BIM-M Benchmark Projects: Lessons for Masonry Design and Construction in the Digital Age
|
|
|
- Kerrie Lambert
- 9 years ago
- Views:
Transcription
1 BIM-M Benchmark Projects: Lessons for Masonry Design and Construction in the Digital Age Russell Gentry, PhD, PE Georgia Institute of Technology Digital Building Laboratory Franca Trubiano, PhD, AIA Architecture, Penn Design University of Pennsylvania
2 Presentation Outline Background Approach BIM as Process Workflows and Systems Modeling Case Study Review (Gentry) Engineered Biosystems Building Drew Charter Fleming Hall Detailed Case-Study Discussion (Trubiano) Huntsman Hall New College House A View from the Profession Wrapup
3 Masonry Project Types CMU and Brick Structural Masonry Complex Masonry
4 Project Phases Schematic Design Design Development Construction Documents Contractor Coordination Subcontractor Installation
5 Project BIM States Current No-BIM Project documentation and communication are primarily Current No-BIM through 2-D drawings, by fax, PDF, sketches, Current BIM Project team is using BIM software, model exchanges and Current BIM integration to the degree possible Future BIM A collective vision of what BIM-enabled processes for masonry Future BIM design and construction might look like in the future (BIM-M)
6 BIM-M Benchmark Study Criteria
7 BIM as Process The Importance of Workflows BPMN Flow Chart Process Model Activity Diagram Value Chain Map
8 Material Supply: Cast Stone Workflow Flow of information and material in a custom cast stone masonry process (image courtesy Midwest Cast Stone, Kansas City, Kansas)
9 Design and Construction Processes
10 Case Study Projects Project GT Engineered Biosystems Building Drew Charter School, Senior Academy Emory/Oxford Fleming Hall Woodward Academy Humanities Building Breckinridge Place GCSU Ennis Hall + GT Hinman Hall Young Harris, Enotah Hall UPenn, Huntsman Hall UPenn, New College House Architect Cooper Carry Perkins + Will Cooper Carry Perkins + Will Holt Architects Lord Aeck Sargent Lord Aeck Sargent KPF Bohlin Cywinski Jackson Mason Contractor Jollay Masonry Cornerstone Masonry Pyramid Masonry Cornerstone Masonry Dave Trayer Masonry Southeastern Restorations Zebra Construction Dan Lepore and Sons Dan Lepore and Sons Building Type Concrete Frame - Brick Veneer on Steel Studs - Interior CMU Concrete Frame - Field Stone and Cast Stone over CMU Load Bearing Block - Precast Plank, Brick/Stone Exterior Steel Frame - Brick and Cast Stone on Steel Stud Backup Load Bearing Block - Precast Plank, Brick/Cast Stone Exterior Load Bearing Brick and Stone - Restoration Load Bearing Block - Precast Plank, Brick Exterior Complex Masonry, Custom Clay Units, Concrete Frame Complex Masonry, Custom Clay Units
11 11
12 Georgia Tech Engineered Biosystems Building
13 Schematic Design Phase: Masonry Unit Selection
14 Façade Mockup Is this a BIM opportunity? Virtual mockup
15 Subcontractor Installation Phase: Brick Façade
16 Current BIM Representation
17 Brick Façade Installation: Coordination Issues 1. Re-align construction joint with center of windows southeast façade. 2. Remove relief angles between three windows metal panel here not brick. 3. Relief angle drops 0.8 in. (200mm) caulk joint will increase to 1.25 in. (31mm) thick. Resolve? Stretch brick coursing or increase caulk joint width. 4. Trim projecting leg of relief angle 0.25 in. (6mm) 5. Steel stud window framing out brick will not wrap opening. 6. Steel outriggers for shade not aligned with curtain wall or brick coursing per A1102 D7. 7. Improper waterproofing for below-grade application.
18 Is this an opportunity for a future BIM state automatic geometry update in BIM before masonry installation?
19 Brick Installation: Overview Swing Stage Pump Jack Fraco Lift 2 masons 0 laborers 3 masons 2 laborers Total 9 masons 5 laborers 4 masons 3 laborers Daily Usage ~max 10 cubes ~4500 bricks ~31.5 bags of mortar Total on Wall ~80 cubes ~42,500 bricks 283 courses 18 loose lintels Daily Schedule 7 AM: 2 laborers start mortar 10 hours of work with a 15 min breaks 30 min lunch end at 5.30 p.m.
20 Façade Construction Process
21 Time-lapse of Façade Installation
22 Subcontractor Installation Phase: CMU in Vivarium
23 CMU Construction: Vivarium Level LOD 300 EBB Revit Model
24 Construction Joint Placement for Vivarium Level Is this an opportunity for BIM? Jollay Masonry
25 CMU Construction: Vivarium Level LOD CADBLOX Tom Cuneio
26 Contractor Coordination Phase: Cast Stone
27 Cast Stone Construction: Window Sills The BIM model is not quite right. The brick still exists inside the placed cast stone, creating an internal masonry clash. EBB Revit Model
28 Opportunities for BIM Future State: Design Phases Mockup budget was $80,000 and multiple mockups were created. Virtual mock ups? Need better tools for inserting cast stone accents into wall system family. Masonry patterning not properly aligned to building surface. Unable to encode glazed masonry pattern onto BIM model. BIM execution plan explicitly called for no modeling of relief angles so design BIM model was not useful for façade construction planning. No automation of construction joint placement in CMU walls. Need rule-based CJ propagation.
29 Opportunities for BIM Future State: Construction Phases One person-month of mason contractor time spent on re-measuring concrete frame and relief angles. Steel stud backup required adjusting in many locations. Need to promote BIM-M design model to BIM-M construction model. Increase LOD selectively and carefully. Break wall into parts based on project schedule. Need simple interface model for mason contractors showing masonry plus its touch points. Nominal geometry and as built. BIM model not useful for cast stone detailing due to use of wall sweeps. Need wall sweep propagation tool. Cutting units in vivarium level was messy and it would have been great to cut outside unable to pull cuts from BIM model Plumbing and wiring inside of CMU were difficult to coordinate due to use of different control lines by plumbing and masonry crews need BIM-hosted control lines
30 Drew Charter Senior Academy
31 Field- and Cast Stone Locations Cast Stone Field Stone
32 Fieldstone: East Wall A-417: 8 Exterior Details (bottom, between level 1 and 2) Field Stone CMU 2 Foam-Plastic Board Insulation Cavity Drainage Material Fluid-Applied Air Barrier Grout Fill (Cavity) 4 CMU Compressive Filler Self-Adhering Sheet Waterproofing Through Wall Flashing
33 West Wall of Academic Building (Fieldstone) Sophisticated detailing required for fieldstone relief angles Architect provided very strict rules on fieldstone installation (mockup)
34 Activity Diagram: Installation Of Fieldstone 34
35 Cast Stone
36 Cast Stone
37 Opportunities for BIM Future State: Design Phases Need library of standard cast stone shapes. Need tools for maximizing use of fieldstone given a distribution map of field stone sizes in supply. Need fieldstone wall generator given a rule-set supplied by the architect.
38 Opportunities for BIM Future State: Construction Phases Need to manage production and shipment of custom masonry material. Need to manage quantity estimates for cut stone. Potential for scanning of fieldstone supply and matching to architects wall model and to mock-up.
39 Oxford College - Emory University Fleming Hall
40 Background Information Owner Architect General Contractor Subcontractors Supplier Structural Engineer Civil MEP Emory University Cooper Carry, Inc. Brasfield & Gorrie Pyramid Masonry Block USA Uzun+Case Southern Civil Engineers Nottingham, Brook, & Pennington Size 52,000 ft 2
41 Project Masonry Scope
42 CMU Block Wall Locations precast plank on block
43 Granite Rigid Insulation 4 CMU Backup Drainage Mat CMU
44 Brick Veneer Rigid Insulation CMU Damp proofing Concrete Plank Complex masonry details shown only in 2D details not in 3D BIM 44
45 One Phase Construction Two Phase Construction 45
46 Construction/Planning Phase: Procurement Process
47 Opportunities for BIM Future State: Design Phases Revit does not provide a clear path for federation of models in masonry. Architect and structural engineer duplicate modeling effort. No one source of truth. Structural engineering of this simple load-bearing building is expensive compared to structural steel buildings poor interoperability
48 Opportunities for BIM Future State: Construction Phases Need process planning tools for load-bearing masonry, tied to resource planning. Need high-fidelity BIM models for off-site cutting of masonry (and perhaps a shop drawing process).
2008-2009 Cost Comparisons for Common Commercial Wall Systems
An Independent Study LA MS KY TN AL GA SC NC FL 2008-2009 Cost Comparisons for Common Commercial Systems CAPITAL BUILDING CONSULTANTS PROFESSIONAL CONSTRUCTION ESTIMATORS 2008 2009 INDEPENDENT COST COMPARISONS
Mortenson Construction Virtual Mockups A Collaborative Solution
San Diego, CA February 10, 2011 Mortenson Construction Virtual Mockups A Collaborative Solution Rick Khan, LEED AP Senior Integrated Construction Manager Building what s next. Mortenson Construction Family
Building Information Modeling for Masonry (BIM-M)
Building Information Modeling for Masonry (BIM-M) Charles Clark, AIA, PE, LEED AP BD+C Vice President Engineering Services Acknowledgements Much of the information and images in this presentation are from
Window Installation Instructions
Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for
The Difference Between Cast Stone and Adhered Manufactured Stone Masonry Veneer
Submitted 9/16/08 For publication - Feb 2009 Masonry Construction Magazine by Bill Russell Chairman, Cast Stone Institute Committee on Educational Standards On many construction documents today, there
LAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
Built to Last. Built for Beauty. Good. Solid. Logix. TM
Built to Last. Built for Beauty. Good. Solid. Logix. TM Quality, Value and Service Introducing LOGIX Insulated Concrete Forms. Based on the simple concept of interlocking blocks, LOGIX ICF gives you a
RESIDENTIAL MASONRY A BEST PRACTICES GUIDE
RESIDENTIAL MASONRY A BEST PRACTICES GUIDE Build With Brick Build With Boral CONTENTS BRICK :01 MASONRY CEMENT :03 MASONRY SAND :04 WALL TIES :05 STEEL LINTELS :07 DRAINAGE WALL SYSTEM :09 FLASHING :11
We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden window unit.
Important Information for New Construction Installations Attention Installer! We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden
The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs
The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................
EAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
Natural Thin Stone Veneer
Natural Thin Stone Veneer Until recently, if a project called for the natural look of stone but could not support its weight or thickness, the options were limited to manufactured imitation stone. More
Olilo's AEC Design Services. SrinSoft Inc, Partners of
Olilo's AEC Design Services SrinSoft Inc, Partners of Olilo provides design services that include design and analysis, cost estimation, 3D modeling, 2D drafting, conversion from 2D to 2D, quantity take-off,
Ver. 2. Guide to. Inspecting Residential Brick Veneer
Ver. 2 Guide to Inspecting Residential Brick Veneer 1. A guide created by industry professionals. The knowledgeable staff at MASONPRO together with technical support from the Masonry Institute of Michigan
Masonry Blueprint. * Considered essential competencies ** Should be mastered at the journeyman level All other items are considered supplemental
Masonry Blueprint This Blueprint contains the subject matter content of this Skill Connect Assessment. This Blueprint does NOT contain the information one would need to fully prepare for a SkillsUSA Championships
Exhibit C: Scope of Work and Schedule of Deliverables
Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza
Packaged Terminal Air Conditioner Wall Sleeve Installation
Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation
Williamson and Associates, Inc. Report of Building Exterior Condition Evaluation, dated January 2 nd, 2013. (68 pages)
INNOVATIVE BUILDING AND ARCHITECTURE CONSULTANTS Mr. Bud Hall Senior Vice President of construction Turnberry Associates 19501 Biscayne Boulevard, Suite 400 Aventura, FL 33180 Subject: The Nashville Hilton
Architectural Concrete Masonry
1. Adams Profile Split Face Units (PSF). 2. Adams Profile Split Face Single Score Units (PSF-1). 3. Adams Profile Split Face Double Score Units (PSF-2) 4. Adams Profile Wide Split Rib Four Units (PWSR-4).
BIM: FOR PROJECT MANAGERS. 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am
BIM: FOR PROJECT MANAGERS ANA BAKER BRANDON GARRETT 2011 CSI Southwest Region Conference Program 1B 8:45am 11:00am 1 2 3 4 BIM Overview BIM Level of Development Evolution of the Drawing Process BIM Workflow
INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS
2009 Pella Corporation INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS Part Number: 80WH0100 Installation Instructions for Typical Wood Frame Construction.
BIM and Lean Construction Can BIM remove waste from construction processes?
Tekla European BIM Forum 2014 BIM and Lean Construction Can BIM remove waste from construction processes? Assoc. Professor Rafael Sacks What is Lean Construction? Waste in construction? Lean and BIM Synergies
WINDOW INSTALLATION GUIDE
WINDOW INSTALLATION GUIDE is not responsible for or liable for any use or misuse of the information contained in this window installation guide. Window Installation Guide This guide provides basic information
Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing
1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize
ST. MONICA FOOD PANTRY HOUSTON, TEXAS
PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,
Design Development Quality Management Phase Checklist Project Phase Checklist Series
Best Practices Design Checklist Project Phase Checklist Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA
IMPORTANT INSTALLATION GUIDE VALENCIA SQUARE CORNER SHOWER READ ALL INSTRUCTIONS CAREFULLY BEFORE STARTING THE INSTALLATION
INSTALLATION GUIDE VALENCIA SQUARE CORNER SHOWER SEALANT REQUIRED TO COMPLETE THIS INSTALLATION: (Not supplied) Sika Sikasil NG (Arctic White) To seal the WHITE shower door and returns to the shower tray.
Sun Windows General Information Sun New Construction Window Installation Instructions
Sun Windows General Information Section 1 G F H H H A. Apply Weather Resistive Barrier B. Apply Sill Flashing Tape C. Place Waterproof Sill Shims D. Caulk Back of Nail Fin Sides & Top, Set Window, Fasten
Think Of Us First! When It s Time to Distribute Your Plans
Think Of Us First! When It s Time to Distribute Your Plans CONSTRUCTION NOTEBOOK WILL LIST YOUR PLANS AND SPECS FREE CALL TODAY FOR DETAILS 702-876-8660 Why use Experience We have over 60 years of experience
SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT
SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows americancraftsmanwindows.com Project Requirements: Read
K2 STONE NATURAL VENEER
INTRODUCTION WHAT IS K2 NATURAL THINSTONE VENEER? Natural K2 Stone veneer is real stone, cut 1 inch thick, making it light enough to be installed as a veneer. Sometimes referred to as thin veneer, thin
STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM
Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally
Summit Anchor Company, Inc.
Summit Anchor Company, Inc. Safety From The Top Down Roof and Wall Safety/Tie-Back Anchors Suspended Access Systems and Fall Protection Overview National Safety Standards OSHA regulations specifically
Brick Veneer Construction
Brick Veneer Construction Check list of suggested tools & support items Claw hammer Tape measure 3/4" [19 or 20] Wood chisel Wood or plastic shims Pry bar Utility knife Caulking and caulking gun Power
IFMA Building Tour THE MAIN LIBRARY AT GOODWOOD. a library in the park ~ a park in the library 07.15.2014
IFMA Building Tour THE MAIN LIBRARY AT GOODWOOD a library in the park ~ a park in the library 07.15.2014 COLLABORATIVE PROJECT TEAM The location of the library and its development within Independence Park
201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE
STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,
Superform Products Ltd.
TYPICAL CORNER REINFORCING NOTE : SEE ENGINEERED REBAR SCHEDULES SUPPLIED BY THE MANUFACTURER STEEL REINFORCEMENT WALL CORNER 90 Copyright 2012 Sept. 2012 5.1.1 Rebar Spacing 6" 12" Max. Load LB./FT. 2000
Photo courtesy of Delta Stone, Heber City, UT. Installation Solutions for: Manufactured Stone, Natural Thin Veneer, and Thin Brick
Photo courtesy of Delta Stone, Heber City, UT Installation Solutions for: Manufactured Stone, Natural Thin Veneer, and Thin Brick THIN VENEER INSTALLATION SYSTEMS PREMIUM BONDING MORTARS Premium PCL Stone
NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
Installation Solutions for: Manufactured Stone, Natural Thin Veneer, and Thin Brick ARCHITECTURAL SPECIFICATIONS / CAD MODELS TVISTM WARRANTIES
ARCHITECTURAL SPECIFICATIONS / CAD MODELS With more than 40 years of manufacturing high quality, innovative building products in the commercial and residential markets, Custom Building Products TVISTM
cement Masonry Cement Engineered for quality and reliability, Lafarge cements for masonry deliver consistent performance. page 2 Lafarge Cement
cement Masonry Cement Engineered for quality and reliability, Lafarge cements for masonry deliver consistent performance. page 2 Lafarge Cement Lafarge in North America The Lafarge Group is the world leader
Installation Instructions
Installation Instructions One-Piece Deep Wall Sleeve For Use with Packaged Terminal Units Please read these instructions completely before attempting installation. NOTE: Ensure that the unit is only installed
GUIDELINES FOR REHABILITATION OF TRADITIONAL COMMERCIAL BUILDINGS DESIGN GUIDELINES
GUIDELINES FOR REHABILITATION OF TRADITIONAL COMMERCIAL BUILDINGS DESIGN GUIDELINES PAGE 13 DESIGN GUIDELINES The following design guidelines have been developed to guide appropriate design in the Downtown
CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
Clad Direct Glaze Window Installation Instructions
Clad Direct Glaze Window Installation Instructions Sill flashing and sealing: 2. An overview of the proper flashing sequence is shown in figure 1. Please read entire installation instructions carefully
PART 1 GENERAL 1.1 SECTION INCLUDES
J-1 Section 09110 Long Form Specification INTERIOR METAL STUD FRAMING This section includes lightweight, usually 0.036 inch (0.9 mm) thick or lighter, non-axial load bearing metal stud framing including
ASTM E 1886 and ASTM E 1996 TEST REPORT. Rendered to: NORSE, INC.
Architectural Testing ASTM E 1886 and ASTM E 1996 TEST REPORT Rendered to: NORSE, INC. SERIES/MODEL: Flush Mount/Surface Mount PRODUCT TYPE: Hurricane Shutter Fastening System This report contains in its
CHAPTER 2 QUANTITY TAKE-OFF
CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate
Civil Engineering and Architecture (CEA) Detailed Outline
Civil Engineering and Architecture (CEA) Detailed Outline Unit 1: Overview of Civil Engineering and Architecture (23 days) Lesson 1.1: History of Civil Engineering and Architecture 1. Many features of
INSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
Building Construction. Structural Systems 1. Load-bearing wall construction 2. Skeleton framing 3. Combination of the two
Structural Systems 1. Load-bearing wall construction 2. Skeleton framing 3. Combination of the two Factors governing type selection Economics not necessarily the one that requires the least structural
Avoiding Air Barrier Pitfalls
Avoiding Air Barrier Pitfalls Design & Durability November 2013 Air barriers, when correctly installed, help buildings achieve high levels of energy efficiency by decreasing heat loss. For example, great
Scottsdale, Arizona. Presentation by: Hermes Norero, P.E. President and CEO
Scottsdale, Arizona Presentation by: Hermes Norero, P.E. President and CEO Mr. Hermes F. Norero, P.E. is the founder and President of Building Drops. The concept of Building Drops first arose after realizing,
SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM
Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and
Technical Notes 3B - Brick Masonry Section Properties May 1993
Technical Notes 3B - Brick Masonry Section Properties May 1993 Abstract: This Technical Notes is a design aid for the Building Code Requirements for Masonry Structures (ACI 530/ASCE 5/TMS 402-92) and Specifications
Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit
R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed
BIM Extension into Later Stages of Project Life Cycle
BIM Extension into Later Stages of Project Life Cycle Pavan Meadati, Ph.D. Southern Polytechnic State University Marietta, Georgia This paper discusses the process for extending the implementation of the
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10
VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1
March 14, 2007. Installation of Bay, Bow and Garden Windows
March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed
WELCOME. Recommended Window Installation. 1.5 credits Minnesota Department of Labor and Industry
WELCOME Recommended Window 1.5 credits Minnesota Department of Labor and Industry In accordance with the Department of Labor and Industry s statute 326.0981, Subd. 11, This educational offering is recognized
We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden window unit.
Important Information for New Construction Installations Attention Installer! We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden
Dimensioning and Estimating Brick Masonry
TECHNICAL NOTES on Brick Construction 1850 Centennial Park Drive, Reston, Virginia 20191 www.gobrick.com 703-620-0010 10 February 2009 Dimensioning and Estimating Brick Masonry Abstract: This Technical
Thin Veneer Stone Installation Guide
Thin Veneer Stone Installation Guide Complete step by step How-to guide for installing Thin Veneer Stone. Important: From pallet to pallet of natural thin veneer stone, as with any natural stone product,
2012 BIM Guidelines and Standards (Rev. 00) University at Albany
A. Building Information Modeling (BIM) Guidelines: The Office of AECM will require the submission of BIM modeling files as part of an electronic file submission to the AECM project manager as requested
The Prefab Package. Modular EIFS construction offers benefits to today s busy jobsites. Building Envelope. Roland Serino, P.E., of Dryvit Systems Inc.
26 D+D MARCH 2015 Building Envelope Roland Serino, P.E., Dryvit Systems Inc. here has always been a need for a more efficient way to build in large cities like Chicago, New York, Los Angeles or other central
Columbia Theological Seminary to Celebrate Ground-blessing for New, Green Residence Hall
FOR IMMEDIATE RELEASE News Release Contact: Anne Taylor Lord, Aeck & Sargent 404-253-6710 [email protected] or Ann Kohut Kohut Communications Consulting 770-913-9747 [email protected] Columbia
SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS
SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier by using Tools / Options / View / Hidden Text. On newer versions of Microsoft Word
GYPSUM AREA SEPARATION FIREWALLS GA-620-2011
GYPSUM AREA SEPARATION FIREWALLS GA-620-2011 GA-620-2011 Copyright 2011 Gypsum Association All rights reserved. Printed in U.S.A. Characteristics, properties, or performance of materials or systems herein
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
Building Information Modeling Management To Facility Management
To Building Information Modeling Management To Facility Management I: INTRODUCTION - aaecs Team Thomas J. Jeff Prine, CCM, LEED AP COO Program / Facility Management Specialist Bonnie K. Gorman, Assoc.
The Harold J. Becker Company, Inc.
The Harold J. Becker Company, Inc. It is the mission of The Harold J. Becker Company, Inc. to deliver the absolute best possible quality product at the most efficient cost to our clients, while providing
4 5/16 Subframe Installation
4 5/16 Subframe Installation The subframe system is a great installation tool for installing windows in masonry conditions. Typically subframes are used in masonry openings so that windows can be anchored
EXISTING MASONRY WALL TO REMAIN (TYP.). EXISTING PARTITION TO REMAIN PROVIDE 3'-3" W. X 8'-0"H. NEW PELLA WINDOWS AS INDICATED ON PLANS. (TYP.
EXISTING MASONRY WALL TO REMAIN N EXISTING MASONRY WALL TO REMAIN (TYP.). PROVIDE COPPER THROUGH-WALL FLASHING DN EXISTING MASONRY PARTY CHIMNEY AND WALL TO REMAIN (TYP.). EXISTING MASONRY PARTY WALL TO
TEST REPORT. Report No.: A9814.01 109 44. Rendered to: BAMCO INC. Middlesex, New Jersey. PRODUCT TYPE: Wall Cladding System SERIES/MODEL: Dry Concept
Architectural Testing TEST REPORT Report No.: A9814.01 109 44 Rendered to: BAMCO INC. Middlesex, New Jersey PRODUCT TYPE: Wall Cladding System SERIES/MODEL: Dry Concept AAMA 508 07, Voluntary Test Method
City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures
City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures SECTION 7201 - PURPOSE The purpose of this appendix chapter is to establish minimum prescriptive standards
Is Your Envelope Effective? Mark Lawton P.Eng Morrison Hershfield Limited Vancouver
Is Your Envelope Effective? Mark Lawton P.Eng Morrison Hershfield Limited Vancouver Designing an Effective Envelope Roofs Below Grade Walls and slabs Glazing & Windows Opaque portions of walls 2 3 Energy
K. D. FRAME ASSEMBLY FOR CLOSED STEEL STUD WALLS...Ins 10. FRAME INSTALLATION DETAILS FOR CLOSED STEEL STUD WALLS...Ins 11
K. D. FRAME ASSEMBLY FOR MASONRY WALLS...........................Ins 2 FRAME INSTALLATION DETAILS FOR MASONRY WALLS......................Ins 3 INSTALLING EXISTING MASONRY WALL ANCHORS IN FRAME..................Ins
R-Value and Densities Chart
R-Value and Densities Chart Material R-Value Per Inch R-Value Per Unit Inside Air Film 0.68 Air Space between Studs 0.95 Building Pa 0.06 ½ in. Fiberboard Sheathing 1.52 Gypsum Wallboard or Drywall 0.90
City of San Diego, CWP Guidelines
PART 1 -- GENERAL SECTION 08520-1.1 WORK OF THIS SECTION City of San Diego, CWP Guidelines A. The WORK of this Section includes providing aluminum windows with frames, bracing, glazing attachments, screens,
Replacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin
Replacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin americancraftsmanwindows.com Project Requirements: Failure to follow these instructions may void product
Turner Innovation Series BIM Conference Istanbul May 2012. Brian Krause, Dan Gramer, Turner Construction Company
1 Why BIM? Excessive Re-Work and Waste TURNER INNOVATION SERIES May 2012 BIM for Design, Preconstruction, & Construction Brian Krause Manager, Integrated Building Solutions [email protected] Value Value
Laying the First Course. 1. Excavate the site and construct the footing.
Use QUIKRETE Mortar Mix or Mason Mix lay up a concrete block wall as shown. QUIKRETE Mortar Mix or Mason Mix Concrete block Mason's line Line blocks 4' level brick trowel Jointer Mason's hammer Stiff brush
School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191
School Building Authority of West Virginia BUILDING INFORMATION MODELING (BIM) EXECUTION PLAN SBA FORM 191 Section 1: General 1.0 Alignment with Organizational Vision In the space provided below, read
Residential Inspection Guidelines
Residential Inspection Guidelines 201 Pre-Pour Foundation Dimensions Building Location Certificate - if required in the building consent Construction and Advice Notes Check the building dimensions against
UPDATE October 8, 2012 Chicago Roofing Contractors Association CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS
UPDATE October 8, 2012 Chicago Roofing Contractors Association CHICAGOLAND S ROOFING, INSULATION, AIR-BARRIER REQUIREMENTS Executive Summary: There is a proposal at the Joint Committee on Administrative
ISO Types 1-6: Construction Code Descriptions
ISO 1 Frame (combustible walls and/or roof) Class 1B Buildings where the exterior walls are wood or other combustible materials, including construction where the combustible materials are combined with
NEW BUILDING CONSTRUCTION INTERIOR WORK & FINISHES EXTERIOR RESTORATION & WATERPROOFING. www.janbarinc.com
EXTERIOR RESTORATION & WATERPROOFING NEW BUILDING CONSTRUCTION INTERIOR WORK & FINISHES www.janbarinc.com Janbar Inc is a general contracting company located in Brooklyn NY. Started originally in 2002
3rd Annual Design Drafting Contest
3rd Annual Design Drafting Contest YTI Career Institute 3 rd Annual Design Drafting Contest The purpose of this contest is to encourage excellence in effort and discipline, and to give recognition to outstanding
Basement & Foundation Damage
Basement & Foundation Damage Please note-this presentation is only intended to be used as a basic educational tool and is by no means all encompassing. Each property should be treated on a case by case
Calvert USA, Inc. Attic Stairs
Calvert USA, Inc. Attic Stairs Instructions for installation of vertical opening access stairs Model numbers: 7035 through 7047 Calvert USA, Inc., P.O. Box 841, Solomons, MD 20688, Tel. (410) 286-1430,
SECTION 11014 WINDOW WASHING SYSTEMS
SECTION 11014 WINDOW WASHING SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section includes, but is not limited to, design and furnishing portable davits, davit sleeves, dvit bases, four (4) removable outriggers,
SG Series 65mm Frame Windows (Fixed Lite Window Illustrated)
(Fixed Lite Window Illustrated) SINGLE LEAF CLADDING / CORRUGATED STEEL (Awning Window Illustrated) SINGLE LEAF CLADDING / FOAM BOARD (Casement Window Illustrated) BRICK VENEER CONSTRUCTION (Horizontal
Introduction...COMB-2 Design Considerations and Examples...COMB-3
SECTION DIRECTORY General Information Introduction...COMB-2 Design Considerations and Examples...COMB-3 Combination Assembly Recommendations and Limitations Composite Configurations...COMB-4 Typical Sealant
COMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
Vanishing Lid Trays Construction Methods with Tile or Masonry
1-800-447-2838 Installation Instructions Vanishing Lid Trays Construction Methods with Tile or Masonry Table of Contents 1. Tools and Equipment...1 2. Vanishing Lid Trays...3 2.1 Materials for Finished
0331 Brick and block construction
0331 BRICK AND BLOCK CONSTRUCTION This worksection has been written for Class 1 and 10a buildings that fully conform to the scope of AS 4773.1. If the works include isolated structures, (totally separate