ROOT CAUSES OF CONSTRUCTION PROJECT DELAYS IN DUBAI
|
|
|
- Jerome Summers
- 9 years ago
- Views:
Transcription
1 ROOT CAUSES OF CONSTRUCTION PROJECT DELAYS IN DUBAI Z. Ren 1, M. Atout and J. Jones 1 Built Environment Division, Glamorgan University, Pontypridd, CF37 1DL Dubai presents a special set of circumstances where the construction industry operates. Factors such as rapid growth in construction, tight construction schedule, unique architectural features, the involvement of international contractors and consultants, multinational work forces, unique culture and religion, readily available investment, and mixed contracts and conditions generate particular impacts on construction project progress. With the impacts of these factors, delay is a common problem for construction projects in Dubai. This research aims to identify the most important causes of delays in Dubai construction projects. A serial of questionnaire survey and interviews were conducted to explore each project participant's contributions to the causes of delays. The results show that the major causes of delays vary from the unrealistic project duration, nominated sub-contractors, and the culture impacts. Keywords: claims, contracting, delays, project management. INTRODUCTION During the last two decades, Dubai has witnessed a remarkable growth in its economic and social development. Major social development projects are established by both public and private sectors, which include housing projects, hospitals, schools and educational institutions and other utilities. Given its cultural background, procurement system and operational environments, the booming building and construction industry is facing many unique challenges which affect project progress. For example: Large scale and high quality requirements: Numerous large projects (e.g. the Palm, Dubai International Airport extension, Dubai Marina, Souk Al Nakheel) were initiated in the last few years. These developments request high quality, not only in workmanship and construction materials but also in design for an upscale lifestyle. The design, construction and management of these projects are challenging to the local construction industry. International involvement: Since the indigenous companies often do not have the qualifications to design, construction or management these projects. Foreign companies are involved in all the industry sectors. They bring the state of art construction technology and management techniques, however, many of them are involved in contractual claims and disputes with project delayed and cost overrun. Traditional procurement approach: So far, most of the construction projects adopt traditional procurement approach. FIDIC is a widely used as the general 1 [email protected] Ren, Z, Atout, M and Jones, J (2008) Root causes of construction project delays in Dubai. In: Dainty, A (Ed) Procs 24th Annual ARCOM Conference, 1-3 September 2008, Cardiff, UK, Association of Researchers in Construction Management,
2 Ren, Atout and Jones conditions of contact. The consultant, often from aboard, is responsible for designing the project and preparing the contract documents. Large amount of small contractors: There are a large number of small construction firms with a capital less than a million Dirhams, who are incapable to work on large scale or middle-sized projects. They often delay their work due to the limited resources. It is remarkable that these companies are easily affected by the fluctuation of the market. Over commitment of construction firms: given the high demanding industry, most of the construction firms are over-loaded by taking more projects than what they can handle. The multitude of projects often beyond their capacity and cause delay in delivery. International workforces: The workforces employed in projects are of mixed nationalities, which bring different traditions, rules, habits, religions. For example, the religions holidays include holy Friday for Muslims, Sunday holiday for Christians, and regular holidays and festivals for Indians. The impact of such a multi-national workforce to construction is significant. Lack of skilled labour and high quality professionals: There is a high demand for skilled labour and professional in the local market. Many companies suffer from the high turn over of skilled technicians, engineers and labours. The impact is quite severe during the high peak of construction period. Wrong time estimation: With more than 95% of the workforces from south Asia, they are not acclimatised to the Gulf weather especially in summer. This often reduces the productivity and delays project progress. Thus, the work programmes from the clients or the contractors need to be checked by experience planners to include hot season adjustment in order to avoid over optimistic programme. Language barrier: In Dubai, the contract language is always Arabic and then translated into English. Most of the project participants prefer to speak and write in their own language without employing qualified interpreters. This affects the communication, progress and quality of work. Using the Arabic language in the contract documents is an important issue and most of the construction companies have not resolved this problem. Communication with the client: Unlike other countries, the clients in Dubai have absolute power in the project. When the client visits site, s/he may issue change orders which must be obeyed. On the other hand, they do not always see the necessity for prompt action with respect to their contractual obligations. Some words such as Insha allah which mean in English When God wants are very familiar words and most of managers and site engineers use it as a promise which is a part of Islamic tradition culture. Foreign engineers do not understand the deep meaning of that word and may consider it as a part of uncertainty that causes disputes when executing the project. Local regulations and customs: Law of Sharia, procedures and formalities for work permit and visa application and other local regulations (e.g. application for construction or enter permits) could generate critical impacts on project progress. For example, the construction work in free economic zone (FEZ) needs special permits which are issued under the control of the full control of FEZ. Local partners: There is a legal requirement for foreign companies to form partnerships with local companies in order to qualify to tender for construction works, and this also applies in sub-contracting sectors. As a 750
3 Causes of construction project delays consequence, there is often a difference in the working procedures and systems operated by foreign and indigenous companies, and also within partnership companies. The situation is compounded in construction where there are many parties involved in a project. According to the government regulations, the local must have at least 51% share of the joint venture which authorise them to make immediate and important decisions, if conflicts rise between partners. It is not easy to change a local partner s decision if it has been confirmed. This can adversely affect the work progress in construction projects. Given such a complex construction environment, it is not surprising that many projects are delayed. Project participants are involved in protracted contractual claims and disputes, often resolved either by arbitration, significant compromise or legal processes. This paper presents the outcome of a research project which aims to identify the primary causes of project delays in Dubai construction project and to categorise these causes in terms of the impacts upon the project completion time as well as the contributing parties. COMMON CAUSES OF PROJECT DELAYS Given the severe impacts of project delays, it has been widely studied by researchers from different countries (Bramble and Callahan 1992, Mansfield et al. 1994, Assaf, and Mohammed 1995, Al Kass and Mazeroll 1996, Thorvaldsson et al. 1996, Odeyinka and Yusif 1997, Scott 1997, Kumaraswamy and Chan 1998, Al Khalil 1999, Odeh 2002, Aibinu'A and Jagboro 2002, Battaineh 2002, Hussein 2002, Crawford and Frimpong 2003, Koushki and Kartam 2005, Lo et al. 2006, Abdul Rahman and Yahya 2006, Ajibade and Henry 2006). Table 1 summaries the general causes of project delays identified in these research projects. 10, 13 and 30 causes of project delays are identified contributed by the client, the consultant or the contractor respectively. Table 1: General causes of delays Client Consultant Contractor Regular interference and poor Incomplete contract Inappropriate organization communication documents management Variation order and late Incomplete drawings Lack of technical professional in approval for payment the organisation Late supply of information Poor design management Unsmooth external and internal and late decision making communications Project objectives are not very Slow response Lack coordination with subcontractors clear Nomination of Subcontractors Delayed approval of drawings Centralization with top and suppliers and BOQ for construction management Many provisional sums and Inadequate duration for Delayed mobilization prime cost inspection Duration is not enough for Experience of staff in Incompetent contractor staff constructing the project management and technical Factors, Reasons and Causes of delay Irregular payments and disturbed cash flow of main contractor Routine of government authorities and approvals Irregular attending of weekly meetings inspection Delay in submittal and approval Poor communication between consultant staff Poor quality control Poor planning, scheduling or resource management Poor quality control Congested construction site 751
4 Ren, Atout and Jones Client Consultant Contractor Incompetence to contractor's Mistakes during construction technical enquiries Changes in drawings and specifications Lack of experience of similar projects Incompetent technical staff Shortage of materials Poor quality of materials Materials specifications Delay of delivery Shortage of manpower Inadequate skill of manpower Low productivity Unavailability of equipments on request Wrong allocation of equipments on site Financing the project by contractor Irregular payments of subcontractors Unexpected weather conditions Inadequate site investigation Different nationalities of workforce on site Problems with neighbours Preparing the method statement for each work activity Work permits DATA COLLECTION The survey was designed based on the 53 causes of delay shown in Table 1, to which participants were asked to indicate the level of importance of each cause. These causes were categorized into three major groups: The Client: Related factors include finance, payments, client interference, slow decision and unrealistic contract duration. The Consultant: Related factors include contract management, preparation and approval of submittals and materials and site supervision. The Contractors: Related factors include site management, improper planning, inadequate contractor experience, mistakes during construction and preparing the construction methodology. Other significant issues of concerns such as project location, site conditions, neighbours, and changes, materials including quality and shortage and the nominated Sub-contractors were also considered in the questionnaire survey in Dubai. Two rounds of survey were conducted. In the first round, questionnaire was distributed to 52 construction companies who were working on large and medium projects in Dubai with project values from US $ 41Million to US $ 150Million. Questionnaire was sent to the general managers, manager of technical affairs, project department managers, site project managers, chief engineers and construction managers who have specific experience in this area that can provide an insight into both underlying causes of delay and their relative effect. The second round of the questionnaire was distributed to 10 construction firms to further clarify some of the key issues raised in the first round of questionnaire survey. The response rate in both round of questionnaire was 100%. 752
5 Causes of construction project delays RESULTS AND DISCUSSION The results of the survey were analysed using a severity weighting method. Value of 5 is considered as 100% severity, value of 4 is considered as 85%, value of 3 is considered as 65% value of 2 is considered as 45% and value of 1 is considered as 25% of severity (for details see Atout, 2008). The average of the severity causes by the client, the consultant and the contractor ranging from 45% to 85% percentage wise. The result of the analysis shows that: The client s contribution to causes of delay is of 11.76% (4 out of 34 major causes) The consultant s contribution to causes of delay is of 26.47% (9 out of 34 major causes) The contractor s contribution to causes of delay is of 61.76% (21 out of 34 major causes) The result also demonstrates a high consistency between the causes of delay in Dubai construction project (Figures 1, 2, 3) and the general causes identified by previous researchers Attendance 1.9 Authorities & Approval 1.8 Irregular Payment 1.7 Compressed Duration 1.6 Many Provisional Sums 1.5 Nominated Subcontractors 1.4 Project Objectives 1.3 Late Information 1.2 Variations 1.1 Regular Information 48% 51% 82% 65% 51% 52% 60% 55% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% Figure 1: Factors of Delay Caused by the client 2.13 Irregular staff attendance 2.12 Changes in drawings 2.11 Late response of tech inquiries 2.10 Quality control 2.9 Mis-communication 2.8 Late approval of submittals 2.7 Less Experience of staff 2.6 Long Inspection Procedure 2.5 Drawings & BOQ 2.4 Slow Response 2.3 Poor Design Management 2.2 Incomplete Drawings 2.1 Incomplete Contract Documents 41% 47% 65% 74% 74% 0% 10% 20% 30% 40% 50% 60% 70% 80% Figure 2: Factors of Delay Caused by the consultant 753
6 Ren, Atout and Jones 3.30 Traffic problem 3.29 Permits of authorities 3.28 Preparing method statement 3.27 Neighbors problem 3.26 Multinational force 3.25 Site investigation 3.24 Weather conditions 3.23 Subcontractor payment 3.22 Project finance 3.21 Allocation of equipments 3.20 Availability of equipments 3.19 Productivity of manpower 3.18 Skills of manpower 3.17 Shortage of manpower 3.16 Delay of delivery 3.15 Material specifications 3.14 Quality of materials 3.13 Storage of materials 3.12 Similar projects 3.11 Mistakes in construction 3.10 Confined site 3.9 Quality control 3.8 Planning & scheduling 3.7 Qualification 3.6 Mobilization & survey 3.5 Centralization 3.4 Coordination 3.3 Communication 3.2 Incomplete drawings 3.1 Contract document 50% 60% 81% 66% 48% 68% 72% 80% 68% 62% 52% 74% 65% 52% 76% 65% 70% 66% 55% 79% 50% 70% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% Figure 3: Factors of Delay Caused by the contractor The follow section outlines the top five causes contributed by each project participant. A) Key Causes from the Client The causes of delay original from the client could be more important than from the consultant and the contractor because decisions made by the client significantly affect others. A-1 Unrealistic Control Duration: Clients are looking for a rapid return on their investment. In the UAE it is usual for a client to stipulate a completed design date within which consultant may not appraise designs sufficiently. This results that design has a lot of changes during construction. A-2 Many Provisional Sums and Prime Cost: Clients always like to leave some unquantifiable items in the bill of quantities, this prevents the contractor from estimate these items on time, and when the details of this bill are given (at very late stage), the work programme will be disturbed and the main contractor will find difficulties in achieving the target of the project. 754
7 Causes of construction project delays A-3 Nomination of Sub-Contractors and Suppliers: Most clients prefer their own sub-contractors or suppliers for some specialized work. They often instruct the contractors directly through the consultant to enter the subcontract agreement based on limited conditions that may not suit the main contractor such as an advanced payment, duration, penalties, submittals and approvals. If the main contractor rejects these terms, conflicts will occur and delay will progress until a final agreement is signed between those involved parties. A-4 Client s irregular Payment to the Main Contractor: Delay in monthly payment from the client significantly disturbs the contractor s cash flow. This in turn affects the payments to sub-contractors, who are obligated to purchase material from suppliers. Project execution will be consequently affected financially. This will be reflected in the work progress and it can cause major delay to the project. B) Key Causes from the Consultant The consultant offices in Dubai are reluctant to refuse potential commission and follow a policy of we are always ready to design your project. The design offices are often overloaded due to rapid development in construction in the city. Most of them do not have sufficient time and lack of effective management, which affects the quality of the work and consequently reflected on the contractors performance. B-1 Incomplete Drawings: If the client requests an unrealistic deadline for design, large margins of errors will appear in the project drawings and specifications. Conflicts often appear between drawings from different disciplines. This is considered as a delay factor from the consultant side. B-2 Delay in Approval of Documents: It is time-consuming and complex process for consultant to approve documents submitted by the constructor (e.g. method statement or specifications). It is reported that the contractor can rarely get the approval from the consultant in Dubai. B-3 Incomplete Contract Documents: The Consultant has the full authority to issue changes, correct the mistakes in the drawings and the discrepancies in the contract document on behalf of the client. However the consultant s site staff does always not have confidence in issuing instructions until they discuss with their top managers. The contractor often cannot receive instructions about those discrepancies in time. B-4 Changes in Drawings and Specifications: Some engineers from the consultant s side do not have enough experience in design practices. Some problems in the design cannot be found until the contractor inquires about them in the construction. It takes extra time for municipality to approve new design solutions, for instance. B-5 Duration of Inspection Procedure: Consultants inspect the project to make sure that the project meets the standard of quality. This work is carried out by qualified engineers and authorities. However due to lack of the specialists, some projects could be inspected on time. C) Key Causes from the Contractor As illustrated in Figure 3, most of the project delay factors in Dubai construction projects are attributed by the contractor. 755
8 Ren, Atout and Jones C-1 Preparing the Method Statements: Project manager should establish detailed method statements. Most of them in Dubai project do not have enough time to prepare for method statements as they often have to play more than one role (e.g. site manager and quantity surveyor). C-2 Financing Project by the contractor: When contractors receive advanced or monthly payment from the client, most of them may use the money to finance other urgent or more profitable projects. It often leads to the problems such as shortage of material, delayed payment to sub-contractors, etc. C-3 Organizational Chart: Project manager should implement an effective human resource management. However, due to lack of experienced technical staff and time constraints, most of posts cannot be filled by staff with required experience or knowledge. C-4 Communication Externally and Internally: Contractors have to frequently communicate with the other project participants. While in the Dubai construction participants could come from different countries, misunderstanding among them often happen because of the different cultural backgrounds. C-5 Mistakes during Construction: With the high demand of workforce in the local construction market, the majority of the labours are from South Asia without adequate training or limited experience. This often leads to poor workmanship. Some work has to be re-done or repaired before the consultant or quality control engineers could accept them. CONCLUSIONS AND FURTHER STUDIES Delays are a major problem suffered by most of the construction projects in Dubai whilst the causes of delays and the procedures to avoid delays or mitigate the impacts of delays are still not fully understood by project participants. This research discussed the specific operational environment of Dubai construction projects and investigated the root causes of the delay contributed by the major project participants. Unlike other countries or regions, the construction projects in Dubai face many special challenges such as the unique cultural, high architecture and quality requirements, short of workforce, and international construction teams. These constraints make the causes of delays different from other countries. For example, unrealistic project duration, many provisional sums and prime cost, nomination of sub-contractors and suppliers, client s irregular payment to the main contractor and variations are the top five causes of delay contributed by the client. Incomplete drawings, delay in approval of documents, incomplete contract documents, changes in drawings and specifications, and duration of inspection procedure are the major causes contributed by the consultant. Preparing the method statements, ill-financed project, inappropriate organization management, unsmooth external and internal communications, and mistakes in construction are the top causes contributed by the contractor. Based on the outcome of this research, further research will be conducted on how each party should control their root causes of project delays. More specifically, this includes the control of cultural impacts, the contract and coordination with nominated sub-contractors and suppliers and the adaptation of FIDIC conditions of contract. The latter has been raised by many of the project participants as need to be further studied when it is used in Middle East. 756
9 Causes of construction project delays REFERENCES Abdul Rahman A and Yahya A (2006) Delay Mitigation in the Malaysian Construction Industry. Journal of Construction Engineering and Management, 132(2), Aibinu'A A and Jagboro G O (2002) The Effect of Construction Delays on Project Delivery in Nigerian Construction Industry. International Journal of Project Management, 20(8), Ajibade A and Henry A (2006) Construction Delays and their Causative Factors in Nigeria. Journal of Construction Engineering and Project Management, 132(7), Al Kass S and Mazeroll M (1996) Construction Delay Analysis Techniques. Journal of Construction Management and Economics, 14(5), Al Khalil M I (1999) Important Causes of Delay in Public Utility Projects in K.S.A. Journal of Construction Management and Economics, 17(5), Assaf, S A and Mohammed A H (1995) Causes of Delay in Large Building Construction Project. Journal of Construction Engineering and Management, 2(11), Battaineh H (2002) Cause of Construction Delays: Traditional Contracts. International Journal of project Management, 20, Bramble, B and Callahan, M (1992) Construction Delay Claims. 2ed. New York: Wiley. Crawford L and Frimpong Y (2003) Causes of Delay and Cost Overruns in Construction Projects. International Journal of Project Management, 21, Hussein H (2002) Causes of Construction Delays. International Journal of Project Management, 20, Koushki, P A and Kartam, N (2005) Delay and Cost Increases in the Construction of Private Projects in Kuwait. Journal of Construction Management and Economics, 23(3), Kumaraswamy M and Chan D (1998) Contributors to Construction Delays. Journal of Construction Management and Economics, 16(1), Lo TY, Fang I W H and Tung K C F (2006) Construction Delays in Hong Kong Civil Engineering Projects. Journal of Construction Engineering and Management, 132(6), Mansfield N R, Ugwuo O O and Doran T (1994) Causes of Delay and Cost Overruns in Nigerian Construction Projects. Journal of Construction Engineering and Management 13(4), Odeyinka H and Yusif A (1997) The Causes and Effect of Construction Delays of Housing Projects in Nigeria. Journal of Finance Management and Property Construction, 3(2), Odeh A M (2002) Causes of Construction Delay. International Journal of Project Management, 20, Scott S (1997) Delay Claims in U.K. Contracts. Journal of Construction Engineering and Management, 123(3), Thorvaldsson K Skjoldebrand C Kabissa J C B Kayumbo H Y Yarro J G Glass N Ogunlana S O Promkuntong K Jearkjirm V (1996) Construction Delay in Fast Growing Economy: Comparing Thailand with Other Economies. International Journal of Project Management, 14(1),
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
Causes and effects of delays in Malaysian construction industry
International Journal of Project Management 25 (2007) 517 526 INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT www.elsevier.com/locate/ijproman Causes and effects of delays in Malaysian construction industry
Causes and Effects of Delays in Large Construction Projects of. Pakistan
Causes and Effects of Delays in Large Construction Projects of Pakistan M. Haseeb 1, a, Xinhai-Lu 1, Aneesa Bibi 1, Maloof-ud-Dyian 2, Wahab Rabbani 3 1 College of Public Administration, Huazhong University
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October
Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria
Journal of Construction in Developing Countries, 18(1), 53 72, 2013 Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria Olajide Timothy Ibironke, Timo Olugbenga
Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects
Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects Dr. Rashad Zakieh (PMP) 27 April, 2010 Copyright Saudi Aramco, 2010. All rights reserved.
Control Environment Questionnaire
Control Environment Questionnaire Internal Control Questionnaire Question Yes No N/A Remarks INTEGRITY AND ETHICAL VALUES Management must convey the message that integrity and ethical values cannot be
CAUSES OF DELAY IN NIGERIA CONSTRUCTION INDUSTRY
CAUSES OF DELAY IN NIGERIA CONSTRUCTION INDUSTRY KASIMU ALHAJI MOHAMMED DEPT OF QUANTITY SURVEYING, FEDERAL POLYTECHNIC, BIDA. NIGERIA ABUBAKAR DANLADI ISAH DEPT OF ARCHITECTURE, FEDERAL UNIVERSITY OF
bout your HOUSE Hiring a contractor
A bout your HOUSE Hiring a contractor CE 26 a At some time, most homeowners will hire someone for repairs or renovations. Even a homeowner experienced in home repairs may have to hire a contractor or renovator
Introduction to Social Compliance & Its Business Benefits
Proposal for Conducting Seminar on Introduction to Social Compliance & Its Business Benefits Submitted to: Environment Agency, Abu Dhabi Table of Contents Summary..02 Seminar Objectives 02 Content Outline..02
The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:
The Role of Construction Managers FIDIC offers two contributions on the question of the role of a construction manager in a construction contract: A. Notes on the use of FIDIC in the Middle East B. A Communication
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS: INHIBITING FACTORS AND MITIGATING MEASURES IN PRACTICE
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS: INHIBITING FACTORS AND MITIGATING MEASURES IN PRACTICE Yakubu Adisa Olawale, Ph.D., MCIOB and Ming Sun, Ph.D. (Professor) Abstract Despite the availability
AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts
11 AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff Risk Allocation in Construction Contracts Risks 2 In the absence of a contract, all risks are the owner's Contracting is
CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact [email protected] or telephone 029 2031 5512
A Guide to Small Works. A brief explanation
A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here
PRACTICE NOTES FOR QUANTITY SURVEYORS
PRACTICE NOTES FOR QUANTITY SURVEYORS Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant Quantity Surveyors and the Hong Kong
Study of Delay Management in a Construction Project - A Case Study
Study of Delay Management in a Construction Project - A Case Study B. Indhu 1, P. Ajai 2 1 M.tech, Student, 2 Assistant professor, Dept of Civil Engineering, SRM University Abstract The problem of delays
Steel procurement in major projects: Guidance on the application of social issues. Purpose
Steel procurement in major projects: Guidance on the application of social issues Purpose 1. This is a practical guide on how to incorporate social issues in major projects with a significant steel component.
THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE. John R. Lethbridge
Page 1 of 5 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK November 1990 Transport No. PS-2 THE USE OF OUTSIDE CONTRACTORS FOR PORT MAINTENANCE John R. Lethbridge The use of outside
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria.
ISSN: - Vol. Issue, January - Factors Affecting The Contractor s Cost Overrun Of Building Project In Kano State, Nigeria. Abdulrahman Haruna, Sani Usman Kunya, Musa Mohammed Department of Building Technology
Managing construction procurement risks
CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: [email protected]
ISO/IEC 17025 QUALITY MANUAL
1800 NW 169 th Pl, Beaverton, OR 97006 Revision F Date: 9/18/06 PAGE 1 OF 18 TABLE OF CONTENTS Quality Manual Section Applicable ISO/IEC 17025:2005 clause(s) Page Quality Policy 4.2.2 3 Introduction 4
PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN
PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN M. Haseeb College of Public Administration, Huazhong University of Science and Technology, Wuhan, P.R. China, 430074.
Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201
PURCHASE ORDER ATTACHMENT Q-201A Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201 1. A qualified employee shall be selected by the Software Quality Manager
Ashghal (or the Public Works Authority) is the government organisation responsible for providing major infrastructure for the State of Qatar.
Quantity Surveyor Summary of Position To support Commercial & Procurement section of the Expressway Department of Ashghal, in pre-contract and post contract functions required within the team. This includes
The FIDIC Suite of Contracts
Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October
The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, Claims & Counterclaims
The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, 469 (ECCM Workshops 3, 4 & 5) Certified Program التقنيات العملية في إعداد الجدول الزمني والمالي اإلدارة الموقعية
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 6 EVALUATING
Monitoring programmes and resources
Unit 3: P lanning construction work processes and efficient use of resources in construction and the. 34 Monitoring programmes and resources This topic guide explores how to monitor construction project
Risk Management Guide
Risk Management Guide Page(s) Introduction 3 The 5 steps to identifying risk 4 Risk Management Process - Step 1 5 Identify - Step 2 Assess Step 3 5-6 6 Control - Step 4 6 Monitor and Review -Step 5 6 Risk
Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry
CIB World Building Congress 2007 549 CIB2007-370 Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry Dr Tabarak Ballal 1, Dr Taha Elhag 2 and Mr Salim Ambusaidy 3 1
Project and Building Consultancy. Capabilities and track record Enhancing the physical and economic potential of built assets
Project and Building Consultancy Capabilities and track record Enhancing the physical and economic potential of built assets Introduction Cavendish Maxwell 2205 Marina Plaza Dubai Marina P.O. Box 118624
Delay Analysis in Construction Project
Delay Analysis in Construction Project Abstract Delay of a construction project is defined as late completion of the project as compared to the planned schedule. Construction delays are often result of
Quantity Survey - Higher National Diploma (HND)
Quantity Survey - Higher National Diploma (HND) Law and Management Courses Construction Management I... 2 Course: Construction Management II... 4 Contract Law and Arbitration... 6 Conditions of Contract...
Key Words: Flood Reconstruction, Resource Contracts, Coal Seam Gas, Contract Management, Project Management, Relationship Contracting
Rebuilding Flood Damaged Roads in South East Queensland in the middle of the Coal Seam Gas Expansion/Explosion - A Local Governments Experience and Learning's David Pemberton [email protected] Mobile
Engineering Council of South Africa
Government Gazette No. 26180, 2 April 2004 Page 1 of 30 Board Notice 42 of 2004 Engineering Council of South Africa Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the
Environmental Association for Universities and Colleges (EAUC) EAUC Head Office, University of Gloucestershire, The Park Campus, Cheltenham
JOB DESCRIPTION Job Title: EAUC Membership Services Manager Salary Grade: Grade 6 24,273-28,983 Reference Number: School/Department: Base Location: S817 Environmental Association for Universities and Colleges
AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES
AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES This agreement is made and entered into, on day the. of, 1991 by and between: Mr/. of P.O. Box.. hereinafter refereed to as the "Owner" on
ICE Legal Notes Series
ICE Legal Notes Series Legal Notes Reviewing the work of another Engineer and replacing another Engineer Institution of Civil Engineers www.ice.org.uk Published by the Institution of Civil Engineers (ICE).
6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
CONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT Characteristic of Construction Industry One of the biggest sector as * total turnover is more than $3,9 trillion annually * 7 million employee (USA) Affects vast and different industries:
Dr. Simon Chee, Professor Michael Hor, Distinguished Guests, Ladies and. 2. Hong Kong has never been short of infrastructure and construction
Speech by the Hon Rimsky Yuen, SC, JP, Secretary for Justice Hong Kong Construction Arbitration Centre & University of Hong Kong Joint Conference on Construction Dispute Resolution 2015 Resolution of Construction
NCS Contract Director, North East of England
NCS Contract Director, North East of England vinspired and National Youth Agency NCS Partnership NCS Contract Director Candidate Pack March 2015 EXECUTIVE SUMMARY Accountable to: Directors of vinspired
CAPITAL PROJECTS IMPLEMENTATION
CAPITAL PROJECTS IMPLEMENTATION 2.4 Over the years, I have been reporting on the shortcomings encountered during implementation of projects. These include, among others, excessive delays, variation costs,
Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)
Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament
Developing a Project
Developing a Project From Concept to Completion www.ecb.co.uk Sources of Grant Aid and Funding for Cricket Clubs 1 Contents Developing a Project From Concept to Completion Section Page Introduction 1 1
Sales Training Programme. Module 8. Closing the sale workbook
Sales Training Programme. Module 8. Closing the sale workbook Workbook 8. Closing the sale Introduction This workbook is designed to be used along with the podcast on closing the sale. It is a self learning
How To Design A Project
Introduction to Procurement Why is procurement important? Client needs are unique and consequently each project meeting those needs has unique characteristics. This means that achieving the right project
Using Risk Assessment to Improve Highway Construction Project Performance
Using Risk Assessment to Improve Highway Construction Project Performance Mohamed F. Diab, MBA, Ph.D. and Amiy Varma, Ph.D., PE North Dakota State University Fargo, ND Khaled Nassar, Ph.D. American University
Design quality and the private finance initiative
Design quality and the private finance initiative This paper sets out CABE s perspective on the ability of the private finance initiative (PFI) to deliver well-designed public buildings, and considers
Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement
Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement Action Note 14/15 27 August 2015 Issue 1. Raising skills levels within the UK workforce is key to delivering sustainable
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey
Avoiding Claims in Egyptian Construction Projects: A Quantitative Survey Hesham A. Bassioni 1, Mohamed E. Abd El-Razek 2 and Wael A. Abd El-Salam 3 Abstract Construction claims are considered by many project
Multiproject Scheduling in Construction Industry
Multiproject Scheduling in Construction Industry Y. Gholipour Abstract In this paper, supply policy and procurement of shared resources in some kinds of concurrent construction projects are investigated.
Code of Practice for Agents Undertaking Renovation Grants
Code of Practice for Agents Undertaking Renovation Grants July 1998 Contents Introduction Page 1 Approved List of Agents Page 1 Procurement Page 2 Approval Page 5 Works in Progress Page 6 Completion Page
Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals
Journal of Construction in Developing Countries, Vol. 16(1), 41 67, 2011 Attitudes of People in the Thai Construction Industry Sector on Issues Related to Delay in the Approval of Submittals Visuth Chovichien
Project Implementation: Procurement & Contract Management. April 2012
& Contract Management April 2012 & Contract Management We would like to acknowledge the contribution of the Programme Management Department in the preparation of this presentation that will introduce some
MONTE CARLO SIMULATION FOR SCHEDULE RISKS. Brenda McCabe. Department of Civil Engineering University of Toronto Toronto, ON, M5S 1A4, CANADA
Proceedings of the 2003 Winter Simulation Conference S. Chick, P. J. Sánchez, D. Ferrin, and D. J. Morrice, eds. MONTE CARLO SIMULATION FOR SCHEDULE RISKS Brenda McCabe Department of Civil Engineering
Procurement Strategy and Contract Selection
GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works
Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual.
This manual is proprietary and no part thereof shall be copied without written authorisation from the company Ref: Quality Manual.ind Issue: June 2009 INDEX 1 Amendment Status 2 Controlled Distribution
Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study
International Journal of Project Management 21 (2003) 321 326 www.elsevier.com/locate/ijproman Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana
OLB certification process for Forestry Companies GP01
OLB certification process for Forestry Companies GP01 Reference: GP01 OLB FC 1.2 version, 22/03/2013 Bureau Veritas Certification France 60 Général de Gaulle Avenue - 92046 Paris - La Défense Cedex - France
ANTI BRIBERY AND FOREIGN CORRUPT PRACTICES ACT COMPLIANCE POLICY
ANTI BRIBERY AND FOREIGN CORRUPT PRACTICES ACT COMPLIANCE POLICY THIS POLICY DOES NOT CREATE A CONTRACT OF EMPLOYMENT OR ALTER THE AT WILL NATURE OF ANY EMPLOYEE S EMPLOYMENT IN ANY WAY. 1. Statement of
Nominated Subcontractors on International Projects: Approaches to Risk Allocation
Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.
Explaining an architect s services. General information on the usual tasks undertaken by an architect
Explaining an architect s services General information on the usual tasks undertaken by an architect June 2008 What an architect may do for you Introduction The root cause of disputes and complaints against
To be used in conjunction with the Invitation to Tender for Consultancy template.
GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small
Randstad MENA Salary Survey 2016
The Randstad MENA Salary Survey 2016 Based on salaries throughout the Middle East and North Africa With the oil prices at their lowest point since 2009, the Middle East is having to find strategic ways
Competence Criteria for Associate (ACIBSE)
Competence Criteria for Associate (ACIBSE) FACTSHEET A21 The competence criteria for the Associate grade of CIBSE (ACIBSE) is directly aligned to the Competence Statements issued by the Engineering Council,
Contract Management Framework
Contract Management Framework Contents Purpose and Scope... 2 The Contract... 2 The importance of the Contract... 2 Contract Management... 3 The Toolkits... 4 Outline of establishing a Contract Management
THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS $20 1999 EDITION
THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS $20 1999 EDITION Printed by the Printing Department 1594862 50L 11/99 (Printed on paper made
PROJECT MANAGER. Grade: Salary:
PROJECT MANAGER Grade: Salary: Career Grade F/G* *see career grade structure 24,427 to 33,771 per annum Status: 12 months fixed term contract with potential for a further 12 months extension subject to
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT
PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes
North American Development Bank. Prequalification of Contractors
North American Development Bank Prequalification of Contractors PREQUALIFICATION NOTE This note is prepared for the exclusive use of the borrower (the purchaser in this document) and should not be included
JOB DESCRIPTION. 1. JOB TITLE: Assistant Procurement Officer. 4. DEPARTMENT: Chief Financial Officer/Bursar s Office
JOB DESCRIPTION 1. JOB TITLE: Assistant Procurement Officer 2. REFERENCE NUMBER: HR13297a 3. ROLE CODE: APOBO 4. DEPARTMENT: Chief Financial Officer/Bursar s Office 5. ORGANISATION CHART: Chief Financial
Fatemeh Akbari* Master of Industrial Engineering Islamic Azad University, Zahedan Brench, Iran
To Design and to Present a Tool to Prevent Extra Expense Incurring in School Reconstruction Projects (A case study: Reconstruction Department affiliated to School Equipment and Development Unit in Sistan
PROJECT MANAGEMENT BASICS
PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the
INTERNATIONAL EMPLOYMENT GROUP. Employment Services in Oman
INTERNATIONAL EMPLOYMENT GROUP Employment Services in Oman We continue to recommend them to others because of their strength in dealing with detail CHAMBERS GLOBAL 2015 10-5112821-9 0 Addleshaw Goddard's
Construction Delays Causing Risks on Time and Cost - a Critical Review
Construction Delays Causing Risks on Time and Cost - a Critical Review Chidambaram Ramanathan, SP Narayanan and Arazi B Idrus, (Universiti Teknologi Petronas, Malaysia) Abstract There is an increase in
Critical Factors Affecting the Implementation of Total Quality Management in the Construction Industry in U.A.E
Global Journal of HUMANSOCIAL SCIENCE: H Interdisciplinary Volume 15 Issue 5 Version 1. Year 215 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global Journals Inc. (USA) Online
CONTRACTOR DEFAULT & SURETY PERFORMANCE:
CONTRACTOR DEFAULT & SURETY PERFORMANCE: A PRACTICAL GUIDE FOR UNDERSTANDING AND NAVIGATING A BOND DEFAULT SITUATION TEXAS CITY ATTORNEYS ASSOCIATION SUMMER CONFERENCE JUNE 9-11, 2010 SOUTH PADRE ISLAND,
DRAFT. Anti-Bribery and Anti-Corruption Policy. Introduction. Scope. 1. Definitions
DRAFT Change History: Anti-Bribery and Anti-Corruption Policy Control Risks Group Ltd Commercial in confidence Introduction This document defines Control Risks policy on the avoidance of bribery and corruption.
Investors in People First Assessment Report
Investors in People First Assessment Report K.H.Construction Cambridge Assessor: Lesley E Ling On-site Date/s: 3 rd September 2008. Recognition Date: Contents 1. Introduction Page 2 2. Assessment and Client
Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO
Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr
Newsletter No. 194 (EN) Directors and Officers (D&O) Liability Insurance in Hong Kong
Newsletter No. 194 (EN) Directors and Officers (D&O) Liability Insurance in Hong Kong December 2015 All r ig ht s r e ser ved Lo r e nz & P art ner s 2015 Although Lorenz & Partners always pays great attention
Further information can be obtained by calling Glenn Shaw, Acting Manager Infrastructure and Waste Services on 9400 4353.
The City of Joondalup takes pride in being a Local Government that has been internationally recognised for providing outstanding services to the local community. To continue to set the standard in WA Local
Terms of Reference for consulting services financed under a World Bank executed Trust Fund
Terms of Reference for consulting services financed under a World Bank executed Trust Fund Design and Procurement of long-term pilot contracts for the Performance-based Management and Maintenance of Roads
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK
A REVIEW ON FACTORS AFFECTING CONTRACTOR PERFORMANCE IN CONSTRUCTION WORK Mihirkumar B. Naik 1, Dr. Neerajkumar D. Sharma 2, Prof. Bhavin K. Kashiyani 3 PG. Student, S.N. Patel Institute of Technology
Planning, Organisation and Control of Resources in Construction and the Built Environment
Unit 7: Planning, Organisation and Control of Resources in Construction and the Built Environment NQF Level 3: Guided learning hours: 60 BTEC National Unit abstract A successful project requires careful
NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard
New Zealand Standard Conditions of contract for building and civil engineering construction Superseding (in part) NZS 3910:2003 NZS 3910:2013 COMMITTEE REPRESENTATION This Standard was prepared under the
Business Continuity Policy & Plans
Agenda Item 8.3a SNCCG Governing Body 11.03.2014 Business Continuity Policy & Plans Ref Number: Version: 1 Status: Pending Approval Author: A Brown Approval body Governing Body Date Approved Date Issued
Audit Quality Thematic Review
Thematic Review Professional discipline Financial Reporting Council January 2014 Audit Quality Thematic Review Fraud risks and laws and regulations The FRC is responsible for promoting high quality corporate
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
Comparative Study on Quality Assurance of Construction Project in Taiwan and Japan
Comparative Study on Quality Assurance of Project in Taiwan and Japan Tsung Chieh, T. National Yunlin University of Science & Technology, Taiwan (email: [email protected]) Furusaka, S. Kyoto University,