The UW Capital Projects Office and NW Construction Consumer Council
|
|
|
- Carmella Gardner
- 10 years ago
- Views:
Transcription
1 The UW Capital Projects Office and NW Construction Consumer Council Present: Changing Project Delivery at the UW through Innovation, Integration, and Adoption of MC/CM and EC/CM PACCAR Hall, the Gordon Kloft Classroom June 22, 2011
2 Case Study and Panel Discussion: MC/CM & EC/CM Part 3 UW Bothell 1. UWB3 MC/ECCM Delivery Overview 2. UWB3 Mechanical Case Studies and Discussion 3. UWB3 Electrical Case Studies and Discussion 4. MEP Panel Q & A Session Slide 2
3 UWB MC/ECCM Delivery Overview Troy Bloedel Lease Crutcher Lewis Slide 3
4 UWB MC/ECCM What is MC/ECCM? Mechanical Contractor as Construction Manager Electrical Contractor as Construction Manager New Alternative Delivery model within the GCCM delivery which allows early selection of MEP subcontractors for providing input during preconstruction phase of the project Slide 4
5 CPARB Sponsored Continuing Education UWB MC/ECCM GCCM MCCM ECCM delivery method AGC Education Foundation Erica Peterson T: (206) F: (206) Slide 5
6 UWB RCW Alternate Subcontractor Selection Process Alternate to RCW , which provides the low bid subcontractor selection process If M or E anticipated value of the subcontract is over $3 million Early in the life of the project (how early is early?) Slide 6
7 (1) Determination UWB MC/ECCM Selection Process GCCM and Public Body = this process is in the best interest of the public What is the best interest of the public? Slide 7
8 UWB MC/ECCM Selection Process (a) Provide notice of intent to use the procedure and establish a hearing date. Publish in legal newspaper Justify the need (a few lines) Describe how to obtain the draft request for proposals ( or website) Slide 8
9 (b) Conduct a hearing. UWB MC/ECCM Selection Process Review Justification and Evaluation Criteria Provide an opportunity for written and verbal comments. Slide 9
10 UWB MC/ECCM Selection Process (c) Consider the comments and determine if process is still in the best interests of the public. Slide 10
11 UWB MC/ECCM Selection Process (d) Issue a written final determination (including final RFP). Revise RFP to incorporate accepted comments Slide 11
12 UWB MC/ECCM Selection Process The public solicitation of proposals must include: (d) A description of the selection process Evaluation factors Weight of factors (points) Slide 12
13 UWB MC/ECCM Selection Process The public solicitation of proposals must include: (e) The form of the contract, including pre-con services requirements (f) The estimated maximum allowable subcontract cost (g) Bid instructions Slide 13
14 UWB MC/ECCM Selection Process (3) Evaluation Factors for selection of the subcontractor must include, but not be limited to: Assign points to each one of these based on the project Slide 14
15 Evaluation Factors (a) Ability of the firm s professional personnel. Ask for resumes of PM and Superintendent. Be clear about the expectations and skills. (b) The firm s past performance on similar projects. How to evaluate performance Fair Responsible UWB MC/ECCM Selection Process Slide 15
16 UWB MC/ECCM Selection Process Evaluation Factors (c) The firm s ability to meet time and budget requirements. Recommend asking the firms to demonstrate competency. Slide 16
17 UWB MC/ECCM Selection Process Evaluation Factors (d) Self-performed work What is this? The work performed by employees of the firm. How is effectiveness evaluated. (e) Outreach to minority-and women-owned businesses. Plan or Evidence of a plan Slide 17
18 UWB MC/ECCM Selection Process Evaluation Factors (f) The firm s proximity to the project. How important is this? (g) The firm s capacity to successfully complete the project backlog. Discuss different approaches. Concerns about the level of financial information requested. Slide 18
19 Evaluation Factors (h) The firm s approach to executing the project. (i) UWB MC/ECCM Selection Process What ideas do they have? Be specific about particular challenges, like bidding out subcontracts. The firm s approach to safety summary, not safety manual. Any particular concerns, rigging, lifting, crane, confined space. Slide 19
20 UWB MC/ECCM Selection Process Evaluation Factors (j) The firm s safety history. EMR, Incidence, average, over/under. Concerns about EMR metrics. (k) The fee and cost proposal. Not a lump sum bid of MACC Misconceptions General Conditions Profit or Margin Slide 20
21 UWB MC/ECCM Selection Process (4) Proposal Evaluation Establish committee Final proposals including percent fee and general conditions Indicates a 2-step process Part 1 Short-List Most Qualified Firms Interview (?) part of Step 2 Select the firm with the highest scored final proposal Provide Part 1 scoring before opening Part 2 Slide 21
22 Slide 22
23 (8) Total Subcontract cost = Subcontract MACC + Specified General Conditions + Percent Fee UWB MC/ECCM Selection Process Subcontract MACC = cost of work including selfperformed work + contingency + negotiated support services + change orders Documents must be 90% complete why? Public Body Approves Slide 23
24 Slide 24
25 UWB MC/ECCM Selection Process (9) Savings goes to GC; over-runs are on subcontractor. Independent audit how robust of an audit? Slide 25
26 UWB MC/ECCM Selection Process (10) Subcontractor can self-perform work Set up a system to verify the estimate Otherwise must subcontract out in accordance with the low bid 380. How do subcontractors plan to execute bid packages? Slide 26
27 Slide 27
28 UWB Mechanical Case Studies & Discussion Brett Magnuson UW Facility Services Len Klein GLUMAC Dave Nehren - Hermanson Slide 28
29 Level 2 North Slide 29
30 Early Integration works! Team-work atmosphere Constructability Issues discussed as design evolved Cost (VE) ideas put forth as design evolved Client/users better informed of issues and decisions fewer surprises Projected decrease in substitutions requests, and RFI s Slide 30
31 Data Center HVAC: System Types UWB Server Room Initial Approach: Chilled Water AHU with Traditional Space Temps Slide 31
32 Data Center HVAC: System Types UWB Server Room What if we could have.: Greener approach Reduced carbon footprint Greater reliability More energy efficient More cost effective Improved maintainability Slide 32
33 Data Center HVAC: System Types UWB Server Room Alternate Approach: Evaporative Cooling with Elevated Space Temps Slide 33
34 Data Center HVAC: System Types UWB Server Room Alternate Approach: Evaporative Cooling with Elevated Space Temps Slide 34
35 UWB Server Room Data Center HVAC: Elevated Space Temps Slide 35
36 Data Center HVAC: System Types UWB Server Room What questions need to be resolved to validate this approach? Is it proven? Comfort level? End User Facilities Staff How do you train the end user and facilities staff? Do we gain all the previously mentioned benefits? Slide 36
37 Data Center HVAC: System Types UWB Server Room What questions need to be resolved to proceed? Is it proven? Comfort level? End User Facilities Staff How do you train the end user and facilities staff? Do we gain all the previously mentioned benefits? Final decision: All the stakeholders bought into this alternate concept (Designers, Builders, and Owner) Slide 37
38 UWB Server Room Q: How do we make it even better? Slide 38
39 UWB Server Room System Location: Initial Slide 39
40 UWB Server Room System Location: Final Slide 40
41 Data Center HVAC: Value Added UWB Server Room Cost Other Benefits: Improved Maintainability Improved Energy Efficiency More Centralized Equipment Improved Reliability A more sustainable solution for less money Slide 41
42 UWB Electrical Case Studies & Discussion Brett Magnuson UW Facility Services Judi Ebmeyer GLUMAC Tim Nelson Nelson Electric Slide 42
43 UWB Generator What loads would the generator serve? No Code required for this building Egress Lighting Server Room HVAC Equipment for the Server Room Fume Hoods in Labs for Research Cold Room (Walk in Cooler) Fire Alarm Control Panel Security Panel Elevator(s) This building and future building(s) Slide 43
44 UWB Generator What size should the generator be? 900 kw or 750 kw (smaller generator $95,000 savings) What is the real load at build-out for the Server Room? What is the HVAC load associated with the Server loads? Is it dedicated to this building or to future buildings as well? What can the budget handle? Slide 44
45 UWB Generator Where should the generator be located? Slide 45
46 Current Location Adjacent to New UW3 Building Slide 46
47 In the Parking Lot across NW 180 th St. Adjacent to the UW2 Additional 350 feet of feeder: + $54,000 Slide 47
48 Adjacent to the UW2 Transformer Additional 195 feet of feeder: + $23,000 Slide 48
49 At the Physical Plant Adjacent to the UW2 + $200,000 for Generator/Transformer package To Physical Plant Slide 49
50 Optimizing Lighting Controls UWB Lighting Controls Designer/Contractor working together Understanding local energy codes Perform cost analysis Code requirement vs. desire vs. cost Eliminated dimming zones ($36,000) User feedback Control and reporting through DDC keeping a familiar format Slide 50
51 Light Fixture Selection Understanding design concept UWB Light Fixtures Offer alternate product selection during design process, not submittal process Retain open spec CFL vs LED User feedback Reducing lamp types Maintainability Stairwells, high ceilings Slide 51
52 UW Bothell Panel Format Q&A Session Slide 52
CONSIDERING GC/CM There are some benefits and risks to using GC/CM. Departments should consider these carefully.
Department of Finance and Administrative Services ALTERNATIVE PUBLIC WORKS GENERAL CONTRACTOR/CONSTRUCTION MANAGER (GC/CM) GENERAL INFORMATION INTRODUCTION This manual provides the policy framework, procedures
PORT OF SEATTLE MEMORANDUM. COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015
PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6a ACTION ITEM Date of Meeting January 6, 2015 DATE: TO: FROM: Michael Ehl, Director Airport Operations Wayne Grotheer, Director Aviation Project Management
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Campus Elevator Upgrades Response Deadline 9/03/13
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector
Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector Approved March 23, 2011 Purpose: While the traditional Design-Bid-Build
Energy Design Resources Commissioning Plan Outline Template
IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) Administration of Project: Local Higher Education Project Name FAES- Student Success Center Response Deadline 03/04/2013 4:30 pm local time Project Location
A Guide to Hiring a Custom Home Builder
A Guide to Hiring a Custom Home Builder A Guide to Hiring a Custom Home Builder Copyright 2013 Published by Christian Gladu Design 2721 NW Nordic Avenue Bend, OR 97701 All rights reserved. Except as permitted
GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES
REQUEST FOR QUALIFICATIONS GENERAL CONTRACTOR / CONSTRUCTION MANAGER SERVICES NEW DINING HALL MONTANA STATE UNIVERSITY Bozeman, Montana PPA NO. 15-0103 Campus Planning, Design & Construction Plew Building
Los Angeles Community College District PROGRAM MANAGEMENT SERVICES. Terri Mestas Program Director
Los Angeles Community College District PROGRAM MANAGEMENT SERVICES Terri Mestas Program Director CMAA Southern California Chapter February 13, 2015 1 LACCD Overview Established in 1969 Governed by seven-member
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Higher Education Project Name Shideler Hall Renovation Response Deadline 12/20/13
Evaluating Project Delivery Options
Evaluating Project Delivery Options Scot A. Bini Vice President, URS August 24, 2004 Design-Bid-Build Overview Design Build Construction Management at Risk Owner Representation Terminology Project Manager
1. Request for Qualifications - GC/CM Services 2. Project Description and Background Information
GC/CM Services for Lynnwood Elementary & Mountlake Terrace Elementary Schools Modernization/Replacement Projects Request for Qualifications Edmonds School District November 6, 2015 1. Request for Qualifications
Mid Michigan Community College
Mid Michigan Community College REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT/CONSTRUCTOR SERVICES PART 1 -- GENERAL INSTRUCTIONS A. PROJECT DESCRIPTION Mid Michigan Community College (the "Owner")
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 REF. LOCATION DESCRIPTION OF CHANGE. Revised Scope of Work. Work tasks have been revised.
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 DATE PUBLISHED: MAY 18, 2016 TO ALL PROSPECTIVE SUBMITTERS: THE FOLLOWING CHANGES ARE MADE: REF. LOCATION DESCRIPTION OF CHANGE Attachment A Attachment
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents Administration of Project: School District Board + OFCC Project Name Wellington New K-8 EM/MS Response Deadline
Mechanical Contractor Pre-Qualification Packet. SPSC N180 Computer Data Room Phase II. Project No. CP 159313. Notice No. Notice 13-11.
Mechanical Contractor Pre-Qualification Packet SPSC N180 Computer Data Room Phase II Project No. CP 159313 Notice No. Notice 13-11 Issued by Department of Facilities Management Delivery address: Research
Request for Proposal No. RFP02658. Project Construction Management Services. for. Capital Levy BTA IV Project: Ingraham High School Classroom Addition
Seattle Public Schools Contracting Services 2445 Third Avenue South Seattle, WA 98134 Telephone: (206) 252-0566 Fax: (206) 743-3018 [email protected] Request for Proposal No. RFP02658
Owner s project control review. 2014 Baker Tilly Virchow Krause, LLP
Owner s project control review 2014 Baker Tilly Virchow Krause, LLP About Baker Tilly > Established in 1931 > One of the top 20 largest accounting and advisory firms in the United States according to Accounting
Construction Management At-Risk
Oconee County Schools P.O. Box 146, 34 School Street Watkinsville, GA 30677 706-769-5130 706-769-3513 REQUEST FOR PROPOSALS ISSUE DATE: March 10, 2016 RFP REF: Construction Management At-Risk Construction
NOTICE TO CM/GC Companies
NOTICE TO CM/GC Companies Facilities and Construction Management Jefferson County School District R-1 (Jeffco) is pre-qualifying Construction Manager/General Contractors for CM/GC services for a new K-6
Establishing Commissioning Costs
Establishing Commissioning Costs Portland Energy Conservation, Inc. (PECI) 9/12/00; Revised 02/14/02 The following summarizes the latest information on commissioning costs taking into account costing studies
Construction Company Capacity Assessment
Business/Firm Name: Vendor NCDOT Number: Contact Address: Construction Company Capacity Assessment Name/Title of Person Taking Assessment: Phone Contact Information: Email Contact Information: List Current
Request for Qualifications 2015-162
Kitsap County Human Services Department Request for Qualifications 2015-162 Architectural and Project Management Services - Kitsap County Work Release Facility Remodel Response Deadline: November 17, 2015
Manage Deliverables - Construction Step 6. July 12, 2012
Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement
Covance Construction Management Staffing Plan Chandler, Arizona
INTRODUCTION: This Construction Management (CM) Staffing Plan has been prepared for Covance to identify the critical organizational structure necessary to successfully complete the Chandler project according
Request for Qualifications (CM at Risk Contract) State of Ohio Standard Forms and Documents
Request for Qualifications (CM at Risk Contract) Administration of Project: School District Board + OFCC Project Name Groveport Madison High School Response Deadline 10/17/2014 4:00pm local time Project
Sample - Existing Building Commissioning Plan
Sample - Existing Building Commissioning Plan Version: Draft for Review Final Approved: Owner Site Address: Primary Site Contact Name and Telephone Number: Date Building Description The site consists of
REQUEST FOR PROPOSALS BUILDING ENVELOPE, LIGHTING, & HVAC TESTING/RESTORATION SERVICES
REQUEST FOR PROPOSALS FOR BUILDING ENVELOPE, LIGHTING, & HVAC TESTING/RESTORATION SERVICES ISSUED BY TOWN OF COLCHESTER DEPARTMENT OF PUBLIC WORKS 781 Blakely Road P.O. Box 55 Colchester, VT 05446 Date
CITY OF KALAMA REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES. Proposal Due Date: April 13, 2016
CITY OF KALAMA REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES Proposal Due Date: April 13, 2016 The City of Kalama (CITY) invites proposals for the services of a registered architect and their team
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER
RFP #2016-02 REQUEST FOR PROPOSAL TO PROVIDE CONSTRUCTION MANAGEMENT AND GENERAL CONTRACTOR SERVICES FOR SPRINGVILLE CITY NEW AQUATICS AND ACTIVITIES CENTER RELEASE DATE: January 29, 2016 DUE DATE: February
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES. Part I: Qualifications Information
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT PROFESSIONAL SERVICES A. General Information Part I: Qualifications Information The Tacoma School District is soliciting Qualifications for onsite
Volume II- Project Development Processes
Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required
BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS
CARROLL COUNTY PUBLIC SCHOOLS ADMINISTRATIVE REGULATIONS BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS Administrative Procedures For Appointment of Architectural, Engineering and Construction
ANCHORAGE SCHOOL DISTRICT ANCHORAGE, ALASKA. ASD MEMORANDUM #186 (2011-2012) March 22, 2012
ANCHORAGE SCHOOL DISTRICT ANCHORAGE, ALASKA ASD MEMORANDUM #186 (2011-2012) March 22, 2012 TO: FROM: SUBJECT: SCHOOL BOARD OFFICE OF THE SUPERINTENDENT AWARD OF CONTRACT: IT DATA CENTER MOVE TO KENNEDY
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK
Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community
Request of Qualification Proposal for Construction Management Services
Request of Qualification Proposal for Construction Management Services Dated June 10, 2014 Table of Contents Overview 3 Introduction 4 Scope of Construction Managers Services 4 Submission of Qualifications
RESOLUTION NO. 2012-11
RESOLUTION NO. 2012-11 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF GARIBALDI ACTING AS CONTRACT REVIEW BOARD APPROVING A REQUEST FOR PROPOSAL DOCUMENT AND SAMPLE CONTRACT FOR THE GARIBALDI FIRE STATION
Doniphan-Trumbull Public School BP 902.05 Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE
Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE The school district adopts this policy in the event it resolves to use the construction management at risk (CM at risk) construction
Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides
Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides for experience in the Construction Company's three areas
Project Delivery Methods & Contract Types CSTM 102 Spring 2013
Project Delivery Methods & Contract Types CSTM 102 Spring 2013 Schedule February 16- Building Information Modeling February 21- Midterm Review February 23- Midterm In the industry the term Pre-Construction
STATE UNIVERSITY CONSTRUCTION FUND GUIDELINES FOR AWARD OF PROCUREMENT CONTRACTS
STATE UNIVERSITY CONSTRUCTION FUND GUIDELINES FOR AWARD OF PROCUREMENT CONTRACTS Section I. Purpose The purpose of these Guidelines is to describe the methods and procedures governing the use, awarding,
Module 1: INTRODUCTION. Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION"
Module 1: INTRODUCTION Submodule 1: What is Construction Quality Management (CQM)? "PROACTIVE PREVENTION vs. REACTIVE INSPECTION" Objectives: After completing this submodule, you will be able to: State
Project Procurement Management
Project Procurement Management 1 2 Procurement Planning Procurement Planning is the process of identifying which project needs can be best met by procuring products or services outside the project organization
Lump Sum Request for Proposal ( RFP ) Insert Project Name University Project Number: xx-xxx-xx-xxxx
Lump Sum Request for Proposal ( RFP ) Insert Project Name University Project Number: xx-xxx-xx-xxxx Insert RFP Issue Date Throughout this RFP Respondent or you means the prime firm responding to this RFP.
Request for Qualifications. Owner s Project Manager. Design and Construction of a New School Facility. K~8 Charter School
Request for Qualifications Owner s Project Manager Design and Construction of a New School Facility K~8 Charter School 26 Madeira Avenue New Bedford, MA 02746 REQUEST FOR QUALIFICATIONS (RFQ) Issued: 4/16/2014
AC Proposal Texarkana Regional Airport Airport Operations Director 201 Airport Drive Texarkana, AR 71854
I. INTRODUCTION This solicitation is being offered by Texarkana Airport Authority. The Airport is a public entity owned by the Cities of Texarkana, AR and Texarkana, TX. Funding for this project is being
TRANSBAY JOINT POWERS AUTHORITY
STAFF REPORT FOR CALENDAR ITEM NO.: 14 FOR THE MEETING OF: November 13, 2014 BRIEF DESCRIPTION: TRANSBAY JOINT POWERS AUTHORITY Amending Contract No. 08-04-CMGC-000, authorizing Webcor/Obayashi Joint Venture
Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program
Request for Qualifications for Program Management Support Services for The Greenville-Spartanburg International Airport Terminal Improvement Program SECTION 1 - GENERAL INFORMATION The Greenville-Spartanburg
CONSTRUCTIBILITY REVIEWS: CASE STUDY OF BID DOCUMENT ERRORS AND OMISSIONS
BY: KEN PRUETT, PROJECT MANAGER, PINNACLEONE The specific objective of a Constructibility Review should be to minimize or eliminate potential change orders and delay claims during construction by ensuring
Capital Projects Construction Manager At-Risk (CMR) Guaranteed Maximum Price (GMP) Best Value Selection Procedure Manual
Page 1 of 21 Connecticut Department of Administrative Services Capital Projects Construction Manager At-Risk (CMR) Guaranteed Maximum Price (GMP) Best Value Selection Procedure Manual Prepared for Capital
9 Keys to Construction Loan Funding Success
9 Keys to Construction Loan Funding Success By Barbara Leuin, Ph.D. Commercial Lending Expert www.sofiacapitalventures.com Key Steps to Construction Loan Funding Success Most people think construction
The CM Perspective. Preconstruction Phase
The CM Perspective The Elements of Project Management Preconstruction Phase Preconstruction: Setting the Project Up to Succeed Project Plan Critical Milestones Define all major deadlines and critical dates
Project Implementation Guide for CT, PET/CT, X-Ray, and Nuclear Systems
GE Healthcare Project Implementation Guide for CT, PET/CT, X-Ray, and Nuclear Systems Working together to get your new technology online so you can begin providing patient care. Table of Contents Table
Design-Build Mississippi Gate Additional Lane
Design-Build Mississippi Gate Additional Lane Buckley Air Force Base, Colorado Completion Date: December 2010 Client: United States Army Corps of Engineers Omaha District Project Reference: Jennifer McQueen,
Seattle Public Schools The Office of Internal Audit
seaonly Seattle Public Schools The Office of Internal Audit Capital Internal Audit Report Issue Date: December 16, 2014 Executive Summary Background In accordance with the Capital Risk Assessment and Audit
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request
The Business Inclusion Program (BIP) Outreach Process
The Business Inclusion Program (BIP) Outreach Process As of 9/25/2012 The Los Angeles Business Assistance Virtual Network (BAVN) at http://www.labavn.org is a free service provided by the City of Los Angeles
Creating Credible, Actionable Energy Audits
1 Creating Credible, Actionable Energy Audits www.kw-engineering.com Jim Kelsey, PE kw Engineering What We ll Cover 2 Elements of ASHRAE Audit Levels 1, 2 and 3 Summary of audit levels On-site techniques
REQUEST FOR QUALIFICATIONS PROJECT / PROGRAM MANAGEMENT CONSULTANT
REQUEST FOR QUALIFICATIONS PROJECT / PROGRAM MANAGEMENT CONSULTANT DUE: January 9, 2015 @ 5:00 PM Lopez Island School District 86 School Road Lopez Island, WA 98261 Contact: Bill Evans, Superintendent
Request for Qualifications & Proposal. Architectural Team. Lake County School District R-1. On-Call Services. For
Request for Qualifications & Proposal Architectural Team For Lake County School District R-1 On-Call Services Provided by: Submittal Deadline: April 23, 2015 Time: 5:00 PM 1.0 Introduction On behalf of
Career Path Project Engineer to Project Manager 1
Career Path Project Engineer to Project Manager 1 The Career Path standards listed below are designed to help a Project Engineer at Samet Corporation understand what skills, knowledge and experience they
Using Construction Manager at Risk to Save Time and Money Laura McCluskey University Center Sioux Falls / South Dakota Board of Regents
Using Construction Manager at Risk to Save Time and Money Laura McCluskey University Center Sioux Falls / South Dakota Board of Regents Primary Author: Laura McCluskey 4801 N Career Ave Sioux Falls, SD
REQUEST FOR QUALIFICATIONS (RFQ) FOR PROFESSIONAL ARCHITECTURAL/ENGINEERING AND CONSULTING SERVICES FOR Fiscal Years 2015 2018
REQUEST FOR QUALIFICATIONS (RFQ) FOR PROFESSIONAL ARCHITECTURAL/ENGINEERING AND CONSULTING SERVICES FOR Fiscal Years 2015 2018 Solicitation No.: BFZ1523 1. Mission Statement and General Information 1.1.
Request for Proposal Digital Asset Management October 24, 2014
Request for Proposal Digital Asset Management October 24, 2014 INTRODUCTION Brand USA is a public-private not for profit organization created by the Travel Promotion Act of 2009. The mission of Brand USA
DATA CENTER COOLING INNOVATIVE COOLING TECHNOLOGIES FOR YOUR DATA CENTER
DATA CENTER COOLING INNOVATIVE COOLING TECHNOLOGIES FOR YOUR DATA CENTER DATA CENTERS 2009 IT Emissions = Aviation Industry Emissions Nations Largest Commercial Consumers of Electric Power Greenpeace estimates
Job Analysis-based Performance Appraisal
Job Analysis-based Performance Appraisal By Dale J. Dwyer, Ph.D Instructor s Manual, Application Exercises and Activities 1 2008 SHRM. Dale J. Dwyer, Ph.D. EMPLOYEE AND LABOR RELATIONS Learning Module
REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES)
REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGER / GENERAL CONTRACTOR (CM/GC SERVICES) Return Completed Qualifications To: Twin Falls School District No. 411 Administrative Office 201 Main Avenue West Twin
All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.
2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other
CITY OF MESA, ARIZONA ENGINEERING DEPARTMENT REQUEST FOR QUALIFICATIONS
CITY OF MESA, ARIZONA ENGINEERING DEPARTMENT REQUEST FOR QUALIFICATIONS On-Call Consultant List for Mechanical Engineering Services TABLE OF CONTENTS REQUEST FOR QUALIFICATIONS PAGE NO. SECTION I PROJECT
Auditing construction contract change orders
Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. Auditing construction contract change orders Presenter Tony Ollmann, CPA,
Planned and Emergency Utility Outage Guidelines
Revised: April 4, 2014 GUIDELINES: PURPOSE: The purpose of these guidelines is to define roles and responsibilities in requesting, coordinating scheduling, and executing utility outages and restoration
Developing a Proper Scope of Work, Request for Proposal & Commissioning Specification
Developing a Proper Scope of Work, Request for Proposal & Commissioning Specification Joseph Lorino, P.E., LEED Horizon Engineering Associates, LLP Synopsis In order for the commissioning process to have
Green Professional (GPRO) Building Skills Training Through the Urban Green Building Council
OFFICE FOR ASSESSMENT OF PROFESSIONAL AND WORKPLACE LEARNING ACADEMIC PROGRAM REVIEW Green Professional (GPRO) Building Skills Training Through the Urban Green Building Council of REVIEW DATE: JUNE 10,
The University of North Carolina Plan to Increase Utilization of Historically Underutilized Businesses in Construction Projects
The University of North Carolina Plan to Increase Utilization of Historically Underutilized Businesses in Construction Projects May 2002 1 of 15 The University of North Carolina Office of The President