting the health of the project that are significantly impacting the ability to deliver the project, the project has exceeded its threshold The issues have been escalated for higher management attention for resolution, and a plan for corrective action is already in place. The return to green comments should specifically state the level to which the issues have been escalated and what corrective action is being taken. 6.3 Delivery Confidence This provides an overall indicator of the level of confidence in project delivery, based on the reported status of the other dashboard elements and latest estimates at completion It is recognised that large complex programmes/projects contain a mixture of good progress and problematic issues. The project/programme manager will use their judgment and insight to select the appropriate indicator using the guidelines as a common framework for their decision-making. Table 6: Delivery Confidence Indicators Definitions Traffic Light Green Amber Definition High: The project is running smoothly. Any issues experienced by project are under control and there is confidence that the project will be delivered within the agreed thresholds of time, quality and cost, and the benefits outlined in the business case are achievable. Medium: The project is experiencing some issues, which require Projects Reporting Support Guide version 0.5 Page 14
15 management attention as they may impact the ability to delivery project within the agreed thresholds of time, quality, cost or the benefits outlined in the business case. A corrective action plan in place/being agreed with higher management and this area is being monitored as high risk. The return to green comments should specifically state the level to which the issues have been escalated and what corrective action is being taken. Red Low: The project/programme is not performing within the agreed thresholds of the project management plan, as there are significant issues impacting the schedule, budget, quality, or benefits delivery that have been escalated to higher management for intervention and corrective action. The project/programme plan maybe undergoing a re-baseline and will require higher management attention until the issues are considered as under control and confidence in the delivery of the project has been regained. 6.4 Project Governance This indicates whether an appropriate governance structure is in place, the effectiveness of the governance structure and associated processes, and the engagement of key stakeholders. Table 7: Project Governance Indicators Definitions Traffic Light Green Definition Active/ Full Representation: An effective and clear governance structure has been implemented that is setting direction and actively managing major project issues on a regular basis. All appropriate stakeholder groups are represented within the process. Amber Active/ Partial Representation: A governance structure has been implemented, setting direction but not actively managing major project issues on a regular basis. Not all stakeholder groups are represented within the structure, and/or the structure is not entirely clear. Although this is not immediately impacting the ability to deliver successfully, corrective action is needed, and this area should be monitored as high risk. Red None/ Not Effective: No governance structure is in place, or the existing governance structure is ineffective, e.g. inappropriate stakeholder representation to ensure effective management decisions/intervention. There is a significant risk the governance structure will not be able to resolve project issues if/when they arise. Projects Reporting Support Guide version 0.5 Page 15
16 6.5 Business Change Management This indicates the readiness of the business with regards to managing and supporting the business and the human side of change, ensuring any new processes required are defined, the targeted community is ready, willing and able to utilise the new processes and tools and a change management implementation plan exists. Table 8: Business Change Management Indicators Definitions Traffic Light Green Amber Red Definition Actively Managed: The following framework of activities are underway: The impact of changes and the risks involved have been analysed and are being actively managed. Any new processes required have been defined, or plans exist to define them. Stakeholders are involved and are actively preparing for the transition. Business Change management Plans have been built and are being executed. The appropriate communications and training are being provided. Incentives are being provided to stakeholders to realise the change. Change agents are identified and equipped with reasons for and advantages of the change Top management support exists Minor Issues/Major Risks: The issues experienced in this area are considered as under control and a corrective action plan is being/has been agreed with higher management and this area is being monitored as high risk. Significant Issues: Significant issues exist in this area, which need immediate attention, as there is a significant impact on the successful delivery of the project due to inability of the business to effectively accept and adopt the change. The return to green comments should specifically state the level to which the issues have been escalated and what corrective action is being taken. 6.6 Benefits Realisation Projects Reporting Support Guide version 0.5 Page 16
17 6.6.1 This indicates whether the Institution has developed, documented and committed to a robust benefits realisation plan that will ensure all planned benefits are realised when the project is completed. Table 9: Benefits Realization Indicators Definitions Traffic Light Green Definition The Benefits Realisation Plan is documented to ensure the benefits outlined in the business case are achieved. Amber Red The Benefits Realisation Plan has been documented and agreed; however, the benefits may not be realized due to changes in environment or policy The Benefits Realisation Plan has not been formulated. The return to green comments should specifically state the level to which the issues have been escalated and what corrective action is being taken. 6.7 Project Dependency This indicates how well project dependencies are being managed. Table 10: Project Dependency Indicators Definitions Traffic Light Green Amber Red Definition Agreed and managed: All external and internal project dependencies have been identified. All relevant meetings with all parties have been set-up and the project plans have been integrated with those of the affected parties. Low risk of dependencies impacting the ability to deliver the project/programme successfully. Minor Issues/High Risk: There are issues, which may delay, or cause material changes to the project due to a dependency on an affected party or another project. The dependencies are either 1) being managed with the risk of impact being closely monitored and controlled, or 2) a corrective action plan is in place/being agreed with higher management to prevent the dependencies from having an impact. Impact is considered as under control and being monitored as high risk. Significant Issues: There is a major impact on the ability to deliver the project due to dependencies either 1) not having been identified or 2) being unmanageable. The issues have been escalated to higher management for intervention and corrective action, to enable the project to be delivered within the agreed thresholds. Projects Reporting Support Guide version 0.5 Page 17
18 6.8 Project Resourcing This indicates the status of project resources. Project managers provide their management judgment and insight on the appropriateness of the number and quality of their resources. Table 11: Project Resourcing Indicators Definitions Traffic Light Green Amber Red Definition Fully Resourced: All resources have been identified in the plan or are already assigned. Minor Issues/High Risk: Resources have not been identified, or made sufficiently available, or do not have the right capabilities to deliver the project work required. The issue with resources is either 1) being managed with the risk of impact being closely monitored and controlled, or 2) a corrective action plan is in place/being agreed with higher management. Impact is considered as under control and being monitored as high risk. Significant Issues: The project is significantly under-resourced, which is having a major impact on the ability to deliver within the agreed thresholds. The issues have been escalated to higher management for intervention and corrective action, to enable the project to be delivered within the agreed thresholds. 6.9 Project Scope This indicates how well the scope is being managed and all changes are being controlled. Table 12: Project Scope Indicators Definitions Traffic Light Green Definition Stable: Scope is well defined and a robust change control process is in place and being strictly adhered to. All changes have been assessed effectively and can be delivered within the agreed thresholds of the project. Project scope is considered as stable. Projects Reporting Support Guide version 0.5 Page 18
19 Amber Red Minor Issues/High Risk: There are a number of issues which may require a change to the project scope. The impact of the potential change to scope is either 1) being assessed, or has been assessed, and is considered as high risk as contingency will be required, or 2) management intervention may be required. Significant Scope Issues: There are significant scope issues and/or change control processes are not effective. The issues have been escalated to higher management for intervention and corrective action, to enable the project to be delivered within the agreed thresholds. 7. Project Stage Gates 7.1 Project Stage Gate Definitions The stage gates should be used to monitor and control project delivery, and additional information regarding to required documentation can be found in the main methodology section There are four stage gates and in the following section we define the indicators. Table 13: Stage Gate Status Indicators Definitions Traffic Light White Definition Not Started. Green Amber Achieving Schedule: The project is performing within the agreed baseline threshold for the stage schedule. Recoverable Deviation: The project is experiencing minor deviation (ranges from 6% - 15%) from the agreed baseline schedule, which is recoverable through corrective action recovery plan. There is minor or no impact on the critical path, business benefits or dependent projects. Red Significant Deviation: The project is experiencing major deviation (> 15%) from the agreed baseline schedule, and cannot be recovered with corrective action. There is sufficient impact on the critical path, business benefits or dependent projects that a correct action recovery plan will not bring the project back on track. The project scope and plan may need to be re-assessed and re-baselined. Projects Reporting Support Guide version 0.5 Page 19
20 Blue Completed. 8. Project Schedule Indicators 8.1 The following indicators should be referenced when monitoring and reporting project schedule Variance: Table 14: Schedule Variance Indicators Definitions Traffic Light Green Definition Achieving Schedule: The project is on or ahead of time (schedule). Amber Recoverable Deviation: The project has experienced some setbacks, which have led to a delay of between 5% - 15% over schedule. Has a minor and recoverable impact to the overall project delivery, i.e. the delays will not adversely affect the critical path, or impact dependent projects or committed benefits. Red Significant Deviation: Delays are >15% behind schedule. The project has experienced setbacks, which have led to delays that cannot be recovered. The overall project delivery will have to be put back, which may impact dependent projects and benefits delivery. The project plan is likely to require re-baselining to fully understand the business impact Percentage (%) Schedule variance is based on the difference between the planned schedule thresholds with the actual. Final Completion date Variance = Final date Planned. Schedule Variance Is a useful metric used to measure schedule performance on a project. SV = EV-PV. Positive SV means ahead of schedule; negative means the project is behind schedule. Zero means that all planned value was earned. Projects Reporting Support Guide version 0.5 Page 20
21 9. Project Budget Indicators 9.1 The Project Budget includes the agreed planned spend for the project. Additional information on Project Budget can be found in the Cost Management Guide. The following indicators are applied to monitor budget variance. Table 15: Budget Variance Indicators Definitions Traffic Light Green Amber Red Definition Achieving Budget for Current Spend to Date: The actual spend for the project to date is within the budgeted spend to date. Recoverable Deviation: The actual spend for the project to date is between 6% and 15% over / under the budgeted spend to date. Significant Deviation: The actual spend for the project to date is more than 15% over / under the budgeted spend to date. 9.2 Budget Variance % based on Estimate at Completion s the variance, as a percentage, between the Estimate at Completion (EAC) and the Total Project Budget. Variance = (EAC Budget) / Budget. Cost Variance Is a useful metric used to measure cost performance on a project. CV = EV- AC Positive CV means below budget; negative means the project is above budget. Zero means on budget It is important to determine the cause of variance and deciding whether corrective or preventive action is required. The larger percentage variances allowed at the start of the project can decrease as the project nears completion. Projects Reporting Support Guide version 0.5 Page 21
22 10. Related Support Guides The following support guides should be referenced when using this guide: 1. Project Initiation Support Guide 2. IT Project Steering Committee Support Guide 3. Project Manager Selection Support Guide 4. Project Change Management Guide 5. Project Reporting Support Guide Monthly Project Reporting Templates Detailed report Projects Reporting Support Guide version 0.5 Page 22
23 Dashboard Projects Reporting Support Guide version 0.5 Page 23
IT Project Management Methodology. Project Execution Support Guide. Version 0.3
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Execution Support Guide Version 0.3 Table of Contents 1 INTRODUCTION... 4 1.1 When should Project Execution
Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3
/01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,
IT Project Management Methodology. Project Scope Management Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
Project organisation and establishing a programme management office
PROJECT ADVISORY Project organisation and establishing a programme office Leadership Series 1 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital
OE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
How To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.
Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
ESKITP7145.01 Manage IT service delivery performance metrics
Overview This sub-discipline covers the competencies required to manage the monitoring, analysis and communication of IT service delivery performance metrics. Monitoring service level performance is a
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
IT Project Management Methodology. Project Risk Management Guide. Version 0.3
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Risk Management Guide Version 0.3 Project Risk Management Support Guide version 0.3 Page 1 Version Date Author
Certification Exam Objectives: PK0-003
Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate
PMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
Effective & Practical. Management of Projects
Effective & Practical Concepts, Methods & Techniques Project Planning & Delivery Management of Project Risks High Quality Training Courses presented by Internationally Recognised Expert Speakers The Diamond
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
Appendix 3: CMT Programme Board Highlight Report - Template and Guidance notes
Appendix 3: CMT Board Highlight Report - Template and Guidance notes What is it? This is an exception report that provides a quick means of assessing a programme s status. It allows CMT programme board
Project Execution, Monitoring and Control (IS PM 8. Lecture; 2012 Spring)
Project Execution, Monitoring and Control Topics of the lecture as follows: PDCA cycle Project execution processes by PMBOK Project monitoring and controlling processes by PMBOK Project monitoring and
John A Manzoni Chief Executive of the Civil Service. Email [email protected]
John A Manzoni Chief Executive of the Civil Service Email [email protected] 70 Whitehall London SW1A 2AS Telephone +44 (0) 20 7271 8822 Web www.cabinetoffice.gov.uk Paul Chinn Cabinet
Understand why, when and how-to to formally close a project
Project Closure Purpose: Understand why, when and how-to to formally close a project Audience: Project managers, project sponsors, team members and other key stakeholders Learning Objectives: Describe
NFSA Project Management Guidelines
NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and
Dallas IIA Chapter / ISACA N. Texas Chapter. January 7, 2010
Dallas IIA Chapter / ISACA N. Texas Chapter Auditing Tuesday, October Project 20, 2009 Management Controls January 7, 2010 Table of Contents Contents Page # Project Management Office Overview 3 Aligning
Earned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 5 PROJECT CLOSEOUT PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 5 PROJECT CLOSEOUT PHASE Table of Contents Introduction... 3 Project Closeout Phase... 3 Activities and Documents in the Closeout Phase... 4 Project Closeout Task...
Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
Project Risk Analysis toolkit
Risk Analysis toolkit MMU has a corporate Risk Management framework that describes the standard for risk management within the university. However projects are different from business as usual activities,
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
The Transport Business Cases
Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business
Project Execution Guidelines for SESAR 2020 Exploratory Research
Project Execution Guidelines for SESAR 2020 Exploratory Research 04 June 2015 Edition 01.01.00 This document aims at providing guidance to consortia members on the way they are expected to fulfil the project
TenStep Project Management Process Summary
TenStep Project Management Process Summary Project management refers to the definition and planning, and then the subsequent management, control, and conclusion of a project. It is important to recognize
Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review
Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review October 2013 The purpose of this document is to share lessons learned to support agencies to better identify
DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA
Appendix 2c DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA Review of Programme and Project Management Framework- Strategic Land and Property DISTRIBUTION LIST Audit Team David
Sample Examination Questions
Sample Examination Questions The following questions are examples of the type of questions that appear on the PMP Certification Examination. Disclaimer: These questions are intended for study purposes
White Paper. PPP Governance
PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting
Frank P.Saladis PMP, PMI Fellow
Frank P.Saladis PMP, PMI Fellow Success factors for Project Portfolio Management The Purpose of Portfolio Management Organizational Assessment Planning a Portfolio Management Strategy The Portfolio Management
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Assurance Reviews Process - A Handbook for Conducting Assurance Reviews Resource Management Guide No. 105. Archived
Assurance Reviews Process - A Handbook for Conducting Assurance Reviews Resource Management Guide No. 105 SEPTEMBER 2014 Commonwealth of Australia 2014 ISBN 978-1-922096-69-2 (Online) With the exception
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013
JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling
IT Professional Standards. Information Security Discipline. Sub-discipline 605 Information Security Testing and Information Assurance Methodologies
IT Professional Standards Information Security Discipline Sub-discipline 605 Information Security Testing and Information Assurance Methodologies December 2012 Draft Version 0.6 DOCUMENT REVIEW Document
Project Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
Selecting a project management methodology
VICTORIAN GOVERNMENT CIO COUNCIL Project Management Selecting a project management methodology Guideline This guideline provides advice for selecting and tailoring a project management methodology. Keywords:
ENTREPRENEURS TOOLKIT
Blueprint for success for entrepreneurial businesses ENTREPRENEURS TOOLKIT SOFTOOLS ENTREPRENEURS TOOLKIT PROVIDES A SUITE OF 8 INTEGRATED APPLICATIONS THAT WILL DRAMATICALLY ACCELERATE THE GROWTH OF ENTREPRENEURIAL
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
TEC Capital Asset Management Standard January 2011
TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
Prepared for: Prepared by:
Executive Project Review Prepared for: Prepared by: Table of contents Introduction... 3 WHY an Executive Project Review?... 3 WHO is Involved?... 4 WHAT is an Executive Project Review?... 5 WHEN? - Schedule
PHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
PMO Metrics Recommendations
Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project
Date of Trust Board 29 th January 2014. Title of Report Performance Management Strategy - 2013-2016
ENCLOSURE: P Date of Trust Board 29 th January 2014 Title of Report Performance Management Strategy - 2013-2016 Purpose of Report Abstract To set out the Performance Management Strategy of the Trust in
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee
Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have
Monitoring capital projects and addressing signs of trouble
/01 / Leadership Series 6 PROJECT ADVISORY Monitoring capital projects and addressing signs of trouble Leadership Series 6 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards
Personal Financial Planning As a Project
Personal Financial Planning As a Project By Greg Caramanica, PMP, General Securities Representative Financial Planner with Arlington Wealth Planning (www.arlingtonwealthplanning.com) Introduction Having
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
Change Management Procedure For Increase Bandwidth to University Buildings Project
Change Management Procedure For Increase Bandwidth to University Buildings Project Version number 1.0 Draft as of 4/11/2011 Printed on 7/1/2011 Author William M. Jones Owner William M. Jones Change Management
A Framework for Project Metrics
A Framework for Project Metrics Deciding what to measure and how to measure it August 13, 2007 Dr. Gary J. Evans, PMP CVR/IT Consulting LLC www.cvr-it.com Welcome! Focus of this workshop: Project Metrics
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM
DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM
PHASE 9: OPERATIONS AND MAINTENANCE PHASE
PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.
IPL Service Definition - Project Management, Programme Management and Governance
IPL Proposal IPL Service Definition - Project Management, Programme Management and Governance Project: Date: 16th Dec 2014 Issue Number: Issue 1 Customer: Crown Commercial Service Page 1 of 8 IPL Information
Introductory Certificate. The APM Project Fundamentals Qualification
The syllabus provides a summary of the coverage of the qualification, the details are then found in the learning outcomes and assessment criteria. Both the syllabus and the learning outcomes and assessment
PHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
PROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
NSW Government ICT Benefits Realisation and Project Management Guidance
NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control
How to successfully manage your mega-project
BUILDING, CONSTRUCTION & REAL ESTATE How to successfully manage your mega-project Part II Stakeholder communication and project controls integration kpmg.com 2 Building, Construction & Real Estate How
National IT Project Management Methodology. IT Project Governance and Reporting Support Guide
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA National IT Project Management Methodology IT Project Governance and Reporting Support Guide Draft 0.5 Project Governance and Reporting Support Guide
LGS Project Management Methodology
Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant
North European Functional Airspace Block Avinor, Norway EANS, Estonia Finavia, Finland LGS, Latvia. NEFAB Project CHANGE MANAGEMENT MANUAL
NEFAB Project CHANGE MANAGEMENT MANUAL Version 0.5 Page 1 of 38 Revision history Version Date Description Approved 0.5 14/12/2011 Page 2 of 38 Table of Contents 1. Introduction... 4 1.1. The Scope of this
State of XXXXX. Project Name/Phase (Planning Development Implementation) Status Report. Date Ending: Mm/dd/yy
APPENDIX E SAMPLE STATUS REPORT ** This sample report is a suggested guideline, and models the Status Report Checklist found in Appendix D State of XXXXX Project Name/Phase (Planning Development Implementation)
PMAP. Project Management At Penn PMAP
Project Management At Penn 1 Fundamentals Course Objective To provide you with an overview of Topics Project Management at Penn () Project Governance Phases & Project Management Activities Project Management
Auditing Capital Projects and Project Controls. March 2013
Auditing Capital Projects and Project Controls March 2013 Internal Audit Perspective Oversight Insight Foresight Is the process operating as planned? Are controls, resources, and performance measures adequate
PROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
CDC UNIFIED PROCESS JOB AID
Purpose The purpose of this document is to provide guidance on the practice of using Microsoft Project and to describe the practice overview, requirements, best practices, activities, and key terms related
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
1 What does the 'Service V model' represent? a) A strategy for the successful completion of all service management projects
1 What does the 'Service V model' represent? a) A strategy for the successful completion of all service management projects b) The path to Service Delivery and Service Support for efficient and effective
LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012
PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE
Essential Elements for Any Successful Project
In this chapter Learn what comprises a successful project Understand the common characteristics of troubled projects Review the common characteristics of successful projects Learn which tools are indispensable
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
CONTRACT MANAGEMENT FRAMEWORK
CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...
Earned Value Management for Enterprise Resource Planning Implementations
Earned Value Management for Enterprise Resource Planning Implementations Venu Kotamraju Abstract ERP implementations are a special breed of projects. They are often characterized by aggressive timelines,
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
Organization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
Overview. The Concept Of Managing Phases By Quality and Schedule
The Project Management Dashboard: A Management Tool For Controlling Complex Projects Project Management White Paper Series--#1001 John Aaron, Milestone Planning And Research, Inc. 5/14/01 Overview The
THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)
PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
Risk/Issue Management Plan
Risk/Issue Management Plan Centralized Revenue Opportunity System November 2014 Version 2.0 This page intentionally left blank Table of Contents 1. Overview... 3 1.1 Purpose... 3 1.2 Scope... 3 2. Roles
Technical Journal. Paper 142
Technical Journal 09 Paper 142 142 Kevin Balaam Programme Manager Highways & Transportation Atkins The Area 6 MAC approach to planning and programme management Introduction Steve Dickinson Schemes Manager
Operations. Group Standard. Business Operations process forms the core of all our business activities
Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations
Aberdeen City Council IT Security (Network and perimeter)
Aberdeen City Council IT Security (Network and perimeter) Internal Audit Report 2014/2015 for Aberdeen City Council August 2014 Internal Audit KPIs Target Dates Actual Dates Red/Amber/Green Commentary
Program Management Professional (PgMP) Examination Content Outline
Program Management Professional (PgMP) Examination Content Outline Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published by: Project Management
