MESA WATER TREATMENT PLANT FILTER MEDIA REPLACEMENT PROJECT SPECIFICATIONS TABLE OF CONTENTS

Size: px
Start display at page:

Download "MESA WATER TREATMENT PLANT FILTER MEDIA REPLACEMENT PROJECT SPECIFICATIONS TABLE OF CONTENTS"

Transcription

1 MESA WATER TREATMENT PLANT FILTER MEDIA REPLACEMENT PROJECT SPECIFICATIONS TABLE OF CONTENTS SECTION TITLE DIVISION 1 - GENERAL REQUIREMENTS Summary of Work Coordination with Operation of Existing Facilities Project Management and Construction Schedule Contract Time Project Meetings Submittal Procedures Safety and Health Environmental Protection Mobilization & Demobilization Demolition and Salvage Record Documents DIVISION 46 WATER AND WASTEWATER EQUIPMENT Filter Underdrains Filter Media

2 SECTION SUMMARY OF WORK PART 1 GENERAL 1.1 SCOPE OF WORK A. The scope of work to be performed under this contract consists of removal and replacement of filter media and repairs to filter underdrains at the Colorado Springs Utilities (OWNER) Mesa Water Treatment Plant. Major project components are described below. 1.2 PROJECT DESCRIPTION A. The work consists of the removal of existing granular filter media, inspection and repair of clay tile filter underdrain systems and furnishing and installation of new granular filter media in eight filter units. B. The work will be completed in three phases beginning in 2013 and finishing in 2015 as follows: 1. Phase 1 to be complete by December 15, 2013 shall include filters No. 1, 3 and 5. 2 Phase 2 to be complete by December 15, 2014 shall include filters No. 2, 4 and Phase 3 to be complete by December 15, 2015 shall include filters No. 7 and 8. C. The Plant will remain in operation at a reduced rate during the work of this project. CONTRACTOR shall schedule and conduct his work and coordinate with plant operating staff so as to minimize interference with plant operation and maintenance. D. The OWNER will perform all backwashing required during cleaning, washing and scraping, and testing. E. The work of this project requires removal and reinstallation of surface wash agitator arms and supply piping. Other miscellaneous items may be temporarily removed at the CONTRACTOR s option for his convenience in performing the work. All equipment and materials required to be temporarily removed and reinstalled shall be carefully removed to minimize damage, protected during storage, and reinstalled to original condition. CONTRACTOR s cost shall include all materials and labor required to restore all equipment and systems disturbed during the course of the work to their original condition. F. All equipment and materials indicated to be permanently removed, including filter media, shall be removed and transported by the CONTRACTOR to an area near the sludge drying beds as identified by the OWNER. Coordinate specific location and acceptable pile height with OWNER SUMMARY OF WORK DECEMBER

3 1.3 SITE ACCESS AND CONTRACTOR STAGING AREA A. Access to site is through the Mesa Water Treatment Plant main gate off Mesa Road. CONTRACTOR is required to keep all on-site access routes open and free from debris and construction equipment at all times. B. CONTRACTOR shall provide a list of all CONTRACTORs and subcontractors in advance of site access and performing work. Specifically, the names and driver s license number of all personnel shall be provided to Security as well as a work schedule. Coordinate with OWNER on projected delivery schedule to have Security personnel stationed at the Mesa Gate Guard Station appropriately. C. The CONTRACTOR s construction staging area will be located near the east end of the Filter Building in an area designated by the OWNER. Coordinate with OWNER on specifics related to staging area, designated vehicle parking area, and set up for CONTRACTOR provided outside toilet facilities. D. CONTRACTOR will be responsible to schedule and attend a site visit with OWNER s Safety Representative to review CONTRACTOR s Safety Plan. During the course of work, CONTRACTOR should be prepared for unannounced, periodic site inspections by OWNER s Safety Representative. 1.4 COMPLETION SCHEDULE A. CONTRACTOR shall submit a construction-sequencing schedule to the ENGINEER and OWNER prior to mobilization. This schedule shall depict how the CONTRACTOR will schedule the work to complete the project within the specified time. PART 2 PART 3 PRODUCTS (Not used) EXECUTION (Not used) END OF SECTION SUMMARY OF WORK DECEMBER

4 SECTION COORDINATION WITH OPERATION OF EXISTING FACILITIES PART 1.0 GENERAL 1 SCOPE OF WORK: A. The water treatment plant will be in continuous operation at a reduced flow rate throughout the execution of this Contract. The CONTRACTOR, therefore, shall schedule and conduct his work so as to minimize interference with plant operation and maintenance. It is the intent of this Contract that the construction activity, insofar as possible, shall not interfere with the operation of the plant. The CONTRACTOR shall be responsible for coordinating and scheduling the Work in such a sequence that the plant will function properly with no disruption of treatment, bypassing or short-circuiting. B. OPERATIONS WORK PLAN: 1. CONTRACTOR shall submit a written Work Plan two weeks in advance of the time when construction operations will require connection to, or modification of, in-service portions of the existing facility. The plan shall describe the CONTRACTOR's method for preventing bypassing of other treatment units, the length of time required to complete Work for the said operations and the necessary plant and other equipment which the CONTRACTOR shall provide in order to prevent bypassing of associated treatment units. The Work Plan shall address each of the following coordination, planning, and scheduling activities: a. Safety Plan including Emergency procedures to stop accidental bypassing. b. Planned operational disruptions. c. Planned utility interruptions including electrical power, natural gas, potable water, and telephone services. d. Temporary facilities. e. Process units to be taken out of service. f. Demolition Plan. g. Connection of new and existing facilities. h. Impact on Work sequence and Construction schedule COORDINATION WITH OPERATION OF EXISTING FACILITIES DECEMBER

5 1.2 PERFORMANCE REQUIREMENTS A. GENERAL: 1. When modifications, additions, or connections to existing facilities are required, the CONTRACTOR shall schedule such activities with the OWNER and ENGINEER. No system, structure, tank, circuit, or individual process unit shall be modified, dewatered, drained, de-energized, or removed from existing facilities unless authorized, in writing, by the ENGINEER. Insofar as possible, no interconnections between existing systems and new systems shall be made until all the Work of the new system has been completed, and tested up to the point of interconnection to the existing system in accordance with specification Section 01810, Installation, Testing, and Commissioning. B. TEMPORARY FACILITIES: 1. Whenever interruption of routine plant operation is required to accomplish the Work, the CONTRACTOR shall provide temporary facilities to ensure that all plant flows are accommodated and that treatment requirements are satisfied to the same quality as existing prior to the start of construction. Adequacy of temporary facilities shall be determined by the ENGINEER. 2. The CONTRACTOR shall submit to the ENGINEER and OWNER for approval all detailed drawings showing equipment, piping, power, controls, and weather protection for all proposed temporary systems whether described in this section or anticipated by the CONTRACTOR. The submittals shall indicate equipment capacities. C. SUBMITTALS: 1. In accordance with specification Section and in addition to the requirements of that section, the following submittals shall be provided: a. Area operations Work Plan. b. Drawings of proposed temporary facilities. PART 2 PART 3 PRODUCTS (NOT USED) EXECUTION 3.1 OPERATION A. Unless otherwise specified, normal daily operation and maintenance of the existing water treatment facilities will be performed by plant personnel. Whenever operational functions on existing facilities or new facilities which affect operating systems are required to permit construction operations, these functions will also be performed by COORDINATION WITH OPERATION OF EXISTING FACILITIES DECEMBER

6 plant personnel. The OWNER shall be notified at least 48 hours in advance of the need to operate valves, gates, equipment, or other actions that could affect plant operations. 3.2 TEMPORARY FACILITIES A. The CONTRACTOR shall not use proposed new equipment in any temporary facility. Temporary facilities shall not be removed from service until the new proposed system has been satisfactorily tested and commissioned as specified in individual technical specification sections and Section All temporary facilities shall be removed from the site by the CONTRACTOR and shall remain the property of the CONTRACTOR when no longer required. B. The OWNER shall operate any temporary facilities while they are needed. All maintenance shall be provided by the CONTRACTOR. During the time of use of the temporary facility, the OWNER shall pay for all power and chemicals necessary to operate the systems. 3.3 MODIFICATION OF EXISTING STRUCTURES: A. The CONTRACTOR shall alter or rework existing concrete structures as shown and specified. Generally, when items of equipment and piping are removed, the areas and surfaces from which items were removed shall be left with a neat appearance and finish compatible with surrounding areas, colors, and surfaces. Holes and pipe and conduit penetrations in walls and slabs shall be plugged smooth with grout. The CONTRACTOR shall do all painting, sanding, grouting, sacking, resurfacing, and other work as necessary to comply with the above requirements. Prior to structural modifications, all surfaces shall be subject to inspection by the ENGINEER. Colors shall match existing colors as closely as possible. B. When removing materials or portions of existing structures and when making openings in walls and partitions, the CONTRACTOR shall take all precautions and use all necessary barriers and other protective devices so as not to damage the structures beyond the limits necessary for the new work, nor to damage the structures or contents by falling or flying debris. C. All work of altering existing structures shall be done at such time and in such manner as will comply with the approved time schedule. So far as possible before any part of the work is started, all tools, equipment, and materials shall be assembled and made ready so that the work can be completed without delay. D. Where holes in existing masonry are required to be sealed, unless otherwise herein specified, they shall be sealed with cement mortar or concrete. The sides of the openings shall be provided with keyed joints and shall be suitably roughened to furnish a good bond and make a watertight joint. All loose or unsound material adjacent to the opening shall be removed and, if necessary, replaced with new material. The method of placing the mortar seal shall provide a suitable means of releasing entrapped air COORDINATION WITH OPERATION OF EXISTING FACILITIES DECEMBER

7 E. Surfaces of seals visible in the completed work shall be made to match as nearly as possible the adjacent surfaces. F. Nonshrink grout shall be used for setting wall castings, sleeves, leveling pump bases, doweling anchors into existing concrete and elsewhere as shown. 3.4 DISPOSAL/HANDLING OF HAZARDOUS MATERIALS A. The CONTRACTOR is solely responsible for storage, use and disposal of materials, including subcontractor materials classified as hazardous substances in accordance with HSWA 1984 and RCRA regulations except as noted. After completion of construction, the CONTRACTOR, shall remove and dispose of off-site all construction related materials with hazardous waste classifications in accordance with local, state, and federal regulations. The used filter media removed from the existing filters will remain on the Mesa WTP site near the sludge drying beds. The OWNER reserves the right to designate the storage location of the hazardous materials and conduct periodic inspections on the site. 3.5 SECURITY A. CONTRACTOR shall comply with all OWNER security measures and requirements for personnel and access to OWNER sites. Security measures vary by site, and include the following provisions: B. CONTRACTOR shall provide the OWNER Project Manager a list of all individuals full names who will or may be working under this contract and their Driver's License numbers. This list shall be updated and submitted to OWNER every time an employee change (addition or subtraction) is made for all individuals working under this contract in any capacity. CONTRACTOR shall submit initial employee lists to the designated OWNER representative at least 48 business hours before CONTRACTOR or Subcontractor arrives on site. Any additions to the list must be sent to the designated OWNER representative 48 business hours prior to the person needing site access so security can be notified. The designated OWNER representative must be notified within 24 business hours of a person being removed from the access list so security can be notified and the list updated. C. If required by OWNER for a specific project, it is the responsibility of CONTRACTOR to conduct a background check on each employee working on a project and forward this to the designated OWNER S representative. The designated OWNER S representative will forward the background check to the Physical Security, Security Administrator for review. A minimum of ten (10) days must be allowed before an employee may report to work after submitting a background check. Each employee is required to allow both photographs and fingerprints in order to work at any of OWNER S facilities where background checks are deemed necessary by OWNER S security administrator COORDINATION WITH OPERATION OF EXISTING FACILITIES DECEMBER

8 D. Each of CONTRACTOR'S employees or Subcontractors shall display an OWNER issued identification card while on an OWNER site to be worn on an external garment at all times, while performing services on any of OWNER S facilities. If the ID presents a safety concern it may be stored on their person, in a pocket and must be show if requested by security of other OWNER personnel. E. OWNER reserves the right to request additional security measures or to further control access to the site as conditions dictate and to refuse access to any of CONTRACTOR'S employees or Subcontractors for misconduct or illegal activity. Notifications of this nature will be made to CONTRACTOR through the designated OWNER S representative. END OF SECTION COORDINATION WITH OPERATION OF EXISTING FACILITIES DECEMBER

9 SECTION PROJECT MANAGEMENT AND CONSTRUCTION SCHEDULE PART 1 GENERAL 1.1 SCOPE A. This section specifies procedures for preparing and revising the construction schedule by the critical path method. Construction schedule format, review and evaluation, updating schedules, determining progress status relative to specific dates and completion time. This section also describes the requirements for the CONTRACTOR for holding regular progress meetings to discuss project issues, the project schedule and the completion of the Work. 1.2 SUBMITTALS A. In accordance with Section 01300, submit initial schedule within twenty (20) days after Notice to Proceed. After review, resubmit revised schedule within seven (7) days. The cost loaded schedule must be approved by the ENGINEER and OWNER. B. Submit revised Progress Schedules with each Application for Payment. Provide the number of opaque reproductions which CONTRACTOR requires, plus one (1) copy which will be retained by ENGINEER and OWNER. C. Provide samples of meeting documentation, status reports, and other items to be used for project meetings for review and approval at the pre-construction meeting. PART 2 PRODUCTS 2.1 PROJECT SCHEDULE A. The CONTRACTOR shall provide a graphic construction schedule prepared by the critical path method of analysis. The critical path schedule shall be prepared from estimates of the required duration and sequence for each item of work and function to be performed. A general guide for preparing such a schedule is contained in "The Use of CPM in Construction, A Manual for CONTRACTORs," published by the Associated General CONTRACTORs of America. B. The schedule shall be computerized using an analysis program capable of computing the monetary value of completed and partially completed activities, accepting revised completion dates, and re-computing all dates and float time. It shall depict all significant construction activities and all items of work listed in the breakdown of contract prices submitted by the CONTRACTOR in accordance with the Bid Schedule. The PROJECT MANAGEMENT AND CONSTRUCTION SCHEDULE DECEMBER

10 dependencies between activities shall be indicated so that it may be established what effect the progress of any one activity has on the schedule. C. Time for completion, and all specific dates and sequencing requirements shall be shown on the schedule. Activities making up the critical path shall be clearly identified. No activity on the schedule shall have duration longer than 21 days or assigned value greater than $50,000, except activities comprising only fabrication, and delivery may extend for more than 21 days. Activities which exceed these limits shall be divided into more detailed components. The schedule duration of each activity shall be based on the work being performed during the normal 40-hour work week with allowances made for legal holidays and normal weather conditions. PART 3 EXECUTION 3.1 PRE-CONSTRUCTION CONFERENCE A. A Pre-construction conference shall be held at the beginning of each Phase of the work at the location, date, and time designated by the OWNER in accordance with Section SCHEDULE DEVELOPMENT A. Prepare network analysis and diagrams based on estimates of the required duration and sequence for each item and work and function to be performed. Include all significant construction activities and all items of work listed in the Bid Schedule. B. Provide dates for delivery of major equipment, and dates for installation and testing. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the last day of each month. C. Tabulate each activity of detailed network diagrams, using calendar dates, and identify for each activity: 1. Activity description and percentage of activity completed 2. Preceding and following event numbers 3. Estimated duration of activity, in maximum seven (7) day intervals 4. Earliest start date and finish date 5. Actual start date and finish date 6. Latest start date and finish date 7. Total and free float 8. Monetary value of each activity, keyed to Schedule of Values 3.3 PROJECT STATUS UPDATES AND SCHEDULE REVISIONS A. Revisions to the accepted construction schedule affecting the contract value of any activity, the timing of any activity on the critical path, contract completion date, and work sequence may be made only with written approval of the CONTRACTOR and OWNER. Changes in PROJECT MANAGEMENT AND CONSTRUCTION SCHEDULE DECEMBER

11 timing for activities which are not on the critical path may be modified by mutual agreement of the CONTRACTOR and ENGINEER. Float time shall accrue to the benefit of the OWNER. B. Project status review and updates shall be provided each month at a weekly progress meeting. Maintain schedules to record actual start and finish dates of completed activities. Indicate progress of each activity to date of revision, with projected completion date of each activity. Update schedule diagrams to graphically depict current status of Work. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes. Provide narrative report to define problem areas, anticipated delays, and impact on Schedule. Report corrective action taken, or proposed, required to comply with specified Date of Completion. 3.4 PROGRESS MEETINGS A. Progress meetings shall be held in accordance with Section END OF SECTION PROJECT MANAGEMENT AND CONSTRUCTION SCHEDULE DECEMBER

12 SECTION CONTRACT TIME PART 1 GENERAL A. The work of this project will be bid and awarded as a single contract but will be completed in three phases, by issuing Task Orders, beginning in 2013 and finishing in 2015 as follows: 1. Phase 1 to be complete by December 15, 2013 shall include filters No. 1, 3 and 5. 2 Phase 2 to be complete by December 15, 2014 shall include filters No. 2, 4 and Phase 3 to be complete by December 15, 2015 shall include filters No. 7 and 8. B. Each Phase will be initiated by a Task Order and a separate Notice to Proceed (NTP) C. Each Phase shall be completed within the following times: 1. Substantial Completion: 150 days after the date of NTP 2. Final Completion: 180 days after the date of NTP PART 2 PRODUCTS (NOT USED) PART 3 EXECUTION (NOT USED) END OF SECTION CONTRACT TIME DECEMBER

13 SECTION PROJECT MEETINGS PART 1 GENERAL 1.1 SUMMARY A. This section includes requirements for all Project Meetings including the pre-construction conference, progress meetings, and schedules and reports. B. The work of this project will be bid and awarded as a single contract but will be completed in three phases beginning in 2013 and finishing in 2015 as follows: 1. Phase 1 to be complete by December 15, 2013 shall include filters No. 1, 3 and 5. 2 Phase 2 to be complete by December 15, 2014 shall include filters No. 2, 4 and Phase 3 to be complete by December 15, 2015 shall include filters No. 7 and 8. Project meeting shall be scheduled as noted to suit the project phasing. 1.2 PROJECT MEETINGS A. Preconstruction Conference: To be held at the beginning of each Phase 1. The OWNER will administer a preconstruction meeting to be attended by the OWNER, ENGINEER, CONTRACTOR and his on-site superintendent, and representatives of principal subcontractors and suppliers. Items to be discussed will include construction schedules, critical work sequencing, project coordination, quality control procedures, procedures for making field decisions, substitutions, submittals, change orders, and applications for payment. Other items to be covered will include procedures for testing, maintaining record documents, construction facilities, temporary utilities, and project security. B. Progress Meetings: To be held while work is in progress during each Phase 1. Progress meetings shall be conducted at weekly intervals or at some other frequency if approved by the OWNER. These meetings shall be attended by the Project Manager, ENGINEER, and CONTRACTOR s Project Manager and Superintendent and other construction team members as appropriate such as subcontractor representatives. 2. The meetings will be conducted by the CONTRACTOR. The agenda of these project meetings shall include reports on construction progress, field observations, problems, conflicts, status of submittal reviews, status of information requests, revisions to construction schedule, and any general business PROJECT MEETINGS DECEMBER

14 1.3 SCHEDULES AND REPORTS A. Initial Coordination Submittals 1. Within ten days after the Effective Date of the Agreement, CONTRACTOR shall submit the following to OWNER for review and acceptance: a. A preliminary Work progress schedule. b. A preliminary schedule of submittals. c. A preliminary schedule of values for the Work. B. Work Progress Schedule 1. Submit a schedule of work for each Phase of the project within 10 days of Notice to Proceed for that Phase. The schedule shall be developed in accordance with Section ENGINEER will review and comment on schedule and, upon agreement with CONTRACTOR on any necessary changes, CONTRACTOR will furnish OWNER and ENGINEER prints of the accepted schedule. CONTRACTOR shall not change the accepted progress schedule without prior concurrence of OWNER. 3. Submit to OWNER for acceptance of an updated schedule monthly. Schedule shall show actual progress and any proposed changes in the schedule of remaining Work. C. Work Progress Reports 1. The schedule of work shall be monitored on a weekly basis and updated on a monthly basis. More frequent reports may be required should the Work fall behind the accepted schedule. 2. Work progress reports shall consist of marked copies of prints made from the accepted Work progress schedule and a narrative report. 3. A Work progress report shall accompany each application for partial payment. Work reported complete but not readily apparent to OWNER must be substantiated with supporting data. D. List of Subcontractors and Major Suppliers 1. CONTRACTOR shall submit to OWNER, at the first preconstruction meeting, a list of all subcontractors and major suppliers complete with contact person, address, and telephone number of each. Submit updates if necessary at subsequent preconstruction meetings at the beginning of each Phase. PART 2 PRODUCTS (NOT USED) PROJECT MEETINGS DECEMBER

15 PART 3 EXECUTION (NOT USED) END OF SECTION PROJECT MEETINGS DECEMBER

16 SECTION SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 SCOPE Provide product and materials information for review by the Engineer to demonstrate that the materials and equipment to be furnished and the methods of work comply with the provisions and intent of the contract documents. Furnish manufacturers' fabrication drawings, specifications, descriptive data, certificates, samples, test methods and results, schedules, and manufacturer's installation and other instructions, operation and maintenance manuals, repair/replacement parts, maintenance supplies, requests for substitutions, and miscellaneous items specifically required in the contract documents 1.2 QUALITY ASSURANCE A. ACCURACY AND COMPLETENESS 1. The CONTRACTOR shall be responsible for the accuracy and completeness of the information contained in each submittal and shall assure that the material, equipment or method of work shall be as described in the submittal. The CONTRACTOR shall verify that all features of all products conform to the specified requirements. 2. Submittal documents shall be edited to indicate only those items, models, or series of equipment, which are being submitted for review. All extraneous materials shall be crossed out or otherwise obliterated so it is clear which specific item is being submitted and which sizes, materials and details of construction apply to the specific application on this project. B. COORDINATION Coordinate submittals with the work so that work will not be delayed. Coordinate and schedule different categories of submittals, so that one will not be delayed for lack of coordination with another. No extension of time will be allowed because of failure to properly schedule submittals. C. CONFORMANCE WITH SPECIFIED REQUIREMENTS Submittals are specified for those features and characteristics of materials, equipment, and methods of operation that can be selected based on the CONTRACTOR's judgment of their conformance to the specified requirements. Other features and characteristics are specified in a manner that enables the CONTRACTOR to determine acceptable options without submittals. The review procedure is based on the CONTRACTOR's guarantee that all features and characteristics not requiring submittals conform as specified. Review shall not extend to means, methods, techniques, sequences or procedures of construction, or to verifying quantities, dimensions, weights or gages, or fabrication processes (except where specifically indicated or required by the Contract Documents) SUBMITTAL PROCEDURES December

17 or to safety precautions or programs incident thereto. Review of a separate item, as such, will not indicate approval of the assembly in which the item functions. D. EFFECT OF SUBMITTAL REVIEW Review of drawings, methods of work, or information regarding materials or equipment proposed by the CONTRACTOR shall not relieve the CONTRACTOR of responsibility for errors therein. In reviewing submittals to confirm compliance with the provisions and intent of the contract documents, Engineer and OWNER, and any officer or employee thereof, assume no risks or liability for construction. The CONTRACTOR shall have no claim under the contract on account of the failure, or partial failure, of the method of work, material, or equipment so reviewed. PART 2 PRODUCTS 2.1 MANUFACTURER'S OR PRODUCT DATA Manufacturer's data shall include, but not be limited to, cut sheets, brochures, model number identification, and standard published manufacturer's material specifying the quality, make-up, application and materials of fabrication for the specified products. 2.2 TESTING AND TEST REPORTS Notify the Engineer not less than 14 days prior to the date that the equipment installation(s) and/or other materials or portions of the Work will be ready for inspection and testing. All equipment tests shall be completed in accordance with Section and witnessed by the Engineer unless otherwise approved in writing by the Engineer. Test certification shall be provided and signed by the responsible party to the satisfaction of the Engineer within two weeks of the actual test. It shall include the following: 1. Date of report, name, address, telephone number and signatures of individuals performing the test or inspection and of individuals issuing the report. 2. Project name, number, and Contract Number. 3. Dates, times, temperature, weather conditions, and locations of tests and inspections. 4. Identify the work or product by specification section and test or inspection method. 5. Complete inspection or test data, results of test, interpretation of test results, compliance with the Procurement Contract Documents, and recommendations regarding retesting. 2.4 ENGINEERED PRODUCTS SUBMITTAL PROCEDURES December

18 Products requiring professional Engineering design and/or certification shall include an Engineer's certification form and shall be stamped by a professional Engineer with valid registration in the State of Colorado. Such stamp shall be consistent with the rules and regulations of the state governing Professional Engineering registration. 2.6 CONSTRUCTION SCHEDULE A construction schedule shall be submitted and maintained in accordance with this section and with the General Conditions. PART 3 EXECUTION 3.1 SUBMITTAL PROCEDURE A. GENERAL Furnish shop drawings with product data as required in the individual specification sections and as required by the General Conditions. When the Contract Documents require a submittal, the CONTRACTOR shall submit a minimum of 6 copies of all submittal information for review and comment. All submittals shall be submitted to the Engineer for review and comment. B. TRANSMITTAL FORM Unless otherwise specified, all submittals shall be accompanied by Submittal Transmittal Form specified in this section. A separate form shall be used for each specific item, class of material, equipment, and items specified in separate, discrete sections, for which the submittal is required. Submittal documents common to more than one piece of equipment shall be identified with all the appropriate equipment numbers. Submittals for various items shall be made with a single form when the items taken together constitute a manufacturer's package or are so functionally related that expediency indicates checking or review of the group or package as a whole. C. SUBMITTAL NUMBER A unique number, sequentially assigned, shall be noted on the transmittal form accompanying each item submitted. Original submittal numbers shall have the following format: "XXX"; where "XXX" is the sequential number assigned by the CONTRACTOR. Re-submittals shall have the following format: "XXX-Y"; where "XXX" is the originally assigned submittal number and "Y" is a sequential letter assigned for re-submittals, i.e., A, B, or C being the 1st, 2nd, and 3rd resubmittals, respectively. D. EQUIPMENT CERTIFICATION AND FORMS All equipment item submittals shall include an Equipment Record Form as specified in this section. When applicable, submittals shall also be accompanied by the P.E. Certification Form, the Equipment Record Form and/or the Motor Data Form provided at the end of this section SUBMITTAL PROCEDURES December

19 D. DEVIATION FROM CONTRACT If the CONTRACTOR proposes to provide material, equipment, or method of work which deviates from the Contract Documents, he shall indicate so under "deviations" on the transmittal form accompanying the submittal copies. E. REVIEW PROCEEDURE Unless otherwise specified, within 20 calendar days after receipt of a submittal for review and comment, the Engineer shall review the submittal and return 3 copies of the marked-up original. The returned submittal shall indicate one of the following actions: 1. If the review indicates that the material, equipment or work method complies with the Contract Documents, submittal copies will be marked "NO EXCEPTIONS TAKEN." In this event, the CONTRACTOR may begin to implement the work method or incorporate the material or equipment covered by the submittal. 2. If the review indicates limited corrections are required, copies will be marked "MAKE CORRECTIONS NOTED." The CONTRACTOR may begin implementing the work method or incorporating the material and equipment covered by the submittal in accordance with the noted corrections. Where submittal information will be incorporated in O&M data, a corrected copy shall be provided. 3. If the review reveals that the submittal is insufficient or contains incorrect data, copies will be marked "AMEND AND RESUBMIT." Except at his own risk, the CONTRACTOR shall not undertake work covered by this submittal until it has been revised, resubmitted and returned marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED." 4. If the review indicates that the material, equipment, or work method does not comply with the Contract Documents, copies of the submittal will be marked "REJECTED - DEVELOP REPLACEMENT." Submittals with deviations which have not been identified clearly may be rejected. Except at his own risk, the CONTRACTOR shall not undertake the work covered by such submittals until a new submittal is made and returned marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED." 5. If the review reveals that the submittal is substantially incomplete and/or missing information which was required to be provided, the submittal will be marked "INCOMPLETE, NOT REVIEWED". This review action indicates that additional information is required and that a re-submittal will be necessary before review can begin. F. A mark of "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED" shall mean that the OWNER has no objection to the CONTRACTOR, upon his own SUBMITTAL PROCEDURES December

20 responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed. G. SUBMITTAL COMPLETENESS Submittals which do not have all the information required to be submitted, including deviations, are not acceptable and will be returned without review. 3.2 FORMS Form A Submittal Transmittal Form SUBMITTAL PROCEDURES December

21 01300-A. SUBMITTAL TRANSMITTAL FORM Submittal Description: SUBMITTAL TRANSMITTAL Submittal No.: Spec. Section: Routing Date Sent Date Received OWNER: PROJECT: Contractor/Engineer Engineer/Contractor CONTRACTOR: We are sending you: Attached Under separate cover via Submittals for review and comment Product data for information only Remarks: Item Copies Date Section No. Description Review action a Reviewer initials Review comments attached a Note: NET = No exceptions taken; MCN = Make corrections noted; A&R = Amend and resubmit; R = Rejected, Develop Replacement; I = Incomplete, not reviewed. Attach additional sheets if necessary. Contractor Certify either A or B: A. We have verified that the material or equipment contained in this submittal meets all the requirements, including coordination with all related work, specified (no exceptions). B. We have verified that the material or equipment contained in this submittal meets all the requirements specified except for the attached deviations. No. Deviation Certified by: Contractor's Signature SUBMITTAL PROCEDURES December

22 END OF SECTION SUBMITTAL PROCEDURES December

23 SECTION SAFETY AND HEALTH PART 1--GENERAL 1.01 SCOPE A. CONTRACTOR shall be responsible for workers safety and shall comply with all Federal, State and Local safety rules, regulations and guidelines. B. CONTRACTOR shall obtain necessary permits for work in confined spaces. C. CONTRACTOR shall provide all necessary safety equipment required for performance of the work of this project REFERENCES The following reference documents are a part of this Section as specified and modified: 1. Colorado Springs Utilities Safety and Health Manual WORK SITE CONDITIONS A. Portions of the existing plant are exposed to water of varying degrees of treatment. Employees involved in any work within the treatment plant may be exposed to treatment chemicals, solvents, fuels, and other hazardous materials. Certain areas are designated as confined spaces, unventilated occupancy, or may be subject to explosion hazards. All personnel shall observe established plant safety precautions and procedures and maintain hygiene when working in these areas. B. Filters are considered non-permit confined spaces by the OWNER s Safety Department. CONTRACTOR shall coordinate entry and safety equipment requirements prior to starting any work in the filters. Unless otherwise directed by the OWNER the CONTRACTOR shall provide air monitors for personnel working in the filters and shall record monitor readings at intervals as required by the OWNER. PART 2--PRODUCTS Not Used PART 3--EXECUTION 3.01 SAFETY AND HEALTH REGULATIONS A. Comply with Safety and Health Regulations for Construction under Section 107 of the Contract Work Hours and Safety Standards Act, Title 29, CFR. B. Comply with the provisions of the Federal Occupational Safety and Health Act, as amended. C. Comply with requirements of Colorado Springs Utilities Safety and Health Manual found on SAFETY AND HEALTH DECEMBER

24 the internet. Coordinate with Project Manager and OWNER s Safety representative for specifics. END OF SECTION SAFETY AND HEALTH DECEMBER

25 SECTION ENVIRONMENTAL PROTECTION PART 1 GENERAL 1.1 SCOPE This Specification describes requirements for maintaining the environment during construction activities. The control of environmental pollution requires consideration of air, water, and land, and involves management of noise and solid waste, as well as other pollutants. 1.2 SUBMITTALS Material Safety Data Sheets (MSDS) for hazardous compounds brought on site and/or used by the CONTRACTOR in performance of the Work shall be submitted in accordance with the requirements of Section ENVIRONMENTAL PROTECTION A. DEFINITION OF ENVIRONMENTAL POLLUTION Environmental pollution is defined as the presence of chemical, physical, or biological elements or agents, which adversely affect human health or welfare; unfavorably alter ecological balances or adversely affect other species of importance to man; or degrade the aesthetic or recreational quality of the environment. Such pollution includes, but is not limited to, eroded soils, refuse, garbage, cement, concrete, sanitary waste, industrial waste, oil and other petroleum products, mineral salts and spirits, noise pollution, and thermal pollution. B. ENVIRONMENTAL LAWS AND REGULATIONS Comply with all applicable Federal, State of Colorado, and local laws and regulations concerning environmental pollution control and abatement. Conform with all applicable safety laws, particularly Part 1926 of the OSHA Safety and Health Standards for Construction. CONTRACTOR shall determine the specific construction techniques to meet all applicable laws and regulations. C. ACCIDENTAL RELEASE OF CHEMICALS In the event of any accidental release of petroleum products and other chemical pollutants, CONTRACTOR shall notify the Colorado Department of Public Health and Environment through the 24-hour emergency Response Line (303) Report any accidental release of chemicals in accordance with the brochure Reporting Chemical Spills and Releases in Colorado published by the Colorado Department of Public Health and Environment. In the event of any chemical spill or whenever notified of any non-compliance with Federal, State or local environmental protection requirements, the CONTRACTOR shall immediately take corrective ENVIRONMENTAL PROTECTION DECEMBER

26 action. If the CONTRACTOR fails or refuses to comply promptly, the OWNER may issue an order stopping all or part of the work until satisfactory corrective action has been taken. Stop Work orders to achieve compliance with environmental regulations shall not be justification for extension of time or for any costs or damages to the CONTRACTOR. D. CONSTRUCTION IMPACT ON THE ENVIRONMENT Construction activities and methods shall minimally impact the environment surrounding the project, including dust, air and noise pollution and prevention of entrance or accidental spillage of solid matter, contaminants, debris and other pollutants and wastes into any water course, and/or any underground water sources. Such wastes include, but are not limited to, eroded soils, refuse, garbage, cement, concrete, sanitary waste, industrial waste, oil and other petroleum products, chemicals, mineral salts and spirits, and thermal pollution. 1.4 RUBBISH CONTROL Maintain the site of the Work in a neat and clean condition, free from any accumulation of rubbish. At regular intervals, collect and dispose of all rubbish and waste materials. Provide trash bins or otherwise control the collection, storage and transport of rubbish and waste materials so as to preclude blowing of loose trash due to high winds. Furnish, at a minimum, one covered dumpster at the project site. The dumpster shall be emptied at least once per week, or more frequently, whenever the dumpster is full. Keep roadways free from dirt, rubbish, and obstructions during construction operations. 1.5 CHEMICALS AND PETROLEUM BASED PRODUCTS A. APPROVED CHEMICALS All chemicals used during project construction or furnished for project operation shall show approval of either the U.S. Environmental Protection Agency or the U.S. Department of Agriculture. Use of all such chemicals and disposal of residues shall be in strict accordance with the printed instructions of the manufacturer. Submit Material Safety Data Sheets (MSDS) for any hazardous material proposed to be used in the construction of the Work. Follow the information on the MSDS to assure safe use, handling, storage and environmentally acceptable disposal of the material used. B. FLAMMABLE AND COMBUSTIBLE MATERIALS Storage and handling of flammable and combustible materials and provisions for fire prevention shall be in accordance with the latest applicable OSHA requirements. C. CHEMICAL STORAGE AND HANDLING All chemicals and petroleum based products stored in drums or tanks on site shall be provided with secondary containment facilities meeting Federal, State, and local laws, ordinances, regulations and permit conditions. All spigots shall be positioned so that secondary containment ENVIRONMENTAL PROTECTION DECEMBER

27 facilities catch any drips. All-weather temporary roofs or covers shall be provided over such containers and secondary containment facilities to the satisfaction of the ENGINEER. D. DISPOSAL OF WASTE PETROLEUM PRODUCTS All waste petroleum based products shall be contained in sealed containers and disposed of at approved recycling facilities, and, if not recyclable, shall be disposed of at an approved dump site. Any spills shall be promptly cleaned up and waste, spillage, and contaminated materials disposed of at an approved dump site. Proof that a spill is cleaned up adequately shall be done to the satisfaction of the OWNER, the ENGINEER, and appropriate regulatory authority. 1.7 NOISE CONTROL Maintain noise below levels proscribed by the Occupational Safety and Health Administration. All construction equipment operated at the site shall be equipped with manufacturer's standard noise control devices such as mufflers, lagging, and/or engine enclosures which normally achieve compliance with noise limits. Inspect construction equipment regularly to ensure proper maintenance and presence of noise control devices such as mufflers and shrouding. Monitor construction equipment noise to ensure compliance to the required noise limits. Maximize the distance between noisy construction activities and noise-sensitive land uses. Noisy temporary equipment, such as pumps and air compressors, shall be located on the construction boundary most distant from nearby occupied structures. 1.8 WELDING Notify all occupants of nearby buildings prior to welding activities within their visual range. Safeguard construction workers and all others from welding activities. 1.9 CLEANUP AND DISPOSAL OF EXCESS MATERIAL Keep the site of operations in a clean and neat condition. Dispose of all construction residue at an appropriate disposal site or facility. Remove and haul away any surplus excavated material, broken pavement, lumber, equipment, temporary structures and any other refuse remaining from the construction operations. Leave the entire site of the work in a neat and orderly condition. Burning at the project site for the disposal of refuse and debris will not be permitted PROTECTION OF WATER RESOURCES A. TREATMENT OF CONTAMINATED WATER Protect all streams, wetlands, and groundwater resources from environmental pollution resulting from operation of equipment, materials storage, or other construction activity in or near such water resources. Water used for washing or processing, from dewatering operations, or that contains oils or sediments, shall not be discharged directly to any waters of the State of Colorado or indirectly through any storm sewer or temporary drainage channel. Contaminated or polluted waters shall be diverted through a settling basin, filter, or other treatment process acceptable to ENVIRONMENTAL PROTECTION DECEMBER

28 the Colorado Department of Public Health and Environment prior to discharge off-site. Place all erosion control measures in an area prior to any construction activity in that area. B. EROSION CONTROL Provide positive means of erosion control such as shallow ditches around construction to carry off surface water. Erosion control measures, such as silt basins, hay check dams, mulching, jute netting and other equivalent techniques, shall be used as appropriate. Offsite surface water shall be diverted around the site, to a downstream channel ahead of silt barriers. Flow of surface water into excavation areas shall be prevented. Ditches around construction area shall also be used to carry away water resulting from dewatering of excavated areas. At the completion of the work, ditches shall be backfilled and the ground surface restored to its original condition PROTECTION OF LAND RESOURCES A. GENERAL Land resources within the project boundaries and outside the limits of permanent work shall be restored to a condition, after completion of construction that will appear to be natural and not detract from the appearance of the project. Confine all construction activities to areas shown on the Drawings. Protect monuments and markers with fences or barricades before beginning operations near them. B. PROTECTION OF VEGETATION Outside of areas requiring earthwork for the construction of the new facilities, maintain and protect trees, shrubs, and other vegetation. Do not remove or cut trees or shrubs without prior approval. Where trees may be defaced, bruised, injured, or otherwise damaged by construction equipment or operations, protect such trees by placing fences or barricades around them. Restore any trees or other landscape feature scarred or damaged by construction equipment or operations as nearly as possible to its original condition. Trees that are to remain, either within or outside established clearing limits, that are damaged by the CONTRACTOR and are beyond saving in the opinion of the ENGINEER, shall be immediately removed or replaced PROTECTION OF AIR QUALITY A. DUST CONTROL Dust control shall be performed as the work proceeds and whenever a dust nuisance or hazard occurs, as determined by the OWNER. Control fugitive dust from all excavations, embankments, stockpiles, access roads, waste areas, and borrow areas by sprinkling with water or other similar methods. The use of petroleum products is prohibited. Repeat sprinkling at such intervals as to keep all disturbed area at least damp at all times. Furnish sufficient competent equipment on the job to accomplish sprinkling. PART 2 PRODUCTS (NOT USED) ENVIRONMENTAL PROTECTION DECEMBER

29 PART 3 EXECUTION 3.1 GENERAL Maintain all facilities constructed for pollution control or site protection, as long as the potential for pollution or damage from construction activities exists. At completion of the work, remove temporary fencing, silt barriers, backfill temporary ditches, and other temporary environmental protection measures, and restore the ground surface to original condition. END OF SECTION ENVIRONMENTAL PROTECTION DECEMBER

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

Waste Handling & Disposal

Waste Handling & Disposal Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Improper storage and handling of solid wastes can allow toxic compounds, oils and greases, heavy metals, nutrients, suspended

More information

SECTION 02221 SELECTIVE DEMOLITION

SECTION 02221 SELECTIVE DEMOLITION SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on

More information

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION (1) Project Name: (2) Project Contractor: (3) Erosion Control Supervisor/SWMP Administrator: (4) CDOT Project

More information

Activity Yes No N/A Notes

Activity Yes No N/A Notes CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3

More information

SECTION 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

SECTION 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS SECTION 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. Regulations: Comply with industry standards and applicable laws and regulations of authorities

More information

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local

More information

ALLEGANY WIND POWER PROJECT CONSTRUCTION SPILL PREVENTION PLAN

ALLEGANY WIND POWER PROJECT CONSTRUCTION SPILL PREVENTION PLAN ALLEGANY WIND POWER PROJECT CONSTRUCTION SPILL PREVENTION PLAN Best Management Practices (BMPs) will be implemented during construction of the Allegany Wind Power Project to prevent and contain spills.

More information

Extraction Oil and Gas, LLC. Diamond Valley Central Oil Terminal Waste Management Plan

Extraction Oil and Gas, LLC. Diamond Valley Central Oil Terminal Waste Management Plan Extraction Oil and Gas, LLC. Diamond Valley Central Oil Terminal Waste Management Plan Scope: This Extraction Oil and Gas Waste Management Plan has been prepared to provide operations personnel at the

More information

SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS PART 1 - GENERAL 1.1 DESCRIPTION A. This section specifies the control of environmental pollution and damage that the Contractor must consider for air,

More information

Improper storage of fuel on construction sites will increase the risk of water pollution that may occur as a result of leaks or spills.

Improper storage of fuel on construction sites will increase the risk of water pollution that may occur as a result of leaks or spills. WQ-10 Best Management Practice (BMP) Water Quality Protection Guideline Secondary Containment Design Standards Fuel Storage on Construction Sites According to the EPA, the majority of water pollution in

More information

Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations

Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations SWPPP for Park Operations 2 Chapter 2 Stormwater Pollution Prevention Plan (SWPPP) for Park Operations Bordered by Lake Washington & Lake Sammamish, the City of Bellevue has more than 60 miles of streams,

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 311 NETWORK ANALYSIS SCHEDULE Part 1.1 DESCRIPTION A. Scope: Provide projected network analysis schedules for the entire Work and revise periodically. This type of schedule is acceptable for

More information

Pollution Prevention And Best Management Practices For Dry Cleaners Operating In Broward County

Pollution Prevention And Best Management Practices For Dry Cleaners Operating In Broward County FORWARD In 1991, the Broward County Environmental Protection and Growth Management Department, who was then known as the Department of Natural Resource Protection (DNRP), initiated the development of Pollution

More information

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy.

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy. UNIVERSITY OF HERTFORDSHIRE HIGHER EDUCATION CORPORATION SITE RULES FOR CONTRACTORS The University s Site Rules for Contractors are issued on the authority of the Director of Estates, Hospitality and Contract

More information

SECTION 810 SEWER LINE CLEANING

SECTION 810 SEWER LINE CLEANING SECTION 810 SEWER LINE CLEANING I. GENERAL 1.1 DESCRIPTION OF WORK The work covered by this section consists of providing all labor, equipment, material and supplies and performing all operations required

More information

Independent Contractor Policy

Independent Contractor Policy Independent Contractor Policy This Policy has been implemented to prevent accidents and personal injuries. It is not intended to be entirely inclusive. It is the responsibility of the Independent Contractor

More information

UDOT SPILL PREVENTION and RESPONSE PLAN for CONSTRUCTION SITES

UDOT SPILL PREVENTION and RESPONSE PLAN for CONSTRUCTION SITES UDOT SPILL PREVENTION and RESPONSE PLAN for CONSTRUCTION SITES February 2014 The plan contained in the following pages was developed in part from UDOT Construction Division s Safety and Health Manual,

More information

Spill Prevention, Control & Cleanup SC-11

Spill Prevention, Control & Cleanup SC-11 Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Spills and leaks, if not properly controlled, can adversely impact the storm drain system and receiving waters. Due to

More information

SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION

SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION 104-1 Description. Provide erosion control measures on the project and in areas outside the right-of-way where work is accomplished

More information

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and

More information

SILICON VALLEY CLEAN WATER. May 2015

SILICON VALLEY CLEAN WATER. May 2015 SILICON VALLEY CLEAN WATER May 2015 Slug Discharge Control and Spill Containment Guidelines This document was revised and used with the permission of the Los Angeles County Sanitation District, Industrial

More information

Preventing Storm Water Pollution: What We Can Do

Preventing Storm Water Pollution: What We Can Do Preventing Storm Water Pollution: What We Can Do ~Employee Training Series~ Streets and Drainage Maintenance PREPARED IN COOPERATION WITH THE Texas Commission on Environmental Quality AND U.S. ENVIRONMENTAL

More information

Florida Department of Environmental Protection

Florida Department of Environmental Protection Florida Department of Environmental Protection Background Mobile vehicle and equipment washing involves washing at a location where vehicles are based (such as a trucking company, warehouse, bus station,

More information

Appendix I: BMP Inspection Form CASQA SWPPP Template 91 January2011 BMP INSPECTION REPORT Date and Time of Inspection: Date Report Written: Inspection Type: (Circle one) Weekly Complete Parts I,II,III

More information

Outdoor Storage of Raw Materials SC-33

Outdoor Storage of Raw Materials SC-33 Objectives Cover Contain Educate Reduce/Minimize Description Raw materials, by-products, finished products, containers, and material storage areas exposed to rain and/or runoff can pollute stormwater.

More information

SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN

SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN XXXX FARM (CITY OR COUNTY), MICHIGAN CONTACT (NAME), OWNER CERTIFICATION: I hereby certify that I have examined the facility, and being familiar with the

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING 1 TABLE OF CONTENTS 1.0 Introduction and Purpose 3 2.0 Description of Work 3 3.0 Site Supervisor/Foremen Responsibilities 4 4.0 Equipment

More information

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY 1. Applicant's Name Address (Street or Rural Route) (City & State) (Zip) Person to contact Title Phone Fax

More information

ARLINGTON HEIGHTS MUNICIPAL CODE CHAPTER 22 SEWERS

ARLINGTON HEIGHTS MUNICIPAL CODE CHAPTER 22 SEWERS ARLINGTON HEIGHTS MUNICIPAL CODE CHAPTER 22 SEWERS Article I General Provisions Section 22-101 Definitions Section 22-102 Supervision of Sewer System Section 22-103 Inspections Section 22-104 Use of Public

More information

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting

More information

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials

V. ENVIRONMENTAL IMPACT ANALYSIS E. Hazardous Materials E. HAZARDOUS MATERIALS An Environmental Site Assessment Phase I Update was performed on the subject properties by California Environmental Inc. in March 2000 1. This report is included in Appendix E of

More information

1. Water Line Maintenance 2. Sanitary Sewer Maintenance 3. Spill/Leak/Overflow Control, Response, and Containment

1. Water Line Maintenance 2. Sanitary Sewer Maintenance 3. Spill/Leak/Overflow Control, Response, and Containment WATER AND SEWER UTILITY OPERATION AND MAINTENANCE Although sewage systems the operation and maintenance of public utilities are not considered themselves are not a chronic sources of stormwater pollution,

More information

Environmental Site Inspection Checklist

Environmental Site Inspection Checklist Note : This form is designed for general use and may not be exhaustive. Modifications and additions may be necessary to suit individual projects and to address specific environmental issues and associated

More information

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of

More information

SECTION EIGHT BONDING REQUIREMENTS

SECTION EIGHT BONDING REQUIREMENTS SECTION EIGHT BONDING REQUIREMENTS 8-00 BONDING REQUIREMENTS 8-01 No building permit for any construction in the subdivision shall be issued nor any lot within the subdivision conveyed until a bond has

More information

DRAFT Guidelines for Manually Diverting Outdoor Wastewater to the Sanitary Sewer

DRAFT Guidelines for Manually Diverting Outdoor Wastewater to the Sanitary Sewer Only RAIN down the Storm Drain... DRAFT Guidelines for Manually Diverting Outdoor Wastewater to the Sanitary Sewer This publication applies to you if: You generate wastewater outdoors, and The wastewater

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

TITLE 6. Health and Sanitation CHAPTER 1. Health and Sanitation

TITLE 6. Health and Sanitation CHAPTER 1. Health and Sanitation TITLE 6 Chapter 1 Chapter 2 Pollution Abatement CHAPTER 1 6-1-1 Health Officer; Duties and Powers 6-1-2 Rules and Regulations 6-1-3 Health Nuisances 6-1-4 Compulsory Connection to Sewer and Water 6-1-5

More information

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering

More information

C. Section 014510 TESTING LABORATORY SERVICE.

C. Section 014510 TESTING LABORATORY SERVICE. SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,

More information

Storm Water Management Requirements for Construction Projects Less than One Acre

Storm Water Management Requirements for Construction Projects Less than One Acre Storm Water Management Requirements for Construction Projects Less than One Acre Purpose: UC Irvine s Phase II Small MS4 Storm Water Permit requires construction projects less than one acre in size to

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials. PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,

More information

BEST MANAGEMENT PRACTICES (BMPs)... What are They? GOOD HOUSEKEEPING PRACTICES Your Business Should Employ

BEST MANAGEMENT PRACTICES (BMPs)... What are They? GOOD HOUSEKEEPING PRACTICES Your Business Should Employ BEST MANAGEMENT PRACTICES (BMPs)... What are They? CLEAN STREETS MEAN CLEAN STREAMS Inexpensive to implement and easy to use, BMPs help you to do your share to protect the environment. The term Best Management

More information

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE

CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities.

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

CONSTRUCTION PERMIT REQUIREMENTS

CONSTRUCTION PERMIT REQUIREMENTS CONSTRUCTION PERMIT REQUIREMENTS Any work to be done in the City right-of-way (ROW), in a utility easement, and certain work on private property, requires an Engineering Inspection Permit from the Department

More information

APPENDIX G Materials Storage and Handling Guidelines

APPENDIX G Materials Storage and Handling Guidelines APPENDIX G Materials Storage and Handling Guidelines 1.0 INTRODUCTION Operations at Austin-Bergstrom International Airport (ABIA) comprise several different industrial activities including aircraft, ground

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule 763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project

More information

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...

SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards... SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement

More information

SPILL CONTAINMENT AND CONTROL PLAN

SPILL CONTAINMENT AND CONTROL PLAN SPILL CONTAINMENT AND CONTROL PLAN PUD NO. 1 TREATMENT PLANT 1257 GLASS ROAD PORT ANGELES, WASHINGTON PUD No. 1 Treatment Plant 2431 East Highway 101 P.O. Box 1090 Port Angeles, WA 98362 Facility Description:

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

SPILL PREVENTION AND RESPONSE PLAN TEMPLATE FOR BUSINESSES IN DAYTON S SOURCE WATER PROTECTION AREA

SPILL PREVENTION AND RESPONSE PLAN TEMPLATE FOR BUSINESSES IN DAYTON S SOURCE WATER PROTECTION AREA SPILL PREVENTION AND RESPONSE PLAN TEMPLATE FOR BUSINESSES IN DAYTON S SOURCE WATER PROTECTION AREA Regulated Substance Management: All Regulated Substances, including chemical wastes, are to be managed

More information

Asbestos Storage Facility Plan Examples

Asbestos Storage Facility Plan Examples Asbestos Storage Facility Plan Examples The purpose of this document This document contains examples of what an operational plan, plans and specification, contingency plan and closure plan should look

More information

How To Get A Stormwater Discharge Permit In A City Of Scottsdale

How To Get A Stormwater Discharge Permit In A City Of Scottsdale Environmental Regulations Guide Section 4 Pollution Prevention 4. 0 Pollution Prevention The Pollution Prevention Act (PPA) focuses on source reduction, i.e. on reducing the amount of pollution through

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

SECTION 202. REMOVAL Of ROADWAYS AND BUILDINGS

SECTION 202. REMOVAL Of ROADWAYS AND BUILDINGS SECTION 202 REMOVAL Of ROADWAYS AND BUILDINGS 202.1 Description. This work shall consist of the removal and disposal of all existing improvements from the right of way and within the limits of any construction

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site- Specific BMP Plans for projects. plan reviewers will use this checklist to review the Site-Specific

More information

SECTION 7 UNDERDRAIN SERVICE

SECTION 7 UNDERDRAIN SERVICE SECTION 7 UNDERDRAIN SERVICE ARTICLE I USE OF THE PUBLIC UNDERDRAIN SYSTEM 7.100 The purpose of the District s underdrain system is to provide a method for conveying ground water from around building foundations

More information

Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts. Submitted to: Town of Sudbury

Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts. Submitted to: Town of Sudbury Operations and Maintenance Plan The Residences at Johnson Farm 189 Landham Road Sudbury, Massachusetts Submitted to: Town of Sudbury December 2011 Table of Contents 1.0 Introduction... 1 1.1 Responsibility...

More information

Civil Engineering Sector Labour-Management Health and Safety Committee

Civil Engineering Sector Labour-Management Health and Safety Committee PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION SITES Civil Engineering Sector Labour-Management Health and Safety Committee July 2008 PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION

More information

Sanitary Sewer Overflow Response Plan Working Committee SANITARY SEWER OVERFLOW RESPONSE PLAN

Sanitary Sewer Overflow Response Plan Working Committee SANITARY SEWER OVERFLOW RESPONSE PLAN Sanitary Sewer Overflow Response Plan Working Committee SANITARY SEWER OVERFLOW RESPONSE PLAN I. PURPOSE The Municipality / Authority has structured this Sanitary Sewer Overflow Response Plan to satisfy

More information

How To Install An Overhead Sewer

How To Install An Overhead Sewer Village of Broadview Flood Control Assistance Program Village of Broadview 2350 S. 25 th Avenue, Broadview, IL 60155 INTRODUCTION The Village of Broadview is served by combined sewers which carry sewage

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY. August 2012

DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY. August 2012 DIRECTIVE 055: STORAGE REQUIREMENTS FOR THE UPSTREAM PETROLEUM INDUSTRY August 2012 SECTION 2 The storage requirements in Directive 055 apply to upstream petroleum facilities, well sites, and pipelines

More information

Cleaning. Wash vehicles over an indoor drain leading to an oil/water separator that flows to the sanitary sewer system.

Cleaning. Wash vehicles over an indoor drain leading to an oil/water separator that flows to the sanitary sewer system. Underground Oil/Water Separator Cleaning Wash water from cleaning often contains solvents, detergents, and metals. Wash water should never be discharged to a street, gutter, or storm drain. Contact your

More information

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is ~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions

More information

New York State Department of Environmental Conservation 625 Broadway, Albany, NY 12233 www.dec.ny.gov. Environmental Self Audit For Small Businesses

New York State Department of Environmental Conservation 625 Broadway, Albany, NY 12233 www.dec.ny.gov. Environmental Self Audit For Small Businesses New York State Department of Environmental Conservation 625 Broadway, Albany, NY 12233 www.dec.ny.gov Environmental Self Audit For Small Businesses Disclaimer The materials in this document are intended

More information

Moyer Heavy Use Area Project Hollenback Township Luzerne County, PA. Bid Package. Contracting Officer: Joshua Longmore, District Manager 570-674-7991

Moyer Heavy Use Area Project Hollenback Township Luzerne County, PA. Bid Package. Contracting Officer: Joshua Longmore, District Manager 570-674-7991 Moyer Heavy Use Area Project Hollenback Township Luzerne County, PA Bid Package Contracting Officer: Joshua Longmore, District Manager 570-674-7991 1. PROPOSALS INSTRUCTIONS TO BIDDERS A. The Drawings

More information

SOLICITATION STATEMENT OF WORK CONSTRUTING OVERHEAD ROOF COVER ON THE TENT AT DTFS. US. Embassy, Sawan Street, Himyar Zone

SOLICITATION STATEMENT OF WORK CONSTRUTING OVERHEAD ROOF COVER ON THE TENT AT DTFS. US. Embassy, Sawan Street, Himyar Zone SOLICITATION STATEMENT OF WORK CONSTRUTING OVERHEAD ROOF COVER ON THE TENT AT DTFS US. Embassy, Sawan Street, Himyar Zone Property Number: X369 1.0 INTRODUCTION The American Embassy in Sana Yemen requires

More information

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued) BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset

More information

IAC 7/2/08 Agriculture and Land Stewardship[21] Ch 44, p.1

IAC 7/2/08 Agriculture and Land Stewardship[21] Ch 44, p.1 IAC 7/2/08 Agriculture and Land Stewardship[21] Ch 44, p.1 CHAPTER 44 ON-SITE CONTAINMENT OF PESTICIDES, FERTILIZERS AND SOIL CONDITIONERS [Prior to 7/27/88, see 21 Ch 9] PESTICIDES 21 44.1(206) Definitions.

More information

DIVISION I GENERAL REQUIREMENTS SECTION 01005

DIVISION I GENERAL REQUIREMENTS SECTION 01005 Subdivision Requirements Manual Page 1 of 13 PART I - GENERAL 1.1 Description.1 The requirements of this specification shall apply to the contract as a whole and pertain to all of the work as specified

More information

Mine Plan of Operations Reclamation Bond Checklist

Mine Plan of Operations Reclamation Bond Checklist Mine Plan of Operations Reclamation Bond Checklist NOTE: This checklist is provided to assist the operator in calculating the engineering and environmental costs required to properly stabilize, reclaim,

More information

CSC-DIVISION 1-MASTER SECTIONS Description

CSC-DIVISION 1-MASTER SECTIONS Description CSC-DIVISION 1-MASTER SECTIONS Description 01 11 00 Summary of Work by Consultant 01 12 00 Multiple Contract Summary by Consultant 01 14 00 Work Restrictions see below 01 21 00 Allowances by Consultant

More information

Underground Commercial Electric Service

Underground Commercial Electric Service Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer

More information

Spill Control Prevention Plan (SCPP)

Spill Control Prevention Plan (SCPP) Spill Control Prevention Plan (SCPP) FACILITY INFORMATION PLEASE PRINT Facility Name: Mailing Address: Physical address if different: Owner Name: Owner Address: Primary Contact Name: Work Phone Number:

More information

FOOD SERVICE FACILITIES Best Management Practices Stormwater Management Program City of Bluff City P.O. Box 70, Bluff City, TN 37618 423-538-7144

FOOD SERVICE FACILITIES Best Management Practices Stormwater Management Program City of Bluff City P.O. Box 70, Bluff City, TN 37618 423-538-7144 FOOD SERVICE FACILITIES Best Management Practices Stormwater Management Program City of Bluff City P.O. Box 70, Bluff City, TN 37618 423-538-7144 This document may be printed and used for reference by

More information

Austin Used Cooking Oil Initiative Voluntary Compliance Standards

Austin Used Cooking Oil Initiative Voluntary Compliance Standards Austin Used Cooking Oil Initiative Voluntary Compliance Standards The City of Austin invites Used Cooking Oil Generators - including brick-and-mortar restaurants, mobile food vendors and other food service

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address:

Permit No. Permit Fee: $295.00. Permit Expires (D+90 days): Business Name: Applicants Name: Telephone Number: E-mail Address: City of Woodland Park Internet Service Provider (IPS) Permit for Installation of Telecommunication Infrastructure within City Owned Rights-of-Way (up to five locations per single permit) Permit No. Permit

More information

CHAPTER 10 POLLUTION PREVENTION PLAN

CHAPTER 10 POLLUTION PREVENTION PLAN CHAPTER 10 10.1 INTRODUCTION Virginia Stormwater Management Program (VSMP) land-disturbing activities covered under the General Construction Permit (GCP) are required to develop a Stormwater Pollution

More information

City of San Diego Urban Runoff Management Program. Appendix XI. Minimum BMPs for Mobile Businesses

City of San Diego Urban Runoff Management Program. Appendix XI. Minimum BMPs for Mobile Businesses City of San Diego Urban Runoff Management Program This Page Left Intentionally Blank. Minimum Best Management Practices (BMPs) for Mobile Businesses No. BMP Title Description and Examples Justification

More information

Good Housekeeping Practices for DPW/Fleet Maintenance Facilities

Good Housekeeping Practices for DPW/Fleet Maintenance Facilities Good Housekeeping Practices for DPW/Fleet Maintenance Facilities Kevin P. Walker C&S Engineers, Inc. Best Management Practices Best Management Practices (BMPs) are measures and/or controls used to prevent

More information

16. Storm water drainage

16. Storm water drainage 16. Storm water drainage There are three principal ways to dispose of rainwater from roofs, courtyards and paved areas: storm water sewers, soakaways and collection in storage tanks. Storm water sewers,

More information

The Clean Up of Clandestine Drug Lab Sites in Minnesota

The Clean Up of Clandestine Drug Lab Sites in Minnesota CLEANUP OF CLANDESTINE DRUG LAB SITES ORDINANCE for Renville County ARTICLE I. GENERAL PROVISIONS SECTION 1.10 SECTION 1.20 SECTION 1.30 SECTION 1.40 SECTION 1.50 SECTION 1.60 SECTION 1.70 TITLE AND STATUTORY

More information