O LUPA Page 1. Olmsted County Planning Advisory Commission February 6, Kristi Gross, AICP, CFM Senior Planner-Floodplain Administrator

Size: px
Start display at page:

Download "O LUPA Page 1. Olmsted County Planning Advisory Commission February 6, Kristi Gross, AICP, CFM Senior Planner-Floodplain Administrator"

Transcription

1 O LUPA Page 1 Olmsted County Planning Department Olmsted County Planning Advisory Commission February 6, 2020 Prepared by: Request: Kristi Gross, AICP, CFM Senior Planner-Floodplain Administrator Olmsted County Land Use Plan Amendment #O LUPA by Rochester Township to redesignate approximately 30 acres from "Urban Service Area" to Resource Protection/Potential Suburban on the Olmsted County Future Land Use Map. Location: The property is located in the East 1/2 of the Southwest 1/4 of Section 6, Rochester Township, west of Lilly Farm Subdivision and north of Boulder Creek Subdivision. Zoning: A-3 Agricultural District ACTION ITEMS Board Action Summary: The request is a land use plan amendment from Urban Service Area to Resource Protection/Potential Suburban. Planning Staff Recommendations: Deny the land use map amendment based on the findings of fact in the staff report. BACKGROUND INFORMATION Background The property in question is zoned A-3 Agricultural District. It is located in the Southwestern quarter of Section 6 of Rochester Township. North and west of the property is identified as Urban Service Area in the Olmsted County Land Use Plan. This is the Urban Service Area for the city of Rochester. The area east and south of the property is identified as Suburban Development. The property to the east was removed from the Urban Service Area in At that time, the City of Rochester stated that the elevations made the property to the East unable to physically serve with city services and did not object to it being removed from the Urban Service Area. The City of Rochester has submitted a referral comment to this request. The property is shown as the Urban Reserve Area Beyond 2050 on the City of Rochester s Growth Management map

2 O LUPA Page 2 adopted in They state that the property can be served by municipal services in the future. Therefore, they believe this property should remain in the Urban Service Area. The city is recommending denial of the land use plan amendment at this time. Soils and Topography The soils on the property have mostly a prime crop equivalency rating of over 55. Approximately 7 acres of the 30-acre parcel consist of soils with a CER of 55 or less. See attached soils map. Cascade Creek crosses the north side of the property. Cascade Creek is a protected water and shoreland standards apply. There is a mapped floodway that extends southernly from the creek, see attached floodplain map. See the attached floodplain map. Based on the topography of the property there is a bluff on the property. There is a 30 foot setback from the top of the bluff. This could limit the buildable area of lots 9 and 10 on the concept plan. This does not impact the land use plan designation, but the applicant should be aware of this and adjust the lots prior to future development. See the Bluff Impact Zone Exhibit attached to this report. The property falls within the Decorah Edge Support Area, including soil 477B. A Decorah Edge study will need to be completed prior to development to ensure that no Decorah Edge features are disturbed by the development. Transportation The property has access along Boulder Creek Ln SW, a township road. Boulder Creek Ln SW connects to Boulder Creek Dr SW and Weatherhill Rd SW. These roads both access 60 Ave SW, (County Rd 104). 60 Ave SE is identified in the Rochester-Olmsted Council of Governments (ROCOG) 2040 plan as Secondary Urban Arterial Corridor Upgrade. Weatherhill Rd SW also connects to Salem Rd SW (County Rd 25) which is identified in the ROCOG 2040 plan as a Major Regional Arterial Corridor Upgrade. Environmental Analysis Staff has reviewed the environmental factors surrounding the property and have found no significant issues that would result from the land use plan amendment. The property contains a small area of Decorah Edge; a drainageway with Floodplain and a bluff. These factors can be taken into account with proper site design of future development. Referral Comments As stated earlier, the City of Rochester has submitted a comment that does not support the change of land use designation. Planning staff has received a referral from Don Vankeulen commenting on behalf of the Local Government Unit for wetlands that the property contains Decorah Edge and Hydric soils. The

3 O LUPA Page 3 property owner is responsible for identifying wetlands and Decorah Edge conditions on the property and submitting a wetland delineation prior to a preliminary plat. ANALYSIS AND FINDINGS Analysis The request is for a land use plan amendment to amend the land use plan map from Urban Service Area to Resource Protection-Potential Suburban. The City of Rochester is recommending denial of the land use plan amendment. The Olmsted County General Land Use Plan (GLUP) states that proposed map amendments must be compared to the land use policies and locational criteria for the requested land use category. The policies for the Urban Service Area can be found in Chapter Four of the Land Use Plan which has been included in this staff report. In addition, the analysis of proposed map amendments must address the following policy questions, as evaluated below by Staff. 1. Was a mistake made in the data used or in the application of the data at the time the Plan was adopted? No mistake was made in the data used or in the application of the data at the time the Plan was adopted. Staff had met with and received municipal land use data for the City of Rochester when the 2011 Plan was drafted and adopted. City and township representatives were involved in shaping the boundaries of the Urban Service Areas. The intent of this designation is to (1) delineate the best areas for urban growth until the year 2040, (2) accommodate uses and development patterns compatible with future urban growth, and (3) allow for the continuation of agricultural and other resource uses. 2. Have conditions of land use, land subdivision, ownership, or growth in the community changed the character of the site and surrounding area? The property to the east of the site has developed. A land use plan amendment was approved in 2014 to remove the 180-acre property from Urban Service Area to Resource Protection-Potential Suburban and has continued to develop. The third phase of Lilly Farm was approved in July 2019 by Rochester Township. The City of Rochester conducted a more detailed sewer feasibility study this year for the area that included this property. The study has not fully concluded. It is unclear at this time if the City of Rochester will amend their urban service areas based on results of that study. 3. Have policies related to the proposal changed since the Plan was adopted?

4 O LUPA Page 4 Policies regarding the Urban Service Area and Resource Protection-Potential Suburban Development lands have not changed since the 2011 Plan update. State Statutes do not require that Urban Service Areas delineated on the County plan map be consistent with those adopted by municipalities, however consistency among them optimizes cooperation and efficiency in their implementation. 4. Is there an unanticipated shortage of land available for the proposed use? There is not an unanticipated shortage of Urban Service Area land. There is also not an unanticipated shortage of Suburban Development land. When the 2011 Olmsted County Future Land Use Map was adopted, 8500 acres were designated for Potential Suburban use. The GLUP is projected to be updated this year and this data will be reanalyzed. 5. Is the land under consideration as suited or better suited for the proposed use than other lands now designated for the proposed use, and are those lands now properly designated according to the land use policies? (This analysis will be based in part on the Comprehensive Land Use Evaluation System Model.) Urban Service Area boundaries are delineated without respect to their underlying CLUES scores; they are based on meetings and information provided by each municipality regarding their planned municipal service extensions, projected employment, and population growth. The CLUES model treats the Urban Service Area like a mask or overlay. With respect to Suburban Development, there are 8500 acres of land designated for potential suburban development that have not been developed. The CLUES scores in those areas range from The underlying CLUES scores on this site fall within these limits. It is likely that had this land not been included in Rochester s Urban Service Area, it would have been recommended for designation for suburban uses. 6. Is the proposed amendment consistent with the policies of the Plan? As described above, inclusion in the Urban Service Area is typically determined by the municipality intending to eventually provide services to the area. If this property can be served by municipal services, as stated by the City of Rochester, it should remain within the Urban Service Area. There are other ways to develop the property without creating a barrier to future growth of the city. 7. Is there an alternative to the proposed change that better meets the intent of the Plan (a different use designation or a smaller land area, for example)?

5 O LUPA Page 5 If the land use plan is not amended the landowner has the following options for the property: 1. Build non-farm dwellings under A-3 zoning restrictions. This requirement is under the jurisdiction of Rochester Township. Reviewing the site to Olmsted County A-3 standards, as long as there is a 33-foot easement to each building site, it appears there could be 3 non-farm parcels built under the current zoning designation. 2. Request an Interim Development. If city services will not serve the property for 10 years it may be appropriate to enter into an interim development with the City of Rochester and develop the property under the current land use designation. This would require a special zoning district and platting. 3. Wait to see if and the City of Rochester amends their urban service area boundaries and growth management map based on the results of the sewer study. Staff Recommendation Based on the above stated findings of fact planning staff recommend denial of the land use plan amendment from Urban Service Area to Resource Protection-Potential Suburban. ATTACHMENTS 1. Staff Report 2. Notification Map 3. Site Location Map 4. Application and Attachments 5. Concept Map with Aerial 6. Aerial with Floodplain 7. Decorah Edge Map 8. Bluff Impact Zone Exhibit 9. Referral Report and Comments 10. Chapter Four GLUP

WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24

WESTFIELD-WASHINGTON ADVISORY PLAN COMMISSION December 7, 2015 1512-SPP-24 & 1512-ODP-24 Petition Number: Subject Site Address: Petitioner: Request: East side of Oak Road, north of 151 st Street Langston Development Co. Primary Plat and Overall Development Plan amendment review for Mapleridge

More information

ADMINISTRATIVE LAND SPLIT APPLICATION

ADMINISTRATIVE LAND SPLIT APPLICATION ADMINISTRATIVE LAND SPLIT APPLICATION File # Date Filed: PID: Landowner Name: Address: Description of Request: Phone: Administrative Land Splits 10.6.A Mortgages Subdivision for the purpose of securing

More information

Information Packet SOLAR ENERGY SYSTEM (SES) WHEN IS A SOLAR ENERGY SYSTEM ZONEING PERMIT NECESSARY? Application for Solar Energy System

Information Packet SOLAR ENERGY SYSTEM (SES) WHEN IS A SOLAR ENERGY SYSTEM ZONEING PERMIT NECESSARY? Application for Solar Energy System 1 Information Packet Land Use Management 509 W 5th Street Suite 103 Red Wing, MN 55066 s could require more than one application approval: Residential-Building Permit Commercial-SES Zoning Permit and Building

More information

REZONING 16-000009 & PRELIMINARY PLAT 16-000005

REZONING 16-000009 & PRELIMINARY PLAT 16-000005 REZONING 16-000009 & PRELIMINARY PLAT 16-000005 REZONING REQUEST AND REVISED PRELIMINARY PLAT FOR THE BLUFFS AT WINDCASTLE - 4165 FAREDALE LANE Application: Engineer: Developer: Property Owner: Current

More information

COMMONWEALTH OF PENNSYLVANIA AGRICULTURAL SECURITY AREA HANDBOOK

COMMONWEALTH OF PENNSYLVANIA AGRICULTURAL SECURITY AREA HANDBOOK COMMONWEALTH OF PENNSYLVANIA AGRICULTURAL SECURITY AREA HANDBOOK Bureau of Farmland Preservation 2301 North Cameron Street Harrisburg, PA 17110 Phone: 717-783-3167 Fax: 717-772-8798 www.agriculture.state.pa.us

More information

Wildlife Habitat Conservation and Management Program

Wildlife Habitat Conservation and Management Program Wildlife Habitat Conservation and Management Program Manual for Counties and Cities Oregon Department of Fish and Wildlife 2015 Table of Contents 1. Introduction Purpose of the habitat program Objective

More information

THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330

THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330 THE APPRAISAL OF REAL ESTATE 3 RD CANADIAN EDITION BUSI 330 REVIEW NOTES by CHUCK DUNN CHAPTER 10 Copyright 2010 by the Real Estate Division and Chuck Dunn. All rights reserved ARE 3 rd EDITION REVIEW

More information

PROPERTY LINE ADJUSTMENT APPLICATION

PROPERTY LINE ADJUSTMENT APPLICATION PROPERTY LINE ADJUSTMENT APPLICATION City of Klamath Falls Planning Division 226 S. 5 th St. / P.O. Box 237, Klamath Falls, OR 97601 File No. A property line adjustment is required any time an adjustment

More information

A REQUEST FOR A CONDITIONAL USE PERMIT BY:

A REQUEST FOR A CONDITIONAL USE PERMIT BY: A REQUEST FOR A CONDITIONAL USE PERMIT BY: National Outdoor Leadership School (NOLS), FOR: The expansion of their existing education facility, WHERE: Darby Townsite (1830 S 1750 E) Prepared for the Public

More information

INTRODUCTION TO ZONING DISTRICT REGULATIONS

INTRODUCTION TO ZONING DISTRICT REGULATIONS INTRODUCTION TO ZONING DISTRICT REGULATIONS Classification of Zoning Districts Zoning districts in Dorchester County are categorized as Suburban Urban, Suburban Transition, or Rural. These districts are

More information

Application No.: 14.074 Steve Rush, representing Rocky Mountain Power Rocky Mountain Power Project Location: approximately 1600 N. 6800 E.

Application No.: 14.074 Steve Rush, representing Rocky Mountain Power Rocky Mountain Power Project Location: approximately 1600 N. 6800 E. Planning Commission Staff Report Planning and Development Services Croydon Substation Conditional Use Permit Public Meeting August 28, 2014 Application No.: 14.074 Applicant: Steve Rush, representing Rocky

More information

V. EVASION CRITERIA. 1. Any person seeking exemption from the requirements of the MSPA (76-3- 101, MCA) shall submit to the County:

V. EVASION CRITERIA. 1. Any person seeking exemption from the requirements of the MSPA (76-3- 101, MCA) shall submit to the County: V. EVASION CRITERIA A. PROCEDURES AND GENERAL REQUIREMENTS 1. Any person seeking exemption from the requirements of the MSPA (76-3- 101, MCA) shall submit to the County: a. A certificate of survey, exempt

More information

3. The submittal shall include a proposed scope of work to confirm the provided project description;

3. The submittal shall include a proposed scope of work to confirm the provided project description; QIN Shoreline Master Program Project Summary The Shoreline Master Program (SMP) development process for the Quinault Indian Nation (QIN) includes the completion of inventory and analysis report with corresponding

More information

Conservation Tax Credit Regulations Chapter 391-1-6 A-1 RULES OF GEORGIA DEPARTMENT OF NATURAL RESOURCES CHAPTER 391-1-6

Conservation Tax Credit Regulations Chapter 391-1-6 A-1 RULES OF GEORGIA DEPARTMENT OF NATURAL RESOURCES CHAPTER 391-1-6 Conservation Tax Credit Regulations Chapter 391-1-6 A-1 RULES OF GEORGIA DEPARTMENT OF NATURAL RESOURCES CHAPTER 391-1-6 GEORGIA CONSERVATION TAX CREDIT PROGRAM TABLE OF CONTENTS 391-1-6-.01 Purpose and

More information

THREE MILE PLAN/URBAN GROWTH BOUNDARY INTERGOVERNMENTAL AGREEMENT

THREE MILE PLAN/URBAN GROWTH BOUNDARY INTERGOVERNMENTAL AGREEMENT THREE MILE PLAN/URBAN GROWTH BOUNDARY INTERGOVERNMENTAL AGREEMENT THIS INTERGOVERNMENTAL AGREEMENT, entered into by and between the BOARD OF COUNTY COMMISSIONERS OF THE COUNTY OF GUNNISON, COLORADO, a

More information

Conducting a Land Use Inventory

Conducting a Land Use Inventory Chapter 3 Conducting a Land Use Inventory Included in this chapter: Determining Current Land Use Conditions Preparing a Base Map Deciding on Land Use Categories Collecting Current Land Use Data Preparing

More information

CPED STAFF REPORT Prepared for the City Planning Commission

CPED STAFF REPORT Prepared for the City Planning Commission CPED STAFF REPORT Prepared for the City Planning Commission CPC Agenda Item #1 June 23, 2014 RLS-72 LAND USE APPLICATION SUMMARY Property Location: 222 Hennepin Avenue Project Name: 222 Prepared By: Becca

More information

Urban Planning and Land Use

Urban Planning and Land Use Urban Planning and Land Use 701 North 7 th Street, Room 423 Phone: (913) 573-5750 Kansas City, Kansas 66101 Fax: (913) 573-5796 Email: planninginfo@wycokck.org www.wycokck.org/planning To: From: Unified

More information

SITE DEVELOPMENT PLAN CHECKLIST. Project Name: Site Plan No.:

SITE DEVELOPMENT PLAN CHECKLIST. Project Name: Site Plan No.: SITE DEVELOPMENT PLAN CHECKLIST 5/12/05 Rev.3/14/06 Project Name: Site Plan No.: REVIEW CRITERIA Plans: A site development plan (signed and sealed) shall be on a 24 x 36 sheet at a scale that is no smaller

More information

PLANNING COMMISSION REPORT Regular Agenda - Public Hearing Item

PLANNING COMMISSION REPORT Regular Agenda - Public Hearing Item Z-15-00063 Item No. 1-1 PLANNING COMMISSION REPORT Regular Agenda - Public Hearing Item PC Staff Report 04/20/2015 ITEM NO. 1 Z-15-00063 CS TO RS5; 832 Ohio Street (BJP) Z-15-00063: Consider a request

More information

Presentation to Knox County Commission Monday, February 23, 2015

Presentation to Knox County Commission Monday, February 23, 2015 The Northwest County Sector Plan Update Presentation to Knox County Commission Monday, February 23, 2015 COMMUNITIES OF THE NORTHWEST COUNTY SECTOR Ball Camp Cedar Bluff Last NW Sector Update: 2003 Land

More information

1.7.0 Floodplain Modification Criteria

1.7.0 Floodplain Modification Criteria 1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:

More information

D3 April 8, 2015 Public Hearing

D3 April 8, 2015 Public Hearing D3 April 8, 2015 Public Hearing APPLICANT AND PROPERTY OWNER: ASSEMBLY OF YAH, INC. STAFF PLANNER: Kevin Kemp REQUEST: Conditional Use Permit (Religious Facility - church) ADDRESS / DESCRIPTION: 5151 Locke

More information

SPECIAL USE PERMIT 22-01. JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing

SPECIAL USE PERMIT 22-01. JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing SPECIAL USE PERMIT 22-01. JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing This report is prepared by the James City County Planning Division

More information

Environment Virginia Conference April 6, 2011. Integrating Stormwater, Urban Design, and Growth Policies

Environment Virginia Conference April 6, 2011. Integrating Stormwater, Urban Design, and Growth Policies Environment Virginia Conference April 6, 2011 Integrating Stormwater, Urban Design, and Growth Policies Integrating Stormwater, Urban Design, and Growth Policies Sara Hollberg, AICP, Valley Conservation

More information

A-2, RURAL ESTATE-AGRICULTURE DISTRICT

A-2, RURAL ESTATE-AGRICULTURE DISTRICT CHAPTER 52 A-2, RURAL ESTATE-AGRICULTURE DISTRICT SECTION: 10-52-1: Purpose 10-52-2: Permitted Uses 10-52-3: Accessory Uses 10-52-4: Conditional Uses 10-52-5: Interim Uses 10-52-6: Lot Area, Density, and

More information

Kirkland Zoning Code 113.25

Kirkland Zoning Code 113.25 Kirkland Zoning Code 113.25 Chapter 113 COTTAGE, CARRIAGE AND TWO/THREE-UNIT HOMES Sections: 113.05 User Guide 113.10 Voluntary Provisions and Intent 113.15 Housing Types Defined 113.20 Applicable Use

More information

2229-2245 Kingston Rd Removal of a Holding Provision (H) Application Final Report

2229-2245 Kingston Rd Removal of a Holding Provision (H) Application Final Report STAFF REPORT ACTION REQUIRED 2229-2245 Kingston Rd Removal of a Holding Provision (H) Application Final Report Date: May 29, 2015 To: From: Wards: Reference Number: Scarborough Community Council Director,

More information

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013

PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580

More information

PC 23-11 Nate Lundgren-Auto Repair Business Conditional Use Permit 9/7/11 Applicants

PC 23-11 Nate Lundgren-Auto Repair Business Conditional Use Permit 9/7/11 Applicants PC 23-11 Nate Lundgren-Auto Repair Business Conditional Use Permit 9/7/11 Applicants Nate Lundgren Triple K Partnership Mankato 105 LeSueur Ave 320 Mallard Lane Eagle Lake, MN 56024 Mankato MN 560001 Request

More information

Land Use Series. Check List # 1I For Adoption of an Amendment to a Plan. December 22, 2010. Bringing Knowledge to Life!

Land Use Series. Check List # 1I For Adoption of an Amendment to a Plan. December 22, 2010. Bringing Knowledge to Life! Land Use Series Bringing Knowledge to Life! Thirty seven million acres is all the Michigan we will ever have. Former Governor William G. Milliken Michigan State University Extension Land Use Team http://ntweb11a.ais.msu.

More information

DEVLOPMENT APPLICATION PROCEDURES

DEVLOPMENT APPLICATION PROCEDURES DEVLOPMENT APPLICATION PROCEDURES Bylaw No. 2444 and amendments thereto CONSOLIDATED FOR CONVENIENCE ONLY This is a consolidation of the bylaws listed below. The amending bylaws have been consolidated

More information

22.01 SETTLEMENT 24/04/2014 C73

22.01 SETTLEMENT 24/04/2014 C73 22.01 SETTLEMENT 24/04/2014 C73 22.01-1 Urban Growth and Development 24/04/2014 C73 This policy applies to the urban areas and fringes of Portland, Heywood, Casterton, Dartmoor, Nelson, Cape Bridgewater,

More information

Yuma County Land Use Code

Yuma County Land Use Code Yuma County Land Use Code THE BOARD OF COUNTY COMMISSIONERS OF YUMA COUNTY ADOPTED REVISED EFFECTIVE JANUARY 15, 2015 REVISED EFFECTIVE DECEMBER 1, 2011 REVISED EFFECTIVE FEBRUARY 1, 2010 EFFECTIVE JULY

More information

MACOMB TOWNSHIP PLANNING COMMISSION MEETING MINUTES AND PUBLIC HEARING TUESDAY, May 5, 2009 PAGE 1 OF 8

MACOMB TOWNSHIP PLANNING COMMISSION MEETING MINUTES AND PUBLIC HEARING TUESDAY, May 5, 2009 PAGE 1 OF 8 PAGE 1 OF 8 LOCATION: PRESENT: ABSENT: ALSO PRESENT: MACOMB TOWNSHIP MEETING CHAMBERS 54111 BROUGHTON ROAD MACOMB, MI 48042 EDWARD GALLAGHER, CHAIRMAN DEAN AUSILIO, VICE CHAIRMAN MICHAEL D. KOEHS, SECRETARY

More information

CITY OF WEST PALM BEACH PLANNING BOARD Meeting Date: August 20, 2013 Planning Board Case No. 1564C

CITY OF WEST PALM BEACH PLANNING BOARD Meeting Date: August 20, 2013 Planning Board Case No. 1564C CITY OF WEST PALM BEACH PLANNING BOARD Meeting Date: August 20, 2013 Planning Board Case No. 1564C Rezoning from Community Service (CS) to Community Service Planned Development (CSPD) Hanley Center 5200

More information

The Metropolitan Planning Commission. DATE: May 19, 2015

The Metropolitan Planning Commission. DATE: May 19, 2015 TO: FROM: The Metropolitan Planning Commission MPC Staff DATE: May 19, 2015 SUBJECT: Petition of LLC, Owner Harold Yellin, Agent PIN: 2-0015-01-002 & 003 Lot Size:.85 Acres (approximately) Aldermanic District:

More information

CHAPTER 23 Wireless Communication Facilities

CHAPTER 23 Wireless Communication Facilities CHAPTER 23 Wireless Communication Facilities Section 23.1 Purpose It is the general purpose and intent of this Section to comply with the requirements of the Federal Telecommunications Act of 1996, as

More information

TOWN OF DAVIE TOWN COUNCIL AGENDA REPORT

TOWN OF DAVIE TOWN COUNCIL AGENDA REPORT TOWN OF DAVIE TOWN COUNCIL AGENDA REPORT TO: Mayor and Councilmembers FROM/PHONE: Mark Kutney, AICP, Development Services Director/(954) 797-1101 Prepared by Annie Feng, Planner II SUBJECT: Resolution

More information

Rural Residential Buildable Lands Inventory

Rural Residential Buildable Lands Inventory The Dalles Periodic Review, May 2013 Rural Residential Lands Inventory Contents Introduction and Summary... 1 Concerns related to the 2007 Analysis... 2 Rural Residential Capacity Summary... 2 Methodology...

More information

5.14 Floodplains and Drainage/Hydrology

5.14 Floodplains and Drainage/Hydrology I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important

More information

FACTORS INFLUENCING GROWTH

FACTORS INFLUENCING GROWTH FACTORS INFLUENCING GROWTH Many factors influence the future utilization of land and the intensity and nature of development within Henderson County. Physiographic and infrastructural factors are linked

More information

TOWN BOARD OF THE TOWN OF NORTH SALEM WESTCHESTER COUNTY, NEW YORK LOCAL LAW # OF THE YEAR 2012

TOWN BOARD OF THE TOWN OF NORTH SALEM WESTCHESTER COUNTY, NEW YORK LOCAL LAW # OF THE YEAR 2012 TOWN BOARD OF THE TOWN OF NORTH SALEM WESTCHESTER COUNTY, NEW YORK LOCAL LAW # OF THE YEAR 2012 CHAPTER 250, ZONING ORDINANCE AMENDMENTS - PD-CCRC DISTRICT Section 1. Purpose: The purpose of this Local

More information

Much Ado About Kelo: Eminent Domain and Farmland Protection

Much Ado About Kelo: Eminent Domain and Farmland Protection Much Ado About Kelo: Eminent Domain and Farmland Protection December 2005 In the case of Kelo v. the City of New London, the Supreme Court ruled that the Connecticut city could acquire land by eminent

More information

Eureka Township Strategic Vision

Eureka Township Strategic Vision Working Draft Eureka Township Strategic Vision This is a working draft of a land use plan for Eureka Township. It is being presented to the public by the Citizens Advisory Committee to promote discussion

More information

REPORTS SUSTAINABILITY AND ENVIRONMENT 11 MAY 2015 ORDINARY COUNCIL MEETING OF COUNCIL

REPORTS SUSTAINABILITY AND ENVIRONMENT 11 MAY 2015 ORDINARY COUNCIL MEETING OF COUNCIL REPORT NO: 0.0 REPORT TITLE: SOURCE: DIVISION: FILE NO: POLICY: - STRATEGIC OBJECTIVE: Planning Scheme Amendment C202: 140-204 Western Avenue, Westmeadows Gareth Edgley, Senior Strategic Planner City Sustainability

More information

ELEMENT 4 - FUTURE LAND USE ELEMENT

ELEMENT 4 - FUTURE LAND USE ELEMENT ELEMENT 4 - FUTURE LAND USE ELEMENT Goal 1 To create a long-range development pattern which directs growth into developable areas and away from environmentally sensitive areas, in a manner that is compatible

More information

1161.01 CONFORMITY WITH PLANS; DRAINAGE.

1161.01 CONFORMITY WITH PLANS; DRAINAGE. CHAPTER 1161 Subdivision Requirements 1161.01 Conformity with plans; drainage 1161.07 Easements 1161.02 Trees 1161.08 Streets 1161.03 Subdivision name 1161.09 Blocks 1161.04 Street names 1161.10 Lots 1161.05

More information

A Break Even Analysis and Potential Profitability of a Proposed Residential Development within the City of La Crosse, Wisconsin USA

A Break Even Analysis and Potential Profitability of a Proposed Residential Development within the City of La Crosse, Wisconsin USA A Break Even Analysis and Potential Profitability of a Proposed Residential Development within the City of La Crosse, Wisconsin USA Chad M. Clower Department of Resource Analysis, Saint Mary s University

More information

HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES

HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES Approved 6/26/01 HIGHWAY DEPARTMENT ACCESS AND RIGHT OF WAY WIDTH GUIDELINES All new, modified and/or changed use access(es) onto county roads shall be subject to the access and corridor protection guidelines

More information

Draft ARTICLE 20A "AO" ANTIETAM OVERLAY DISTRICT

Draft ARTICLE 20A AO ANTIETAM OVERLAY DISTRICT Draft ARTICLE 20A "AO" ANTIETAM OVERLAY DISTRICT Section 20A.0 Purpose The purpose of the Antietam Overlay District is to provide mechanisms for the protection of significant historic structures and land

More information

Village of Spring Valley Comprehensive Plan 2009-2029

Village of Spring Valley Comprehensive Plan 2009-2029 Chapter 8: Intergovernmental Cooperation Introduction Intergovernmental communication, coordination, and cooperation can make a significant difference in the implementation and administration of a comprehensive

More information

IMPLEMENTATION STRATEGIES The following sections list the implementation strategies for following chapters.

IMPLEMENTATION STRATEGIES The following sections list the implementation strategies for following chapters. CHAPTER 13: IMPLEMENTATION INTRODUCTION The purpose of the Implementation Chapter is to set forth the actions that the City will take to ensure that the plans, programs, and policies set forth in the plan

More information

Buffer and Soil Loss Legislation

Buffer and Soil Loss Legislation Buffer and Soil Loss Legislation Laws of Minnesota 2015, 1 st Special Session, Chapter 4, Article 4 Sec. 72. Minnesota Statutes 2014, section 103B.101, is amended by adding a subdivision to read: Subd.

More information

SECTION ELEVEN: ACTIVITIES REQUIRING A CERTIFIED EROSION AND SEDIMENT CONTROL PLAN 1

SECTION ELEVEN: ACTIVITIES REQUIRING A CERTIFIED EROSION AND SEDIMENT CONTROL PLAN 1 SECTION ELEVEN: ACTIVITIES REQUIRING A CERTIFIED EROSION AND SEDIMENT CONTROL PLAN 1 An application for approval of a soil erosion and sediment control plan in accordance with these regulations shall be

More information

9.0 Alta Vista/Faircrest Heights/Riverview Park (Key Principles)

9.0 Alta Vista/Faircrest Heights/Riverview Park (Key Principles) 9.0 Alta Vista/Faircrest Heights/Riverview Park (Key Principles) Official Plan Consolidation for the City of Ottawa 1 9.1 Location This Chapter applies to Alta Vista/Faircrest/Riverview Park, which corresponds

More information

Planning Commission Staff Report

Planning Commission Staff Report 10 Planning Commission Staff Report TO: FROM: THROUGH: PLANNING COMMISSION AMY TEMES, SENIOR PLANNER (480) 503-6729, AMY.TEMES@GILBERTAZ.GOV CATHERINE LORBEER, AICP, PRINCIPAL PLANNER (480) 503-6016 CATHERINE.LORBEER@GILBERTAZ.GOV

More information

Corridor Goals and Objectives

Corridor Goals and Objectives Corridor Goals and Objectives This chapter presents the goals and objectives, developed by the Corridor Study Committee, that serve as the purpose and intent of the Corridor Plan. This plan covers a twenty

More information

MAP TYPES FLOOD HAZARD BOUNDARY MAP MAP READING & FLOOD INSURANCE STUDIES. FHBM Flood Hazard Boundary Map. FIRM Flood Insurance Rate Map

MAP TYPES FLOOD HAZARD BOUNDARY MAP MAP READING & FLOOD INSURANCE STUDIES. FHBM Flood Hazard Boundary Map. FIRM Flood Insurance Rate Map FLOODPLAIN MANAGEMENT 101 MAP READING & FLOOD INSURANCE STUDIES MAP TYPES FHBM Flood Hazard Boundary Map FIRM Flood Insurance Rate Map FBFM Flood Boundary and Floodway Map DFIRM Digital Flood Insurance

More information

12 February 8, 2012 Public Hearing APPLICANT:

12 February 8, 2012 Public Hearing APPLICANT: 12 February 8, 2012 Public Hearing APPLICANT: PROPERTY OWNER: VIRGINIA BEACH ASSOCIATES, LC REQUEST: Conditional Change of Zoning (I-1 to Conditional A-36) STAFF PLANNER: Faith Christie ADDRESS / DESCRIPTION:

More information

City of El Paso City Plan Commission Staff Report

City of El Paso City Plan Commission Staff Report City of El Paso City Plan Commission Staff Report Revised Case No: SUSU14-00124 Fresno Place Replat A Application Type: Resubdivision Combination CPC Hearing Date: February 12, 2015 Staff Planner: Joaquin

More information

COUNTY OF ELBERT. 18 September, 2014 For the Planning Commission meeting of 25 September, 2014 ELBERT COUNTY PLANNING COMMISSION

COUNTY OF ELBERT. 18 September, 2014 For the Planning Commission meeting of 25 September, 2014 ELBERT COUNTY PLANNING COMMISSION COMMUNITY & DEVELOPMENT SERVICES OFFICE P.O. BOX 7 215 COMANCHE STREET KIOWA, COLORADO 80117 303-621-3136 FAX: 303-621-3165 COUNTY OF ELBERT 18 September, 2014 For the Planning Commission meeting of 25

More information

4. Priority Areas of Conservation

4. Priority Areas of Conservation 4. Priority Areas of Conservation A. SIGNIFICANT RESOURCE AREAS This Open Space and Farmland Plan identifies the key issues facing open space and agricultural resources in the Town, highlights the location

More information

21.03 SETTLEMENT AND HOUSING

21.03 SETTLEMENT AND HOUSING 21.03 SETTLEMENT AND HOUSING 09/10/2014 C187Prop osed C189 21.03-1 Housing 09/10/2014 C187 This clause provides local content to support Clause 11 (Settlement) and 15 (Built Environment and Heritage) and

More information

Polk Commerce Centre CRA Spine Road Alignment Study

Polk Commerce Centre CRA Spine Road Alignment Study Polk Commerce Centre CRA Spine Road Alignment Study Florida Polytech Pace Road (LIMIT) Berkley Road Williams DRI Proposed Alignment Polk Commerce Centre CRA Boundary Braddock Road (LIMIT) Lake Myrtle Sports

More information

WASHINGTON COUNTY PLANNING COMMISSION MINUTES

WASHINGTON COUNTY PLANNING COMMISSION MINUTES WASHINGTON COUNTY PLANNING COMMISSION MINUTES April 2, 2015 7:00 p.m. Supervisors Room, County Courthouse, 1555 Colfax Street, Blair, Nebraska * * * * * * * * * * * * * * * * * * * * * * * * * * * * *

More information

Maine Forest Service Interpretations of the Maine Forest Practices Act Statute and Rules (12 MRSA 8867-A to 8888 & MFS Rules Chapter 20)

Maine Forest Service Interpretations of the Maine Forest Practices Act Statute and Rules (12 MRSA 8867-A to 8888 & MFS Rules Chapter 20) Maine Forest Service Interpretations of the Maine Forest Practices Act Statute and Rules (12 MRSA 8867-A to 8888 & MFS Rules Chapter 20) These interpretations take into account the full context, meaning,

More information

Zoning Most Frequently Asked Questions

Zoning Most Frequently Asked Questions Zoning Most Frequently Asked Questions Zoning is needed to achieve the following: Orderly development consistent with utility location/capacity, street network, public services; Compatible land uses in

More information

KEYPORT COMMUNITY PLAN

KEYPORT COMMUNITY PLAN PLANNING COMMISSION TASKS Collect Public Comments on Draft Plan. Provide Clear Direction for: Preferred LAMIRD Boundary Lot Clustering Provision View Protection Recommendation to Board of County Commissioners.

More information

3 September 9, 2015 Public Hearing

3 September 9, 2015 Public Hearing 3 September 9, 2015 Public Hearing APPLICANT: PI TELECOM INFRASTRUCTURE T, LLC PROPERTY OWNER: JSW HOLDINGS, LLC STAFF PLANNER: Carolyn A.K. Smith REQUEST: Conditional Use Permit (communications tower-monopole)

More information

DOUGLAS COUNTY RESOLUTION NO. 87-38 CITY OF LAWRENCE RESOLUTION NO. 5094

DOUGLAS COUNTY RESOLUTION NO. 87-38 CITY OF LAWRENCE RESOLUTION NO. 5094 DOUGLAS COUNTY RESOLUTION NO. 87-38 CITY OF LAWRENCE RESOLUTION NO. 5094 A JOINT RESOLUTION OF THE GOVERNING BODIES OF DOUGLAS COUNTY AND THE CITY OF LAWRENCE CONCERNING THE SOUTH LAWRENCE TRAFFICWAY;

More information

MINUTES HUGO PLANNING COMMISSION December 19, 2013

MINUTES HUGO PLANNING COMMISSION December 19, 2013 MINUTES HUGO PLANNING COMMISSION December 19, 2013 Call to Order Chairman Gwynn called the meeting to order at 7:00 pm. PRESENT: ABSENT: ALSO PRESENT: Arcand, Gwynn, Lessard, Kleissler, Knauss, McRoberts,

More information

Welcome to the Inland Wetlands Commission Town of Barkhamsted, CT

Welcome to the Inland Wetlands Commission Town of Barkhamsted, CT Welcome to the Inland Wetlands Commission Town of Barkhamsted, CT Introduction Purpose Barkhamsted is a residential community located in Litchfield County, 15 miles northwest of Hartford. Our population

More information

Chapter 13: Implementation Plan

Chapter 13: Implementation Plan Chapter 13: 13.1. INTRODUCTION The purpose of the implementation chapter of the Comprehensive Plan is to set forth the actions that the City will take to ensure that the plans, programs and policies set

More information

On-Farm Solar Energy Generation. Susan E. Craft, Executive Director State Agriculture Development Committee

On-Farm Solar Energy Generation. Susan E. Craft, Executive Director State Agriculture Development Committee On-Farm Solar Energy Generation Susan E. Craft, Executive Director State Agriculture Development Committee P.L. 2009, c. 213 Defines the extent of solar, wind and biomass energy generation that is considered

More information

Step Two: Conduct the Economic Opportunities Analysis Basic Approach

Step Two: Conduct the Economic Opportunities Analysis Basic Approach 2 Step Two: Conduct the Economic Opportunities Analysis Basic Approach The Economic Opportunities Analysis (EOA) is defined in Oregon Administrative Rule (OAR) 660-009-0015. The Advanced approach follows

More information

North Carolina Department of Commerce

North Carolina Department of Commerce rth Carolina Department of Commerce Version 5.5 (May 2014) TABLE OF CONTENTS Program Overview... 2 Program History and Success... 2 Program Structure and Organization... 3 Steering Committee... 3 Technical

More information

Using Land Use Planning Tools to Support Strategic Conservation

Using Land Use Planning Tools to Support Strategic Conservation Using Land Use Planning Tools to Support Strategic Conservation Resources A Citizen s Guide to Planning & Zoning in Virginia (2003) Provides background information on how basic land use planning tools

More information

Texas Motor Speedway Area Master Plan January 2009 WATER INFRASTRUCTURE

Texas Motor Speedway Area Master Plan January 2009 WATER INFRASTRUCTURE WATER AND SEWER INFRASTRUCTURE Water and Sewer Infrastructure in the TMS Study Area Streets and other transportation infrastructure are addressed in Chapter 6 of this plan. Non-transportation infrastructure

More information

Chair Jim Wideman and Members of the Planning and Works Committee. Mid-Year 2013 Region of Waterloo Industrial and Business Park Vacant Land Inventory

Chair Jim Wideman and Members of the Planning and Works Committee. Mid-Year 2013 Region of Waterloo Industrial and Business Park Vacant Land Inventory Report: P-14-010 Region of Waterloo Planning Housing and Community Services Community Planning To: Chair Jim Wideman and Members of the Planning and Works Committee Date: January 28, 2014 File Code: D13-40

More information

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY 1. Applicant's Name Address (Street or Rural Route) (City & State) (Zip) Person to contact Title Phone Fax

More information

Major General Plan Amendment. Project Narrative

Major General Plan Amendment. Project Narrative Major General Plan Amendment BARNEY FARMS Project Narrative NEC of Signal Butte and Queen Creek Roads Prepared: Submitted to: TOWN OF QUEEN CREEK PLANNING DEPARTMENT 22350 South Ellsworth Road Queen Creek,

More information

D4 - D12 May 8, 2013 Public Hearing

D4 - D12 May 8, 2013 Public Hearing D4 - D12 May 8, 2013 Public Hearing CITY OF VIRGINIA BEACH AMENDMENTS PERTAINING TO APPLICATION FEES REQUESTS: D4. An Ordinance to Amend Section 110 of the Chesapeake Bay Preservation Area Ordinance Pertaining

More information

Site Analysis. Floyd Zimmerman, FASLA. Summary CLIENT NEEDS. Supplemental Architectural Services 2000 AIA 1 SITE ANALYSIS SERVICES

Site Analysis. Floyd Zimmerman, FASLA. Summary CLIENT NEEDS. Supplemental Architectural Services 2000 AIA 1 SITE ANALYSIS SERVICES Site Analysis Floyd Zimmerman, FASLA Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 Sensitive owners and designers understand that from the facility user s perspective,

More information

Planning for Casey s Community

Planning for Casey s Community 2 July 2013 ITEM 2 ATTACHMENT 1 Council Report from Meeting This information is circulated separately. Council Meeting Page 9 Amendment C143 to the Casey Planning Scheme Revisions to various areas within

More information

STAFF REPORT. December 20, 2004. North District Community Council. Director of Community Planning - North

STAFF REPORT. December 20, 2004. North District Community Council. Director of Community Planning - North STAFF REPORT December 20, 2004 To: From: Subject: North District Community Council Director of Community Planning - North Preliminary Report Respecting Revised Application OPA & Rezoning Application 01

More information

5 March 12, 2014 Public Hearing

5 March 12, 2014 Public Hearing 5 March 12, 2014 Public Hearing APPLICANT: MOORE FARM, L.L.L.P. PROPERTY OWNER: MOORE FARM L.L.L.P. STAFF PLANNER: Kevin Kemp REQUEST: Change of Zoning (B-1A Limited Community Business to Conditional B-2

More information

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PIPELINE ROUTING PERMIT For A NATURAL GAS PIPELINE IN DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PUC DOCKET No. G002/GP-05-1706 In accordance with the requirements

More information

# U N I V E R S I T Y A V E N U E S P E C I F I C P L A N Page 1-1 # 1.0 INTRODUCTION. 1.1 University Avenue, Historical Context

# U N I V E R S I T Y A V E N U E S P E C I F I C P L A N Page 1-1 # 1.0 INTRODUCTION. 1.1 University Avenue, Historical Context 1.0 INTRODUCTION 1.1 University Avenue, Historical Context By the late 1880s, the role of University Avenue, then known as Eighth Street, was already well established as a link between the original Riverside

More information

FILE NO.: Z-6915-C. Gamble Road Short-form PCD and Land Alteration Variance Request

FILE NO.: Z-6915-C. Gamble Road Short-form PCD and Land Alteration Variance Request FILE NO.: Z-6915-C NAME: Gamble Road Short-form PCD and Land Alteration Variance Request LOCATION: Located on the Northwest corner of Chenal Parkway and Gamble Road DEVELOPER: Davis Properties P.O. Box

More information

SUBDIVISION APPLICATION GUIDE

SUBDIVISION APPLICATION GUIDE SUBDIVISION APPLICATION GUIDE August 2013 This brochure provides an overview of the steps involved in the Subdivision Application process. This is a general guide only. It is not meant to replace bylaws

More information

Revised General Plan Amendment Report (GPAR) PAA 05-017 GPA 06-003 BC 05-0104 R06-006 ER06-08-024 APN # 268-130-43 APN # 268-130-42

Revised General Plan Amendment Report (GPAR) PAA 05-017 GPA 06-003 BC 05-0104 R06-006 ER06-08-024 APN # 268-130-43 APN # 268-130-42 LAW OFFICES OF VATCHE CHORBAJIAN ATTORNEYS AT LAW 655 North Central Avenue 17 th Floor Glendale, CA 91203 phone 818.409.6700 fax 858.923.2124 12707 High Bluff Dr, Ste 100 San Diego, CA 92130 phone 858.259.5577

More information

TEXT AMENDMENT SUMMARY INFORMATION

TEXT AMENDMENT SUMMARY INFORMATION Comprehensive Plan Update Public School Facilities Section Planning Commission Workshop: January 12, 2015 PEOPLE, PLACES AND NATURAL SPACES TEXT AMENDMENT SUMMARY INFORMATION Application type Agency Review

More information

DOUGLAS COUNTY ZONING RESOLUTION Section 5 RR - Rural Residential District 3/10/99. -Section Contents-

DOUGLAS COUNTY ZONING RESOLUTION Section 5 RR - Rural Residential District 3/10/99. -Section Contents- SECTION 5 RR - RURAL RESIDENTIAL DISTRICT -Section Contents- 501 Intent...5-2 502 Principal Uses...5-2 503 Accessory Uses...5-3 504 Uses Permitted by Special Review...5-4 505 Land Dedication...5-4 506

More information

Adopted 9/23/98 CHATTAHOOCHEE CORRIDOR PLAN. The goals of the Chattahoochee Corridor Plan (hereinafter also referred to as the Plan ) are:

Adopted 9/23/98 CHATTAHOOCHEE CORRIDOR PLAN. The goals of the Chattahoochee Corridor Plan (hereinafter also referred to as the Plan ) are: CHATTAHOOCHEE CORRIDOR PLAN Adopted 9/23/98 PART 1: GOALS. POLICY. COVERAGE. A. Goals The goals of the Chattahoochee Corridor Plan (hereinafter also referred to as the Plan ) are: 1. Preservation and protection

More information

PLANNED UNIT DEVELOPMENT (P.U.D.), REZONING, and COMPREHENSIVE PLAN AMENDMENT APPLICATION PACKET VILLAGE OF HANOVER PARK DEVELOPMENT COMMISSION

PLANNED UNIT DEVELOPMENT (P.U.D.), REZONING, and COMPREHENSIVE PLAN AMENDMENT APPLICATION PACKET VILLAGE OF HANOVER PARK DEVELOPMENT COMMISSION PLANNED UNIT DEVELOPMENT (P.U.D.), REZONING, and COMPREHENSIVE PLAN AMENDMENT APPLICATION PACKET VILLAGE OF HANOVER PARK DEVELOPMENT COMMISSION Village of Hanover Park Department of Community Development

More information

Chapter 22A Forest Conservation Law

Chapter 22A Forest Conservation Law Chapter 22A Forest Conservation Law 2014 1 Table of Contents Table of Contents Article I - General... 4 Sec. 22A-1. Short title... 4 Sec. 22A-2. Findings and purpose... 4 Sec. 22A-3. Definitions... 4 Sec.

More information

Electronic Signature and Fee Payment Confirmation

Electronic Signature and Fee Payment Confirmation Jeff Levine, AICP, Director Planning & Urban Development Department Electronic Signature and Fee Payment Confirmation Notice: Your electronic signature is considered a legal signature per state law. By

More information

The Board of Zoning Appeals shall have the duty and power to:

The Board of Zoning Appeals shall have the duty and power to: Section 21-09.03. (a) Establishment and Jurisdiction. The for the City of South Bend, Indiana, is hereby re-established in accordance with Indiana Code 36-7-4-900 et seq. The for the City of South Bend,

More information

PINELLAS COUNTY COMPREHENSIVE PLAN

PINELLAS COUNTY COMPREHENSIVE PLAN PINELLAS COUNTY COMPREHENSIVE PLAN Future Land Use Map (FLUM) Category Descriptions and Rules Amended March 17, 2009 (Ordinance 09-17) Amended March 16, 2010 (Ordinance 10-18) Amended October 26, 2010